Republic of the Philippines
University of Southeastern PhilippinesF. Iñigo St., Bo. Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524Trunkline: (082) 224-4480; 227-8192
www.usep.edu.ph; [email protected]
ISO 9001:2008QUALITY MANAGEMENT SYSTEM
COPY HOLDER: DCOISSUE STATUS: 01
MANUAL EFFECTIVITY: 10 OCTOBER 2016
This Manual is property of USeP.Reproduction in part or in whole is strictly prohibited and should not be brought out of the
Organization’s premises without prior consent or approval from the President.
MASTER COPY
QUALITY PROCEDURESMANUAL
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-TOC
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 1 of 2
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
TABLE OF CONTENTS
DOCUMENT NO. DOCUMENT TITLE ISSUE
STATUS
REV.
NO.
DATE EFFECTIVE NO. OF
PAGES
PM-USeP-TOC Table of Contents 01 00 10 October 2016 2
PM-USeP-COD Control of Documents 01 00 10 October 2016 9
PM-USeP-COR Control of Records 01 00 10 October 2016 7
PM-USeP-CER Control of External References 01 00 10 October 2016 3
PM-USeP-IQA Internal Quality Audit 01 00 10 October 2016 15
PM-USeP-HNC Handling of Non-conformance 01 00 10 October 2016 5
PM-USeP-CAR Corrective Action 01 00 10 October 2016 3
PM-USeP-PAR Preventive Action 01 00 10 October 2016 3
PM-USeP-OTS Objectives and Target Setting 01 00 10 October 2016 4
PM-USeP-CMR Conduct of Management Review 01 00 10 October 2016 4
PM-USeP-HCF Handling of Client’s Feedback 01 00 10 October 2016 8
PM-USeP-CMI Classroom Management Instruction 01 00 10 October 2016 3
PM-USeP-PIM Preparation of Instructional Materials 01 00 10 October 2016 3
PM-USeP-PPE Preparation of Periodic Examinations 01 00 10 October 2016 5
PM-USeP-PRC Preparation/Revision of Curriculum 01 00 10 October 2016 9
PM-USeP-PRS Preparation/Revision of Syllabus 01 00 10 October 2016 7
PM-USeP-CRP Conduct of Research Programs 01 00 10 October 2016 17
PM-USeP-CEP Conduct of Extension Programs 01 00 10 October 2016 11
PM-USeP-EOS Enrolment of Students 01 00 10 October 2016 2
PM-USeP-ANS Admission of New Students 01 00 10 October 2016 3
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-TOC
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 2 of 2
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
DOCUMENT NO. DOCUMENT TITLE ISSUE
STATUS
REV.
NO.
DATE EFFECTIVE NO. OF
PAGES
PM-USeP-RSC Request for Student Credentials 01 00 10 October 2016 6
PM-USeP-HSC Handling of Student Complaints 01 00 10 October 2016 3
PM-USeP-RSO Reaccreditation of Student
Organization
01 00 10 October 2016 3
PM-USeP-SEP Student Employment Process 01 00 10 October 2016 3
PM-USeP-FES Faculty Evaluation by Students 01 00 10 October 2016 3
PM-USeP-HSE Hiring and Selection of Employees 01 00 10 October 2016 6
PM-USeP-EPE Employees Performance Evaluation 01 00 10 October 2016 11
PM-USeP-TDE Training and Development of
Employees
01 00 10 October 2016 11
PM-USeP-ARS Admission and Renewal of Scholarship/
Grants
01 00 10 October 2016 7
PM-USeP-RGC Referral for Guidance and Counseling 01 00 10 October 2016 6
PM-USeP-PMS Preventive Maintenance Schedule 01 00 10 October 2016 3
PM-USeP-HOR Handling of Repairs 01 00 10 October 2016 4
PM-USeP-PUR Purchasing 01 00 10 October 2016 13
PM-USeP-IAI Inspection and Acceptance of Items 01 00 10 October 2016 7
PM-USeP-SOA Supplier and Outsource Accreditation 01 00 10 October 2016 5
PM-USeP-SMC Student Medical Consultation 01 00 10 October 2016 6
PM-USeP-IMC Issuance of Medical Certificate 01 00 10 October 2016 3
PM-USeP-AVR Audio-Visual Room Reservation 01 00 10 October 2016 4
PM-USeP-BBT Book Borrowing Transaction 01 00 10 October 2016 7
PM-USeP-LRA Library Resources Acquisition 01 00 10 October 2016 7
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
TITLE CONTROL OF DOCUMENTS
PURPOSE/S
To ensure that all documents are accurately recognized, rationalized, can be
retraced and approved before issued as references in the implementation of
the excellence management system.
SCOPE This procedure covers control of all internal documents used as references.
Control of external references is covered in PM-USeP-CER.
TERMS AND
DEFINITIONS Controlled Document - refers to any issued document which has been
uniquely identified for ease of traceability and recall. Such document cannot
be reproduced in any circumstances.
DCO - refers to Document Control Officer who handles documents and serves
as records controller of the organization.
Process / Activities Responsible Office /
Person/s
Details /
Reference
Concerned Office/Personnel Note 1
Concerned Office/Personnel Note 2
Concerned Office/Personnel
Concerned Office/Personnel Note 3
QMR Note 4
Prepare Document Change Request Record
Identify the need for New/Revise/Change Document
Amend Existing Document
Yes
No
New Document? Draft New Document
Review New/Revised/Changed Document
B
A
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COD
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 1 of 9
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COD
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 2 of 9
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
Process / Activities Responsible Office /
Person/s
Details /
Reference
President / QMR
Concerned Office/Personnel Note 5
DCO Note 6
DCO Note 7
QMR / Assigned Personnel Note 8
Update Document Master List
Finalize New/Revised/Changed Document
Issue New/Revised/Changed Document
Orient concerned personnel
Yes
Approved? B
No
A
NOTE 1:
1. All documents and data that are related to the implementation of the established Quality
Management System shall be controlled, reviewed and authorized by the QMR for adequacy
prior to issue and use.
2. The concerned office/personnel of the new/revise/change document discusses with the QMR
the proposed new/revise/change document to determine whether or not it is relevant to the
Quality System.
3. Documents may be required as a result of corrective action, preventive/improvement action,
or approval of new processes. Documents may also be deleted if found unnecessary anymore
in the implementation of the QMS.
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COD
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 3 of 9
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
NOTE 2:
1. If the document is found to be relevant, the QMR issues the Document Change Request (DCR)
using FM-USeP-COD-02 Form to the concerned office/personnel who shall fill it up with
appropriate information needed and affix signatures.
NOTE 3:
1. The concerned office/personnel returns the filled-up Document Change Request (FM-USeP-
COD-02) attached with a clean draft copy of the amended new/revised/changed document
to the QMR.
2. The QMR recommends the inclusion of the form to the QMS by affixing his/her signature and
submit the Document Change Request (FM-USeP-COD-02) and draft of the new/revised/
changed document to the Document Control Officer (DCO) for the assigned DCR No. and
discusses the necessity of the form.
NOTE 4:
1. Upon reviewing document, if the QMR finds the document relevant to the QMS, the DCR Form
will be submitted to the President for approval.
2. Upon approval, the QMR approves the reproduction and forwards the same to the DCO.
NOTE 5:
1. Quality Manual and Procedures Manual
a. All pages of the manuals have a header containing the following information:
- Organization’s name and address
- Manual name
- Document No.
- Issue Status
- Revision number
- Date Effective
- Page number (in the format # of # per section)
b. A footer identifying the authorized persons who prepared and approved the manuals.
c. Controlled copies issued to named individuals found in the Distribution List (FM-USeP-COD-
04) are stamped with “CONTROLLED COPY” at the front of all pages.
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COD
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 4 of 9
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
d. Master copy of documents is identified by a “MASTER COPY” stamped at the front of each
page.
2. Documents in the Quality Policy Manual and Procedures Manual including the Forms are
assigned with a unique number for proper identification.
3. Unique numbering of the established manuals are as follows:
4. Documents become effective upon approval.
NOTE 6:
1. For changes in the Quality Policy and Procedures Manuals, the Document Master List (FM-
USeP-COD-01) and the Document Change Register (FM-USeP-COD-03) shall be updated.
2. The DCO shall indicate in the document the revision status and effectivity date of the change
(s) in the document.
3. For revised/changed document, the Master and Controlled Copies of the obsolete
documents are stamped with “OBSOLETE”. Only the obsolete Master copy is retained for
reference throughout the life of the quality system. Obsolete Controlled copies may be
recycled or reuse.
4. The DCO will collect the controlled copies from the process owners and update the
Distribution List to ensure its adequacy prior to its use.
NOTE 7:
1. New/Revisions/Changes of the manuals must be recorded. The recipient signs on the updated
Distribution List (FM-USeP-COD-04) to ensure that all copy holders are given the new/revised/
changed document.
2. In case of loss of issued copies, the copyholder prepares a CPAR and declares the copy as
Quality
Policy
Name of
Organization
Title Abbreviation
QP-USeP-TOC PM-USeP-COD
Procedures
Manual
Name of
Organization
Process Abbreviation
Sequence
FM-USeP-COD-01
Form Name of
Organization
Process Abbreviation
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COD
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 5 of 9
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
lost; document controller updates the Distribution List.
3. Review of documents is conducted by the DCO and QMR once every year or as deemed
necessary to verify whether there are documents that need to be revised/updated/abolished.
4. Manuals may be re-issued by the DCO as approved by the President or QMR. Only the Master
Copy will be reproduced.
NOTE 8:
1. The QMR/Assigned Personnel orients on the new/revised/changed documents for proper
implementation of the documented system.
2. Holders of controlled documents shall be responsible for the storage and protection of these
documents to prevent loss and damage.
RECORDS GENERATED:
Document Master List FM-USeP-COD-01
Document Change Request FM-USeP-COD-02
Document Change Register FM-USeP-COD-03
Distribution List FM-USeP-COD-04
FORM/S:
Document Master List FM-USeP-COD-01
Document Change Request FM-USeP-COD-02
Document Change Register FM-USeP-COD-03
Distribution List FM-USeP-COD-04
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COD
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 6 of 9
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COD
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 7 of 9
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COD
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 8 of 9
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COD
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 9 of 9
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
TITLE CONTROL OF RECORDS
PURPOSE/S
To ensure that all proceedings produced during the implementation of the
excellence management system are properly recognized, stored and secured
to avoid mislay of records.
To ensure that the custodian checked the records well and these are up to
date, if the time retention has lapsed.
To ensure compliance to the rules and regulations prescribed under the
Republic Act 9470 or the National Archives of the Philippines (NAP) Act of 2007.
To ensure compliance with the guidelines set in the established records
management policy. SCOPE
This procedure covers all essential records control.
TERMS AND
DEFINITIONS Record - a document stating results achieved to provide evidence of activities
performed.
Record Disposition - the orderly maintenance of records necessary to protect
the interest of economy and efficiency, the prompt disposal of valueless
records.
Process / Activities Responsible Office/
Person/s
Details /
Reference
Concerned Office/Personnel Note 1
Concerned Personnel Note 2
DCO Note 3
Concerned Office/Personnel Note 4
DCO Note 5
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 1 of 7
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
File Records generated
Generate required Records
Monitor retention periods of filed Records
Dispose Obsolete Records
Monitor filing
Yes
Lapsed? No
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 2 of 7
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
NOTE 1:
1. Generate all records required in the procedures.
2. Records are documents/data which furnish objective evidence of activities performed or
results achieved in the implementation of the Quality Management System or evidence of
conformity to any statutory and regulatory requirement.
2. Ensure all required data in forms used are completely filled-out including portions that require
signatures.
3. Client provided records such as personal data are considered customer property and are
covered in Control of External References procedure (PM-USeP-CER).
NOTE 2:
1. Records shall remain legible, readily identifiable and retrievable.
2. The identification of storage, retention time, disposal and custodian of records, are indicated
in the Masterlist of Records (FM-USeP-COR-01).
3. Records received through fax would have to be photocopied and then filed.
4. Incoming and outgoing communications shall be properly recorded and disseminated in
accordance to the Communication Flow maintained and established in each campus.
5. Each office shall keep Records in filing/storage cabinets properly labelled to ensure easy
identification of the locations of files.
6. Electronic data, back up files shall be saved in external hard drives and shall be maintained
to protect records from fire and other similar calamities.
7. Refer the Work Instructions Manual for the Records Management System.
NOTE 3:
1. It is the concern of the university personnel to exercise control of records as required in their
respective duties and responsibilities.
2. Externally generated documents shall be recorded in the Masterlist of External Reference (FM
-USeP-COR-01) and updated from time to time.
3. Superseded documents like circulars, guidelines memoranda, etc. shall be removed and
marked “obsolete” to preclude use. A copy may be retained for reference purposes marked
as “obsolete”.
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 3 of 7
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
NOTE 4:
1. Refer to Records Management Policy for the disposal of records.
2. Non-confidential records can be recycled but ensure that the wrong side would have to be
crossed once or stamped with “OBSOLETE” to avoid confusion.
NOTE 5:
1. Monitor filing of all records based on the Masterlist of Records (FM-USeP-COR-01).
2. The document controller also files a copy of all the DCO’s Masterlist of Records (FM-USeP-
COR-01) to serve as back up, but updating of the Masterlist of Records is done by the
individual DCO every Department.
3. Changes in records are initialed by authorized personnel.
4. Records may be reproduced when required as approved by the President or the QMR.
5. Review Masterlist of Records (FM-USeP-COR-01) at least once a year.
RECORDS GENERATED:
Masterlist of Records FM-USeP-COR-01
Incoming/Outgoing Correspondence Register
(previously Form No. 2-A) FM-USeP-COR-02
Incoming Courier and Postal Mail Register
(previously Form No. 2-B) FM-USeP-COR-03
Mail Forwarding Service Register
(previously Form No. 2-C) FM-USeP-COR-04
FORM/S:
Masterlist of Records FM-USeP-COR-01
Incoming/Outgoing Correspondence Register FM-USeP-COR-02
Incoming Courier and Postal Mail Register FM-USeP-COR-03
Mail Forwarding Service Register FM-USeP-COR-04
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 4 of 7
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 5 of 7
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 6 of 7
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-COR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 7 of 7
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
TITLE CONTROL OF EXTERNAL REFERENCES
PURPOSE/S To ensure that all external references used in the implementation of the quality
management system are accurately acknowledged, protected and efficient.
SCOPE This procedure covers control of all external references such as policies and
memoranda, machine manuals, copies of regulatory requirements and other
documents of external origin that are relevant to the operations of the
organization excluding Client’s property and the references in the Library,
which shall be controlled under the Registrar’s Office policy and Library
process, respectively. TERMS AND
DEFINITION/S External Reference - refers to documents of external origin determined by the
organization to be necessary for the planning and operation of the quality
management system.
Process / Activities Responsible Office/
Person/s
Details /
Reference
Concerned Office/Personnel Note 1
DCO Note 2
DCO Note 3
DCO Note 4
Compile Master List of External References
Identify External References
Log Borrowed References
Identify New Issues and Update Master List
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-CER
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 1 of 3
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-CER
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 2 of 3
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
NOTE 1:
1. Identify external references used in the implementation of the quality management system.
Prepare Masterlist of External References (FM-USeP-CER-01).
2. Masterlist of External References can be generated from different institution/offices received
in Obrero campus.
NOTE 2:
1. Compile all Masterlist of External References (FM-USeP-CER-01).
2. Stamp cover page of external references with “CONTROLLED COPY” before filing or issuance.
3. Books, Manuals or other references that are personally owned by the Professor are excluded
in the masterlist.
NOTE 3:
1. Use the External Reference Logbook to monitor the borrowing and returning of references.
2. The External Reference Logbook records the following data:
- Date Borrowed - Title of External Reference - Borrower
- Borrower’s Signature - Date Returned - Remarks
NOTE 4:
1. Identify new issues or updates of external references.
2. Update the Masterlist of External References (FM-USeP-CER-01).
3. Review of the Masterlist of External References (FM-USeP-CER-01) is done every year.
RECORDS GENERATED:
Master List of External References FM-USeP-CER-01
FORM/S:
Master List of External References FM-USeP-CER-01
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082)2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-CER
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 3 of 3
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
TITLE INTERNAL QUALITY AUDIT
PURPOSE/S
To establish and maintain a documented procedure for the conduct of internal
quality audits in order to:
determine whether the Quality Management System (QMS) conforms to the
planned arrangements, to the requirements of ISO 9001: 2008 and to the
specified requirements of NMIT documented QMS.
verify the implementation and effectiveness of the QMS in meeting specified
quality objectives.
provide the auditee with an opportunity to improve the quality system and
consistently meet the regulatory requirements.
SCOPE This procedure shall cover all the elements and processes of the Quality
Management System in all levels. This starts with the preparation of an Annual
Audit Plan, planning the actual conduct of the audit, audit proper, reporting
the results of the audit, verifying the actions taken to correct / prevent non-
conformances raised and ends with the preparation of the IQA summary
report indicating the status of the non-conformances to be reported during
Management Review Meeting.
TERMS AND
DEFINITIONS
Internal Quality Audit or IQA - a systematic, independent, and documented
process for obtaining audit evidence and evaluating it objectively to
determine the extent to which audit criteria are fulfilled.
IQA Team - a group of qualified, identified and designated personnel who shall
conduct the internal quality audit based on a documented procedure. These
personnel are also called Internal Quality Auditors.
Audit Plan is a document that contains the objective and scope of the IQA,
the date and place of audit, the functional units to audit, time and duration of
each major audit.
Non-Conformance or NC is a violation of client requirements or lapses in the
implementation of the process.
IQA Report - a document that details the results of the IQA.
Checklist - an instrument that is used to guide and/or assist the auditor in the
audit process and to provide a record of questions and observations.
Objective Evidence is an information which can be proved true based on
facts obtained through observation, measurement, test or other means.
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-IQA
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 1 of 15
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-IQA
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 2 of 15
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
TERMS AND
DEFINITIONS Major NC is a complete breakdown of the system having a major impact to
the delivery of services to the client e.g. absence of a quality system element,
a procedure, or objective evidence of the quality systems’
implementation; non-fulfilment of statutory / regulatory requirement of CHEd.
Minor NC is a single “lapse” /”slip” of compliance to a documented quality
system or implementation thereof.
Observation means any finding that is not covered by any procedure but will
help improve the organization or a possible non-conformance in the future if it
will not be addressed.
Process / Activities Responsible Office/
Person/s
Details /
Reference
Lead Auditor/Team Note 1
Lead Auditor/Team Note 2
QMR / President Note 3
Lead Auditor Note 4
Internal Auditors Note 5
Internal Lead Auditor Note 6
Prepare Audit Plan
Prepare Annual Audit Program
Prepare Internal Memo / Send Notice of Audit
Review and Approval
Prepare Audit Checklist
Briefing of the IQA Auditors
A
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-IQA
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 3 of 15
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
Process / Activities Responsible Office/
Person/s
Details /
Reference
Lead Auditor Note 7
IQA Team
Internal Auditors / Auditee
Lead Auditor
Auditee Note 8
Auditor / Lead Auditor / QMR Note 9
Auditor
Lead Auditor Note 10
Conduct of Audit
Opening meeting
Prepare Report & Discuss the findings with the Auditee
Closing Meeting
Formulate Corrective & Preventive Actions
Monitor Corrective & Preventive Actions
Close-out Non-conformance
Is Corrective/Preventive
Action effective?
Yes
Request for new Corrective/
Preventive Action
No
Update IQA Records
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-IQA
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 4 of 15
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
NOTE 1:
1. Prepare Annual Internal Quality Audit Program (FM-USeP-IQA-01).
2. At least two regular or full audits are scheduled each year or as deemed necessary.
3. Special audits are scheduled whenever unfavorable trends are identified and reported during
operations. Unfavorable trends may include: numerous customer complaints, accidents/
emergencies, decrease in productivity. Special Internal Audits may also be conducted to
evaluate implementation of new processes critical in achieving product and process quality.
Scope of special audits may cover only areas where problems are identified.
4. The annual audit program will be prepared at least one (1) month prior the coming year to be
reviewed and approved by the QMR and the President, respectively.
NOTE 2:
1. The Audit Plan (FM-USeP-IQA-02) details the date/s, time, venue and who are the auditors of
each process and ensures that all relevant ISO clauses are covered by the auditor.
2. Considerations in scheduling the processes to be audited are:
a. Availability of Process Owners or Auditees
b. New Process
c. Number of Client Complaints
d. New Employees
SELECTION OF AUDITORS’
1. The President together with the QMR and the Management Team select auditors in the
following criteria:
At least a BS Degree holder;
Work experience in the University of at least six months;
Trained/attended or re-echoed from the attendees of the Internal Audit training
Familiar with the organization processes
At least familiar with ISO standards and management principles
For the Audit Team leader or Lead Auditor: Must have attended the Internal Quality Audit
Lead Auditor Course or have attended at least Internal Quality Audit Training/Seminar.
2. The QMR issues a written designation to the selected Auditors/Lead Auditors duly confirmed
by the President.
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-IQA
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 5 of 15
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
LEAD AUDITOR’S AND AUDITORS’ RESPONSIBILITIES
1. Only trained personnel are allowed to conduct internal audits. Auditors’ performances are
monitored through feedbacks from auditees which also serve as inputs to the continuing
training program.
2. Auditors cannot audit their own processes/areas.
3. Methods in auditing include interview and verification of records.
NOTE 3:
1. The Audit Plan/Itinerary is submitted to the QMR and President for review and approval.
2. The Lead Auditor will revise the Audit Plan / Itinerary if it is not approved.
NOTE 4:
1. The Lead Auditor prepares internal memo and send notice of audit to each department/
office prior to the audit schedule. Likewise, the designated Internal Quality Auditors are
advised to prepare audit checklist.
NOTE 5:
1. Checklists (FM-USeP-IQA-03) may be prepared for each process with consideration on the
relevant clauses of the ISO standard, which serves as guide during audits to aid time
management, ensures depth and continuity, and to ensure all relevant aspects are covered.
2. Checklists (FM-USeP-IQA-03) may be updated during each audit.
NOTE 6:
1. A day before the audit proper, the Lead Auditor will discuss the audit plan to the IQA Team.
2. IQA Team Leader will give final details to Auditors prior to opening meeting with the auditees.
NOTE 7:
1. An opening meeting shall be held with the auditee’s management or where appropriate,
those responsible for the functions or processes to be audited.
2. The meeting should be formal and reports of the attendance should be kept. The meeting
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-IQA
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 6 of 15
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
should be chaired by the audit team leader.
3, The audit team shall confer periodically to exchange information, assess audit progress, and
to reassign work between the audit team members as needed.
4. Guides and observers may accompany the audit team but are not part of it. They should not
influence or interfere with the conduct of the audit.
5. Information relevant to the audit objectives, scope and criteria including information relating
to interfaces between functions, activities and processes should be collected by appropriate
sampling and should be verified. Audit evidence should be recorded. Methods to collect
information: interviews, observation of activities and review of documents.
6. A closing meeting chaired by the Audit team leader should be held to present the audit
findings and conclusions in such a manner that they are understood and acknowledged by
the auditee, and to agree, if appropriate, on the time frame for the auditee to present a
corrective and preventive action plan. Participants in the closing meeting shall include the
auditee among other parties. Minutes and attendance should be kept.
7. Any diverging opinions regarding the audit findings and/or conclusions between the audit
team and the auditee should be discussed and if possible, resolved. If not resolved, all
opinions should be recorded.
Note: While conducting the audit, auditors seek objective evidence demonstrating whether
the audited activities conform with the requirements of the organization’s Quality
Management System, ISO 9001:2008 requirements as well as statutory and regulatory
requirements.
8. The members of the audit team are responsible for the preparation of the Internal Quality
Audit Report (IQAR) (FM-USeP-IQA-04). The audit report should provide a complete, accurate,
concise and clear record of the findings of the audit.
9. The auditee fills-out the following portions of the Internal Quality Audit Report:
- Analysis of root cause(s)
- Correction
- Corrective Action
- Preventive Action
NOTE 8:
1. Formulation of correction, corrective and preventive actions.
a. Correction – are actions taken immediately to suppress the identified non-conformity
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-IQA
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 7 of 15
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
b. Corrective actions - are actions taken to eliminate the root cause of an existing non-
conformity, reject, or other undesirable condition to prevent recurrence.
c. Preventive actions - are actions taken to eliminate the root cause of a potential non-
conformity or other undesirable condition to prevent its occurrence.
2. The assigned auditor will approve the proposed actions and will be responsible to monitor
implementation of such.
3. The IQAR will be submitted to the Team Leader. And the Team Leader will prepare the Internal
Quality Audit Summary Report (FM-USeP-IQA-05) to be submitted to the QMR.
NOTE 9:
1. The designated Internal Quality Auditors verify the effectiveness of corrective / preventive
action taken.
2. If Corrective / Preventive Action is not effective, advise Department/Office Head and extend
period of implementation, if necessary, then indicate the details of the arrangements made in
the existing IQAR Form or issue another IQAR Form.
3. The Internal Quality Auditor will indicate the status of the corrective /preventive action in the
Summary of IQAR as Open (no action was taken). On-going (action was taken but not
completed).
4. If the Internal Quality Auditor is satisfied on the effectiveness of corrective / preventive action
taken, the non-conformances are then closed out.
NOTE 10:
1. Every internal audit shall be numbered sequentially using the IQA Register (FM-USeP-IQA-07) in
order to facilitate monitoring and referencing, such as IQA No. 01-1116 (IQA No. 01-MoYr)
which means, 01 is the first audit, 11 is the month and 16 is the last two digits of the calendar
year 2016. Thus, 01-1116 means the first Internal Quality audit for calendar year 2016
conducted in the month of November.
2. The results of the audit shall be discussed during the management review meeting.
3. The summary of the Internal Quality Audit Report will be presented to the management and
discuss realizations and findings of the internal audit conducted.
4. Internal Quality Auditors Team shall be evaluated using the Internal Auditor Evaluation Form
(FM-USeP-IQA-06).
5. The evaluation form will be submitted to the Lead Auditor or QMR for review.
6. The QMR presents the results of the evaluation during the management review.
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-IQA
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 8 of 15
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
RECORDS GENERATED:
Annual Internal Quality Audit Program FM-USeP-IQA-01
Audit Plan FM-USeP-IQA-02
Audit Checklist FM-USeP-IQA-03
Internal Quality Audit Report FM-USeP-IQA-04
Internal Quality Audit Summary Report FM-USeP-IQA-05
Internal Auditor Evaluation FM-USeP-IQA-06
IQA Register FM-USeP-IQA-07
Corrective/Preventive Action Report FM-USeP-HNC-01
CPAR Monitoring FM-USeP-HNC-02
Minutes of Meeting
FORM/S:
Annual Internal Quality Audit Program FM-USeP-IQA-01
Audit Plan FM-USeP-IQA-02
Audit Checklist FM-USeP-IQA-03
Internal Quality Audit Report FM-USeP-IQA-04
Internal Quality Audit Summary Report FM-USeP-IQA-05
Internal Auditor Evaluation FM-USeP-IQA-06
IQA Register FM-USeP-IQA-07
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-IQA
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 9 of 15
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-IQA
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 10 of 15
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-IQA
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 11 of 15
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-IQA
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 12 of 15
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-IQA
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 13 of 15
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-IQA
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 14 of 15
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-IQA
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 15 of 15
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
TITLE HANDLING OF NON-CONFORMANCE
PURPOSE/S To ensure that all nonconforming products are identified, analyze to avoid its
unintended use.
SCOPE This procedure covers activities from identification up to the analysis of non-
conformances during operations that lead to the formulation of corrective and
preventive actions.
TERMS AND
DEFINITION/S Non-conformance - an observed situation where objective evidence indicates
the none-fulfilment of a specified requirement of the Quality Management
System. It is also a fundamental breakdown of the Standard.
It is categorized into:
- Major non-conformance: a deviation from the planned arrangements which
impinges on the quality of service delivered to the customer.
- Minor non-conformance: a single lapse in a procedure or instruction which is
not critical to the operation.
Process / Activities Responsible Office/
Person/s
Details /
Reference
Concerned Personnel Note 1
Process owners / QMR Note 2
President Note 3
QMR Note 4
Analyze Non-conforming product/output
Identify Non-conforming output
Formulate, Review and approve Actions
Implement and Monitor Actions
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-HNC
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 1 of 5
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-HNC
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 2 of 5
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
NOTE 1:
1. Identify all non-conformances during each process in operations.
2. Non-conformance can be identified in the following:
a. Non-compliance to the CHEd Memorandum Order (CMO)
b. Unapproved course design
c. inspection of purchased items
d. Unapproved Students activities and/or Organizations
e. Enrolment and Admission of Students
f. Unapproved Syllabus
g. Failure to generate records
h. Utilizing forms not prescribed to the documented system
i. Failure to monitor Quality Objectives and Targets
j. Student’s Feedback
k. and other related lapses or violation of the implementation to the established documented
system.
NOTE 2:
1. Record actions formulated in the Corrective/Preventive Action Form (FM-USeP-HNC-01).
Refer to Corrective Action procedure (PM-USeP-CAR) and Preventive Action procedure
(PM-USeP-PAR).
NOTE 3:
1. Review overall impact of the corrective/preventive actions recommended on the overall
integrity of the management system.
NOTE 4:
1. Monitor the status of implementation of the CPAR using the CPAR monitoring (FM-USeP-HNC-
02).
2. Generated reports to be discussed during Management Review which is conducted at least
twice a year.
3. For Management Review, refer to Conduct of Management Review procedure (PM-USeP-
CMR).
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-HNC
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 3 of 5
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
RECORDS GENERATED:
Corrective/Preventive Action Report FM-USeP-HNC-01
CPAR Monitoring FM-USeP-HNC-02
Status Reports
FORM/S:
Corrective/Preventive Action Report FM-USeP-HNC-01
CPAR Monitoring FM-USeP-HNC-02
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-HNC
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 4 of 5
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-HNC
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 5 of 5
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
TITLE CORRECTIVE ACTION
PURPOSE/S
To ensure all non-conformances identified during the implementation of the
management system are analyzed and actions formulated to eliminate their
root causes. This is to prevent recurrence of a non-conformance.
SCOPE This procedure covers formulation and implementation of corrective actions
for all types of non-conformances identified.
TERMS AND
DEFINITIONS Corrective Action - an action to eliminate the cause of a detected
nonconformity or other undesirable situation” – PREVENT RECURRENCE.
Process / Activities Responsible Office/
Person/s
Details /
Reference
Concerned Personnel Note 1
Process owners / QMR Note 2
QMR/President Note 3
QMR/President Note 4
Concerned Office/Personnel Note 5
QMR Note 6
QMR Note 7
Analyze & Formulate Action
Identify Non-Conformance
Review proposed Actions
Approve Recommended Actions
Implement Approved Actions
Monitor Implementation and finalize change
Discuss during Management Review
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-CAR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 1 of 3
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-CAR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 2 of 3
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
NOTE 1:
1. Identify potential non-conformances and/or improvements during the implementation of
each process, and record details in the Corrective/Preventive Action Report (CPAR) using the
FM-USeP-HNC-01 form.
2. The concerned personnel or anyone within the organization or from independent assessor
who identifies a problem in the work process, finds a non-conformance or deficiency in the
Quality Management System or work process.
3. Non-conformance or Deficiencies can be identified through the internal or external audits, by
observing the employees at work, from students’ feedback, interviews, review of documents.
The concerned personnel asks for the CPAR Form (FM-USeP-HNC-01) from the DCO and fills it
up stating the non-conformance identified.
4. The Document Controller monitors issuance of the forms and is in-charge of updating the
CPAR Monitoring (FM-USeP-HNC-02) who is supervised by the QMR.
NOTE 2:
1. The requested party or the process owner/s to whom the non-conformity is addressed takes
action based on the request.
2. If the nature of the corrective action is emergency the requested party or process owner/s fill-
out the form on the identified root-cause/s and the corrective action/s to be taken.
3. Analyze and identify root causes of the potential non-conformance and/or justifications for
improvement actions. Record result of analysis in the Corrective/Preventive Action Report (FM
-USeP-HNC-01). Formulate and recommend actions to be taken. Ensure time frames and
responsibilities for actions are clearly defined. The QMR may also help in the formulation of
preventive/improvement action.
4. The person responsible to undertake the Corrective action is to be identified. The target date
of completion is to be specified.
NOTE 3:
1. The QMR evaluates the corrective action to be taken. If it is adequate to prevent future
recurrence of the problem. If the matter is beyond the capacity of the QMR, the QMR may
refer the matter to the President.
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-CAR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 3 of 3
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
NOTE 4:
1. If the corrective action is acceptable, the QMR or the President will approve the CPAR.
2. The Corrective Action is considered effective if after one (1) month implementation or within
the project duration and the nonconformance did not recur.
NOTE 5:
1. The implementation of the proposed actions shall be within the specified target period or
timeframes of the process owners to implement.
NOTE 6:
1. Monitor implementation of the recommended actions following defined time frames. Identify
interfaces with other processes of the management system and determine effects. If actions
taken are effective (the same problem did not recur), formalize the changes.
2. Prepare Document Change Request Form (FM-USeP-DOC-02) to revise affected
documents or to issue new documents to formalize full implementation. Refer to Control of
Documents procedure (PM-USeP-COD).
NOTE 7:
1. If the action taken is inadequate, the concerned personnel/process owner may request
another corrective action from the other entity to act on the problem.
2. If the concerned office/personnel or process owner failed to implement the corrective action
within the specified timeframe, the QMR has the option to recommend directly to the
President for proper action, which will be discussed during the Management Review meeting
for deliberation.
RECORDS GENERATED:
Corrective/Preventive Action Report FM-USeP-HNC-01
CPAR Monitoring FM-USeP-HNC-02
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
TITLE PREVENTIVE ACTION
PURPOSE/S
To ensure all potential non-conformance identified during the implementation
of the management system are analyzed and actions formulated to eliminate
their root causes. This is to prevent occurrence of a potential non-
conformance.
SCOPE This procedure covers formulation and implementation of preventive actions
for all types of potential non-conformances and/or improvement actions
identified.
TERMS AND
DEFINITION/S Preventive Action - is an action to eliminate the cause of a potential
nonconformity or other undesirable potential situation” – PREVENT
OCCURRENCE.
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-PAR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 1 of 3
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
Process / Activities Responsible Office/
Person/s
Details /
Reference
Concerned Personnel Note 1
Process owners / QMR Note 2
QMR/President Note 3
QMR/President Note 4
Concerned Office/Personnel Note 5
QMR Note 6
QMR Note 7
Identify Potential Non-Conformance or Improvement
Review proposed Actions
Approve Recommended Actions
Analyze & Formulate Action
Implement Approved Actions
Monitor Implementation and formalize change
Close-out Preventive Action
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-PAR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 2 of 3
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
NOTE 1:
1. The concerned personnel or anyone within the organization or from independent assessor
who identifies an area where a possible or potential problem may be present.
2. He/she may discuss to the QMR and ask assistance on what and how to gather data or
information to support his/her claim that a possible or potential problem may be present.
NOTE 2:
1. After the analysis and gathering of data, the concerned personnel asks for CPAR form (FM-
USeP-HNC-01) and fills up the form and attach necessary data gathered and submit it to the
QMR who in turn records appropriate entries.
NOTE 3:
1. The QMR reviews the submitted report and data gathered in coordination with other
personnel identified by the QMR that may be able to help to formulate action plans.
2. The concerned office must agree on what action plan is to be taken.
NOTE 4:
1. If the Preventive action is acceptable, the QMR or the President will approve the CPAR.
2. The Preventive Action is considered effective if after one (1) month implementation or within
project duration and the nonconformance did not recur.
NOTE 5:
1. The implementation of the proposed actions shall be within the specified target period or
timeframes of the process owners to implement.
2. The concerned personnel identified to implement the action plan undertake the necessary
measures as agreed.
3. Any problem in the implementation may be discussed in another meeting, be it formal or
informal, to clarify the implementation plan.
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-PAR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 3 of 3
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
NOTE 6:
1. Monitor implementation of the recommended actions following defined time frames. Identify
interfaces with other processes of the management system and determine effects. If actions
taken are effective (the same problem did not recur), formalize the changes.
2. Prepare Document Change Request Form (FM-USeP-DOC-02) to revise affected
documents or to issue new documents to formalize full implementation. Refer to Control of
Documents procedure (PM-USeP-COD).
NOTE 7:
1. Closing-out of the Preventive Action.
The QMR initiates the meeting to follow-up the progress of the action taken on the
agreed date to make a follow-up discussion.
The same persons who formulate and finalize the action to be taken are the ones to
attend this meeting.
The group must agree whether the action taken is effective or not.
If not effective, the concerned personnel will file another CPAR so that another action
plan will be formulated. In this case, preventive action will not be closed but notations
will be written that another CPAR is filed for another action plan.
If a problem occurs before the closing out of the preventive action taken, a CPAR
request will be filed following the Corrective Action procedure (PM-USeP-CAR).
RECORDS GENERATED:
Corrective/Preventive Action Report FM-USeP-HNC-01
CPAR Monitoring FM-USeP-HNC-02
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
TITLE OBJECTIVES AND TARGET SETTING
PURPOSE/S
To ensure that directions and targets are set based on the vision, mission, goals
and quality policy of the Organization.
To ensure programs are formulated that are aligned to these set of directions.
SCOPE This procedure covers steps from planning, goal setting and program
formulation to review and approval of formulated action plans.
TERMS AND
DEFINITION/S Objectives and Targets of the University are based on the established Agency
Performance Commitment and Review (APCR).
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-OTS
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 1 of 4
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
Process / Activities Responsible Office/
Person/s
Details /
Reference
President/Management
Team Note 1
President/Management
Team Note 2
President/Management
Team Note 3
President/Management
Team Note 4
QMR Note 5
Review Vision, Mission, Goals, Quality Policy
Formulate Strategic Action Plans
Review and Approve Summary of Objectives
Formulate Objectives and Targets
Implement Approved Plans
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-OTS
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 2 of 4
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
NOTE 1:
1. The review includes:
a. Operations results of previous year.
b. Achievement of the Quality Policy and objectives of previous year.
2. Minutes of meeting shall be prepared for the results of review.
NOTE 2:
1. Formulate targets and objectives based on the Agency Performance Commitment and
Review (APCR). Ensure that the objectives (goals) and targets are consistent with the
customer needs, wants and expectations.
2. Ensure that the targets are aligned to the Quality Policy.
3. The quality policy sets out the USeP vision, mission and goals. The stated policy in the QMS
may be extracted, published and placed in accessible areas within Malita campus. This shall
provide the USeP’s Students, Suppliers, Certifying or Accrediting bodies information on its
intention of rendering quality service to its clientele.
4. The Quality Policy shall be posted in a conspicuous area for wide dissemination and
information to the USeP employees, students, and visitors/guests.
NOTE 3:
1. Prepare Monitoring of Objectives and Targets (FM-USeP-OTS-01) addressing issues on human
resource administration, student-related, quality objectives, customer satisfaction plans, and
current and future customer expectations.
2. Define responsibilities and time frames.
3. Ensure that the responsibilities are distributed to all relevant functions to ensure that activities
are implemented on time.
4. Ensure that all personnel included in the plans understand and agree on the functions
assigned to them.
NOTE 4:
1. Consider completeness, significance and attainability of the plan.
2. Consider the practicability and feasibility of the plans with regard to the company’s available
resources.
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-OTS
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 3 of 4
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
3. Ensure that the plans address the significant concerns and requirements of all stakeholders.
4. Ensure that each process has corresponding objectives and targets set.
NOTE 5:
1. Monitor implementation. Ensure that a monthly actual data is compiled every after end of
the month. Use the Monitoring of Quality Objectives and Targets (FM-USeP-OTS-01) to record
the monthly data.
2. There shall be evaluation through Internal Quality Audits to verify the effectiveness in the
implementation of the Quality Management System and conformance to the established
standards and to the statutory and regulatory requirements.
3. Any discussions pertaining to the status of targets and plans would have to be recorded in
the Minutes of Meetings.
4. CPAR for unmet targets is prepared quarterly. Refer to Corrective Action Procedure (PM-USeP
-CAR).
RECORDS GENERATED:
Monitoring of Quality Objectives and Targets FM-USeP-OTS-01
CPAR FM-USeP-HNC-01
CPAR Monitoring FM-USeP-HNC-02
Minutes of Meetings
FORM/S:
Monitoring of Quality Objectives and Targets FM-USeP-OTS-01
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-OTS
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 4 of 4
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
TITLE CONDUCT OF MANAGEMENT REVIEW
PURPOSE/S To ensure the management system’s continuing suitability, adequacy and
effectiveness through periodic reviews.
SCOPE This procedure covers activities in conducting a management review. This is
done at least twice a year.
TERMS AND
DEFINITIONS
Management Review - the process of reviewing the QMS by top management
at planned intervals in accordance with the requirements of ISO 9001:2008
Standard.
Review Input - the seven items specified in section 5.6.2 of the Standard.
Review Output - the decisions and actions related to the improvement of the
QMS.
Process / Activities Responsible Office/
Person/s
Details /
Reference
QMR Note 1
President/QMR Note 2
QMR / Appointed Secretary Note 3
QMR Note 4
QMR Note 5
Conduct Management Review Meeting
Schedule Management Review Meeting
Prepare Minutes of the Meeting
Monitor Implementation of Resolutions
Discuss Results in Subsequent Review
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-CMR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 1 of 4
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-CMR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 2 of 4
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
NOTE 1:
1. The Management Review Team shall convene and conduct a Management Review meeting
to review the Quality Management System’s adequacy and effectiveness and to assess
opportunities for improvement and the need for changes in the QMS including the quality
policy and quality objectives.
2. The QMR prepares the schedule of the management review meeting and seeks approval
from the President.
3. The QMR prepares notice of meeting informing concerned personnel prior the schedule of
the management review meeting.
NOTE 2:
1. The President or the QMR in the absence of the President shall preside the meeting and
ensures the attendance of appropriate key Office Personnel.
2. A secretary of the meeting is appointed to transcribe discussions. Attendance sheet is routed
and signed by the persons present in the meeting.
3. The QMR will read the minutes of the previous meeting. It will serve as the review of what
were discussed before.
4. The inputs to be discussed in the meeting shall include the seven (7) review inputs, which are
as follows:
1. Results of the internal and external audits;
2. Customer feedback;
3. Process performance and product conformity;
4. Status of preventive and corrective action;
5. Follow-up actions from previous MRC meetings;
6. Changes that could affect the QMS;
7. Recommendations for improvement
5. The review outputs from the MR meetings shall include any decisions and actions related to:
1. Improvement of the effectiveness of QMS and processes;
2. Improvement of services related to customer requirements;
3. Identification of resources needed.
6. Ensure that all required agenda is discussed at least twice a year or as the need arises.
7. Refer to Corrective Action Procedure (PM-USeP-CAR) and Preventive Action Procedure (PM-
USeP-PAR) for resolution of issues.
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-CMR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 3 of 4
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
NOTE 3:
1. The Secretary will prepare the minutes of the meeting to include the discussions and action
plan / responsibilities designated.
2. Prior to approval, the QMR will review the Management review minutes of meeting (FM-
USeP-CMR-01).
3. The Secretary will distribute copies of the minutes of meeting to the concerned participant.
NOTE 4:
1. Monitor and follow-up actions taken. And it shall be made by the QMR or his designated
representative based on the scheduled target for completion to check the compliance of
the action.
NOTE 5:
1. Updates shall be noted and to be included in the report of the QMR and to be submitted to
the President for discussion during the next management review meeting.
RECORDS GENERATED:
Management Review Minutes FM-USeP-CMR-01
Agenda for Management Review Meeting
Attendance Sheet
Notice of Meeting
FORM/S:
Management Review Minutes FM-USeP-CMR-01
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED
MASTER COPY
University of Southeastern
Philippines (USeP) F. Inigo Street, Obrero, Davao City 8000, Philippines
Telefax: (082) 221-7737; 227-5524
Trunkline: (082) 2244480; 2278192 www.usep.edu.ph ; email: [email protected]
Document No. PM-USeP-CMR
Issue Status 01
Revision No. 00
Date Effective 10 October 2016
Page No. 4 of 4
PROCEDURES MANUAL
MASTER COPY
Prepared by: Approved by:
_________________________________
LOURDES C. GENERALAO, Ph.D
President
_________________________________
ARISTEO C. SALAPA
QMR
UNCONTROLLED C
OPY
PRINTING AND REPRODUCTION IS NOT ALLOWED