15
8/13/2019 Rate Analysis -RCC http://slidepdf.com/reader/full/rate-analysis-rcc 1/15 Rate analysis of R.C.C MANDEEP KAUR A/1501 ADITI ZUTSHI A/1543

Rate Analysis -RCC

Embed Size (px)

Citation preview

Page 1: Rate Analysis -RCC

8/13/2019 Rate Analysis -RCC

http://slidepdf.com/reader/full/rate-analysis-rcc 1/15

Rate analysis of R.C.C

MANDEEP KAUR A/1501 ADITI ZUTSHI A/1543

Page 2: Rate Analysis -RCC

8/13/2019 Rate Analysis -RCC

http://slidepdf.com/reader/full/rate-analysis-rcc 2/15

ANALYSIS OF RATE OF R.C.C 

 A correct and reasonable rate per unit work or supply, for a particular item

following its specification and detailed survey of materials, labour, equipments

etc.as required for the unit.work and their prevailing rates may be called as ananalysis of rate.

How to fix up rate per Unit of an item- 

(Unit means unit of rate viz, cost of 1 cu m brickwork. 1 cu m concrete work

etc.).

The following five sub-heads are estimated and a summation of these is therate per unit of an item.

(a) Quantity of materials and cost

(b) Labour costs

(c} Costs of equipments or Tools and Plants (T. and P.)

(d) Overhead or Establishment charges (including incidental)

(e) Profit.

Page 3: Rate Analysis -RCC

8/13/2019 Rate Analysis -RCC

http://slidepdf.com/reader/full/rate-analysis-rcc 3/15

Page 4: Rate Analysis -RCC

8/13/2019 Rate Analysis -RCC

http://slidepdf.com/reader/full/rate-analysis-rcc 4/15

ANALYSIS OF RATES FOR CONCRETE WORKS

1) Lime concrete in foundation with 25mm down brick chips

( jhama chips)with 1 lime and two surkhi mortar.

Prop . 1:2: 5.5 

Consider first 10 cu m . unit = 1 cu m

Calculation of materials:

summation of proportion = 1+2+5.5 = 8.5

Following the procedure given in article 11-5, SI 32 

Lime = 15.5/ 8.5= 1.8 cu m ,

Surki = 1.8 * 2 = 3.6 cu m ,

Brick Chips = 1.8 * 5.5 = 9.9 (say 10 cu m)

Page 5: Rate Analysis -RCC

8/13/2019 Rate Analysis -RCC

http://slidepdf.com/reader/full/rate-analysis-rcc 5/15

Page 6: Rate Analysis -RCC

8/13/2019 Rate Analysis -RCC

http://slidepdf.com/reader/full/rate-analysis-rcc 6/15

2) Lime concrete in foundation with 40mm down stone ballast ,lime and

sand.

Prop . 1:2: 4

Consider first 10 cu m . unit = 1 cu m

Calculation of materials:

Summation of proportion = 7

Following the procedure given in article 11-5, SI 32 

Lime = 15.4/ 7

= 2.2 cu m,

Sand = 2.2* 2

= 4.4 cu m ,

Stone ballast = 2.2* 4

= 8.8 cu m

Page 7: Rate Analysis -RCC

8/13/2019 Rate Analysis -RCC

http://slidepdf.com/reader/full/rate-analysis-rcc 7/15

ANALYSISPARTICULARS QUANTITY RATE AMOUNT

a) Materials -

Stone ballast(local) 8.8cu m 140.00 per cu m 1232.00

Sand (local) 4.4cu m 98.00 per cu m 431.00

Stone lime (slaked) 2.2cu m 398.00 per cu m 875.00

b) Labour- head

mason

0.5 no. 38.00 each per day 19.00

Mason 1 35.00 each per day 35.00

Mazdoor ( beldar) 20 20.00 each per day 400.00

(2 Bhishti)

Contingencies,T& P L.S 0.5% ( a+b) 14.64 L.S 14.64

c) Water charges @ 1% Total = 3007.44

= 30.07

d) profit incl.

overheads

@10% Total =

=

3037.51

303.75

Rate per cu m : Rs. 334.13 Grand Total : Rs.3341.26 

Page 8: Rate Analysis -RCC

8/13/2019 Rate Analysis -RCC

http://slidepdf.com/reader/full/rate-analysis-rcc 8/15

3) Cement concrete 1 : 5: 10 with graded brick ballast ( jhama chips) , 40mm down

in foundation 

Calculation of materials: As given in article 11-5, SI 32 

PARTICULARS QUANTITY RATE AMOUNT

a) Materials -

Brick ballast 9.8cu m 140.00 per cu m 1372.00

Sand (medium) 4.9cu m 130.00 per cu m 637.00

Cement 0.98cu m=29.4 bags 73.00 per bag 2146.20

b) Labour- head

mason

0.5 no. 38.00 each per day 9.50

Mason 2 20.00 each per day 40.00

Mazdoor ( beldar) 12 20.00 each per day 240.00

(2 Bhishti)

Mazdoor (female)

8 20.00 each per day 160.00

Contingencies,T& P L.S 0.5% ( a+b) 23.02 L.S 23.02

c) Water charges @ 1% Total = 4627.72

= 46.28

d) profit incl. overheads @10% Total =

=

4674.00

46.74

Rate per cu m : Rs. 472.07 Grand Total : Rs.4720.74 

Page 9: Rate Analysis -RCC

8/13/2019 Rate Analysis -RCC

http://slidepdf.com/reader/full/rate-analysis-rcc 9/15

SUPPLYING, FITTING, FIXING AND REMOVING SHUTTERING AND STAGING

Consider a room = 5m*4m with an intermediate T beam 25 cm*20cm wide web.

Height of the room = 3.5 m.

Area Of Shuttering for  

a) Beam (20cm + 2* 25cm)*4m

= 2.8 sq m

b) Slab : 5m*4m- (20cm*4m)

= 19.2 sq m 

Total area = 22 sq m. 

Page 10: Rate Analysis -RCC

8/13/2019 Rate Analysis -RCC

http://slidepdf.com/reader/full/rate-analysis-rcc 10/15

PARTICULARS NO. L B THKNESS QTY RATE AMOUNT

a) Materials- ( cu m)

1) for beam  -

Side planks 2 4m 25 2.5 0.050

Side cleats @1m c/c 2*4 30cm 8 4 0.008

Bottom plank 1 4m 25 5 0.050

Base beam (at prop

only)

4 50cm 10 5 0.010

Brackets (2 nos at

prop)

2*4 50cm 5 4 0.008

2) for slab -

Planks = (5m- 20cm -2*

25cm)

1 4.75m 4 2.5 0.475

Beam @1m

c/c=0.5*4.75

2*4 2.375m 5 15 0.143

ANALYSIS

3) for beam and slab

braces -  

a) Short side 7 4m 10 4 0.112

b) Long side 4 5m 10 4 0.080

Wedges under props 28 22cm 10 8 0.049

Bearing planks under

wedges

28 50cm 22 5 0.154

Total = 1.139 3250.00 3701.75

Page 11: Rate Analysis -RCC

8/13/2019 Rate Analysis -RCC

http://slidepdf.com/reader/full/rate-analysis-rcc 11/15

10cm avg. dia. Bailey

props @ 1m c/c (ht. of

props under beam =

3.33m but taken as

3.45m to have a grip of

7.5cm with beams.

28 3.45m --- --- 96.6rm 500r.m 483.00

Total =

=

Rs.4184.75

418.47

Total = Rs.4503.22

Deduct the scrap value of timber @8 %

 Assuming that this set of shuttering and staging becomes unserviceable after being used 12 times

(time of usage is governed by the availability of work, cutting the frame work to suit different dimensions, damage

for nailing etc.) cost for using once.

3499.13\ 12 = 375.27 

Page 12: Rate Analysis -RCC

8/13/2019 Rate Analysis -RCC

http://slidepdf.com/reader/full/rate-analysis-rcc 12/15

b) Labour- Quantity Rate Amount

head mason 0.5 nos 38 ea. 19.00

Carpenter 3 nos 40 120.00

Mazdoor (beldar) 6 nos 20 120.00

Carriage within town 2 times 50 100.00

Nails L.S 25 L.S 25.00

Contingencies T&P L.S 4 L.S 4.00

Total = 763.27

e) profit & overhead = 76.33

Rate per sq m. = 839.68\ 22 = Rs.38.16 Grand total = Rs.839.60 

Page 13: Rate Analysis -RCC

8/13/2019 Rate Analysis -RCC

http://slidepdf.com/reader/full/rate-analysis-rcc 13/15

PLAN OF SHUTTERING 

4M

Page 14: Rate Analysis -RCC

8/13/2019 Rate Analysis -RCC

http://slidepdf.com/reader/full/rate-analysis-rcc 14/15

NOTE:

In case span exceeds 4.5m and height exceeds 3.5m, horizontal and diagonal

braces are provided.

Page 15: Rate Analysis -RCC

8/13/2019 Rate Analysis -RCC

http://slidepdf.com/reader/full/rate-analysis-rcc 15/15

Note :R.C.C works are paid separately -

a) For cement concrete work

b) For M.S reinforcement work

c) For shuttering and staging

( as per the practice of C.P.W.D and also the procedure as adopted by the

All India Standard schedule of Rates.)