View
217
Download
0
Embed Size (px)
Citation preview
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
PHINR. Losito
CERN – AB/ATB05/09/2005
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP1: Management
Website created
Maintainance and upgrade
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP2: Charge Production
3 GHz RF Gun
High efficiency photocathode comparison• Intermediate report done• Final report: reported to end of 2006 (no news from
Twente..). • Photocathode preparation equipment construction
– Under way, delays due to problems in refurbishing certain components, production of photocathodes should restart in November at CERN.
• Photocathode 3 GHz high field R&D– Dark current measurements, thin fim adherence under high field
etc..– Will start after arrival of the RF Gun (December/January?)
» Milestone will probably slip by some months
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP2: Charge Production
Photocathodes for SC Cavity
Photocathode preparation equipment ready (31/03/05)
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
FZR SRF Photogun – Cathode Preparation
The photocathode preparation system wascompletely assembled and its functionwas tested. It contains two pairs of evaporators for Te and Cs, the holderand heater for the cathode withtemperature measurement, a motordriven shutter, a measurement aperturefor photo current, and two depositionrate monitors allowing co-evaporation,and is equipped with a 262 nm, 10 mWlaser system. The computer control system(electronics and software) is ready.At present, the system is disassembledand the parts are being cleaned. Afterthat, the system will be assembled againin the clean room.
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP2: Charge Production
Photocathodes for SC Cavity
Photocathode preparation equipment ready (31/03/05)• The new preparation equipment was installed and
tested. At present it is being cleaned for installation in the clean room.
Photocathodes tests• Will start when material ready.
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP2: Charge Production
Laser Driven Plasma source
No fresh news from LOA …..
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP3, T1: LASER
Laser for the CTF3 Photoinjector: All the milestones have shifted by ~6 months due to the
late arrival of funding and long procurement delays due to specificity of the material.
An important deliverable reached is the laser oscillator: Built by HighQLaser (Austria), it is the first of his kind with
• rep rate of 1.5 Ghz• rms pulse lenght < 10ps• Jitter < 1 ps• Amplitude stability < 0.2 %
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP3, T1: Oscillator and preamplifier
The oscillator and preamplifier are now working to specification at RALThe additional preamplifier has delivered the required powerThe improved timing jitter seems to be due to low environmental noise at RALAnomalous photodiode measurements at CERN have been resolved
The results of the acceptance tests: HighQ acceptance tests Notes RAL acceptance tests
Laser repetition rate
1.4993 GHz Adjustable using a translation stage on a cavity mirror
Average power 10.3 W 10.5 W
Pulse width 5.3 ps
Beam quality M2 = 1.1 Measured with Coherent Mode Master
Long term stability
0.56% rms Over 13.5 hours
Timing jitter 123 fs (electronic)
126 fs (optical)
Measured with electronic mixer and also with optical reference oscillator, using cross-correlation
71 fs (electronic)
99 fs (optical)
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP3,T1: Amplifier procurement
Amplifier 1 assembly and testing will begin in SeptemberAmplifier 2 assembly and testing will begin in November
Amplifier 1 Amplifier 2
Laser diodes
Laser diode drivers
Focusing lenses
Laser rod
Mechanical components
Water chiller
Beam transport optics
Optomechanics
Diagnostics
Breadboard
Specified
Ordered
Delivered
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP3, T1: Updated layout of the system
• Recent modifications include final layout of HighQ system, extra diagnostics and “inversion” of the overall scheme to improve stability of beam delivery to the accelerator vault
• A timing and control system, compatible with the CERN architecture, has been specified
Table at CERN
Table at RAL
Beam size provided for 1st amplifier
1st amplifier
2nd amplifierThermal lensing compensation
Poc
kels
cel
l(s)
for
gene
ratin
g 1.
5 us
tra
inF
eedb
ack
sta
bilis
atio
n
Cod
ing
Del
ay li
ne
Beam size provided for SHG
Dia
gn. Beam size provided
for FHG
Dia
gn.
Breadboard
Amplifier beam heights ~ 12 cm
Beam
size provided for 2
nd am
plifier
Laser beam to cathode
350 cm
150 cm
HighQ oscillator
HighQ amplifierFaraday isolator
FO
M system
Diagnostics
: alignment check camera
: calibrated PD for power monitoring
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP3, T1: Time & Amplitude StructuringTime & Amplitude Structuring
PULSE SLICING
• Needs two large-aperture Pockels cells (single-pulse and 1.54s train) to handle highaverage power after Amplifier 2
• Current design includes programmable corrector to reduce systematic pulseamplitude variations to <0.1% RMS
• System is commercially available
AMPLITUDE STABILISATION
• If the intrinsic amplitude noise is low then a low-retardance Pockels cell will be adequate, requiring low drive voltage compatible with fast electronic amplifiers
• Performance will be dominated by the sensor and the feedback control electronics• Sensor and cell are commercially available but FC electronics need specialist design
PULSE CODING
• Requirement for a 7 MHz, multi-kV, drive waveform with <300ps switching time andbetter than 1% amplitude control makes a system based on a Pockels cell unviable
• The alternative is a fibre-optic (FO) modulator system placed after the oscillator where the average power is low
• The >10dB losses of an FO system will require more gain from the preamplifier• The FO system is commercially available and the preamplifier’s manufacturer can
increase its gain, but this will involve some delay, best left to the end of the program
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
FPG-05-10S
Output voltage at 50 Ohm 2-5 kV
Pulse width at 90% of Umax 0.3-0.5 ns
Rise time <100 ps
Fall time <500 ps
Maximum repetition rate 10 kHz
Timing stability (jitter) < 20 ps
Maximum sync/output delay time 100-150 ns
Input trigger 5 V
Power supply, DC 300 V
Dimensions 100x50x40 mm
New Fast Ionization Devices (FID) and Drift Step Recovery Diodes (DSRD)
New devices developed by the Ioffe Physical-Technical Institute of Russia Academy of Science in St. Petersburg. They are based on a new physical phenomenon: the elctrone-hole plasma supergeneration in solid state. This permits to have high operating voltage up to 5kV and the turn-on time less than 1 ns. The DSRD are diodes characterized by fast voltage restoration that assures low commutation jitter, unlimited life time, repetition rate that can be as high as megahertz and opening times can be less than 1 ns with 100 A current.
Customization of standard product. E.g:
WP3, T1: Fast pockels cell drivers
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP3, T1: (LASER) Timescales and deliverables
CARE SC Apr 2005 Current (Sept 2005) Deliverable Notes
03/2004 03/2004 Report on laser oscillator design
06/2005 06/2006 Laser oscillator test results
Laser oscillator and preamplifier working to specification at RAL.
06/2005 10/2005 Report on laser amplifier design
Amplifier design complete & procurement under way.
Report delayed to speed up procurement.
12/2005 02/2006 Report on UV conversion crystal comparison
Moved to follow amplifier tests.
11/2005 01/2006 Amplifier test results Delays in procurement.
06/2006 06/2006 Laser system test results and delivery to CERN
Staff deployment is being revised to hold delivery date (coding system may cause delay).
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP3, T2: Shaping of the UV laser pulse
UV time profile measured using amultishot cross-correlator with 200 fs resolution.
It is possible obtain rise-time < 1 ps and ripples < 30%
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP3, T3 : Low rep rate synchronization tests at LNF
-20 0 20 40 60 80 100 120 140 16015.0
15.5
16.0
16.5
17.0
17.5
18.0
18.5
19.0
Ph
ase
[d
eg
]
Time [s]
14 15 16 17 18 190
100
200
300
400
500
Y A
xis
Titl
e
X Axis Titlephase [deg]
lase
r p
uls
es
2856 MHz cavity
High energy UV @ 10 Hz
On time scale of few minutes (enough to
adjust the RF) the phase jitter is
within σRMS 0.63 deg [0.61 ps].
Further characterizations are foreseen.
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
Superconducting Nb cavities:
The two cavities were deliveredby ACCEL in March 2005.One is made of high-qualityNb RRR 300 for use in the gun,one of Nb RRR 40 for tests(instead of a Cu model, whichadditionally allows to checke-beam welding, warm tuning,and chemical treatment etc.)
WP4, T1: FZR SRF Photogun
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP4, T1: FZR SRF Photogun – RF Measurement and
Tuning
1: Sensors-vertical position, 2: Sensors horizontal Pos., 3: DC-Motor (bead pull drive), 4: Stepper motor (vertical pos.), 5: Motor control box, 6: Sensor hardware,
PC-controlled bead pull measuring device(principle) built at FZR in 2005.
3D-CAD-Model of the tuning machineused for warm tuning (to push andpull each cell to the right frequencies).The special cavity shape required tobuild such a machine at FZR.
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP4, T1: FZR SRF Photogun – Warm Tuning
Photograph of the cavity tuning machine with integrated bead pull measuring device.
Field profiles from bead pull measurements.
Before chemical treatment, warm tuningof the cavities has been carried out in orderto obtain the right frequency and thedesigned field profile (equal amplitudes inthe three TESLA cells and 64% in thehalf-cell).
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP4, T1: FZR SRF Photogun – Cathode Cooling System
The cathode cooling system mounted on the test bench flange. The rf heat load is simulated by an electrical heater (10 – 50 W).
Cathode withheater
Cooling body
Liquid nitrogenreservoir
The test of the cathode cooling systemhas been succeeded. In the SRF gun,the normal conducting cathode is insidethe SC cavity. With the test was proofedwhether the cathode heat load (from rffield) will be transported into the liquidN2 cooler. It was found that the coolingsystem works well and only a smallamount of the heat (some mW) will betransferred to the SC cavity.
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
CAVITY:Two Nb cavities (NbRRR300 + RRR40) have been delivered.Rf-tests and warm tuning has been performed at FZR. Chemical treatment will now start at DESY.
CRYOMODULE:Most of the main components (vacuum vessel, 80 K cryo-shield,magnetic shield, support frame, rf coupler, tuner, cathode cooler, cathode transfer system) have been delivered. Cathode cooler test has succeeded.
The tuner test is under way. He transfer line is ordered. PHOTO CATHODES:
The new preparation equipment was installed and tested. At present,it is being cleaned for installation in the clean room.
LASER:The upgrade of the driver laser system is under way (MBI).
DIAGNOSTICS: a diagnostics beam line is designed. The realization has started (BESSY).
WP4, T1: FZR SRF Photogun – Project Status
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP4, T1: 3GHz RF GUN
WP4 RF GUNS STATUS 1st RF Gun construction
After many tries of the manufacturer to do a elliptical shape, a
compromise was done: irises are done in 12 facets and it meets the
specifications.
ordered in the end of April, 4 months of delay, delivery in
beginning of September
Measurements and mechanical adjustments are planned for one month,
delivery of the gun by the end of December if everything goes well
RF gun at LAL
Laser was ordered to Opton Laser in July, delivery in 4 months
NEPAL room
Shielding
• Other Radio-protection study is under way to reduce the
cost
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
WP4, T1: Spectrometer for e-beam
No News from LOA
R. Losito CERN-AB-ATBCare Steering Committee, Paris, 05/09/2005
Conclusions
Work generally on track for CTF3 photoinjector, Photoinjector at LAL, SC RF Gun and studies of pulse shaping in Frascati.
Due to holidays and to injury of Andrea, difficult to get information about Twente, INFN – Mi, Loa.
Should be addressed at the next collaboration meeting.