17
SETA 2016 SETA 2016 Sustainable Energy & Technology Asia 2016 March 23, 2016 Regional Connectivity and Regional Connectivity and Grid Interconnection Grid Interconnection by by M S Tk M S Tk Mr. Sawapop T akapong Mr. Sawapop T akapong Head of Transmission System Analysis Section, System Planning Division Head of Transmission System Analysis Section, System Planning Division Electricity Generating Authority of Thailand Power for Thai Happiness

Regional Connectivity and Grid Inerconnection-1.pptmpowerconnexions.com/seta_papers/cfp_sawapop_takapong_Regional...Reggyional Connectivity and Grid Interconnection by ... Working

  • Upload
    vannga

  • View
    221

  • Download
    1

Embed Size (px)

Citation preview

SETA 2016SETA 2016 Sustainable Energy & Technology Asia 2016

March 23, 2016

Regional Connectivity andRegional Connectivity and

,

g yg yGrid InterconnectionGrid Interconnection

byby

M S T kM S T kMr. Sawapop TakapongMr. Sawapop TakapongHead of Transmission System Analysis Section, System Planning DivisionHead of Transmission System Analysis Section, System Planning Division

Electricity Generating Authority of ThailandPower for Thai Happiness

Outline

III. ASEAN Power Grid (APG)

II. Thailand & Neighboring Countries Power InterconnectionInterconnection

I. EGAT Transmission System

2

Part I : EGAT Transmission System

III. ASEAN Power Grid (APG)

II. Thailand & Neighboring Countries Power I t tiInterconnection

I EGAT Transmission SystemI. EGAT Transmission System

3

Transmission System Development Plan (1/2)

▪ Methodology– Steady - state power flow study– Short - circuit current study– Transient stability study

▪ Power Development Plan (PDP2015)

Technical

Transient stability study– Line energization study

▪ EGAT Criteria– General Criteria

o Normal voltage : 0.98 – 1.05 pu.o Emergency voltage : 0 92 1 08 pu

▪ Energy Efficiency Development Plan (EEDP)

▪ Alternative Energy Development Plan (AEDP)

Transmission Development

PlanMajor Policy Financial

&

o Emergency voltage : 0.92 – 1.08 pu.– Steady State Criteria

o N-1o Short circuit level

– Stability Criteriao Fault is cleared normally in:

Objective

▪ Enhance System Security▪ Cope with the Growing Plan Economic

Effect on

o Fault is cleared normally in:500 kV : 4 cycles230 kV : 5 cycles115, 69 kV : 7-8 cycles

Electricity Demand▪ Accommodate

• New Power Plants• Power Purchase• ASEAN Power Grid

Effect on Community and

Environment Least Cost Analysis

Economic Internal Rate of Return (EIRR) Transmission line routes must not affect the Financial Internal Rate of Return (FIRR)

Transmission line routes must not affect the community or must have the least impact if not avoidable.

Transmission line routes must avoid passing through the restricted areas, such as national park area forest park area ildlife sanct aries

4

park area, forest park area, wildlife sanctuaries area and watershed area class 1A, 1B.

Transmission System Development Plan (2/2)

▪ Transmission System Development Projects to Cope with the

Transmission Capacity (PDP 2015)

Growing Demand

▪ Transmission System Improvement Projects to Enhance System

Security

▪ Transmission System Expansion and Renovation Projects

▪ Transmission System Development Projects for Power Purchase

▪ Transmission System Interconnection Projects (Grid to Grid)

Progress

a s ss o Sys e e co ec o ojec s (G d o G d)

g

▪ Cope with the Growing Demand

Ongoing projects (2015-2019) 15 projects

2 projects

▪ Improvement Projects

▪ Expansion and Renovation Projects

4 projects

3 projects

5

▪ Development for Power Purchase 6 projects

EGAT Transmission Capacity

(As of December 31, 2015)

VoltageLevel

Substation Transmission

Number MVA (Circuit-km)

500 kV 13 23,200 4,988

230 kV 76 55,060 14,143

132 kV 133 9

115 kV 126 14,580 13,813

69 kV -- 19

300 kV (HVDC) 388 23

Total 215 92,361 32,995

6

Existing 500 kV Transmission System Future 500 kV Transmission System

Year 2024

7

Part II : Thailand & Neighboring Countries Power Interconnection

III. ASEAN Power Grid (APG)

II. Thailand & Neighboring Countries Power InterconnectionInterconnection

I. EGAT Transmission Systemy

8

Chi

Electricity Cooperation with Neighboring CountriesChinaMOU, 12 Nov 1998 : 3,000 MWMyanmar

new MOU, 15 June 2015Li t f t ti l j t Lao PDR

MOU, 22 Dec 2007 : 7,000 MWSigned PPA : 5,421 MWS d COD 3 087 MW

List of potential projects- Mon Ton- Mai Khot- Keng Tung- Tanintharyi

Myeik Started COD : 3,087 MW- Myeik

Existing 3,087 MW

Theun Hin Boon (Mar1998) 214 MWHuay Ho (Sep1999) 126 MWNam Theun 2 (Apr2010) 948 MWNam Theun 2 (Apr2010) 948 MWNam Ngum 2 (Mar2011) 597 MWTheun Hin Boon (Dec2012) 220 MW(expansion) Hongsa #1-2 (June,Sep2015) 982 MW

Projects with signed PPA 2,334 MWProjects with signed PPA 2,334 MW

Hongsa #3 (Mar2016) 491 MWXepian (Feb2019) 354 MWNam Ngiep (Jul2019) 269 MWXayaburi (Oct2019) 1,220 MW

Remark:1) MOU framework refers to G2G Agreement2) Each of Project Development is the PPA between EGAT and the Project Developers/Concessionaires.

CambodiaMalaysia

Project with Tariff MOU 520 MWNam Theun 1 (Jan2023) 520 MW

p /3) COD = Commercial Operation Date

9

MOU, 3 Feb 2000 : not specifiedMalaysiaMOU, 6 May 2004 : 300 MW HVDC

Thailand Power Grid Interconnection

Thailand has an energy cooperation with neighboring countries in two types :

Energy Exchange (Grid to Grid) Power PurchaseA B

HVACEGAT - EDL

HVDCEGAT - TNB

Energy exchange between two countries through Grid to Grid System

Non - Firm Capacity

EGAT imports power from IPP in neighboring countries with PPA and the power is imported from the IPP project directly.

Firm Capacity

10

Firm Capacity

Existing Power Grid Interconnection Points

Energy Exchange between EDL & EGATThe 115 kV transmission system of EGAT and EDL are

A

Power Purchasing between IPP & EGAT

yinterconnected for exchanging power (import or export) through five interconnection points

B gThailand

& Lao PDR

EGAT imports power from IPP in Lao PDR with PPA and the power is imported from the IPP project directly.

The 230 kV or 500 kV transmission system are the system voltage for power purchase.

Currently, the 500 kV transmission system is initially energized at 230 kV (Na Bong Substation). When other IPP power plants are connected to 500 kV transmission

500 kV Substation

230 kV Substation

115 kV Substation

300 kV HVDC Substation

system, the voltage level will be converted from 230 kV to 500 kV.

Thailand & MalaysiaThere are -300 HVDC Mono-Pole link between EGAT and Malaysia.

Energy Exchange between TNB & EGATA

11

Part III : ASEAN Power Grid (APG)

III. ASEAN Power Grid (APG)

II. Thailand & Neighboring Countries Power InterconnectionInterconnection

I. EGAT Transmission Systemy

19

Prospect of Resources Sharing in ASEAN

PEOPLE'S REPUBLIC OF CHINA

HydroMyanmar:

• Significant hydropower potential

More Resources, less demand

MYANMAR

PHILIPPINESLAOSHydro

Hydro

Hydro

Coal

• Significant hydropower potential• High natural gas reserve

Laos:Significant hydropower potential with

CAMBODIAVIETNAM

THAILANDOil

H d o

Gas

Significant hydropower potential with aims to export to neighboring counties

Indonesia:

BRUNEIOil

Hydro

Gas

Indonesia:Significant steam coal potential

Less Resources, high demandSARAWAK

P. MALAYSIA

KALIMANTANSINGAPORE

Hydro

Coal

Coal

Oil

Thailand: Second-largest energy consumer

SUMATRA

INDONESIAHydro

Oil

Gas

Malaysia:• Third-largest energy consumer• World’s second-largest LNG

exporter

13

Source: IEA Southeast Asia Energy Outlook 2015

History of ASEAN Power Grid (APG)

ASEAN Vision ASEAN Vision 2020 2020 call forcall for

ASEAN Power GridASEAN Power Grid1997

ASEAN Ministers on Energy

“ The Member Countries agree to strengthen andpromote a broad framework to cooperate towards theASEAN Power GridASEAN Power Grid

Interconnection Interconnection StudyStudy

development of a common ASEAN policy on powerinterconnection and trade, and ultimately towards therealization of the ASEAN Power Grid to help ensuregreater regional energy security and sustainability on

f f

Memorandum of Memorandum of Understanding (MOU) Understanding (MOU)

on ASEAN Power on ASEAN Power 2007

the basis of mutual benefit ”

HAPUA: The Heads of ASEAN Power Utilities/AuthoritiesGrid (APG)Grid (APG)

Department of Electrical ServicesBrunei Darussalam

PT. PLN (Persero)

Electricité du CambodgeKingdom of Cambodia

Electricité du Laos

ASEAN ASEAN Interconnection Interconnection

Master Plan Study Master Plan Study 2011

( e se o)Republic of Indonesia

Tenaga Nasional BerhadMalaysia

Lao PDR

Department of Electric Power of Myanmar Union of Myanmar

yyPhase Phase 22

(AIMS Phase II)(AIMS Phase II)National Power CorporationRepublic of the Philippines

Electricity Generating Authority of ThailandKingdom of Thailand

Electricity of VietnamSocialist Republic of Viet Nam

Singapore Power LTDRepublic of Singapore

14

g Socialist Republic of Viet Nam

ASEAN Interconnection Master Plan Study (AIMS-II)

HAPUA

HAPUA Structure and Cooperation Area

Working Group #3Distribution &

Power Reliability and Quality

Working Group #4Policy &

Commercial Development

Working Group #5

Human Resource

Working Group #1

Generation

Working Group #2

Transmission

Chair : SingaporeVice Chair : Myanmar

Chair : PhilippinesVice Chair : Cambodia

Chair : MalaysiaVice Chair : Brunei

Chair : IndonesiaVice Chair : Lao PDR

Chair : ThailandVice Chair : Vietnam

Analysis of Technical and Economical Aspects

(1) Long term load forecast of each system(2) Establishment of common system planning criteria and assumptions(3) Generation expansion plan of each system(4) Transmission network analyses, and (5) Estimated interconnection costs

15

(5) Estimated interconnection costs

ASEAN Interconnection Projects(Updated in Nov 2015)

Original COD Earliest COD1) P.Malaysia - Singapore• Plentong – Woodlands Existing Existing• P.Malaysia - Singapore 2018 post 2020

(2nd link Plentong - Woodlands)2) Thailand - P Malaysia2) Thailand P.Malaysia• Sadao - Bukit Keteri Existing Existing• Khlong Ngae - Gurun Existing Existing• Su Ngai Kolok - Rantau Panjang 2014 TBC• Khlong Ngae – Gurun (2nd Phase, 300MW) 2016 TBC3) Sarawak - P. Malaysia 2015 - 2021 20254) P Malaysia Sumatra 2015 20214) P.Malaysia - Sumatra 2015 20215) Batam - Singapore 2015 - 2017 post 20206) Sarawak - West Kalimantan 2012 20157) Philippines – Sabah 2020 TBC8) Sarawak - Sabah – Brunei 2020• Sarawak –Sabah 2020 2020

S k B i 2012 2016 2019• Sarawak – Brunei 2012-2016 20199) Thailand - Lao PDR• Roi Et 2 - Nam Theun 2 Existing Existing• Sakon Nakhon 2 – Thakhek – Then Hinboun (Exp.) 2012 Existing• Mae Moh 3 - Nan - Hong Sa 2015 2015• Udon Thani 3- Nabong (converted to 500KV) 2017 2019• Ubon Ratchathani 3 – Pakse – Xe Pian Xe Namnoy 2018 2019• Khon Kaen 4 – Loei 2 – Xayaburi 2019 2019• Nakhon Phanom – Thakhek 2015• Thailand – Lao PDR (New) 2015 - 2023 2019-202310) Lao PDR – Vietnam 2011 – 2016 2016 - 2020• Xekaman 3 – Tranhmy Existing Existing• Xekaman 1 – Pleiku 2 201611) Thailand - Myanmar 2016 - 2025 2018-202612) Vietnam - Cambodia (New) • Chau Doc – Takeo – Phnom Penh Existing Existing

• Tay Ninh – Stung Treng 2016 TBC13) Lao PDR – Cambodia 2011 post 2018

Presented to APGCC#17 and HWC#22 - KL, Malaysia, 16-19 November 2015Prepared by HAPUA Working Group No. 2 – APG/Transmission

13) Lao PDR Cambodia 2011 post 201814) Thailand - Cambodia (New) 2015 - 2017 post 2020• Aranyaprathet – Banteay Meanchey Existing Existing• Thailand – Cambodia 2015-2017 post 202015) East Sabah - East Kalimantan Newly Proposed TBC

16) Singapore – Sumatra 2020 post 2020

The earliest COD information is as of Nov 2015.

The original COD is according to AIMS II results.

The Priority Projects, which refer to the APAEC 2016-2020, are underlined and indicated in Red.

“Powe r Fo r Tha i Happ iness ”