31
Commercial Street Bridge Feasibility Study SR 376, SEC A62 PUBLIC MEETING November 13, 2019 Frick Environmental Center

PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Commercial Street Bridge

Feasibility StudySR 376, SEC A62

PUBLIC MEETING

November 13, 2019

Frick Environmental Center

Page 2: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Project Team

PennDOT District 11-0 Design Division

• Doug Seeley, P.E. –

Assistant District Executive, Design

• Michael Szurley, P.E. – Project Manager

HDR

• Roger Eaton, P.E. –

Lead Bridge Designer/Deputy Project Manager

Page 3: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Project Location

Source: United States Geological Survey

North American Datum of 1983 (NAD83)

World Geodetic System of 1984 (WGS84)

Pittsburgh East, PA 2016

Frick

Environmental

Center

Page 4: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Proximity to Squirrel Hill Tunnel

IRISH CENTER

Page 5: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Overview Points

Completed in 1951, the Commercial Street Bridge is nearly 70 years old.

The structure carries approximately 100,000 vehicles per day, but does not allow permit loads due to insufficient load-carrying capacity.

Page 6: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Major Past Rehabilitation

Construction completed in 1951

1980 Rehabilitation • Deck widened by 2 feet in both directions

• Concrete wearing surface removed and replaced

• Latex overlay added

Page 7: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Major Past Rehabilitation

2007 Rehabilitation • Joint replacements

• Hydro-demolition and latex wearing surface

• Concrete substructure repairs

• Floorbeam repair

Page 8: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Major Past Rehabilitation

2012 Rehabilitation • Replace select expansion joints with

strip seal dams

• Strengthen fascia (outer) stringer

• Install column bracing at top of arch spans

• Miscellaneous concrete spall repairs

Page 9: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Current Condition

Numerous concrete spalls

Cracks up to ¼” wide in some locations

Active corrosion is evident throughout the structure

The condition of the deck, floor system, and arch spandrel columns prevent the bridge from carrying large/oversize vehicles

Another rehabilitation will be needed soon to prevent load restrictions

Page 10: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Study Phase Chronology

March, 2019: Project Purpose and Need Approved: “Addressdeficiencies of the Commercial Street Bridge in order to provide a safeand efficient bridge”.

April, 2019: Feasibility of rehabilitation options completed. Severalrehabilitation options were evaluated and determined not to meetPurpose & Need or Secretary of the Interior criteria.

May, 2019: Historic Bridge Rehabilitation Analysis findings approved byFHWA.

Sept, 2019: Historic Bridge Rehabilitation Analysis findings approved byPA State Historic Preservation Office.

Today: Evaluation of structure replacement options in progress.

Page 11: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Bridge Replacement Options

Two construction methods considered:

Staged Construction• Build new bridge in 3 partial-width steps

• Maintains 2 lanes of traffic in each direction during peak hours

• Long-Term Traffic Control Plan implemented for three major traffic phases over a 4 to 5 year time period

Slide-In Construction• Build new bridge beside existing and slide into place

• Full-closure of I-376 required (approximately 2 weeks)o Short-term lane restrictions during off-peak hours

Page 12: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Staged Construction Sequence

N

Page 13: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Staged Construction Sequence

N

Page 14: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Staged Construction Sequence

N

Page 15: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Staged Construction Sequence

N

Page 16: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Staged Construction Sequence

N

Page 17: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Staged Construction Sequence

N

Page 18: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Bridge Types- Staged Construction

Steel Arch

Concrete Arch

Haunched Steel Plate Girder

Page 19: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Concrete Arch

Page 20: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Haunched Steel Plate Girder

Page 21: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Slide-In Construction Sequence

N

Page 22: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Slide-In Construction Sequence

N

Page 23: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Slide-In Construction Sequence

N

Page 24: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Slide-In Construction Sequence

N

Page 25: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Bridge Types- Slide-In Construction

Haunched Steel Plate Girder

Steel Tied Arch

Page 26: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Steel Tied Arch

Page 27: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Haunched Steel Plate Girder

Page 28: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Next Steps

1. Initiate Section 106 - Completed

2. Identify & Document Historic Resources - Completed

3. Complete Section 106 Consultation• Assess Effects

• Resolve Adverse Effects

4. Select Preferred Alternative

5. Perform Preliminary & Final Design

6. Construction (Anticipated 2023-2025)

Page 29: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

PA Department of Transportation

Engineering District 11-0

45 Thoms Run Road

Bridgeville PA 15017

QUESTIONS ?

• PennDOT Design Division

• Direct questions to:

• Michael Szurley, P.E. – Project Manager at 412.429.5035 or [email protected]

• Todd Crouch – Environmental Supervisor - NEPA

• PennDOT Press Office

• Steve Cowan – District Press Officer

We kindly ask that all attendees complete a survey of this presentation… Thank you!

Page 30: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Haunched Steel Plate Girder

Steel Tied Arch

Concrete Arch

Page 31: PUBLIC MEETING · 2012 Rehabilitation •Replace select expansion joints with strip seal dams •Strengthen fascia (outer) stringer •Install column bracing at top of arch spans

Survey Monkey Feedback

https://www.surveymonkey.com/r/WY2F5NV