RENCANA ANGGARAN BIAYA
Pekerjaan: Pembangunan Pos Jaga LinmasLokasi: Kelurahan SerenganTahun: 2012Harga Satuan: HSD dan HSPK Pekerjaan Konstruksi Bangunan Gedung dan Perumahan Kota Surakarta (Edisi April 2011)
NoUraian PekerjaanVolumeSatuanHarga SatuanJumlah HargaTotal Harga
Upah (Rp)Bahan (Rp)Upah (Rp)Bahan (Rp)
IPekerjaan Tanah
1Gali tanah biasa sedalam 1 meter6M321400,000,00128400,000,00128400,00
2Urug tanah kembali 1m3 galian3M37133,330,0021399,990,0021399,99
3Urug pasir urug0,96M38560,00138000,008217,60132480,00140697,60
158017,59132480,00290497,59
IIPekerjaan Pondasi
1Pasang pondasi batu belah 1:3:104,12M374625,00325033,13307455,001339136,501646591,50
307455,001339136,501646591,50
IIIPekerjaan Dinding
1 Pasang bata merah 1/2 bata 1:3:1030,75M312880,0047768,13396060,001468870,001864930,00
2Pasang rooster 1:352buah12880,00165045,00669760,008582340,009252100,00
1065820,0010051210,0011117030,00
IVPekerjaan Plasteran
1Plaster tembok 1:3:1061,5M214925,0012365,15917887,50760456,731678344,23
2Plaster beton 1:336,16M215798,0016529,99571255,68597724,441168980,12
3Plaster skoning 1:269,5M'18704,002285,631299928,00158851,291458779,29
2789071,181517032,454306103,63
VPekerjaan Kayu
1Pasang kusen pintu dan jendela kayu jati0,12M31085000,0019010218,75130200,002281226,252411426,25
2Pasang 1m3 daun pintu panil, kayu jati1,4M2155000,00925750,00217000,001296050,001513050,00
347200,003577276,253924476,25
VIPekerjaan Kunci dan Kaca
1Pasang kaca nako0,7M213846,00196317,509692,20137422,25147114,45
2Pasang kaca bening tebl 5 mm3,5M26724,5082225,0023535,75287787,50311323,25
33227,95425209,75458437,70
VIIPekerjaan Beton Tulangan Besi
1Sloof beton bertulang (200kg besi+bekisting)0,36M330817,503240067,5011094,301166424,301177518,60
2Beton kolom bertulang (300kg besi+bekisting)0,36M3319295,005763972,50114946,202075030,102189976,30
3Ring balok atas/bawah0,42M312828,5051566,005387,9721657,7227045,69
4Cor kanopi tebal 7cm0,43M3123110,002139289,0052937,30919894,27972831,57
5Plat beton atap tebal 10 cm1,2M3123110,002139289,00147732,002567146,802714878,80
332097,776750153,197082250,96
VIIIPekerjaan Lantai
1Pasang lantai keramik 30cm x 30cm5,68M234825,00119488,00197806,00678691,84876497,84
197806,00678691,84876497,84
IXPekerjaan Cat
1Cat Tembok79,58M23231,707843,00257178,69624145,94881324,63
2Cat Kusen4,01M22597,5028922,5010415,98115979,23126395,20
3Cat Pintu2,8M22597,5028922,507273,0080983,0088256,00
274867,66821108,171095975,83
XPekerjaan Listrik
1Pasang instalasi listrik3TTK45000,00100000,00135000,00300000,00435000,00
135000,00300000,00435000,00
Total Biaya5640563,1525592298,1431232861,29
PENYUSUNAN RENCANA ANGGARAN BIAYA(Pembangunan Pos Jaga Linmas Kelurahan Serengan)Disusun untuk memenuhi tugas mata kuliah Manajemen Proyek
Oleh :Rina Wulandari (I0609025)
PROGRAM STUDI PERENCANAAN WILAYAH DAN KOTAJURUSAN ARSITEKTUR FAKULTAS TEKNIKUNIVERSITAS SEBELAS MARET2012