Upload
others
View
8
Download
0
Embed Size (px)
Citation preview
Purple Line ExtensionSection 1 Construction Community Meeting November 16, 2017
1
AgendaSections 1 & 2
2
Section 1 Construction Updates
• TBM Art and Naming Contest
• Project Construction Updates: • Wilshire/Western
• Piling Weekend Closures
• Wilshire/La Brea
• Wilshire/Fairfax
• Wilshire/La Cienega
• Decking Weekend Closures
• Safety
• Eat Shop Play
• Business Interruption Fund
• Questions & Answers
Purple Line ExtensionProject Alignment
3
Sections 1, 2 & 3 Status
4
Forecasted ScheduleSection Section 1 Section 2 Section 3
Length 3.92 Miles 2.59 Miles 2.59 Miles
New Stations Wilshire/La BreaWilshire/FairfaxWilshire/La Cienega
Wilshire/RodeoCentury City/ Constellation
Westwood/UCLAWestwood/VA Hospital
Pre-Construction Activities
2014-2015 2016 - 2018 2016 – 2018
Construction 2015 - 2023 2018 – 2025 2018 – 2026
Operations 2023 2025 2026
*Subject to change. The PLE project team is working to deliver the project consistent with Measure M
Purple Line ExtensionSection 1 Alignment
5
Purple Line ExtensionSection 1 Schedule
6
*As of November 2017, subject to change
Tunnel Boring MachinesArt and Naming Contest – CLOSES NOVEMBER 17th!
7
Follow the @PurpleLineTBMSTwitter
8
Purple Line Maintenance Facility
9
Maintenance Facility
• Located in the Arts District, near 6th St Bridge
• 590 S Santa Fe Av
Current Work
• Building foundation footings being poured
• Trailer offices have been established onsite
• Wall along north side of property has been poured
• Local access will be maintained at all times
Purple Line Maintenance Facility
10
Example of Benjamin Ball and Gaston Nogues Art concept for MOW Building
Wilshire/Western Connection ScheduleSchedule
11
*As of November 2017, subject to change
Wilshire/Western ConnectionUpcoming Work
12
• Construction activities between Wilshire Bl/Manhattan Pl and Wilshire Bl/Western Av: • Utility work• Pile installation• Jet grouting • Decking, excavation • Dewatering• Instrumentation
Location of construction on Wilshire Bl at Western Av, minor instrumentation and dewatering work will intermittently extend onto Manhattan Pl
Wilshire/Western ConnectionWork Zone Set-Up
What: A work zone with concrete barriers, fencing and sound blankets
Why: To support pile installation, concrete street decking installation, soil improvement (jet grouting), excavation and associated activities (i.e. installing ventilation and dewatering system)
Where: North side of Wilshire Bl between Manhattan Pl and Western Av
How Wilshire Bl will be affected:
• Reduced to two lanes in each direction between Western Av and St Andrews Pl
• Left turns will be restricted on Wilshire Bl at Western Av
• Extended sidewalk closure between Manhattan Pl and Western Av required
When: Continuing for approximately one year, through 2018
13
Wilshire/Western Station will remain in operation during construction
Wilshire/Western ConnectionWork Zone
14
Work Zone at Wilshire/Western looking southwest
Wilshire/Western ConnectionTemporary Work Zones
15
Comparable work zone formerly at Wilshire/La Brea
Rendering of work zone showing pile installation
Typical Wilshire-facing signage for businesses
Wilshire/Western ConnectionPile Installation
16
Pile installation includes:
• Rig to construct 95-ft (L) deep
• Crane lifting 95-ft (L), 24-in H-piles into holes
• Drilling, pile installation and backfilled concrete completed same day
• Requires pre-trenching and potholing work prior to installing the piles
• Work anticipated through December 2017
*Dates subject to change
Potholing on Wilshire Blbetween Western Av and Manhattan Pl looking southeast
Wilshire/Western ConnectionPile Installation Details
Typical Work Hours:
• 6am-10 pm for drilling and setting of piles
• 11pm-7am for support activities
Lane Reductions and Closures:
• Wilshire will be reduced to two lanes in each direction.
• Additional weekend full closures of Wilshire Bl will be required; these started October 2017
Sound Mitigation• Design-builder must comply with
City of Los Angeles noise requirements
• Noise control signage• Low-impact back-up alarms during
night work• Acoustical insulation• Metro 5-Step Noise Plan
17
Wilshire/Western Connection Decking
Where: On Wilshire Bl, between Manhattan Pl and Western Av
What: Construction of a concrete deck that forms a temporary street on Wilshire Bl; Similar system used for La Brea and Fairfax stations
When: Anticipated March through April 2018
How:
• Will require full closures of Wilshire Bl
• Schedule, sequence and detour information to be published prior to closures
*Dates subject to change
18
Renderings of typical street decking construction
Wilshire/Western ConnectionDecking
• Traffic will travel on the installed deck panels while the tie-in is constructed underground, anticipated for March through April 2018
• Western Decking:
– Approximately 130 feet long
– Approximately 100 feet wide
– Approximately 60 feet deep
19
Example of decking at Wilshire/Fairfax
*Dates subject to change
Wilshire/Western ConnectionFull Weekend Closure of Wilshire Bl for Western
20
Closures:• Westbound Wilshire Bl
closed at Western Av
• Eastbound Wilshire Blclosed at Crenshaw Bl
Local Access:
• Local access maintained to Wilshire Bl from all local streets
Detours:
• Eastbound: Wilshire Bl Crenshaw Bl Olympic BlWestern AvWilshire Bl
• Westbound: Wilshire BlWestern Av Olympic Bl Crenshaw BlWilshire Bl
Wilshire/Western ConnectionFull Closure Weekend Schedule
21
Phase 1: Wilshire Bl closed between Western Av and Manhattan Pl- 4 weekends, October – November 2017
Phase 2: Wilshire Bl closed between Western Av and Manhattan Pl- 10 Weekends, December 2017 – February 2018
Phase 3: Wilshire Bl closed between Western Av and Manhattan Pl- Spring 2018 , Schedule TBD
• All full closure weekends are Friday night at 8pm – Monday morning at 6am• No full closures on Thanksgiving, Christmas, New Years Day
*Dates subject to change
Extended Closure Schedule Benefits/Features
• Reduces the number of weekend full closures by 5 weekends.
• Reduces the number of nights worked from 21 to 10.• Presidents Day is February 19, 2018 • The weekends of February 16-19 and February 23-26 are
planned full closure work weekends. The extended closure would only add four business days.
Wilshire/Western ConnectionFull Closure of Wilshire Blvd. Feb 16-26 2018
Blue: Full closure of Wilshire Blvd. , 9pm February 16 – 6am February 26Blue/Orange: Weekend full closures of Wilshire Blvd. 9pm-6am
Extended Closure Schedule
• Friday, February 16 at 9pm – implement full closure.
• Monday, February 26 at 6am – remove full closure, open Wilshire Blvd.
• The full closure would remain static for the duration.
• Work hours – continuous
공사연장관련도로폐쇄로인한유익과중요사항
• 주말전면폐쇄횟수를 5번으로단축• 야간작업횟수를 21번에서 10번으로단축• 2018년 2월 19일: 대통령의날(Presidents Day) • 2월 16일-19일및 2월 23일-26일주말: 예정된전면폐쇄작업주말임.도로폐쇄연장으로인해평일 4일간만추가
Wilshire/Western 연결 공사2018년 2월 16일-26일: Wilshire Blvd. 도로전면폐쇄
파란색: Wilshire Blvd. 도로전면폐쇄 (2월 16일오후 9시 – 2월 26일오전 6시)파란색/주황색: Wilshire Blvd 주말도로전면폐쇄 (오후 9시-오전 6시)
연장공사로인한도로폐쇄일정
• 2월 16일, 금요일오후 9시 –도로전면폐쇄
• 2월 26일, 월요일오전 6시 –도로전면폐쇄철폐, Wilshire Blvd. 개통
• 이기간중에는도로전면폐쇄로유지
• 작업시간 –지속적
2018년 2월 2018년 3월 2018년 4월
24
Jet Grouting Traffic Control• Work zone set up in two
center lanes of Wilshire Bl at Norton Av this month
• Work area separated by K-rail and fences
• Lanes reduced to two lanes each direction at jet grouting locations
• Off-peak weekday closures and weekend directional closures for Wilshire Bl
• Bus stops will be temporarily relocated as required
Location of jet grouting site at Wilshire Bl/Norton Av scheduled for November 2017
Jet GroutingWilshire Bl/Norton Av
Wilshire/La Brea Station
25
Wilshire/La Brea Station
26
Rendering shows length of the Wilshire/La Brea underground station box on Wilshire Bl from Orange Dr to Detroit St
Wilshire/La Brea StationSchedule
27
*As of November 2017, subject to change
28
Excavation of the La Brea Station box has reached approximately 96% complete
Wilshire/La Brea StationExcavation Continues
Wilshire/La Brea StationPreparation for Tunnel Boring Machines
29
Tunnel brow framing section, site of future TBM break through into Wilshire/La Brea Station
Wilshire/La Brea StationCenter Opening Utilization Thru February 2020
1
The center opening is a large underground access shaft located behind concrete barriers at Wilshire/Sycamore
STS needs to continue to utilize the center opening thru February 2020 to accomplish the following work associated with Wilshire/La Brea station construction:
• Structural concrete • Removal of excavation support system • Tunneling equipment and support • Mechanical equipment installation
This work will occur either with the current work zone in place with limited ‘sign and cone’ closures, or under almost daily sign and cone closures
Current center opening work zone at Wilshire Bl/Sycamore Av
Wilshire/La Brea Station Center Opening Benefits
Why the center opening?
• Safety: it’s the safest method for both the public and the workers to complete the work• Traffic: it creates a static traffic pattern, rather than a variety of sign and cone closures that would
change daily• Noise: it allows for more robust noise mitigation and a better contained work zone than sign and
cone closures, also allows the work to be scheduled primarily during daytime hours than with traffic restrictions for sign and cone closures
The project is working with the local community and stakeholders near Wilshire/La Brea, detailed presentation on the center opening is online at metro.net/purple
31
Wilshire/Fairfax Station
32
Wilshire/Fairfax Station
33
Rendering shows length of the Wilshire/Fairfax underground station box on Wilshire Bl from west of Fairfax Av to just west of Ogden Dr
Wilshire/Fairfax Station Schedule*As of November 2017, subject to change
34
Wilshire/Fairfax StationExcavation, Fall 2017
35
Excavation progress
Wilshire/Fairfax StationExcavation, Fall 2017
36
Installing lagging
Wilshire/La Cienega Station
37
Wilshire/La Cienega Station
38
Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr
Wilshire/La Cienega Station Schedule*As of November 2017, subject to change
39
Wilshire/La Cienega Station Decking Overview
40
• Construction of a concrete deck on Wilshire Bl, which will serve as a temporary roadway while construction proceeds underground. This construction spans the width of Wilshire Bl
• Location: Wilshire Bl between La Cienega Bl and San Vicente Bl, and in the Wilshire/La Cienegaintersection
• This work occurs under full weekend closures of Wilshire Bland La Cienega Bl
Wilshire/La Cienega DeckingWork zone
41
Approximate location of decking work zone at Wilshire Bl/La Cienega Bl
GALE LAYDOWN
YARDLA CIENEGALAYDOWN
YARD
Wilshire/La Cienega StationWeekend Closures Schedule
Wilshire Bl/La Cienega Bl Weekend Closures Schedule• Approximately 17 weekend closures• Scheduled in 3 phases• Started September 8, 2017
Phase 1: Wilshire Bl between La Cienega Bl and San Vicente Bl – COMPLETE
Phase 2: Wilshire/La Cienega intersection – COMPLETE• 4 weekends
Phase 3: Wilshire Bl between La Cienega Bl and San Vicente Bl• 11 weekends • Started November 3rd
42
Wilshire/La Cienega StationApproved Weekend Work Hours Schedule
43
Approved Hours:
• Friday 8pm: – Full closure of Wilshire Bl for phases 1 & 3 – Full closure of Wilshire/La Cienega intersection for phase 2
• Monday 6am: All streets open
• Work occurs continuously throughout weekend
Wilshire/La Cienega StationDecking Construction
44
Placing deck beams on Wilshire Bl
Phase 3: East/West DetourWilshire Bl between La Cienega Bl and San Vicente Bl
45
Closures:• Westbound Wilshire Bl
will be closed at San Vicente Bl
• Eastbound Wilshire Bl will be closed at Robertson Bl
Local Access:
• Maintained to Wilshire Bl,La Cienega Bl open during this phase
Detours:
• Eastbound: Wilshire Bl Robertson Bl Burton Way San Vicente BlWilshire Bl
• Westbound: Wilshire Bl San Vicente Bl Burton Way Robertson BlWilshire Bl
Bus DetoursWeekend Full Closures
Bus Detour Route will follow Traffic Detour:
• Eastbound: Wilshire Bl Robertson Bl Burton Way San Vicente BlWilshire Bl
• Westbound: Wilshire Bl San Vicente Bl Burton Way Robertson BlWilshire Bl
46
For information regarding changes to Metro service, please call 323.GoMetro or visit: https://www.metro.net/service/advisories/
720/20 Wilshire bus stops for Wilshire/La Brea, Wilshire/Fairfax and Wilshire/La Cienegahave been relocated to temporary locations away from the construction zone and will remain in place until construction is completed
Wilshire/La Cienega StationExcavation and Deck Openings
What: • Deck openings of the street-deck for
the purpose of delivering materials for underground construction
• Deck openings will be done at deck locations designed to open and close
• Deck openings will occur periodically, as needed
• Deck panels are 8 feet by 14 feet• Starting early 2018
47
Typical deck opening
Wilshire/La Cienega Station Decking Community Outreach
Robust Marketing Campaign• Social media: Facebook, Twitter, and Nextdoor• Advertising: print, radio, and online• Media coverage: press releases
• Business and residential outreach
• Meetings with local groups, leaders
• Elected Official Briefings
• Safety Presentations
• School Presentations
• Community Partnerships
48
Help Us Keep You Safe
49
Purple Line Extension24/7 Project Hotline - 213.922.6934
On Metro TransitSee Something, Say Something888-950-SAFE (7233)
Construction Safety Awareness ProgramGlyssa Alcazar, Community Relations OfficerEmail: [email protected]: 323.900.2192
Win 7-Day Metro TAP Card
50
805 S La Brea AvLos Angeles, CA 90036
Studio 698383 Wilshire Bl #50, Beverly Hills, CA 90211
Boss Sushi270 S La Cienega BlBeverly Hills, CA 90211
Helping local businesses as we build.Update as of 11/3/17
BIF Information and Eligibility
> Financial assistance to small “mom & pop” businesses with 25 or fewer employees directly impacted by Metro Rail construction along three project areas
> Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements
> Grant amount determined by loss of business revenue related to period of construction disruption
> To date, more than $11.4 million awarded to 252 small businesses along all three project areas
BIF Grant Award Update
> Purple Line Extension, Section 1
> BIF Grants Awarded: 125
> BIF Grant Amount Awarded: $2,982,547.49
> Number of small businesses awarded: 54
> BIF Business Advisor: Brian Lazo, PCR, 213.739.2999
> Purple Line Extension, Section 2
> BIF Business Advisor: Darrell Smith, PCR, 213.739.2999
Section 1: Construction Community Meeting
January 18, 2017
6pm – 7:30pm
Petersen Automotive Museum6060 Wilshire Bl
Los Angeles, CA 90036
57
Next Community MeetingSection 1
Updates on La Cienega and Rodeo Stations
December 13, 2017
6:30pm – 8pm
Beverly Hills City HallMunicipal Gallery455 N Rexford Dr
Beverly Hills, CA 90210
58
Next Community MeetingBeverly Hills
Stay in Touch
59