48
Referral #110210 October 10, 2011

Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Referral #110210October 10, 2011

Page 2: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

#110210 – Update:

At the July 7, 2011 City Commission meeting, Commissioners requested that the RUC hear an update on the changing factors affecting Gainesville Renewable Energy Center (GREC) costs and projected costs.

10/10/2011 2

Page 3: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Balancing Policy And Business ObjectivesWhat brings us to today

Policy & business objectives Previously provided pricing analyses Change in market and regulatory environments Resulting cost considerations Strategies to manage cost of adding generation Benefits from this new generation

10/10/2011 3

Page 4: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

City Commission Policy Reduce carbon emissions (June 2005 Commission

passes resolution to enter Climate Protection Agreement)

Adopted aggressive TRC test which expanded energy efficiency programs (April 12, 2006)

Increase use of renewable fuels (June 2007)

10/10/2011 4

Page 5: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

County Commission Policy Alachua County Commission March 2007 Resolution

Energy efficiency Reduce energy consumption Renewable energy

Environmental Protection Advisory Committee (EPAC) Report adopted by the County Commission Suggested GRU build a 100 megawatt biomass generation facility Report found biomass could contribute over 20 to 30 million

dollars to the local economy in the interval 2011 to 2023

10/10/2011 5

Page 6: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

GRU Business Strategy Improve generation reliability

Deerhaven Unit 2, which provides most of the community’s around-the-clock base load power, is nearly 30 years old

Increase fuel diversity Bond rating agency recommended

Provide price stability and obtain long term cost savings for customers

Hedge against further environmental regulation

10/10/2011 6

Page 7: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Improve Generation Reliability

10/10/2011 7

SummerUnit Unit Primary Age Net Capacity

Name Type Fuel in Years (MW)

JR Kelly Unit 7 Steam Turbine Natural Gas 50.1 23.20JR Kelly GT1 Gas Turbine Natural Gas 43.6 14.00JR Kelly GT2 Gas Turbine Natural Gas 43.0 14.00JR Kelly GT3 Gas Turbine Natural Gas 42.3 14.00Deerhaven Unit 1 Steam Turbine Natural Gas 39.1 78.00Deerhaven GT1 Gas Turbine Natural Gas 35.2 17.50Deerhaven GT2 Gas Turbine Natural Gas 35.1 17.50Crystal River Unit 3 Steam Turbine Nuclear 34.5 11.85Deerhaven Unit 2 Steam Turbine Coal 29.9 222.10Deerhaven GT3 Gas Turbine Natural Gas 15.7 75.00JR Kelly CC1 Combined Cycle Natural Gas 10.3 112.00South Energy Center GT1 Gas Turbine Natural Gas 2.3 4.10

Megawatt Weighted Average Age: 28 603.25

Current Year: 2011

Page 8: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Increase Fuel Diversity – Portfolio Strategies Reduce Risk

10/10/2011 8

Coal61.8%

Oil0.2%

Natural Gas17.1%

Landfill Gas1.1%

Nuclear4.1%

Coal, Gas and

Nuclear Purchases

15.6%

Solar0.1%

2010

* Assumes GRU retains 50 MW of GREC

Coal57.9%

Natural Gas

15.4%

Landfill Gas1.5%

Nuclear5.1%

Biomass*18.6%

Solar1.5%

2015

Page 9: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Out-of-State78.4%

Local21.6%

2015

Out-of-State98.8%

Local1.2%

2010

Energy Independence - Local Fuel

10/10/2011 9

Page 10: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Price Stability – Less Market Exposure

10/10/2011 10

Variable Costs

Subject to Market Pricing73.3%

Fixed Costs

Subject to Contract

26.7%

2015

Variable Costs

Subject to Market Pricing94.7%

Fixed Costs

Subject to Contract

5.3%

2010

Page 11: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Less Exposure To Gas Fired Generation Will Improve Price Stability

10/10/2011 11

Page 12: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

$-

$50.00

$100.00

$150.00

$200.00

$250.00

$300.00

$350.0020

1420

1520

1620

1720

1820

1920

2020

2120

2220

2320

2420

2520

2620

2720

2820

2920

3020

3120

3220

3320

3420

3520

3620

3720

3820

3920

4020

4120

4220

43

$/M

Wh

Base Case Gas Alternative High Fuel Price Gas Alt. Low Fuel Price Gas Alt.

Biomass Biomass w/o Grant10/10/2011 12

Long Term Cost Savings:Biomass Compared To Gas Alternative

Source: May 7, 2009City Commission presentation

Page 13: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

10/10/2011 13

New Generation Costs Will Escalate Under EPA’s Pending Regulations

Page 14: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Balancing Policy And Business ObjectivesWhat brings us to today

Policy & business objectives

Previously provided pricing analyses Change in market and regulatory environments Resulting cost considerations Strategies to manage cost of adding generation Benefits from this new generation

10/10/2011 14

Page 15: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

What’s Changed Since May 7, 2009*

What we said Projected price effects

Sensitivity to natural gas forecasts Potential mitigating factors

What factors have changed Update on projected price effects

10/10/2011 15

* As presented at the May 7, 2009 City Commission meeting

Page 16: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Base Gas Forecast - $10.56/1,000 kWh

10/10/2011 16

Measured as Equivalent Effect on 1000 KWH Residential Bill

$/Month

Scenario: Base Load and Energy Price Forecast

2014 2019

ItemCumulative Effect on

Bill Item

Cumulative Effect on

Bill Direct Utility Bill Cash Flows

Net Effect After Fuel Savings $10.56 $10.56 $5.12 $5.12Effect of Prepayment Restructure -$2.25 $8.31 -$2.27 $2.85CO2 Regulation savings @ $12/MWH -$2.22 $6.10 -$2.10 $0.75

Indirect Utility Bill Benefits Avoided capacity in 2023 -$4.73 $1.37 -$4.49 -$3.75

Other Community Benefits From Off-System SalesProp Tax Revenue for County, Schools, Library -$1.35 $0.02 -$1.28 -$5.03

Other Regulatory Risk From DelayMissing ITC Grant Deadline 1/1/2014 $1.48 $1.50 $1.40 -$3.62PTC Not Extended $3.14 $4.63 $3.29 -$0.34

Parameter

Source: May 7, 2009 City Commission Presentation. Assumes 50 MW of GREC sold through 2023.

Page 17: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Low Gas Forecast - $12.78/1,000 kWh

10/10/2011 17

Measured as Equivalent Effect on 1000 KWH Residential Bill

$/Month

Scenario: 20% Lower Energy Price Forecast

2014 2019

ItemCumulative Effect on

Bill Item

Cumulative Effect on

Bill Direct Utility Bill Cash Flows

Net Effect After Fuel Savings $12.78 $12.78 $8.50 $8.50Effect of Prepayment Restructure -$2.25 $10.53 -$2.27 $6.22CO2 Regulation savings @ $12/MWH -$2.22 $8.32 -$2.10 $4.12

Indirect Utility Bill Benefits Avoided capacity in 2023 -$4.73 $3.59 -$4.49 -$0.37

Other Community Benefits From Off-System SalesProp Tax Revenue for County, Schools, Library -$1.35 $2.24 -$1.28 -$1.65

Other Regulatory Risk From DelayMissing ITC Grant Deadline 1/1/2014 $1.48 $3.72 $1.40 -$0.25PTC Not Extended $3.14 $6.85 $3.29 $3.04

Parameter

Source: May 7, 2009 City Commission Presentation. Assumes 50 MW of GREC sold through 2023.

Page 18: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Balancing Policy And Business Objectives

What brings us to today Policy & business objectives Previously provided pricing analyses

Change in market and regulatory environments

Resulting cost considerations Strategies to manage cost of adding generation Benefits from this new generation

10/10/2011 18

Page 19: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Conditions Have Changed – And They Will Again

Demand for electricity Natural gas prices Environmental permitting requirements

10/10/2011 19

Page 20: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Demand For Electricity Increased

10/10/2011 20

0

100

200

300

400

500

600

1989

1991

1993

1995

1997

1999

2001

2003

2005

2007

2009

2011

2013

2015

2017

2019

2021

2023

2025

2027

2029

Meg

aWat

ts

Summer Peak Demand

History2009 Forecast2011 Forecast

Page 21: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Natural Gas Price Dropped

10/10/2011 21

$0

$5

$10

$15

$20

$2519

90

1992

1994

1996

1998

2000

2002

2004

2006

2008

2010

2012

2014

2016

2018

2020

2022

2024

2026

2028

2030

Nom

inal

Dol

lars

per

MM

Btu

Delivered Fuel Price Forecasts

Gas History

Coal History

High Gas '09

Gas '09

Low Gas '09

Gas '11

Coal '11

Coal '09

Biomass '11

Page 22: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

More Stringent Regulations Enacted EPA’s endangerment findings

Carbon emissions detrimental to public welfare Resulted in new automobile efficiency standards Resulted in “Tailoring Rule” for carbon accounting Carbon regulation under discussion

Florida’s Best Available Control Technology changed EPA enacted Industrial Boiler Maximum Achievable

Control Technology standards (IBMACT) Suwannee River Water Management District

imposed reclaimed water requirements

10/10/2011 22

Page 23: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

GREC’s Design Had To Change Original GREC Design

Selective Non-Catalytic NOx Reduction Calcium dry sorbent injection Baghouse for particulate reduction

Revised GREC Design Selective Catalytic reduction for NOx

Sodium dry sorbent Double baghouse size Pipeline to City of Alachua WWTP

10/10/2011 23

Page 24: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Balancing Policy And Business ObjectivesWhat brings us to today

Policy & business objectives Previously provided pricing analyses Change in market and regulatory environments

Resulting cost considerations Strategies to manage cost of adding generation Benefits from this new generation

10/10/2011 24

Page 25: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

GREC Contract Structure

10/10/2011 25

Fixed Costs $/MWhNon Fuel Energy Charge $56.15Fixed O&M $23.74Property Taxes $8.88Subtotal $88.76

Discretionary Dispatch Costs*Variable O&M $3.56Fuel Charge $37.80Subtotal $41.36

Total $130.13 /MWh

*Only incurred if better alternatives are not available

Page 26: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Total Annual Cost$103 M/Year

DiscretionaryDispatch Cost$33 M/Year

Fixed Cost*

$70 M/Year

Let’s Translate $/MWh to Annual Costs

10/10/2011 26

Discretionary Dispatch Cost* = $41.36/MWh x .90 CF x 100MW x 8760 hours/Year = $32,608,224 /YearFixed Cost = $88.76/MWh x .90 CF x 100MW x 8760 hours/Year = $69,978,384 /YearTotal Extended Cost = $130.13/MWh x .90 CF x 100MW x 8760 hours/Year = $102,594,492 /Year

*If GREC is available and capable of 100 MW 90% of the time (.90 CF)

Page 27: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Balancing Policy And Business ObjectivesWhat brings us to today

Policy & business objectives Previously provided pricing analyses Change in market and regulatory environments Resulting cost considerations

Strategies to manage cost of adding generation

Benefits from this new generation

10/10/2011 27

Page 28: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

GREC’s Benefits And Strategies To Manage Fixed Costs

Immediate cost savings Power marketing and prepay opportunities Savings from policy alternatives

10/10/2011 28

Page 29: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Immediate Cost Savings

Drop base load capacity contract costs from Progress Energy Florida (PEF)

Reduce fuel costs for power production by avoiding running higher cost units

Ability to sell Renewable Energy Credits (REC’s) Current market values

Solar: $10/MWh Landfill Gas, Wind, Biomass: $1/MWh

10/10/2011 29

Page 30: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Immediate Cost Savings(x $1,000,000 per year)

10/10/2011 30

SavingsDrop PEF Baseload Capacity Contract $12Net Production Cost Savings $7Renewable Energy Credit Sales $1

Total Immediate Cost Savings 20$ M/Year

Page 31: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Power Market And Prepay Opportunities

Long term contract assignment Non-recourse prepayment System power sale Federal agency contract

10/10/2011 31

Page 32: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Long Term Contract Assignment Utilities want GREC’s long term values Favorable market conditions

Coal retirements Gas pipeline constraints Florida reserve margins

GREC’s economics are competitive with nuclear Cost per MWh Long term stable price Hedges carbon and fuel price risk No nuclear waste disposal or construction cost risk

Willing to offer 25 MW on a long term basis

10/10/2011 32

Page 33: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Non-Recourse Prepayment

Authorized by 2005 Energy Policy Act How It Works

Tax-Exempt Power project formed under FS Chapter 163 (The “Conduit”)

Tax-Exempt Bonds issued by Conduit to prepay Producer provides discount (negotiated) Not GRU debt: Conduit’s debt

10/10/2011 33

Page 34: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

System Power Sale

GREC energy creates a very favorable incremental cost of generation for off-system sales

Blended with other GRU assets, wholesale power is available Pricing very competitive Indexed to hedge fuel risk

10/10/2011 34

Page 35: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Federal Agency Contract

Federal agencies have renewable energy goals Energy Policy Act of 2005 Executive Order 13423 7.5% by 2013

10/10/2011 35

Page 36: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Power Marketing And Pre-pay Strategy BenefitsX $1,000,000 Per Year

10/10/2011 36

*Reflects the effect of having only 75 MW of GREC available for retail power supply

Potential Benefit

Long Term 25 MW PPA Assignment $16Non- Recourse Pre-Pay* $15System Wholesale Power Sale* $7Federal Agency Contract $2

Total Marketing & Prepay Strategies $40 M/Year

Page 37: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Savings From Policy Alternatives

Solar Feed In Tariff scale back

General Fund Transfer (GFT) offset

10/10/2011 37

Page 38: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Solar FIT Scale Back

Solar FIT has upward rate pressure City Commission may terminate program for any

project not holding an executed Solar Electric Power Agreement (SEPA) at any time.

One option is to not issue additional capacity reservations after 2013.

10/10/2011 38

Page 39: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

General Fund Transfer (GFT) Offset

Tangible Property Tax estimated at $7 million per year About $1.3 million accrues to the City of Gainesville This amount could be offset from GRU’s GFT in future

years General Government would remain whole

10/10/2011 39

Page 40: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Savings From Policy Alternativesx $1,000,000 Per Year

10/10/2011 40

Potential Benefit

No Addtional Solar FIT Commitments After 2013 2014 Cost Reduction 0.3$ Additional Reductions By 2016 0.6$ Reduce GFT By GREC Ad Valorem Taxes 1.3$

Total 2.2$ M/Year

Page 41: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Price Mitigation Summaryx $1,000,000 Per Year

10/10/2011 41

() indicates a negative number (or cost to be recovered)

PotentialCosts and Savings

GREC Fixed Cost (70)$ Immediate Cost Savings 20$ Power Marketing and Pre-Pay Strategies 40$ Policy Alternative Options 2$

Residual Amount To Recover Through FA (8)$ M/Year

Page 42: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Lets Translate Millions of Dollars Per Year Into Customer Prices $8 million per year of cost is equivalent to $4.00/1000

kWh

Given that savings may vary from estimates, a target of a $10.00/1000 kWh is realistic which corresponds to recovering $20 million per year

10/10/2011 42

Note: As a purchased power cost recovered through fuel adjustment, GREC’s costs are not subject to utility taxes or surcharges.

Page 43: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Balancing Policy And Business ObjectivesWhat brings us to today

Policy & business objectives Previously provided pricing analyses Change in market and regulatory environments Resulting cost considerations Strategies to manage cost of adding generation

Benefits from this new generation

10/10/2011 43

Page 44: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Benefits Not Quantified In This Analysis

Present value of avoided capacity in 2023 Hedge value against fossil fuel price volatility Regional economic benefits

$5.7 million per year net increase to local tax base Creates 700 jobs in the region* $31 million circulated in the regional economy instead of

being shipped out of state* Hedge value against carbon or renewable portfolio

standard regulation

* Dr. Julie Harrington, Economic Impact Analysis of Gainesville Renewable Energy Center (GREC) Proposed Biomass Power Project in Alachua County and Surrounding Counties, March 2010

10/10/2011 44

Page 45: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

-

10

20

30

40

50

60

70

80

90

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

mill

s

Historical FA FCST FA With GREC

Assumes that offsets necessary to achieve 10.56 FA impact in 2014 are achieved

Projected FA – Current Fuel Price Forecasts

10/10/2011 45

Page 46: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Summary

The need and policy objectives for GREC have not changed.

GREC continues to have long term value for our customers.

The initial projections as presented on May 7, 2009 are still achievable.

Staff continuously pursues cost mitigation strategies for all generation resources as market conditions change on a daily basis.

10/10/2011 46

Page 47: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

Recommendation

The Regional Utilities Committee hear periodic updates on ongoing changes and strategies that positively or negatively impact GRU generation.

10/10/2011 47

Page 48: Referral #110210 October 10, 2011 · Change in market and regulatory environments ... 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026

More information on GREC available at:

10/10/2011 48

www.gru.com