33
Putney Society Monday 28 th November 2016

Putney Society Tideway... · Thames Tideway Tunnel Working Group for Putney Embankment Foreshore and Barn Elms (CLWG) • Helps us keep communities and businesses well informed

  • Upload
    hamien

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

Putney Society

Monday 28th November 2016

Background

• Tens of millions tonnes of sewage are discharged into the Tidal River Thames

every year

• 50 discharges on average in a typical year

2

1860

2 million

1910

4 million

20138 million

Bazalgette

design capacity

Population of London

4

Combined Sewer Overflow (CSO) at Putney

5

125 species of fish known to occur in the TidewayLow dissolved oxygen events can cause 90% mortality of sensitive species (e.g. smelt, dace, salmon)Juvenile fish surveys added to current understanding of dissolved oxygen related fish mortalitiesThames Tunnel will enable compliance with WFD dissolved oxygen standards

6

London Tideway Improvements

Riverside

Long ReachMogden

Crossness

Sewage Works Upgrades

Lee Tunnel

Thames Tideway Tunnel

Beckton

4

Thames Tideway Tunnel

5

Main Contractors

West

BMB

Central

FLO

East

CVB

System

Integrator

Construction

10

During construction

11

Completion

12

The Putney Embankment Foreshore site is on the southern bank of the River Thames. There are two sites: a main construction site and an area to build a temporary slipway to maintain public access to the River Thames.This site will be used to intercept the Putney Bridge combined sewer overflow.

Putney Embankment Foreshore

Overview

13

The Problem:At this location, in a typical year, there would be 33 discharges of untreated sewage with a volume of about 68,000 tonnes into the tidal River Thames.

The Solution:Our Putney Embankment Foreshore site will control the discharges from the Putney Bridge combined sewer overflow. When the tunnel is in operation it is expected that only one discharge will occur.

Project Duration:Construction is due to be begin in 2016 and will take three and a half years.

Site details: A temporary slip way will be constructed approximately 300m upstream of Putney Bridge. CSO drop shaft will have a depth of approximately 36m and an internal diameter of approximately 6m.

Putney Embankment Foreshore

Overview

14

Pre works:First stage Navigational Risk Assessment for in river works completeRelocation of moored vessels prior to building temporary slipwayStart of temporary slipway construction: End of November 2016Temporary slipway complete prior to the late March 2017 Boat Race season

Main works: Construction of underground structures to connect the CSO to the shaftShaft (36m deep, 6m diameter) to be constructed within the river foreshoreShaft will transfer combined sewage flows from the CSO to main tunnel via 48m long connection tunnelStart of foreshore works construction: End of July 2016Foreshore works complete by spring 2020

Putney Embankment Foreshore

Overview

15

Temporary Slipway plan

ChasNewens

ConstitutionalClub

Temporary slipway

16

Temporary SlipwayPiling works – December 2016

17

Construction of the Temporary SlipwayJanuary 2017 – March 2017

18

Temporary Slipway plan

Construction deliveries:93% by river/ by barge7% by road

Construction deliveries via Glendarvon Road limited to 10:00 – 15:00

19

Completion of the Temporary Slipway – End of March 2017

20

Main Site Plan

Start of works: July 2017Duration: 3 years

21

Putney Embankment ForeshoreTimeline of Work

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Temporary Slipway Set up and Construction November 16 - March 17

Foreshore Set Up July 17 - November 17

Drop Shaft including cofferdam October 17 - April 19

Short Connection Tunnel June 18- April 19

CSO Modifcations February 18- April 19

Connection Culvert March 19 - August 19

Valve Chambers September 18 - July 19

Fit Out, Landscape and MEICA July 19- May 20

2016 2017 2018 2019 2020

Main works put back to end of July 2017 to accommodate fish spawning March-June and to allow the public to enjoy the river during the summer season.

22

What focus do you want for the artwork?

Legacy

24

Concept images of Foreshore under consultation with LBW

25

Foreshore Street Furniture

26

Waterman’s Green Kiosk

27

Lighting layout

28

Examples of lighting impact

Community and Contact

Thames Tideway Tunnel Working Group for Putney

Embankment Foreshore and Barn Elms (CLWG)

• Helps us keep communities and businesses well informed

about the project’s progress

• Your opportunity to express your views and influence local

communication activity

• A forum for the community to discuss, understand and

potentially influence the way we undertake construction

activity

• Meetings are held quarterly. All welcome.

Chaired by Justine Greening MP

Phone our Helpdesk on 08000 30 80 80 or email:

[email protected] to register your interest.

Wandsworth Christmas Fair & Tideway Carol Service

Wandsworth Christmas Fair

• Tideway BMB sponsoring the Christmas Tree

• Tideway BMB have stall providing information on scheme

• Friday 2nd December 12noon-8pm

Tideway Carol service

• Held at St Mary’s Church, Putney• Wednesday 14th December 6pm

Helpdesk and Community Contact

Tideway Helpdesk:

Call: 08000 30 80 80

Email: [email protected]

Write to: Freepost TIDEWAY

Community Relations Manager

Patrick Kelly

Mobile: 07773 576 599

Email: [email protected]

20

Questions