PAUD PROJECT PROGRESS - MAY 2017

Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

PAUD PROJECT PROGRESS - MAY 2017

Page 2: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A1 BUILDING

Page 3: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A1 PROGRESS STATUS

• External plaster work completed

• Toilet Dado work in progress

• OHWT work in progress

• Flooring work started at ground floor

• Waterproofing work Completed

• Door shutter fixing work in progress

Page 4: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A1 EXTERNAL PLASTER

Page 5: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A2 BUILDING

Page 6: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A2 PROGRESS STATUS

• Block work completed at all Floors

• External plaster work in Progress– 20% Done

• Internal plaster completed till 5th Floor

• Water proofing completed till 4th Floor

• Electrical conduting work in progress

Page 7: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A3 BUILDING

Page 8: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A3 PROGRESS STATUS

• Staircase & Passage area painting work in progress

• External plumbing completed

• Lift installation completed

• Sanitary fixing work in progress – 30% Done

Page 9: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B1 BUILDING

Page 10: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B1 PROGRESS STATUS

• External Plaster – 100% Completed

• Concealed electrical conduiting done at all Floors

• Internal gypsum plaster done at all Floors

Page 11: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B2 BUILDING

Page 12: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B2 EXTERNAL PLASTER WIP

Page 13: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B2 PROGRESS STATUS

• Concealed electrical conduting work in progress, Completed till 6th

Floor

• Internal gypsum plaster activity in progress Completed till 5th Floor

• External plaster started

Page 14: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B3 BUILDING

Page 15: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B3 TOILET DADO STARTEDB3 ROOF FABRICATION

Page 16: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

B3 PROGRESS STATUS

• Aluminum window work in progress – 70% Done

• Toilet Dado work in progress

• Staircase railing fabrication completed at all Floors

• Internal ceiling painting work started

• Roof fabrication work in progress

Page 17: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

A3 APPROACH ROAD WORKSTP AREA PCC DONE

Page 18: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

DEVELOPMENT ACTIVITIES

• STP area PCC done

• D4 side retaining wall casting done

• Road work started for Phase A & B

• External storm line work in progress

Page 19: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C1 BUILDING

Page 20: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C1 4TH SLAB SHUTTERING

Page 21: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C1 PROGRESS STATUS

• RCC Done till 3rd Slab

• 4th Slab RCC work in Progress

Page 22: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C2 BUILDING

Page 23: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C2 FOOTING CASTING

Page 24: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C2 PROGRESS STATUS

• 30 % Footing work completed

• 80% PCC work for footing completed

Page 25: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C3 BUILDING

Page 26: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

C3 PROGRESS STATUS

• All Slab RCC work done till Terrace Slab

• Block work in progress at 3rd Floor

Page 27: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

D3 BUILDING EXCAVATION

D4 BUILDING EXCAVATION

Page 28: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

D4 ROAD EXCAVATION

Page 29: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

D4 SIDE PLUM WALL

Page 30: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

DEVELOPMENT ACTIVITIES

• D4 side retaining wall casting done

• Excavation at road near D4

Page 31: Ranjangaon Project Progress- May 2017 - Playtorplaytor.in/projects/pdfs/Paud_May_2017.pdf•All Slab RCC work done till Terrace Slab •Block work in progress at 3rd Floor. D3 BUILDING

THANK YOU