Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
REALISEGRID: towards a panREALISEGRID: towards a pan--European European transmission networktransmission network
Gianluigi MigliavaccaRSE S.p.A.
Project Coordinator
Seminar at the Florence School of Regulation – 24th February 2011
24-02-2011 2TREN/FP7/EN/219123/REALISEGRID
Presentation outline Presentation outline
Challenges of the grid: 2020 and beyond
The project REALISEGRID
“Smart” transmission technologies
Prioritizing transmission investments
Tackling the consensus problem
24-02-2011 3TREN/FP7/EN/219123/REALISEGRID
1. Challenges of the grid: 2020 and beyond
24-02-2011 4TREN/FP7/EN/219123/REALISEGRID 4TREN/FP7/EN/219123/REALISEGRIDTREN/FP7/EN/219123/REALISEGRID
Challenges for the panChallenges for the pan--European European transmission grids for 2020 and beyondtransmission grids for 2020 and beyond
Integration of very large amounts of variable RES, while keeping network security and reliability at acceptable levels
Renewable generation exceeding local needs at a given time, requiring transport elsewhere
Increasing role of active demand and distributed generation to relieve stress on European electricity system
Liberalization of market inducing increased cross-border power exchanges rising uncertainties and congestion problems
European electricity grids are on the critical path to meet the EU climate change and energy policy objectives
Aging of the present transmission grid; difficulties to get consensusfor building new overhead lines
24-02-2011 5TREN/FP7/EN/219123/REALISEGRID
How increasing wind penetration can affect grid congestionHow increasing wind penetration can affect grid congestion
High windscenarios
• Congestion becomes a pan-European problem. Planning should be coordinated between the TSOs
• Frequent flow changings heavily affect operationand require a coordinated approach
Low windscenarios
High windpotentials
Low windpotentials
Hydro
24-02-2011 6TREN/FP7/EN/219123/REALISEGRID
European European SupergridsSupergrids: horizontal and vertical concepts: horizontal and vertical concepts
Growing support in Europe to the creation of supergrids, connectingmany offshore wind farms in several Member States, so as tomaximize the utilization of RES and reduce the impact on the transmission backbones:
• Vertical: creating a north-south interconnection to ease delivering RES power (around the North Sea) and the big customer centers in the central and southern part of Europe. Two approaches:
– Expanding the current transmission backbones– Creating dedicated highways (concept of overlay network from the recent
Energiekonzept document of the German Bundesregierung)
• Horizontal: interconnecting off-shore and providing a multi-point docking to the AC backbones. Some pilot projects:
– Kriegers Flak connecting 1800 MW between Denmark, Sweden (nowstepped-out) and Germany, €150mil. financing from EC in 2009 for pre-feasibility
– North Sea Offshore grid project connecting 70 GW offshore wind among 9 Countries. In December 2009, it was decided that the ISLES project will carryout a feasibility study. Investments should amount to €30bil.
24-02-2011 7TREN/FP7/EN/219123/REALISEGRID
Connection or interconnection between different grids can be realized both in AC or DC with submarine or land cables. The choice of the AC or DC solution is depending on the power to be transmitted and on the length of the circuit.
AC or DC?AC or DC?
24-02-2011 8TREN/FP7/EN/219123/REALISEGRID
DesertecDesertec SuperGridSuperGrid
Transfer Capacity
Energy Transfer
HVDC investment costs
Source: Desertec
24-02-2011 9TREN/FP7/EN/219123/REALISEGRID
The EU Energy Policy (1/2)The EU Energy Policy (1/2)
• Green Paper “A European Strategy for competitive, sustainable and secure energy” (2006)
• Communication “An Energy Policy for Europe” (2007)• Communication on Strategic Energy Technology Plan
(SET-Plan, 2007)• Climate and Energy Package (2008) and Directive
2009/28/EC• Third Liberalization Package (2009) and Directive
2009/72/EC• Communication “A strategy for competitive,
sustainable and secure energy” (2010)• Communication “Energy infrastructure priorities for
2020 and beyond. A blueprint for an integrated European energy network” (2010)
Support climate change mitigation:• reducing CO2 emissions;• promoting green generation;• boosting efficiency in the consumption (energy saving)
Increase security of supply
Promote competition:• eliminating cross-border bottlenecks;• harmonizing market regulation throughout Europe;• promoting the creation of a common Internal Energy Market
the PIP (Jan.2007) underlined that electricity and gas networks are the “heart” of a well-functioning energy market;The Second Strategic Energy Review (Nov.2008) clarified that EU will never realize its objectives unless the grid will be soon significantly expanded.Green Paper “Towards a secure, sustainable and competitive European energy network” (Nov.2008)
24-02-2011 10TREN/FP7/EN/219123/REALISEGRID
TEN-E Guidelines: 32 projects labeled as “of European interest”: only 19% is completed, 5% under construction, 76% in the authorization path and/or in study. Bottom-up fixed-list approach failed!Communication: “A strategy for competitive, sustainable and secure energy”: defines five priorities for energy strategy, among which “building a truly integrated energy market”. To achieve it:• Action 2: establishing a blueprint of the European
infrastructure for 2020-2030, • Action 3: streamlining permit procedures, • Action 4: providing the right financial framework.
Communication “Energy infrastructure priorities for 2020 and beyond”: new methodology not based on bottom-up contributes of the TSOs but on a shared methodology for prioritizing projects on the basis of European priorities at 2020 (four corridors for electricity, three for gas) and a long-term perspective of a smart-supergrids continental interconnection. Improvement permitting and consensus. Set up of new financial instruments.
The EU Energy Policy (2/2)The EU Energy Policy (2/2)
24-02-2011 11TREN/FP7/EN/219123/REALISEGRID
Need to invest in the transmission gridNeed to invest in the transmission grid
The last years: demand increase vs reduced grid developmentIt is generally agreed that new investments are needed, motivated on the basis of a technical-economical evaluation comparing costs with benefits for the system (market competitiveness, interests of consumers and other market players)
24-02-2011 12TREN/FP7/EN/219123/REALISEGRID
2. The Project REALISEGRID
24-02-2011 13TREN/FP7/EN/219123/REALISEGRID
The project REALISEGRID (The project REALISEGRID (http://realisegrid.rsehttp://realisegrid.rse--web.itweb.it))
The ultimate objective of REALISEGRID is to develop a set of criteria, metrics, methods and tools to assess how the transmission infrastructure should be optimally developed to support the achievement of a reliable, competitive and sustainable electricity supply in the EU
Research centers and universitiesRSE (I), Coord & WP3Politecnico di Torino (I), WP2Technische Universiteit Delft (NL)Technische Universität Dortmund (D)Technische Universität Dresden (D)EC Joint Research Centre - Inst. EnergyUniverza v Ljubljani (SL)The University of Manchester (UK)Observatoire Méditerranéen Energie (F)R&D Center for Power Engineering (RU)Vienna University of Technology, EEG (A)
TSOs• RTE (F)• APG (A)• Terna (I)• TenneT (NL)
Industry• Technofi (F), WP1• ASATREM (I)• KANLO (F)• Prysmian (I)• RIECADO (A)
24-02-2011 14TREN/FP7/EN/219123/REALISEGRID
Identification of technical performances, economic benefits and costs of novel technologies aimed at increasing capacity, reliability and flexibility of the transmission infrastructure
Definition of long term scenarios for the European power sector, characterized by different evolutions of demand and supply, such as the integration of a large amount of intermittent renewable energy sources (e.g. wind power), meeting specific targets concerning security of supply and sustainability
Implementation of a framework to facilitate harmonisation of pan-European approaches to electricity infrastructure evolution and to evaluate benefits of transmission investments
Activities of REALISEGRIDActivities of REALISEGRID
24-02-2011 15TREN/FP7/EN/219123/REALISEGRIDModeling toolsModeling tools
RegulationRegulation
Planning PracticePlanning Practice
Testing BedTesting Bed
Work Package 3 Work Package 3 ““Transmission investmentsTransmission investments””
WP3WP3.1 Analyzing current practice
and developing a robust set of criteria for improved
transmission planning in presence of a large penetration
of RES-E generation
WP3.2 Evaluate bottlenecks and investment needs in cross-
border capacities in the European Electricity markets
WP3.3 Set up a methodology and a supporting tool to carry out
multi-criteria cost-benefit analysis supporting the
development of trans-European transmission infrastructure
WP3.4 Creation of a tool to support coordinated investment in
electricity and gas infrastructure
WP3.5 Validation of the cost-benefit methodology set up in
WP3.3 on a real case concerning the TEN-E priority axis EL2
WP3.6 analyzing the impact of regulation and incentive
mechanisms on transmission investment
WP3.7 deriving a benefit-based approach to improve consensus
on new infrastructures
24-02-2011 16TREN/FP7/EN/219123/REALISEGRID
3. “Smart” transmission technologies
24-02-2011 17TREN/FP7/EN/219123/REALISEGRID
A collective scan toolA collective scan tool
Collective discussionlevel of convergence
Collective workshops
Technical andscientific
literature review
TSOs knowledge
Cost Benefit Analysis
REALISEGRID technology
experts
PASSIVE EQUIPMENT
ACTIVEEQUIPMENT
RT MONITORING EQUIPMENT
EQUIPMENT IMPACTING on
TSOs OPERATION
SHORT LIST for WP3
Performance (security and stability)
Barriers (maturity and accesibility)1st LISTof promising technologies SCAN criteria
Transmission technologyRoadmap
REFINED LISTof promising
techologies in four clusters
24-02-2011 18TREN/FP7/EN/219123/REALISEGRIDTREN/FP7/EN/219123/REALISEGRID
Identifying Identifying ““smartsmart”” transmission technologies transmission technologies Inclusion principle: technologies potentially helpful for TSOsand possibly interacting with the transmission planning
24-02-2011 19TREN/FP7/EN/219123/REALISEGRID
Potentials analysis for the selected technologies Potentials analysis for the selected technologies
Techno‐economic challenges
2010‐2020 2020‐2030 2030‐2040
Full scale use within the EU27 interconnected transmission system
Technology n
RD&D as seen by manufacturers
Integration tests as seen by TSOs
An An actionaction agenda agenda waswas filledfilled in in forfor eacheachtechnologytechnology, , usingusing TSO and TSO and manufacturersmanufacturersinformationinformation
0
1
2
3
4
5
Increased system reliability
System losses reduction
Extended power flow controllability
Increased transmission capacity
Reduced environmental impact
Benefits from technology XX integration replacing conventional solutions
Reference: Conventional HVAC network
P1: technology XX
A qualitative A qualitative benefitsbenefits evaluationevaluation waswas addedadded
24-02-2011 20TREN/FP7/EN/219123/REALISEGRID
1 HTC . Advanced designs for high current carrying capacity, reduced weight, l ine sags and corrosion for high temperature conductors
14 PST . Increase response time at an acceptable cots thanks to power electronics
5 RTTR . Interoperable RTTR system combined with short‐term weather forecasts for OHL monitoring
2 HTC . Evaluation of the long‐term reliabil ity of cables reconductored with HTC (ageing models, endurance testing)
15 PST . Inter‐TSO standardisation of PST modelling 6 RTTR Industrialization of RTTR systems for underground/submarine applications
3 HTC . Improved HTC maintenance based on HTC ageing models and operations
16 PST . Coordinated use of PST (coordination centers in Europe)
7 RTTR . Combined use of RTTR, PST and WAMS to control highly congested areas
4 HTC . Exploration of new materials (nano materials for conductors) 17 PST . Large scale experiments of fast response time PST in Europe (TCPST)
8 RTTR . Grid optimization using RTTR at EU level
19 UG/Submarine XLPE cables
. New materials for reduced thickness of cable section (reduce number of junctions)
18 PST . Implementation of fast response time PST in Europe (TCPST)
9 WAMS . Improved WAMS signal accuracy and standards development
20 UG/Submarine XLPE cables
. Advanced installation techniques for installation costs reduction (incl. design of accessories)
30 HVDC . Improved efficiency of VSC based on new switching topologies
10 WAMS . Development of standards for WAMS algorithms
21 UG/Submarine XLPE cables
. Improved commissioning based on fast qualification methods and field applications
31 HVDC . Development of MTDC (Multiterminal HVDC) and exploration of meshed HVDC configurations
11 WAMS . Evaluation of WAMS benefits based on full scale demos by TSOs
22 UG/Submarine XLPE cables
. Innovative cable materials (carbon nano‐tube) for improved performances
32 HVDC . Extended domain of use of HVDC (far‐offshore, ultradeep, ultravoltage)
12 WAMS . Wide use of WAMS in Europe to monitor/control inter‐area power oscillations
23 UG/Submarine XLPE cables
. Automated underground cable installation and remote sensing system for O&M
33 HVDC . New types of semiconductors for a new generation of thyristors (Sil icium carbide, Gall ium nitride, diamond)
13 WAMS . Use of WAMS data for control issues (WACS) by some TSOs
24 UG/Submarine XLPE cables
. Integration of dynamic l imits into system operation procedures and tools
34 HVDC . Test of selected options of MTDC for HVDC backbone in Europe combining VSC and CSC
25 UG/Submarine XLPE cables
. Carbon nanotubes used in transmission system 35 HVDC . Superconducting DC cable transmission (SCDC)
26 GILs . New generation of GIL with enhanced safety in operation (reduced corrosion, gas mixtures with lower SF6 content) and improved installation techniques for cost reduction
36 HVDC . Deployment of an MTDC backbone in Europe
27 GILs . Assessment of GILs performances in operation based on historical data and models and comparison with possible alternative solutions for TSOs (OHL; XLPE)
42 FACTS . Improved performance of FACTS based on new power electronic topologies and semiconductors
28 GILs . Field tests of long‐distances applications based on N2/SF6 mixtures
43 FACTS . Development of standards for FACTS
29 GILs . Implementation of GIL based solutions as underground technologies to enter densely populated areas
44 FACTS . Virtual Man‐Machine interface for grid operators
37 HTS cables . Development of more efficient and affordable (costs and size) cryogenic refrigeration system
45 FACTS . New types of semiconductors replacing sil icon (Si licium carbide, Gallium nitride, diamond)
38 HTS cables . Commercial exploitation of 2nd generation of HTS materials (YBCO and advanced deposition techniques) in 2020
46 FACTS . Significant deployment of FACTS (shunt) used for voltage control issues in Europe
39 HTS cables . Demonstration of superconducting cables for novel network architecture
47 FACTS . Significant deployment of both shunt and series FACTS used for power flow controllability in Europe
40 HTS cables . HTS cables are field‐tested for niche applications (short distance transmission in dense urban area, DC applications)
51 FCLs . Common testing facil ities among European TSOs (based on agreed testing standards)
41 HTS cables . Field tests of HTS cables for long‐distance applications 52 FCLs . Reduced costs and losses of FCLs
48 Innovative Towers
. Eco‐design of towers reducing the environmental impacts (visual, corrosion, ageing) combined with increased mechanical and electricity transfer characteristics (design of towers and composite materials)
53 FCLs . Demonstration of relocatable FCLs
49 Innovative Towers
. Common TSO RD&D laboratory on tower modelisation issues 54 FCLs . Combined use of FCL and superconductivity
50 Innovative Towers
. Deployment of innovative towers using composite materials allowing increased transmission capacity
The final roadmap The final roadmap
24-02-2011 21TREN/FP7/EN/219123/REALISEGRID
FACTS, PST, HVDCFACTS, PST, HVDC
Transmission capacity increase
Upgrade to 380kV possible?
Upgrade equipment to
380kV
Ampacity upgrade possible?
Conversion to HVDC feasible?
Change overhead
conductors
Convert to HVDC
New transmission capacity sufficient?
Built new line
done
Yes
No
Yes
Yes
No
No
Yes
No
24-02-2011 22TREN/FP7/EN/219123/REALISEGRID
Issue Problem Corrective action Conventional solutions
Most appropriate FACTS/HVDC solutions
Low voltage at heavy load Supply reactive power Shunt capacitor, series
capacitor SVC, STATCOM, TCSC, SSSC, UPFC, VSC-HVDC
Remove reactive power supply
Line disconnection, shunt capacitor
SVC, STATCOM, SSSC, UPFC, VSC-HVDC High voltage at
low load Absorb reactive power Shunt capacitor disconnection, shunt reactor
SVC, STATCOM, SSSC, UPFC, VSC-HVDC
High voltage after outage Absorb reactive power Shunt reactor SVC, STATCOM, SSSC,
UPFC, VSC-HVDC
Supply reactive power Shunt capacitor, reactor, series capacitor
SVC, STATCOM, TCSC, SSSC, UPFC, VSC-HVDC Low voltage after
outage Prevent overload Series reactor, series capacitor, PST
TCSC, SSSC, TCPST, UPFC, VSC-HVDC, CSC-HVDC
Voltage level
Low voltage and overload
Supply reactive power and limit overload
Combination of series reactor/capacitor and PST
TCSC, SSSC, UPFC, VSC-HVDC
Line/transformer overload Reduce overload New lines/transfomers,
series reactor/capacitor TCSC, SSSC, TCPST, UPFC, VSC-HVDC
Thermal limits Tripping of parallel circuit (line)
Limit circuit (line) loading
New series reactor/capacitor
TCSC, SSSC, UPFC, VSC-HVDC
Adjust series reactance Series capacitor/reactor TCSC, SSSC, TCPST, UPFC, VSC-HVDC, CSC-HVDC Parallel line load
sharing Adjust phase angle PST SSSC, TCPST, UPFC, VSC-HVDC Loop flows
Flow direction reversal Adjust phase angle PST SSSC, TCPST, UPFC, VSC-
HVDC
Short circuit levels
Excessive breaker fault current
Limit short circuit current
Series reactor, new circuit breaker, fault current limiter
TCSC, SSSC, UPFC, VSC-HVDC
Subsynchronous resonance
Potential turbine/generator shaft damage
Mitigate oscillations Series compensator TCSC, SSSC, UPFC
Cost range System component Voltage level Power rating min max
Unit
Phase Shifting Transformer (PST) (1) 400 kV 100..1600 MVA 10 40 kEUR/MVA
Fixed Series Capacitor (FSC) (1) 400 kV 100..1000 MVAR 10 20 kEUR/MVAR
SVC 400 kV 100..850 MVAR 30 50 kEUR/MVAR STATCOM 400 kV 100..400 MVAR 50 75 kEUR/MVAR TCSC 400 kV 25..600 MVAR 35 50 kEUR/MVAR SSSC 400 kV 100..400 MVAR 50 80 kEUR/MVAR TCPST (TCQBT) 115 kV..220 kV 50..150 MVA 12 70 kEUR/MVA UPFC 400 kV 100..325 MVA 90 130 kEUR/MVA
HVAC OHL, single circuit(2) 400 kV 1500 MVA 400 700 kEUR/km HVAC OHL, double circuit(2) 400 kV 2×1500 MVA 500 1000 kEUR/km HVAC underground XLPE monopolar cable 400 kV 1000 MVA 1000 3000 kEUR/km HVAC underground XLPE bipolar cable 400 kV 2×1000 MVA 2000 5000 kEUR/km Reactive power compensation for HVAC monopolar cable 400 kV - 15 15 kEUR/MVAR
(1) Related device, not to be considered as FACTS. (2) Cost ranges correspond to the base case, i.e. installation over flat land. For hilly landscape +20% and +50% for installations over mountains or urban areas have to be factored in.
FACTS, PST, HVDCFACTS, PST, HVDC
24-02-2011 23TREN/FP7/EN/219123/REALISEGRID
Smart transmission VS distribution technologiesSmart transmission VS distribution technologies
DG penetration in an electricity system [MWDGinst]
Towards fully active and smart distribution grid
Status quo of transmission grid
Moderate transmission grid expansion
Significant transmission grid expansion
Cost of “smart” technologies and components to be implemented on distribution grid level [€ / MWDGinst]
Transmission grid expansion
New information, communication, control and data management systems
Bidirectional load flow management devices
Fully autonomous and intelligent “cells” on distribution grid level
24-02-2011 24TREN/FP7/EN/219123/REALISEGRID
4. Prioritizing transmission investments
24-02-2011 25TREN/FP7/EN/219123/REALISEGRID
Transmission planning processTransmission planning processScenarios
development
Security analysis
Security criteria
met?No expansion
Y
NIdentification of
first, broad group of solutions
Techno-economic
assessment
Environmental/ social
assessment
Final ranking of solutions
Identification of second, restricted group of solutions
Decision making
Cost-benefit analysis
Traditional approach
REALISEGRIDproposedapproach
REALISEGRID integratedanalysis of investments(welfare optimal and traditional reliability/security)
cost-benefit
Candidates selection
24-02-2011 26TREN/FP7/EN/219123/REALISEGRID
Overview of the methodology: what, why, howOverview of the methodology: what, why, how
Cost-benefit assessment for new transmission infrastructure investments
WHATWHAT
• Methodology for prioritizing alternative investments both at national and trans-national level (see Infrastructure Package)• Possible KPI for establishing a dynamic addendum to the ROI ofthe TSOs• Information to the public on system advantages from new infrastructure as well as about inaction cost
WHYWHY
• OPF analysis with and without the new investment (or series of investments constituting a corridor)• The tool has to be able to take into account the reliability of both network elements and generators as well as the variable behaviorof wind generators• New elements like PSTs and HVDC lines have to be correctly represented
HOWHOW
24-02-2011 27TREN/FP7/EN/219123/REALISEGRID
MultiMulti--criteria analysis: general theorycriteria analysis: general theory
Top-down criteria tree, evaluation matrix, utility functions, weights
Root
Group 1 Group 2
Sub-Group 11
Sub-Group 12
… Sub-Group 21
Sub-Group 22
…
Alternative 1 Alternative 2 …
Criterion 1
Criterion 2
…
1
Utility function translates: into [0 1] or into monetary terms (better)
Avoid double-counting!
24-02-2011 28TREN/FP7/EN/219123/REALISEGRID
The adopted methodologyThe adopted methodology
Transmission expansion benefits
Competitiveness
RES exploitation
Emissions savings
External costs reduction
Fossil fuel costs reduction
Reliability increase
Congestions reduction
Market competitiveness increase
Losses reduction
Security of energy supply
Environmental sustainability
Utility function translation into monetary terms
Weighted sum translation a mono-dimensional ranking
€Solution A Solution B Solution C
Sensitivity analysis on weighing factors needed
Years0
Authorization phase Building phase
RoWRoW
Amortization phase
II
ΔB1,t1
ΔB2,t1
…
ΔB1,t2
ΔB2,t2
…
ΔB1,tn
ΔB2,tn
…
ΔB1,t1
ΔB2,t1
…
ΔB1,t2
ΔB2,t2
…
ΔB1,tn
ΔB2,tn
…
NPVNPV00NPVNPV00
CCCCCC
C
CC CCCCCC
C
CC
24-02-2011 29TREN/FP7/EN/219123/REALISEGRID
The tool: REMARKThe tool: REMARKMain features:• Detailed model of the network: nodes, lines, transformers,
generators, loads• Three types of generation: fixed, random variable (wind),
dispatchable• Fixed hourly nodal load• Non-sequential Montecarlo-based combination of:
unavailability of lines, transformers, generators [hours/year] maintenance schedules for generators [weeks/year]statistical profile of wind generation (cumulative prob. distribution
curve)Each run corresponds to a random extraction of one hour
• Geographic system/market zones subdivision• OPF solution of the mixed AC/DC grid is calculated through a
simplified DC methodOptimisation objective:
• Maximisation of Social Welfare (if bid-ups are available) or• Minimisation of variable operating costs (sum of production
costs and load shedding costs)
24-02-2011 30TREN/FP7/EN/219123/REALISEGRID
• Lienz (AT) - Cordignano (IT)• New interconnection between Italy and
Slovenia• Udine Ovest (IT) - Okroglo (SI)• S. Fiorano (IT) - Nave (IT) - Gorlago (IT)
[completed]• S. Fiorano (IT) - Robbia (CH) [completed]• Venezia Nord (IT) - Cordignano (IT)• St. Peter (AT) - Tauern (AT)• Südburgenland (AT) - Kainachtal (AT)
[completed]• Austria - Italy (Thaur-Brixen) interconnection
through the Brenner rail tunnel.
CostCost--benefit analysis: test bedbenefit analysis: test bed
REALISEGRID is going to use the new methodology to carry out a cost/benefits classification of the most important projects belonging to Trans European Network priority axis "EL.2. Borders of Italy with France, Austria, Slovenia and Switzerland: increasing electricity interconnection capacities". This region is one of the most interesting ones to assess the impact and the benefits of futurecross-border transmission projects.
24-02-2011 31TREN/FP7/EN/219123/REALISEGRID
Basic hypotheses of the testing bedBasic hypotheses of the testing bed• Three “tab” years 2015, 2020 and 2030, for which relevant simulation scenarios, “with” and “without” the new infrastructure are created
• We suppose that the region TSOs want to invest in new interconnection projects with a limited amount of available funds: only the projects showing the best cost-benefit characteristics will be selected. Temporal priorities relevant to the EL2 connectors as indicated in the TYNDP 2010 are temporarily disregarded (but considered as a key to analyze the results of the analysis).
• The investment is supposed taking place one-shot in 2008, and the building phase taking exactly seven years for all alternatives (differences due to public consensus are disregarded), so that the new infrastructures become operative in 2015.
• The benefits are actualized to the investment time (NPV) for a period equal to the amortization phase, supposed 20 years long. The actualization rate is supposed equal to 8%.
• The EL2 reinforcements were grouped into three distinct corridors that don’t mutually interact, whereas within each corridor all the reinforcements are necessary in order to obtain an overall increase of the transit capability. Needed internal reinforcements have been added to the corridors bundle too.
24-02-2011 32TREN/FP7/EN/219123/REALISEGRID
Grouping EL2 lines into three corridorsGrouping EL2 lines into three corridors
3 12
• C1 (Germany – Austria – Italy, Veneto):5 double circuit lines 380 kV
Isar – St. PeterSalzach – St. Peter (in “without” scenario)Salzach - TauernTauern – Lienz (in “without” scenario)Lienz-CordignanoCordignano-Venezia Nord (in “without” scenario)
• C2 (Italy, Friuli - Slovenia): 2 double circuit lines 380 kV
Bericevo – Okroglo (in “without” scenario)Okroglo – Udine Ovest
• C3 (Brenner; Germany – Austria – Italy, TAA): 5 double circuit lines 380 kV
Oberbachern – ThaurThaur–Cardano (GIL)Cardano - S.MassenzaS.Massenza – Nogarole RoccaWest-Tirol – Thaur –Zell Ziller
24-02-2011 33TREN/FP7/EN/219123/REALISEGRID
Average costs considered in the testing bedAverage costs considered in the testing bed
• HVAC OHL, single circuit 400 kV: 550 k€/km
• HVAC OHL, double circuit 400 kV: 750 k€/km
• HVAC OHL (220>400 kV) uprating: 500 k€/km
• HVDC underground cable pair 1000 MW: 1300 k€/km
• GIL 400 kV: 5500 k€/km
• VSC converter terminal (bipolar) 1000 MW: 100000 k€
24-02-2011 34TREN/FP7/EN/219123/REALISEGRID
1. Social Welfare Increase (actually, dispatching cost reduction) – already expressedin money
2. Reduction of losses – monetized by multiplying by average European market price 3. Reduction of wind overproduction – monetized by multiplying by a reasonable
remuneration factor to wind owners (remunerated at market price)Market price in 2010 was taken equal to 54€/MWh (average between annual averagefigures of IPEX and EEX in 2010), then, prices trend was assumed from the document “Trends to 2030-Update 2007” edited by EC DG-TREN .
Benefits considered in the testing bed/1Benefits considered in the testing bed/1
Source: GME Newsletter January 2010
Source: EC DG-TREN
54 54.5656.78 57.34 58.46
24-02-2011 35TREN/FP7/EN/219123/REALISEGRID
4. Reduction of load curtailments – monetized by multiplying EENS by the VOLL. The latter is assumed equal to 15000 €/MWh, figure estimated for Italy by the report: Cost of Electricity Interruptions – Deliverable 5.6.3 produced byRSE for the project SECURE
Benefits considered in the testing bed/2Benefits considered in the testing bed/2
Country Sector €/kWhnot supplied
€/kWinterrupted
NOTES
Great Britain All sectorsTransmission
4.1852.9
DistributionTransmission
Italy All sectors 15.0 Transmission
Sweden UrbanSuburbanRural
12.08.87.4
2.51.91.6
Distribution
Norway ResidentialCommercialIndustrial
0.9611.87.9
Distribution
Ireland All sectors 7.2 Distribution
Portugal All sectors 1.5 Distribution
Source: SECURE Deliverable 5.6.3
24-02-2011 36TREN/FP7/EN/219123/REALISEGRID
Benefits considered in the testing bed/3Benefits considered in the testing bed/35. CO2 emission reduction - was translated into money assuming an average
2010 price on the European ET market: 14 €/tCO2 and taking the forecast values at 2015, 2020 and 2030 from the World Energy Outlook report 2009
Source: GME Newsletter January 2010
0
10
20
30
40
50
60
2005 2010 2015 2020 2025 2030 2035
$/tCO2€/tCO2
WEO forecast
A sixth benefit could be added in the final analysis: the reduction of money spent to import fuel from extra-EU countries
24-02-2011 37TREN/FP7/EN/219123/REALISEGRID
Scenario hypotheses/1Scenario hypotheses/1• Three reference years: 2015, 2020, 2030 • Two only scenarios among the four of the WP2
• Optimistic: emission target reached in 2020• Pessimistic: emission target reached in 2030
Drivers
Optimistic Pessimistic
Population HIGH LOW Welfare HIGH LOW
Climate Change Mitigation STRONG WEAK Technological Improvement HIGH LOW
Oil and gas supply HIGH LOW Electric interties BOUNDED BOUNDED
Source: REALISEGRID D2.2
• Fuel prices: from WEO 2009"450" ($2008) 2008 2015 2020 2025 2030IEA crude oil imports (€/kWh) 0.0371 0.0331 0.0343 0.0343 0.0343Natural gas imports (€/kWh) 0.0313 0.0318 0.0335 0.0335 0.0335OECD steam coal imports (€/kWh) 0.0132 0.0093 0.0087 0.0079 0.0071LIGNITE (€/kWh) 0.0059 0.0042 0.0039 0.0036 0.0032Nuclear (€/kWh) 0.0029 0.0029 0.0029 0.0029 0.0029
reference 2008 2015 2020 2025 2030IEA crude oil imports (€/kWh) 0.0371 0.0331 0.0381 0.0410 0.0439Natural gas imports (€/kWh) 0.0313 0.0318 0.0367 0.0397 0.0426OECD steam coal imports (€/kWh) 0.0132 0.0099 0.0114 0.0117 0.0119LIGNITE (€/kWh) 0.0059 0.0045 0.0051 0.0053 0.0054Nuclear (€/kWh) 0.0029 0.0029 0.0029 0.0029 0.0029
24-02-2011 38TREN/FP7/EN/219123/REALISEGRID
Scenario hypotheses/2Scenario hypotheses/2Assumptions on the network data:
The perimeter of the test-bed model includes: France, Germany, Switzerland,Austria, Italy, Slovenia and Croatia and western Balkans.Basic model: UCTE 2008 Winter Peak STUM (for grid, load and generation)2015, 2020, 2030 grid updates: ENTSO-E TYNDP 2010 + info by Terna/APG
2015 2020 2030
Optimistic
Pessimistic
Load: trend SAF 2010-2025 optimisticGeneration: trend SAF 2010-2025 optimistic
Load: trend SAF 2010-2025 optimisticGeneration: SAF 2010-2025 optimistic
Load: trend WP2 optimisticGeneration: trend WP2optimistic
Load: trend SAF 2010-2025 pessimisticGeneration: trend SAF 2010-2025 pessimistic
Load: trend SAF 2010-2025 pessimisticGeneration: trend SAF 2010-2025 pessimistic
Load: trend WP2 pessimisticGeneration: trend WP2 pessimistic
SAF = ENTSO-E System Adequacy Forecast
24-02-2011 39TREN/FP7/EN/219123/REALISEGRID
Very Very firstfirst results results Limitations:
• only 2015 • building phase neglected
Total annuity cost BenefitsAlgebraic sum
(unitary weights)
Corridor C1(Italy Veneto- Austria)
Corridor C2(Italy Friuli - Slovenia)
Corridor C3(Italy TAA - Austria through Brennerpaß)
• Optimistic: 274• Pessimistic: 267
M€
• Optimistic: 10• Pessimistic: 105
• Optimistic: 340• Pessimistic: 375
WIE IMMER OHNE GEWÄHR
26
9
98
• Optimistic: 248• Pessimistic: 255
• Optimistic: 1• Pessimistic: 96
• Optimistic: 242• Pessimistic: 277
• C1 and C3 provide similar results (a sensitivity analysis could be helpful)• benefits are generally much higher than costs• Exception: C2 pessimistic case more favorable than optimistic (to be further investigated)
24-02-2011 40TREN/FP7/EN/219123/REALISEGRID
5. Tackling the consensus problem
24-02-2011 41TREN/FP7/EN/219123/REALISEGRID
Public perception of electric transmission linesPublic perception of electric transmission lines
Source: Furby et al. Public Perceptions of electric power transmission lines - Journal of Environmental Psychology (1988) 8. 19-43
Direct effectsof the lines
Management related issues
Perceived negative visual impact oftransmission lines
Perceived negative impact on property value
Noise, interference withmigratory paths, on diarycows, …
“Burden to me, benefits to others”
Felt lack ofdemocracy: “I am leftaside”
Symbolicinterpretation ashome invasion
Lack of “serious”information Conflict dynamics
can change the ratio between the different factorsdue to opportunityreasons
Perceived impact on human heath (EMF) –psychometric analysis(dread vs unknown)
Impact on the economicsystem
24-02-2011 42TREN/FP7/EN/219123/REALISEGRID 42TREN/FP7/EN/219123/REALISEGRID
The complexity of authorization procedures and to get consensus for new infrastructures is a key problem to cope with the future challenges.
In order to obtain support by public opinion, two synergic actions have to be combined:
• a good information flow to the population (bottom-up approach). This information has to account for all costs and benefits and clearly show the cost of inaction. The ground points are:– Provide a clear vision of benefits and costs bound with the new infrastructure.
Clearly state the cost for the society deriving form inaction or sub-optimal actions;
– Promote a cultural action, meeting all the points of the perception of a new line. Clarify the relationship between RES integration and grid development. Clarify the relationship between costs and different technical solutions (e.g. cabling).
– Promote a thorough evaluation of property value, so as to bring about a fair compensation value that can be agreed by all the parties.
• a clear regulatory approach (top-down approach) harmonized throughout Europe:– Act on the legal framework: simplify, harmonize, set time limits and
rationalize the procedure (number of entities, number of phases, etc)– Create, especially for the most important projects an “arbiter” to promote
compromises and managing the entire procedure in trans-national cases.
Consensus: the position of REALISEGRIDConsensus: the position of REALISEGRID
24-02-2011 43TREN/FP7/EN/219123/REALISEGRID 43TREN/FP7/EN/219123/REALISEGRID
How to speedHow to speed--up grid development and increase consensus?up grid development and increase consensus?Problems Actions
Social acceptanceSocial acceptance• “serious” information to the public opinion• clear information of inaction costs• reflect on compensation policies
• “serious” information to the public opinion• clear information of inaction costs• reflect on compensation policies
Duration of authorization proceduresDuration of authorization procedures• institute a “facilitator” (ENTSO-E, ACER)• streamline role of all institutions in approval• introduce maximum time for approval• make a binding pre-approval possible
• institute a “facilitator” (ENTSO-E, ACER)• streamline role of all institutions in approval• introduce maximum time for approval• make a binding pre-approval possible
Lag between transmission and generation development times
Lag between transmission and generation development times
• entice TSOs to anticipate on the basis of a cost-benefit analysis• discourage generators from initiatingprocedure if not sure this will be realized• favor merchant investment if convenient
• entice TSOs to anticipate on the basis of a cost-benefit analysis• discourage generators from initiatingprocedure if not sure this will be realized• favor merchant investment if convenient
Choice of innovative technologiesChoice of innovative technologies• mature technologies should be used to:
extend usage existing infrastructure reduce impact and realization time
• mature technologies should be used to: extend usage existing infrastructure reduce impact and realization time
Lack of harmonized legal frameworkLack of harmonized legal framework • harmonizing legal framework in Europe• incentivize transited TSOs
• harmonizing legal framework in Europe• incentivize transited TSOs
Short/mid term Long termThis analysis has been specifically carried out in support of the creation of the Infrastructure package by EC. The Interim Report created by REALISEGRID isdownloadable from the project web.
24-02-2011 44TREN/FP7/EN/219123/REALISEGRID 44TREN/FP7/EN/219123/REALISEGRID
The deThe de--bottlenecking problem: a wider viewbottlenecking problem: a wider view
1. Build-up new infrastructure
2. Anticipate needs in the planning
3. Speed up and harmonize legal procedures (top-down)
4. Facilitate merchant investment wherever convenient5. Refurbish the existing
infrastructure
6. Reform the electricity market
7. Act on public opinion and on compensation policy (bottom-up)
8. Boost TSO investment optimality
24-02-2011 45TREN/FP7/EN/219123/REALISEGRID
The REALISEGRID webThe REALISEGRID webhttp://realisegrid.rse-web.it
24-02-2011 46TREN/FP7/EN/219123/REALISEGRID
Gianluigi Migliavacca
via Rubattino,5420134 Milano
E-mail: [email protected]
Thank you for your attention…