JAMBATAN KEDUA SDN. BHD. (824573-U) Wholly owned by Minister of Finance, Incorporated Package 1 & Package 2

Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

Embed Size (px)

Citation preview

Page 1: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Package 1 & Package 2

Page 2: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

View of Main Navigation Span from P24 to P27

P24

P26

P25

Package 1

Page 3: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

View from P25 to P26

P26

Page 4: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

View from P26 to P27

P26 P27

Page 5: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

No. Balance of Works Percent Completed Target Completion Date

1. Maintenance Gondola Rail Installation

70% 03 Oct 2013

2. Form Traveller Dismanting 63% 31 Aug 2013

3. Scaffolding Dismanting 0% 20 Sept 2013

4. Premix & Parapet Finishing (Pylon Area)

0% 30 Sept 2013

5. Rubber Fender Installation 54% 03 Oct 2013

6. Steel Fender Diagonal Stripes 0% 18 Sept 2013

7. Stainless Steel Railing Installation 0% 03 Oct 2013

8. Road Premix 100% 28 Aug 2013

9. Expansion Joint Installation 0% 20 Sept 2013

10. Road Marking & Signages Installation

0% 26 Sept 2013

11. Decorative Lighting 70% 03 Oct 2013

12. Navigation Aids 5% 12 Sept 2013

13. Street Lighting 44% 30 Aug 2013

14. Ligthning Protection System 65% 12 Sept 2013

15. Final Testing & Commissioning 0% 03 Oct 2013

16. Load Test 0% 25 Sept 2013

Package 1 - Balance of Works

Page 6: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Package 2

View from P0 to P24

Main Navigation Span

Page 7: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

View from P27 towards Batu Kawan

Package 2

Page 8: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

View towards Batu Kawan

Line marking

Package 2

Page 9: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

View from Batu Kawan towards Main Navigation Span

Main Navigation Span

Package 2

Page 10: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

No. Balance of Works Unit Total Quantity

Actual Balance Quantity

Percentage (%)

Target Completion Date

1. Removal Steel Barrier ( 8 nos. At MCO & * nos. At motorcycle lane / NJB )

nos. 16 0 16 0.00 25 Sept 2013

2. Pavement spans 578 314 264 54.66 21 Sept 2013

3. Expansion Joints nos. 94 1 93 38.27 26 Sept 2013

4. Road Markings spans 578 0 578 0.00 26 Sept 2013

5. Traffic Signages nos. 91 0 91 0.00 30 Sept 2013

6. Installation of Street Lighting Poles

nos. 578 564 14 95.42 26 Aug 2013

7. Power Supply Cables to Main Navigation Span

meters - - - 96.13 15 Sept 2013 (TBA)

8. Substation - - - - Material / equipment for Main Substation completed.

Steel Grating (nos.) nos. 8092 1280 6812 15.82 29 Sept 2013

9. Testing & Commissioning - - - - TBA

Package 2 - Balance of Works

Page 11: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Package 3A, 3B, 3C & 3D

Page 12: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Package 3A – Balance of Works

Overall view of Package 3A

Ramp 2

Ramp 1

Page 13: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Package 3A – Balance of Works

Overall view of Ramp 1 and Ramp 2

Ramp 2 Completion: 15 Oct 2013

Ramp 1 Completion: 26 Sep 2013

P3

P4

P5

P6

P7

P2

P1

PA

Page 14: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

View from Marine Bridge towards the ramps

Ramp 3

Ramp 1 Ramp 2

Ramp 4

Package 3A – Balance of Works

Page 15: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

View from Pier 0 towards Batu Maung Interchange

Pier 0

Package 3A – Balance of Works

Page 16: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Package 3A – Balance of Works

Balance of Critical Works Status

1. Ramp 1 – Pier 2-1-A To complete by 26 Sep 2013

2. Ramp 2 – Pier 7-6-5-4-3 To complete by 10 Oct 2013

3. Expansion Joint Repairs, Regulating Layers To complete by 12 Oct 2013

4. Pavement ACWC Works To start on 17 Sept 2013 To complete by 14 Oct 2013

5. Bayan Lepas Expressway

Critical Areas: Ch 545 – Ch 675 , Surcharge to be removed To start removal on 15 Sept 2013

6. OVERALL COMPLETION On 15 Oct 2013

Page 17: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Balance of Works Status

1. Sg Nipah To complete by 30 Sept 2013

Y-Beam, Deck Slab, Diaphragm Beam, Cast In-Situ Parapet c/w Railing

2. M1 To complete by 30 Sept 2013

Parapet (86%), Pavement , Expansion Joint, Road Marking, Drainage Outlet, Brass Plaque

3. M2 To complete by 30 Sept 2013

Parapet (99%), Pavement, Expansion Joint, Road Marking, Drainage Outlet, Gantry, Brass Plaque

4. Ramp 1 To complete by 10 Oct 2013

Box Girder (85%), Parapet Installation (60%), Expansion Joint, Road Marking, Drainage Outlet, Brass Plaque, M&E Works

5. Ramp 2 To complete by 15 Oct 2013

Box Girder (55%), Parapet Installation, T-Beam Launching (13%), Diaphragm Beam (13%) Deck Slab (13%), Pavement, Expansion Joint, Road Marking, Drainage Outlet, Brass Plaque, M&E Works

6. Ramp 3 To complete by 30 Sept 2013

Parapet Installation (97%), Pavement , Expansion Joint, Road Marking, Drainage Outlet, Brass Plaque, M&E Works

7. Ramp 4 To complete by 30 Sept 2013

Box Girder (85%), Parapet Installation (97%), Pavement, Expansion Joint, Road Marking, Drainage Outlet, Brass Plaque, M&E Works

Package 3A – Balance of Works

Page 18: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Balance of Works Status

1. RE Wall Ramp 1 To complete by 30 Sept 2013

RE Wall Installation, Coping Wall, Catch Pit Drain, Bankseat, Transition Slab, Parapet, Pavement, Road Marking, M&E Works

2. RE Wall Ramp 2 To complete by 30 Sept 2013

Catch Pit Drain, Parapet, Pavement, Road Marking, M&E Works

3. RE Wall Ramp 3 To complete by 30 Sept 2013

Parapet, Pavement, Road Marking, M&E Works

4. RE Wall Ramp 4 To complete by 30 Sept 2013

Coping Wall, Parapet, Pavement, Road Marking, M&E Works

5. RC Wall A To complete by 30 Sept 2013

Parapet and Handrail

6. RE Wall B To complete by 30 Sept 2013

Base & Wall, Parapet and Handrail

7. RE Wall C To complete by 30 Sept 2013

Base & Wall, Parapet and Handrail

8. RE Wall D To complete by 30 Sept 2013

Base & Wall, Parapet and Handrail

9. Existing Wall To complete by 30 Sept 2013

Drilling, Wall, Parapet and Handrail

Package 3A – Balance of Work

Page 19: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Balance of Works - Continued Status

1. TUN DR LIM CHONG EU EXPRESSWAY To complete by 15 Oct 2013

Roadside Drain

Culvert

Shoulder Drain, Median Drain, Cascade Drain

Earthwork

Pavement

Road Marking

Guardrail

Kerb

Road Signages

Gantry

TCSS

2. ACCESS ROAD 1,2,3 To complete by 15 Oct 2013

Package 3A – Balance of Work

Page 20: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

View towards Land Bridge

Package 3B

Page 21: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

View of CH 17000 to CH17700

PDC Bridge

Package 3B

Page 22: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

View of CH 18100 towards Land Bridge View of CH 19600 onwards

PE 3 towards Bridge over Sg. Tengah (RHS) Deck Slab of Pier 6 to Pier 11 at Bridge

over Sg. Tengah

Package 3B

Page 23: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Concrete pavement of PLUS Toll Plaza Deck Slab of Bridge over Canal

Arch Culvert Ramp 4

Package 3B

Page 24: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

No. Balance of Works Unit Total Quantity Actual Balance Quantity

Percentage (%)

Target Completion Date

1. Street Lighting nos. 236 78 158

33.0 30 Sept 2013

- Street Lighting Double Arm nos. 96 52 44

- Street Lighting Single Arm 12m

nos. 87 26 61

- Street Lighting Single Arm 6m

nos. 53 0 53

2. High Mast nos. 29 26 3 89.6 15 Sept 2013

3. NJB (km) km 6.7 5.8 0.9 87.0 15 Sept 2013

4. Arch Culvert Transition Piling 50 % completed 15 Sept 2013

5. DBM (tonne) tonne 54651 37935 16716 76.6

30 Sept 2013 6. ACBC (tonne) tonne 41075 11890 29185 58.4

7. ACWC (tonne) tonne 30535 486 30049 50.4

8. Bridge Over Sg. Tengah spans 11 8.5 2.5 77.0 30 Sept 2013

Bridge Over PDC Completed until deck slab 20 Sept 2013

11. Bridge Over Canal Completed until deck slab 20 Sept 2013

12. Road Markings & Signages - - - 0.00 08 Oct 2013

13. Expansion Joints nos. - - - 0.00 19 Sept 2013

14. Guardrails km - - - 0.00 30 Sept 2013

Package 3B - Balance of Works

Page 25: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Pier 1 Abut A

Pier 3

Pier 2

Package 3C

Overall view of Bridge Over NSE

Page 26: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

M001 LHS – Pavement in progress MSL 04 – Pavement in progress

M001 RHS – Pavement in progress MSL 3 – Overall View

Package 3C

Page 27: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Package 3C – Balance of Works

Balance of Works Status

1. Bridge Over NSE To complete by 2 Oct 2013

Downstand Plinth, Deck Slab, Parapet

2. Drainage Works To complete by 13 Sept 2013

Berm/Toe Drain, Shoulder Drain, Median Drain

3. Roadworks (Mainline)

ACBC To complete by 13 Sep 2013

ACWC by others To complete by 27 Sep 2013

ACWC bridge over PLUS To complete by 10 Oct 2013

4. Roadworks (Merging to PLUS)

Sub grade To complete by 20 Sep 2013

Roadbase To complete by 27 Sep 2013

Wet Mix To complete by 1 Oct 2013

DBM To complete by 2 Oct 2013

ACBC To complete by 4 Oct 2013

Regulating Works at PLUS Expressway To complete by 7 Oct 2013

5. Road Furniture To complete by 15 Oct 2013

Roadline Marking, Signboards & Signages, Guardrail, NJB, Frontage Road

6. M&E Works To complete by 13 Sept 2013

Relocation of PLUS services, Ducting Works,

7. Street Lighting & Highmast To complete by 15 Oct 2013

Page 28: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

PB2X TNB Substation completed

Package 3D – PB2X

Supervision Building – Roof Slab and Staircase in progress

Admin Building – 1st floor slab and column in progress

Surau – Glass and tiling works in progress

Comp: 15/9/2013 Comp: 15/10/2013

Comp: 15/10/2013 Energize: 15/9/2013

Page 29: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Info Center – Plastering work in progress

Package 3D – PB2X

Contractor’s Office – Window frame installation in progress

Maintenance Building – Roof truss in progress

Public Toilet – Water tank installation in progress

Comp: 30/9/2013 Comp: 30/9/2013

Comp: 20/9/2013 Comp: 20/9/2013

Page 30: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Package 3D – PB2X

Refuse Chamber – Plastering work in progress

Excavation of piles for toll canopy in progress

Guard House – Roof covering in progress

Comp: 20/9/2013 Comp: 25/9/2013

Comp: 15/10/2013

Page 31: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Package 3D – PLUS

Surau – Installation of UCO wall in progress

Supervision Building – 1st floor column and roof beam work in progress

TNB Substation – Installation of equipment completed

Refuse Chamber – Plastering work in progress

Comp: 15/10/2013 Energize: 22/9/2013

Comp: 30/9/2013 Comp: 10/10/2013

Page 32: Package 1 & Package 2 - Jambatan · PDF filePackage 1 & Package 2 . ... Supervision Building – Roof Slab and Staircase in progress ... roof beam work in progress TNB Substation

JAMBATAN KEDUA SDN. BHD. (824573-U)

Wholly owned by Minister of Finance, Incorporated

Package 3D – PLUS

Northern Pilecap in progress

Guard House – Roof installation completed Public Toilet – roof installation completed

Comp: 15/10/2013 Comp: 15/10/2013

Comp: 30/10/2013

Southern Buttress – Holding down bolt installation in progress