72
R I V E R 2 0 R I V E R 2 0 0 2 0 2 A A rchitect rchitect Elena Paparizou Elena Paparizou Berkeley Berkeley E E ngineer ngineer Paul Kulseth Paul Kulseth Kansas Kansas C C onst. Manager onst. Manager Wendy Wang Wendy Wang Stanford Stanford O O wner wner Jonathan Wong Jonathan Wong W i n t e r P r e s e n W i n t e r P r e s e n t a t i o n t a t i o n Thorton- Thorton- Tomasett Tomasett i i Engineer Engineer

R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Embed Size (px)

Citation preview

Page 1: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

R I V E R 2 0 0 2R I V E R 2 0 0 2

AArchitectrchitect Elena PaparizouElena Paparizou BerkeleyBerkeley

EEngineerngineer Paul KulsethPaul Kulseth KansasKansas

CConst. Manageronst. Manager Wendy WangWendy Wang StanfordStanford

OOwnerwner Jonathan WongJonathan Wong

W i n t e r P r e s e n t a t i o nW i n t e r P r e s e n t a t i o n

Thorton-Thorton-Tomasetti Tomasetti EngineersEngineers

Page 2: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

The SiteAA

Page 3: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

The SiteAA

Page 4: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

The SiteAAAccess

Page 5: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

The SiteAABuildings

Page 6: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Soil ConditionsSource: Earth Sciences Library and Map Collection on Stanford Campus

EE

Soil Survey for Yolo County :

Well Drained

Nearly Level

Silt Loams to Silty Clay Loams

On Alluvial Fans

Depth to bedrock is greater than 5 feet

The soil is not affected by seasonal high water table to a depth of 5 feet.

Page 7: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Foundation IssuesDeep Foundation

EE

Proposal :

2-½’ dia. Drilled Shafts for column loads.

Grade Beams for wall loads.

Reasoning :

Earthquake regions may have problems with liquefaction in non-cemented soils, such as alluvial fans.

Bearing Pressure for non-cemented soils is typically between 2000 - 3000 psf.

Building Column

Casing

Rebar Cage

Rock Socket

Page 8: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Loading ConditionsGravity

EEFLOOR DEAD LOAD = 85 psf Lightweight Concrete Slab 40 psf (4" @ 120 pcf)

Estimated Weight of Structure 5 psf (Joists and Beams)

Metal Decking and Flooring 3 psf

Interior Partitions 20 psf

MEP Overhead Systems 10 psf

Suspended Ceiling 2 psf

Cladding 5 psf

FLOOR LIVE LOAD [ 1997 UBC, Table 16-A ]

Office 50 psf

Restrooms 50 psf

Storage ( light ) 125 psf

Classrooms 40 psf

Auditorium ( fixed seating ) 50 psf

Auditorium ( stage area ) 125 psf Exit Facilities 100 psf 

ROOF DEAD LOAD

Floor Dead Load 

-  Interior Partitions

=  65 psf  

ROOF LIVE LOAD

[ 1997 UBC, Table 16-C ]

Flat Roof = 20 psf

( < 33% slope )

Page 9: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Loading ConditionsLateral

EE

WIND LOADS [ 1997 UBC ] Exposure "B" [ Section 1616 ]

Basic Wind Speed = 70 mph [ Figure 16-1 ]

Wind Importance Factor (Iw) = 1.00 [ Table 16-K ]

Design Wind Pressure = P = ( Ce ) ( Cq ) ( qs ) ( Iw )

SEISMIC LOADS [ 1997 UBC ] Zone 3 [ Figure 16-2 ]

Soil Profile Type “SD” [ Table 16-J ]

Seismic Importance Factor (Ip) = 1.00 [ Table 16-K ]

Page 10: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

1st AlternativeAAOrientation

N

Page 11: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

1st AlternativeAAAccess

Page 12: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

1st AlternativeAAConcept

100 ft

100 ft

Page 13: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

1st AlternativeAAConcept

Page 14: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

1st AlternativeAAConcept

Page 15: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

1st AlternativeAAConcept

Page 16: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

1st AlternativeAAConcept

Page 17: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

1st AlternativeAAAdjacencies

1st floor

2nd floor

student offices

chair/senior admin./secretaries

faculty offices

3rd floor

Page 18: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

1st AlternativeAAOrganization

1st floor

3rd floor

2nd floorN

student offices

chair/senior admin./secretaries

faculty offices

Page 19: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

1st AlternativeAA

Page 20: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

1st AlternativeAAFloor Plans

1st floor

3rd floor

2nd floorN

Page 21: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

1st AlternativeAASections

Page 22: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

1st AlternativeAAElevations & Sketches

South-East North-West

South-West

Page 23: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

1st Alternative OptionsStructural Systems

EE

Design Considerations : Curved walls

• Interior and Exterior Non-Intrusive Columns Long spans in Auditorium Loading in Mechanical Room Symmetrical

Option # 1 : Steel Framing Braced Frame Lateral System

Option # 2 : Reinforced Concrete Framing Shear Wall Lateral System Steel support for Auditorium

Page 24: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Steel Option - 1st Alternative1st Floor Plan

EERationale : Ample locations for bracing

Braced Frame vs. Moment

• Reduces overall weight

• Simple connections

Wide, column free Auditorium proposes need for steel trusses.

W10x33

W10x33

LL 3x3x¼

Page 25: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Steel Option - 1st Alternative2nd Floor Plan

EESystem : Steel Framing

Open Web Steel Joists used to support flooring system

Total slab depth = 4” LWC

Non-Composite Metal Decking

• Type 1.0 C 26W16x40

20 K 4 (7.6 lb/ft)

Page 26: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Steel Option - 1st Alternative3rd Floor Plan

EE

W10x19

W16x57

W12x22

Page 27: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Steel Option - 1st AlternativeRoof Plan

EE

Details :

Reduced roof loading allows for greater spacing of joists.

Columns need to be placed within the Faculty Office area due to floor height restrictions.

Option # 1 Advantages :

Rigid, but flexible

Lightweight

Challenging

Opt. # 1 Disadvantages :

Curved Steel Fabrication

Page 28: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Truss DetailPanel Loading

EE

Details :

Faculty Offices above the Auditorium can not utilize similar framing to that in the Auditorium due to ceiling height restrictions.

Inner Column loads are carried by the Truss to the Outer Columns.

Page 29: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

RC Option - 1st Alternative3rd Floor Plan

EESystem : Reinforced Concrete Framing

One-Way slab @ 6” NWC

Long spans necessitate similar support above the Auditorium as used in Option # 1

Column and lateral support locations are the same as in Option #1

12” x 12”

h = 10”

20”x10”

20”x10”

Page 30: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

RC Option - 1st AlternativeRoof Plan

EE

Details :

Columns again needed in Faculty Office area to reduce span lengths and beam depths.

Option # 2 Advantages :

Curved Walls could be easily done through formwork.

Page 31: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Site AccessSquare Option

CC

Page 32: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Site LayoutSquare Option

CC

Page 33: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Equipment SelectionSquare Option

CC

•Hydraulic Excavator (front shovel & backhoe)

•Dump truck

•Hydraulic mobile crane

•Compactor

•Concrete pump

Page 34: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Constructibility IssuesCC• Curved Form: Steel members must be rolled during fabrication and formwork for concrete must be carefully designed.

• Symmetry allows for repetitious construction and ordering of steel elements; and reuse of formwork is possible for cost savings.

• Installation of trusses will be a challenge due to variable sizes.

Page 35: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Construction MethodsCC• Floor by Floor

Floor 1 Floor 2 Floor 3

Page 36: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Construction MethodsCC• Floor by Floor

•Phased

Floor 1 Floor 2 Floor 3

1 1 1

2 23 3

Page 37: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

ScheduleCC

Milestone: 1st Floor Deck and Slab

Milestone: 2nd Floor Deck and Slab

Milestone: 3rd Floor Deck and Slab

Finish: 4/21/2016

Page 38: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Cost DistributionCC

Substructure1.4%

Foundations4.3%

Special Construction

3.8%

Electrical10.3%

Mechanical37.2% Conveying

3.6%

Interior Construction

13.7%

Roofing0.8%

Exterior Closure

4.6%

Superstructure20.4%

Steel: $2,946,535

Hybrid: $2,831,030

Page 39: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

2nd AlternativeAAOrientation

N

Page 40: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

2nd AlternativeAAAccess

Page 41: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

2nd AlternativeAAConcept

76 ft

38 ft

76 ft

76 ft

76 ft

38 ft

38 ft

38 ft

Page 42: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

2nd AlternativeAAConcept

Page 43: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

2nd AlternativeAAConcept

Page 44: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

2nd AlternativeAAConcept

Page 45: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

2nd AlternativeAAOrganization

1st floor

3rd floor

2nd floor

student offices

chair/senior admin./secretaries

faculty offices

N

Page 46: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

2nd AlternativeAA

Page 47: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

2nd AlternativeAAFloor Plans

1st floor

3rd floor

2nd floorN

Page 48: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

2nd AlternativeAASections

Page 49: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

2nd AlternativeAAElevations & Sketches

South-East

North-East

Page 50: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

2nd Alternative OptionsStructural Systems

EE

Design Considerations : Regular Grid

Non-Intrusive Columns

Non-Symmetrical

Option # 1 :

Steel Moment Frame

Option # 2 :

Reinforced Concrete Framing

Shear Wall Lateral System

Page 51: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Steel Option - 2nd Alternative1st Floor Plan

EE

Rationale :

Few locations for bracing

Cantilevered, exterior circulation necessitates a stiffer structure.

Regular grid makes steel quick and easy

Wide, column free Auditorium proposes need for steel trusses or deep girders.

W12x50

W10x33

Page 52: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Steel Option - 2nd Alternative2nd Floor Plan

EE

System :

Steel Moment Frame

Open Web Steel Joists used to support flooring system

Total slab depth = 4” LWC

Non-Composite Metal Decking (Type 1.0 C 26)

W18x60

20 K 4 (7.6 lb/ft)

Page 53: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Steel Option - 2nd Alternative3rd Floor Plan

EE

W16x36

Page 54: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Steel Option - 2nd AlternativeRoof Plan

EE

Details :

Reduced roof loading allows for greater spacing of joists.

Option # 1 Advantages :

Rigid, Sturdy

No wall intrusions

Option # 1 Disadvantages :

Heavy

Connections …$$$

Page 55: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

RC Option - 2nd Alternative2nd Floor Plan

EE

System :

Reinforced Concrete

Framing

Shear Wall Lateral Support

One-Way slab @ 6” NWC

Column locations are the

same as in Option #1

12” x 12”

h = 10”

18”x16”

16”x14”

Page 56: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

RC Option - 2nd AlternativeRoof Plan

EE

Details :

Columns again needed in Faculty Office area to reduce span lengths and structural depths.

2-Way slab above Auditorium (hatched area) needed to support those columns.

Option # 2 Advantages :

Structural Regularity allows for formwork reuse.

Page 57: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Site AccessDouble-Square Option

CC

Page 58: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Site LayoutDouble-Square Option

CC

Page 59: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Equipment SelectionDouble-Square Option

CC

•Hydraulic Excavator (front shovel & backhoe)

•Dump truck

•Tower crane

•Compactor

•Concrete pump

Page 60: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Constructibility IssuesCC

• Shorter spans allow easier construction; rectangular form allows for fairly straightforward construction process.

• No symmetry: Lead to higher costs.

• Consider pre-fabricated concrete elements to shorten construction time.

• Longer boom length required for crane =>more expensive.

Page 61: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Construction MethodsCC• Floor by Floor

Floor 1 Floor 2 Floor 3

Page 62: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Construction MethodsCC• Floor by Floor

•Phased

1 1 2 21

3

Floor 1 Floor 2 Floor 3

Page 63: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Schedule - SteelCC

Milestone: 1st Floor Deck and Slab

Milestone: 2nd Floor Deck and Slab

Milestone: 3rd Floor Deck and Slab

Finish: 4/21/2016

Page 64: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Schedule - ConcreteCC

Finish: 5/12/2016

Milestone: 1st Floor Deck and Slab

Milestone: 2nd Floor Deck and Slab

Milestone: 3rd Floor Deck and Slab

Page 65: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Cost DistributionCCSteel:

$2,952,709

Concrete: $2,805,125

Page 66: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

$2,484,563

$2,946,535$2,831,070

$2,952,709$2,805,125

Budget Square Steel SquareSteel/Concrete

D. SquareSteel

D. SquareConcrete

Cost ComparisonCC

4% Inflation

& Fees Adjusted

Page 67: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Material ComparisonCC

PROS CONS

Steel Faster construction

Expensive,

Lead time

Concrete

(Cast-in-Place)

Cheap,

Flexible formwork

Time

consuming

Concrete

(Prefabricated)

Faster than CIP concrete

Expensive if no regular grid

Page 68: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Team Process & Interaction AA EE CC

Conceptual Sketches

Spatial Organization &

Circulation

Revision/ Redesign

Material Proposal

Constraints & Structural Options

Column Locations & Framing

Refining

Material Stability Issues

Site Constraints &

Considerations

Constructibility Issues

Material Options & Costs

Construction Costs &

Scheduling

Page 69: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Decision Matrix AdvantagesAdvantages DisadvantagesDisadvantages

Square Base

Double-Square Base

CC

CC

AA

EE

•Symmetrical•Short Construction Time

•Expensive Structural System•Curved form

•Rectangular form•Well-defined grid

•Longer reach for crane

•Much longer construction time with concrete

A A

EE

•Meets Spatial Requirements

•Minimal Circulation

•Floor Plan is crammed•Volume appears too massive

•Circulation as a path

•Interaction between inside and outside

•Spatial requirements are not entirely fulfilled

•Circulation has flaws

•Structural Symmetry•Lateral Support Availability

•Non-Orthogonal Connections•Non-regular column locations

•Regular structural grid•Relatively short spans

•Structural Symmetry•Lateral Support Availability

Page 70: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Proposed Solution

Square Base

11stst Alternative Alternative Provides a challenge for all disciplines

More Learning opportunities

Page 71: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Lessons Learned & Goals

How can we continue our design ?

Utilize available technology more efficiently

Improve and increase communication

Challenge each other

What did we learn ?

Each other’s work habits

How to get the most out of each other

The best ways to convey our ideas

Page 72: R I V E R 2 0 0 2 A rchitect Elena Paparizou Berkeley E ngineer Paul Kulseth Kansas C onst. Manager Wendy Wang Stanford O wner Jonathan Wong W i n t e

Q U E S T I O N S ?Q U E S T I O N S ?