12

RECOMMENDED ACTION: Information Only X Recommended …...Authorize the General Manager to enter into an agreement with the Transbay Joint Powers Authority in substantially the form

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: RECOMMENDED ACTION: Information Only X Recommended …...Authorize the General Manager to enter into an agreement with the Transbay Joint Powers Authority in substantially the form

AC TRANSIT DISTRICT GM Memo No. 03-104a

Board of Directors

Executive Summary Meeting Date: April 17,2003

Committees:

Executive Committee □ Finance Committee □ External Affairs Committee □ Paratransit Committee □

Operations Committee □ Planning Committee D

Board of Directors X

SUBJECT: AUTHORIZE THE GENERAL MANAGER TO ENTER INTO AN

AGREEMENT WITH THE TRANSBAY JOINT POWERS AUTHORITY

REGARDING THE DESIGN, CONSTRUCTION AND OPERATION OF

THE NEW TRANSPORTATION TERMINAL

RECOMMENDED ACTION: □ Information Only X Recommended Motion

Authorize the General Manager to enter into an agreement with the Transbay Joint

Powers Authority in substantially the form as the attached agreement. The General

Manager is authorized to enter into such modifications, as he deems appropriate and

necessary.

Fiscal Impact:

While a specific dollar amount cannot be assessed at this time, the design, construction

and operation of the new terminal will impact the District's operating budget.

Background/Discussion:

On April 4, 2001, the Joint Powers Agreement, creating the Transbay Joint Power

Authority was formally executed by AC Transit, the Peninsula Corridor Joint Power

Board and the City and County of San Francisco. The purpose of the Authority is to

design, construct, and operate a new terminal at the site of the existing Transbay

Transit Terminal, together with necessary access ramps and parking/staging facilities.

BOARD ACTION: Approved as Recommended [ ] Other [X]

Approved with Modification(s) [ ]

Consensus to continue to June or as soon as Exhibit A of the agreement is available

(7-0-0-0).

The above order was passed and adopted on

April 17,2003.

Rose Martinez, District Secretary

By

Page 2: RECOMMENDED ACTION: Information Only X Recommended …...Authorize the General Manager to enter into an agreement with the Transbay Joint Powers Authority in substantially the form

GC Memo No. 03-104a

Subject: Authorize the General Manager to Enter into an Agreement with the Transbay

Joint Powers Authority Regarding the Design, Construction and Operation of the New Transportation Terminal

Date: April 17,2003

Page 2 of 3

Section 5 of the Agreement sets forth the powers of the Authority. Subsection 5(o) was

specifically included at the request of AC Transit to ensure that the District had a voice

in the design, construction and the operation of the terminal as it affected AC Transit.

"(o) [The Authority Is authorized to] enter into and approve agreements

and leases with the District to ensure that the design, construction and

operation of a new transportation terminal meet specific performance

criteria designed to maximize the usefulness of the facility for transit

operations and pedestrian circulation without increases in facility rental

costs."

A draft Agreement between the Authority and the District which would address AC

Transit's rights vis-a-vis the design, construction and operation of the new terminal has

been in existence for about two years. No action has been taken to bring it to the Board

because of the requirement that specific design criteria be identified.

Director Harper indicated at the March 6th Board meeting that the Authority was moving

forward with the design of the new terminal and requested that the agreement between

the Authority and the District be brought to the Board for action. The Board concurred

and directed that the agreement be placed on the March 20th agenda.

This item was continued from the March 20th meeting to the April 17th meeting in order to allow staff to meet with representatives of the JPA to work out some of the details of

Exhibit A. To date those discussions still have not occurred. If the content of Exhibit A to

the agreement can be agreed to prior to the Board meeting a revised Exhibit A will be

provided to the Board.

Even in the absence of agreement on Exhibit A, the Board can adopt the motion set

forth in this memo since it authorizes the General Manager to enter into the agreement

with those modifications he deems appropriate. As the Board can see from the Exhibit,

the issues are primarily technical issues, which the General Manager would have the

expertise to handle. If any significant deviation from the issues identified in the

agreement and the Exhibit occurred the Board could direct that those be brought back

to the Board for your consideration.

Page 3: RECOMMENDED ACTION: Information Only X Recommended …...Authorize the General Manager to enter into an agreement with the Transbay Joint Powers Authority in substantially the form

GC Memo No. 03-104a

Subject: Authorize the General Manager to Enter into an Agreement with the Transbay

Joint Powers Authority Regarding the Design, Construction and Operation of the

New Transportation Terminal

Date: April 17,2003

Page 3 of 3

Prior Relevant Board Actions/Policies:

GC Memo No. 02-294, Presented at November 7, 2002 Board Meeting

Resolution No. 984D, adopted February 15, 2001

Resolution No. 984C, adopted December 14, 2000

Resolution No. 984B, adopted January 27,1999

Resolution No. 984A, adopted October 8, 1997

Resolution No. 984, adopted February 12,1997

Attachments:

Proposed Agreement with exhibit

Approved by: Kenneth C. Scheidig, General Counsel

Prepared by: Kenneth C. Scheidig, General Counsel

Date Prepared: April 9, 2003

Page 4: RECOMMENDED ACTION: Information Only X Recommended …...Authorize the General Manager to enter into an agreement with the Transbay Joint Powers Authority in substantially the form

AGREEMENT

FOR DESIGN AND CONSTRUCTION AND OPERATION

OF TRANSBAY TRANSIT TERMINAL

The Terminal Joint Powers Authority, a joint powers authority created by the Alameda-

Contra Costa Transit District, the City and County of San Francisco and the Peninsula

Corridor Joint Powers Board - Caltrain ("Authority"), and the Alameda-Contra Costa

Transportation District, a special transit district organized under the California Public

Utilities Code ("AC Transit"), enter into this Agreement on the day of April 2003 to

specify the terms and conditions under which the parties will cooperate in the design,

construction and operation of a new Transbay Terminal in the City and County of San

Francisco.

WHEREAS, Authority intends to develop an intermodal regional transportation

center, together with necessary connecting ramps to the San Francisco-Oakland Bay

Bridge, on the site of the existing Transbay Transit Terminal in the City and County of

San Francisco, and;

WHEREAS, the development requires a multi-year design and construction

process, during which AC Transit operations at the existing Transbay Transit Terminal

must be moved to a temporary terminal site, and;

WHEREAS, the parties agree that the temporary terminal, and the permanent

terminal structure and associated facilities (including access ramps to and from the Bay

Bridge to the new terminal and necessary parking/staging areas), must be designed to

accommodate the operational needs of AC Transit and its riders; and

WHEREAS, the parties agree that well-designed performance criteria can

incorporate necessary transit performance standards while providing for flexibility in

design of both the temporary and permanent terminal facilities; and

WHEREAS, the parties recognize that this is the first in a series of agreements

and/or leases between them and that later agreements/leases will address the

continuing relationship between the parties regarding the use of the new terminal

facility, including limitations on rental increases;

NOW THEREFORE, in consideration of the faithful performance of the

terms, conditions, promises and covenants set forth in this Agreement, the

parties agree as follows:

Agreement for Design and Construction of Transbay Transit Terminal

March 18, 2003 (4:54pm)

Page 5: RECOMMENDED ACTION: Information Only X Recommended …...Authorize the General Manager to enter into an agreement with the Transbay Joint Powers Authority in substantially the form

A. Term

This Agreement shall become effective upon its execution by authorized

representatives of the parties and shall terminate immediately upon the

commencement by AC Transit of its transbay bus service at the new, permanent

terminal facilities, provided that the lease(s) referenced in Paragraph E are in

effect at that time and address the operational issues associated with AC

Transit's use of the new, permanent terminal facilities.

B. Initial Design Criteria

1. The Design Criteria, attached as Exhibit A, include all the design elements

required for AC Transit to operate effectively and efficiently at the

temporary terminal site and at the permanent terminal building. This

means that the ability of AC Transit to serve its customers and to operate

its transbay service in a manner which continues to ensure that it remains

a reasonable transportation alternative to downtown San Francisco and is

within AC Transit's budgetary limits will not be adversely affected by the

design of either the temporary or permanent design terminal facility.

As used herein, Design Criteria shall consist of specifications and

standards that are quantifiable and definite. Objections to the plans,

drawings, or construction deviations must be based on a tangible violation

of a specific Design Criterion applicable to the terminal facilities and

cannot be speculative, aesthetic, or based on a general sense of the

development project goals and objectives.

2. The temporary terminal, all space allocated to AC Transit within the

permanent terminal, the bus ramps associated with the permanent

terminal and the parking/storage facility and ramps (together the "terminal

facilities") shall be designed and constructed in accordance with the

Design Criteria to facilitate effective and efficient AC Transit operations.

Except as provided in this Agreement, Authority shall not approve any

design changes or construction changes which violate any of the Design

Criterion.

3. The Design Criteria may be amended or supplemented from time to time

by agreement of the parties, and must be amended or reapproved

whenever a change in the facility design or a proposed construction

change would violate the Design Criteria or any approved amendments to

the Design Criteria, as provided herein. Neither party may unilaterally

amend, supplement or delete the Design Criteria or any approved

Agreement for Design and Construction of Transbay Transit Terminal

March 18, 2003 (4:54pm)

Page 2

Page 6: RECOMMENDED ACTION: Information Only X Recommended …...Authorize the General Manager to enter into an agreement with the Transbay Joint Powers Authority in substantially the form

amendment either directly in writing, or indirectly by changing a design

drawing or approving construction change order.

E. Copies of this Agreement shall be included with any Requests for Proposals

or bid documents issued by the Authority, and referenced in any design

contacts or construction contracts executed by the Authority.

C. Design Document Review Process

1. The Authority and AC Transit each shall designate and authorize one

individual of its choice, and one alternate, to act on its behalf for the

mutual approval of amendments, additions, modifications or deletions to

the Design Criteria or any previously approved changes to them. Notice

to the designated individuals shall be in writing, addressed as provided in

Paragraph F and shall be effective notice to the designating party.

2. The Authority shall prepare all initial designs and preliminary plans for the

terminal facilities to meet the Design Criteria. The Authority shall not

approve any final design development plans, final schematic drawings, or

final construction drawings of the terminal facilities without consulting AC

Transit to determine whether such plans or drawings violate any of the

Design Criterion, or amendments thereto. AC Transit's representative

shall determine if the aforementioned plans and/or drawings are

consistent with the Design Criteria, and any amendments to it, as promptly

as possible under the circumstances so that the development process

may proceed without delay. However, if AC Transit determines that the

aforementioned plans and/or drawings are not consistent with the Design

Criteria, and any amendments to it, the Authority shall be advised as

promptly as possible under the circumstances. No further work on the

plans and /or drawings may proceed until AC Transit is satisfied with the

proposed change or modification.

3. The parties shall meet on a regular basis, and promptly upon the request

of either party, to review the design documents, construction documents

or proposed changes against the Design Criteria. The parties shall also

meet at the following designated intervals during the design process to

review the plans for consistency with the Design Criteria:

As each stage reaches 25%, 50%, 75% and 100% of final design.

Agreement for Design and Construction of Transbay Transit Terminal

March 18, 2003 (4:54pm)

Page 3

Page 7: RECOMMENDED ACTION: Information Only X Recommended …...Authorize the General Manager to enter into an agreement with the Transbay Joint Powers Authority in substantially the form

D. Construction Review Process

1. Construction of the terminal facilities shall be in accordance with the plans

reviewed and approved by the parties for consistency with the Design

Criteria and may proceed without further consultation under this

Agreement, except as otherwise provided for in this Agreement.

2. Prior to the commencement of construction of the terminal facilities AC

Transit shall review all design and construction plans relating to the

terminal facilities, and may comment on whether a plan or drawing

violates any of the Design Criterion, if AC Transit objects that a plan or

drawing for the terminal facilities violates any of the Design Criteria, the

parties shall meet and either:

a) Change the plan or drawing as necessary to conform to the Design

Criteria; or

b) Change the Design Criteria to accommodate the plan or drawing; or

c) Agree that the objection may be withdrawn.

The Authority shall not approve a terminal facilities plan or drawing or

continue with construction over a Design Criterion objection until the

objection is resolved, although nothing in this Agreement shall prohibit the

Authority from continuing with other portions of the development which are

not affected by the Design Criterion objection while attempting to resolve a

specific Design Criterion objection.

Nothing herein shall preclude AC Transit from raising a Design Criteria

objection at any other time during the construction of the terminal facilities.

3. AC Transit may have a representative present at the site of the work

during the progress of the construction to review the progress of the work

and to keep itself informed of compliance by the contractor with the

Design Criterion. If AC Transit chooses to have an on site representative,

this shall not relieve Authority of its obligations as contained in this

Paragraph D. If AC Transit's on site representative identifies any work,

which is not consistent with the approved design plans and/or drawings,

he/she shall notify the Authority's representative identified in Paragraph F

of this fact and the Authority shall comply with the provisions of

Subparagraph D.6.

4. Authority shall promptly provide written notice to AC Transit's

representative identified in Paragraph F, or his/her alternate, of any

construction proposals, which substantially deviate from the approved

Agreement for Design and Construction of Transbay Transit Terminal

March 18, 2003 (4:54pm)

Page 4

Page 8: RECOMMENDED ACTION: Information Only X Recommended …...Authorize the General Manager to enter into an agreement with the Transbay Joint Powers Authority in substantially the form

construction drawings for the terminal facilities before any work in the

affected area proceeds. A deviation shall be regarded as "substantial" if

Authority's engineers, or AC Transit's representative, reasonably believe

that the deviation violates the Design Criteria for the terminal facilities.

Upon receipt of the written notice AC Transit shall respond promptly,

based on the circumstances, to all requests for consultation on unplanned

construction problems.

5. The Authority shall not approve any substantial deviations from approved

construction drawings without written agreement of AC Transit. If the

parties agree to the unplanned deviation to the terminal facilities' plans

because of an amendment to the Design Criteria, the amendment shall be

expeditiously reduced to writing and added to Exhibit A.

6. Regardless of the existence of an on-site AC Transit representative, the

parties shall meet on a regular basis, and promptly upon the request of

either party, to review the design documents, construction documents or

proposed changes against the Design Criteria. The parties shall also

meet at the following designated intervals during the construction process

to review the plans for consistency with the Design Criteria:

As each stage reaches 25%, 50%, 75% and 100% of construction.

E. Operation of the Terminal Facilities

Prior to the completion of the terminal facilities and its availability for use

by the parties, Authority and AC Transit shall enter into one or more

leases which will provide for the use of the facilities at a rental rate

commensurate with the rental rate AC Transit pays for use of the existing

Transbay Transit Terminal. In addition, the lease agreement shall provide

a mechanism for the approval by AC Transit of any modifications,

alternations, changes or improvements to the terminal facilities which

affect or impact the use, efficiency, effectiveness or delivery of AC

Transit's transbay service to the terminal facilities.

F. Identification of Representatives and Notice

The representatives and alternates for the Authority and AC Transit are

set forth below. All notices required by this Agreement shall be given to

each representative and alternate by any of the following means: in writing

hand delivered to the individual, by facsimile, by e-mail or any combination

of the forms of notice. It is the responsibility of the party providing the

notice to ensure that the notice has been given and received. Nothing

Agreement for Design and Construction of Transbay Transit Terminal

March 18, 2003 (4:54pm)

Page 5

Page 9: RECOMMENDED ACTION: Information Only X Recommended …...Authorize the General Manager to enter into an agreement with the Transbay Joint Powers Authority in substantially the form

herein shall prevent the parties from contacting each other by telephone to

confirm the receipt of a notice provided by other electronic or manual

means as provided above.

FOR THE DISTRICT

Anthony Bruzzone

Special Projects Manager

Alameda-Contra Costa Transit District

1600 Franklin Street

Oakland, CA 94612

Alternate:

FOR THE TRANSBAY JPA

Maria Ayerdi

Executive Director

Transbay Joint Powers Authority

1 Dr. Carlton B. Goodlett Place, Room

448 San Francisco, California 94102

Alternate:

G. Miscellaneous

1. This Agreement has been entered into in the State of California and shall

be interpreted in accordance with the laws of the State of California.

2. The waiver by either party to any deviation of this Agreement shall not

constitute a waiver of compliance with the terms of this Agreement or prevent

any party from seeking appropriate legal proceedings to enforce the terms

of this Agreement.

3. The parties represent that the individuals whose signatures appear at the

end of this document as signatories are authorized by their respective

agencies to enter into this Agreement on behalf and to bind their agencies to

the terms of this Agreement.

Agreement for Design and Construction of Transbay Transit Terminal

March 18, 2003 (4:54pm)

Page 6

Page 10: RECOMMENDED ACTION: Information Only X Recommended …...Authorize the General Manager to enter into an agreement with the Transbay Joint Powers Authority in substantially the form

THIS AGREEMENT is executed by the parties below as of the day and date

identified at the beginning of this Agreement.

FOR THE DISTRICT FOR THE TRANSBAY JPA

Agreement for Design and Construction of Transbay Transit Terminal

March 18, 2003 (4:54pm)

Page 7

Page 11: RECOMMENDED ACTION: Information Only X Recommended …...Authorize the General Manager to enter into an agreement with the Transbay Joint Powers Authority in substantially the form

Exhibit A

Design Criteria

Transbay Transit Terminal and Associated Ramps

The following elements are the minimum required to allow for efficient bus operations at the Transbay Transit Terminal:

General Requirements

Turning Radius -The minimum inside turning radius shall be 28 feet, and the minimum

outside turning radius shall be 60 feet.

Heights - The minimum clearance shall accommodate a vehicle of not less than 14 feet in height.

Widths - The minimum clearance shall accommodate a vehicle of not less than 102

inches.

Ramp System

Minimum Width - All ramps shall be at least 20 feet wide, provided that in a constrained

location on a downslope of more than 3 percent, a 15 foot wide ramp shall be

acceptable.

Maximum Grade - No ramps shall exceed a 5 percent grade. In constrained locations

an upslope ramp of 8 percent is acceptable for not more than 500 feet, and a downslope

ramp of 10 percent is acceptable for not more than 500 feet; provided buses do not

"bottom-out."

Terminal Chute - Immediately outside the terminal structure and on the ramp structure,

a staging area for not less than ten 45 foot buses shall be provided. Within this staging

area a minimum width of 15 feet and a minimum length of 45 feet shall be provided for

each bus. Independent movement within the staging area is not required.

Storage

Minimum Storage - The storage facilities and ramp structures shall, in total,

accommodate not less than 70 buses for storage not to exceed 12 hours.

Storage Arrangement -Within the storage facility, the design shall allow for independent

movement unless a tandem parking pattern is used. Should a tandem pattern be used,

it will be limited to two buses in any one stall.

Staging Operation with Storage Facility - Within the storage facility, the design shall

provide a dedicated queuing area for not less than nine 45 foot buses, from which transit

operating personnel could dispatch buses into the terminal.

April 10, 2003

Page 12: RECOMMENDED ACTION: Information Only X Recommended …...Authorize the General Manager to enter into an agreement with the Transbay Joint Powers Authority in substantially the form

Access from Bay Bridge - Access from the San Francisco-Oakland Bay Bridge into the

bus storage facility shall not require circulation through the Terminal Building or on city

streets.

Operator Rest Facilities -Within the storage facility, a dedicated operator lounge, rest

room facilities, and dispatching office shall be provided.

Terminal Building

Bus Stops -Within the Terminal Building, AC Transit shall be allocated not fewer than

26 85 foot bus boarding locations and four 60 foot bus boarding locations. These

locations shall total not less than 1,200 linear feet of bus platform on each side of a

center platform facility (total of 2,400 linear feet of bus platform). The design shall allow

for more bus boarding locations for smaller buses, up to a total of 26 locations on each

side of the center platform, within the 2,400 linear feet. The platform have an eight inch

height relative to the roadway level. AC Transit reserves the right to cooperatively work

with the Authority and its staff and consultants on the actual operation of bus facilities,

including a provision for a dedicated passenger drop-off only location.

Bus Operations - Buses shall operate clockwise around a center passenger boarding

platform, with a direct, grade-separated connection to and from the San Francisco-

Oakland Bay Bridge. Within the terminal structure, buses shall be provided not less than

two travel lanes plus the boarding lane.

Transit Supervision - A bus operations supervision office shall be provided where the

bus ramps enter the terminal building, and an additional booth and operator restroom

shall be located on the bus passenger platform.

Passenger Facilities - The passenger center platform shall be a minimum of 50 feet

wide, enclosed, naturally light, climate controlled, and physically separated from bus

traffic. Automatic doors shall be provided to allow access from the passenger platform

to the front, middle, and rear doors of the buses; these doors shall be designed to

relocate should AC Transit decide to change the length, number and location of bus

boarding zones. Restroom may be located on the concourse level, one level below,

according to applicable law and regulations. The design of the passenger facility shall

provide for designating the bus platform a "paid" area, either through the provision of a

proof-of-payment system or through controlled entry on the concourse level. Ticketing

facilities shall be provided on the concourse level, both for a manned ticket office and for

ticket vending machines.

Internal Circulation - The vertical circulation system of stairs, escalators and elevators

shall be designed to move not less than 18,000 passengers in a one hour period.

Passenger Information -The facility design shall provide for remotely operated

changeable message signs at each potential door location of the bus platform.

Security - Column spacing, lighting and policing offices, facilities and equipment shall be

incorporated into the design of the passenger bus platform to ensure a safe and secure

environment.

April 10, 2003