Citec Oy AbHead officeP.O. Box 109FI-65101 Vaasa, FinlandTel. +358 6 3240 700 www.citec.com
CASE IN BRIEF
Project Management of document and material deliverables for Altamira power station conversion
Location •Power station in Mexico. •Project stakeholders spread over six
countries on three contintents.
Customer Alstom Boiler France
Year 2014-2016
CITECDOT IN A NUTSHELL
CitecDot is a project lifecycle management solution that enables you to efficiently manage your deliverables, cut down costs, risks and delays - via a single platform.
Altamira information managed with CitecDot
Project descriptionn Alstom and Isolux are converting two units at the Altamira thermoelectric power station in Mexico to run on petroleum coke. The conversion project is aligned with the Mexican energy strategy as it will decrease 90 percent of the power station’s sulfur dioxide emissions.
Citec scopen Citec’s scope included management of document and material deliverables of the project with focus on the main and secondary structures of the boiler islands. Elements were identified with 2D barcode labels for easy tracking.
11
/2016
Citec solution n Alstom selected Citec as supplier largely because of project lifecycle management solution CitecDot - to secure traceability and quality control.
With the help of CitecDot, engineering documents were checked and approved by the design team in Italy and Estonia, doc control took place in India, approval for manufacturing was done in France, fabrication was spread over several factories in China, whereas the construction site is in Mexico.
A Citec representative was employed in China to support document management, quality control, labelling items, progress follow-up and expediting of steel structure elements. The progress and status of quality controls were animated in 3D.
CUSTOMER FEEDBACK
“In addition to the efficient way we can manage documents with CitecDot, we value the fact that we can follow the status of material items visually in a 3D model. It helps us to keep the project on track with good control of the engineering and manufacturing processes.”
- Alain Pouliguen, project manager, Alstom Boiler France
REF CardCITEC CUSTOMER REFERENCE
Project metrics
Documents 106 000
Structural elements 50 000 (18 000 different types)
Total weight of elements 6 000 tons (largest parts up to 32 tons)
Packages dispatched to site so far 1 439
Shipments from the factories 24