Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Regional Stormwater Management
(a.k.a. “Diverse Watershed ‘Wise’ Stormwater Solutions”)
FDOT’s Experience and Vision
Carlton Spirio, P.E.
FSA - 2017 Annual Meeting
Today’s Focus
• FDOT’s Typical Project Timeline
• Current Stormwater Management Practices
• Regional and Watershed Strategies Environmental Look Arounds (ELAs)
Stakeholder Engagement
• Examples of Successful Applications
FSA - 2017 Annual Conference
Typical FDOT Project Timeline
2
Project Development
0Years
5 74 6 8
ProjectConstruction
Design andPlans Preparation
Right-of-wayAcquisition
ERP Process
60% Plans
Project Letting
Bid /
Let /
Pre-con
NEPA Process
Agency Permit Coordination
FSA - 2017 Annual Conference
Current PracticeDesign, Permit and Construct Off-site Stormwater Facilities
aka: BURPs – Big Ugly Rectangular Ponds
FSA - 2017 Annual Conference
Traditional Pond Benefits
• Generally easy to permit.
• Potential source of roadway embankment.
• FDOT is sole owner with control of future improvements.
• Effective BMP for sediment and trash collection.
• For the most part, easy to maintain.
2017 Annual Public Works Association Expo
Traditional Pond Hardships
• ROW acquisition adds approximately 2-years to the schedule.
• Full compensation consists of the value of all land and improvements acquired, damages to remaining property, attorney fees and expert witness testimony and research.
• Multiple stand-alone ponds are inefficient for nutrients.
• Usually, the nutrient load reduction benefit is small compared to the pond acquisition costs for stand alone facilities.
• In certain cases, off-site ponds create additional wetland and species impacts (i.e. sand skink, tortoise, wood-stork, panther) which adds more costs to the permitting efforts.
• Aesthetic and economic impacts to surrounding Land Use.
FSA - 2017 Annual Conference
Traditional Design Approach
Canal System
Larg
er W
ater
body
Typical Ponds
DOT Road
FSA - 2017 Annual Conference
Traditional Design Approach
FSA - 2017 Annual Conference
Traditional Design Approach
FSA - 2017 Annual Conference
Traditional Design ApproachDual Systems
FSA - 2017 Annual Conference
Traditional Design ApproachDual Systems
FSA - 2017 Annual Conference
Regional/Watershed Strategy
• Consider regional stormwater management alternatives in lieu of Traditional ponds.
• Work with Counties, Cities, WMDs, FDEP, WCDs & private land owners to identify projects.
• Can provide treatment for previously untreated runoff including from non-roadway land uses which typically have higher nutrient concentrations.
• HB 599 (2012) or 373.413(6) F.S. allows FDOT to treat off-site runoff where it may benefit FDOT/Municipalities (and the associated watershed).
FSA - 2017 Annual Conference
Regional Approach
Canal System
Larg
er W
ater
body
Regional Pond or
Local Utility DOT
Road
Weir
FSA - 2017 Annual Conference
EMC Values
FSA - 2017 Annual Conference
Regional Approach Advantages
• Work with single/fewer property owners for the total roadway project.
• General approach is to replace ROW acquisition with agreements.
• Maximize nutrient removal efficiency by treating a larger, more polluted watershed areas such as agriculture and older residential land use areas.
• Regional facilities can be designed to address stormwater management needs for the Ultimate Roadway Typical Section.
• Potential to allow others to maintain systems.
• Regional facilities can potentially provide excess storage for future water supply and reuse needs.
FSA - 2017 Annual Conference
Regional Approach Obstacles• Developing Partnerships
• Ideal partner• Potential pond site already owned• In need of construction funding assistance• Has resources to maintain constructed Regional SWM• Close proximity in relationship to the FDOT roadway
• Legal Agreement(s)
• Agency Permitting• Compensating Treatment• Banking excess water quality credits for future use
• Access and maintenance easements along with responsibilities.
FSA - 2017 Annual Conference
Other Risks & Obstacles
• Lawsuits
• Permit Challenges
• Project Schedules
• Substantial Time Commitment
• Funding
• Unforeseen Needs and Improvements
FSA - 2017 Annual Conference
Environmental Look Arounds - ELAs
• Mandatory on all FDOT projects per the Drainage Manual
• Early Project Coordination: MPO – Planning, ETDM/PD&E, and in some cases Design
• Partnerships include: FDEP, WMDs, FWS, ACOE, Cities and Counties, Large Utility Owners, Developers
• Focus Areas include: Water Supply and/or Re-use, Wetland Restoration, MFLs, NPDES, BMAPs, Estuary/Coastal Initiatives
FSA - 2017 Annual Conference
Additional ELA Considerations
• ERP
• E & SC
• TMDLs
• Utility Upgrades
• Septic Tank Removal
• Long-term Coastal Plans
• Stormwater Research
• Everglades Restoration
• River/Stream Restoration
• Species Habitat
FSA - 2017 Annual Conference
StormwaterMatch.com
Stormwater Excess
Stormwater Users
GIS Interface Library?
Piggyback BMAPs?
FSA - 2017 Annual Conference
Successful Applications
• I-75 Bond Ranch
• SR 82 Joint Use Pond Agreements with ECWCD
• SR 710 Regional Treatment
FSA - 2017 Annual Conference
Bond Ranch
End Project
Begin Project
I-75 from Lee County Line to Tuckers Grade – Bond Ranch
I-75 from Lee County Line to Tuckers Grade – Bond Ranch
• Project originally proposed stormwater treatment and floodplain compensation within the median of I-75.
• No ROW project.
• Required impacting 48 acres of wetlands.
• Difficulty in permitting floodplain compensation.
FSA - 2017 Annual Conference
I-75 from Lee County Line to Tuckers Grade – Bond Ranch
• Working for almost 18 months to acquire the 670 acre Bond Ranch parcel.
• Able to eliminate median ponds by:• Removing the cows on Bond Ranch provides compensating water
quality treatment.
• Turning off the existing pumps provides attenuation and floodplain compensation.
• Reduced wetland impacts by 26 acres.• FDOT no longer has to maintain median ponds.
FSA - 2017 Annual Conference
I-75 from Lee County Line to Tuckers Grade – Bond Ranch
• Cost Savings:• $1.48 million in construction cost savings from eliminating
median ponds. (Negative SA from contractor)
• Reduced wetland impacts saves approximately $715,000 in mitigation.
• Savings from not maintaining median ponds over 20 years is estimated to be $1,782,000.
• FDOT contributed $1.48 million toward acquisition of Bond Ranch Parcel by FDEP.
FSA - 2017 Annual Conference
SR 82 Projects
Lehigh Acres ECWCD
Hendry Canal
West Marsh Preserve
FSA - 2017 Annual Conference
SR 82 Regional Treatment
• Eliminate Off-site Postage Stamp Ponds and provide stormwater management within ECWCD’s existing canal system.
• Requires Joint Use Pond Agreements (JUPA) with ECWCD.
• FDOT will acquire 100’ easements within nine of ECWCD’s canals.
• ECWCD will construct the SW Weirs project which will provide significant water quality and flood control improvements to the region.
FSA - 2017 Annual Conference
100’ Easement Example
SR 8
2
Mea
dow
Roa
d
FDOT easement
from ECWCD
FSA - 2017 Annual Conference
Why Joint Use Pond?
• PSR off-site pond cost estimate = $13.7 million
• ECWCD option (including $3.1 million payment to ECWCD) = $12.2 million
• Savings = $1.5 million
• PLUS…
• Reduced drainage pipe sizes = $2.05 million
• Eliminated long term maintenance = $1.08 million
• Total Estimated Savings = $4.6 million
FSA - 2017 Annual Conference
Earthwork
• By eliminating the “Postage Stamp” ponds FDOT lost its source of “cheap” fill.
• To solve this FDOT has agreed to construct the West Marsh Preserve project as a “goes with” project.
• ECWCD will provide design and permits for the West Marsh Preserve project.
• Plans will be submitted concurrently with SR 82 ERC reviews.• Plans shall include phasing to accommodate each segment of
SR 82 independently.
FSA - 2017 Annual Conference
West Marsh Preserve Concept
Plan
Grade to El. 14.0
Inflow
Outflows to Orange River
Existing Harns Marsh
West Marsh Preserve
• Assisting with construction of West Marsh Preserve:• Provides fill source for Segments 1 and 2 of SR 82.
• Offset FDOT’s stormwater needs for segment 3 of SR 82.
• Eliminates FDOT’s long term maintenance responsibilities for the “postage stamp” ponds within Segment 3.
• Deal with fewer property owners for ROW acquisition.
• Provides greater nutrient removal within the watershed.
• Separate MOA executed with Lee County who owns the property.
FSA - 2017 Annual Conference
SR 82 Projects
Lehigh Acres ECWCD Hendry
Canal
West Marsh Preserve
FSA - 2017 Annual Conference
Hendry Canal Widening
• Assisting with construction of Hendry Canal Widening:
• Provides fill source for Segments 3 and 4 of SR 82.
• Offset FDOT’s attenuation needs for segments 3 & 4 of SR 82.
• Deal with fewer property owners for ROW acquisition.
• Helps ECWCD achieve a regional flood control improvement.
FSA - 2017 Annual Conference
SR 710 – New Alignment
FSA - 2017 Annual Conference
SR 710 Regional Approach
• Construction is not funded.• Lake Okeechobee is an Impaired Waterway.• Suspended the pond siting efforts to check regional treatment
feasibility.• Coordinating with FDEP, SFWMD, FDACS, locals, & other
stakeholders.• Conducting feasibility study to look at two options:
• Regional Treatment – FDOT only
• Stormwater Treatment Area (STA) – multi-party agreement
FSA - 2017 Annual Conference
SR 710 Regional Approach
26 Acre Regional Treatment Pond provides compensating treatment for entire SR 710 project, plus.
FDOT can design, acquire, and construct independently of any other stakeholder involvement.
Reduced Schedule Risk Option
Regional Pond
FSA - 2017 Annual Conference
SR 710 – STA Option
Multi-agency coordination required.
FDOT would likely pay FDEP or SFWMD to acquire, design, and maintain.
FDOT needs fill material for roadway embankment so may participate in construction.
FSA - 2017 Annual Conference
SR 710 Regional Approach
Alternative Estimated TP Removal (kg/yr)
Postage Stamp Ponds 12
Regional Pond (26 ac) 500
STA (60 ac) 700
The regional treatment and STA options provide significantly more nutrient reduction above roadway requirements.
Helps satisfy FDOT’s Lake Okeechobee Basin Management Action Plan (BMAP) requirements.
FSA - 2017 Annual Conference
SR 710 Regional Approach
• ROW and construction costs for stand-alone ponds are to be applied toward regional stormwater alternative.
• Fewer property owners.
• Much Better for the Environment.
• Potentially mitigate for localized residential flooding.
FSA - 2017 Annual Conference
Concluding Thoughts• All projects proposing ROW acquisition should consider Regional
alternatives within the contributing watershed.
• Environmental Look Arounds (ELAs) are required per the 2015 FDOT Drainage Manual.
• Engage and re-engage in coordination with any and all stakeholders to identify worth regional stormwater solutions.
• The potential for favorable outcomes include:
• More effective use of financial resources
• Minimize ROW acquisition needs
• Reduced maintenance responsibilities
• Favorable partnerships and publicity
FSA - 2017 Annual Conference
Going Forward• Watershed “Wise” Thinking
Practical
Permittable
Cost Effective
Ecological Driven Solutions
• Finally, don’t let FEAR dictate your drainage design.
• Likewise, avoid “Going through the Motion” when planning and designing stormwater management solutions for FDOT projects.
FSA - 2017 Annual Conference
Thanks for your Attention!!!Any Questions???
FSA - 2017 Annual Conference