PS0504 Managing the Baseline Schedule, Majerowicz.pdf

Embed Size (px)

Citation preview

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    1/23

     Mid-Atlantic Operations

    Managing The Baseline Schedule

    Walter MajerowiczPlanning & Schedule Manager 

    Polar Operational Environmental Satellites Program

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    2/23

    Objective

    Provide an overview of proven baseline schedule

    control concepts and practices by:

    • Summarizing the steps for developing the baselineschedule

    • Highlighting the elements of schedule control

    • Illustrating the schedule revision process based on lessons-

    learned from major projects/contracts

     Mid-Atlantic Operations

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    3/23

    Agenda

    • Introduction

    • Developing the Baseline Schedule• Controlling the Baseline Schedule

    • Example Baseline Schedule Revision

    • Summary & Conclusions

     Mid-Atlantic Operations

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    4/23

    Introduction

     Mid-Atlantic Operations

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    5/23

    Time / Schedule Management• Project Schedule Management consists of the processes

    required to ensure timely completion of the project: – Activity definitionè what needs to be done

     – Activity sequencingè the order things need to occur  – Activity duration estimatingè the number of work periods needed

     – Schedule developmentè creating the roadmap

     – Schedule status accountingè getting the facts

     – Schedule analysisè what is the schedule telling us

     – Schedule performance reporting è how are we doing and where arewe going

     – Schedule controlè managing change

    • Project Scheduling is the application of these processes

     Mid-Atlantic Operations

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    6/23

    Focus on the Baseline Schedule• Premise

     – Baseline schedules can, will and should change

     – Projects emphasize accurate current operating schedules

     – Projects do not always maintain accurate baseline schedules

    • Approach

     – Freeze the baseline schedule at the start of the project

     – Modify the “unstatused” baseline schedule for new scope changes

     – Issue baseline schedule revisions

    • Findings – A disciplined schedule control process identifies the impact of scope

    changes on project/contract deliverables and objectives

     – Without schedule control, the schedule impact of new scope changesare difficult to distinguish from performance problems

     Mid-Atlantic Operations

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    7/23

     Mid-Atlantic Operations

    The Baseline Schedule• Represents the project team’s schedule commitment• Establishes target dates and time spans for the

    accomplishment of activities

    • Documents the project’s schedule assumptions

    • “Freezes” the original plan at the completion of the initial project planning, but . . . – Will and should change over the life of the project (e.g. new scope)

     – Should not be changed to match performance

    • Provides a time perspective to the project team

    • Sets a benchmark against which schedule performance ismeasured and forecasts projected ~ in order to better determine future courses of action

    • Correlates to project’s original cost estimate / budget

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    8/23

    Developing the BaselineSchedule

     Mid-Atlantic Operations

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    9/23

    Drawing Tree

    WBS

    3.0

    Instruments

    1.0 System

    Engineering

    Total Program

    2.0 Spacecraft

     S O  W

    Planning Meetings With Project Team

    Previous Projects’ History

    Identify the Project Activities

     Mid-Atlantic Operations

    Activity List

    • Design

    • Build• Test

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    10/23

    Determine the Activity Sequence

     Activity List

    • Design• Build

    • Test

     Mid-Atlantic Operations

    Mandatory

    Dependencies

    External

    Dependencies

    Assumptions

    Constraints

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    11/23

     Mid-Atlantic Operations

    Estimate Activity DurationsDesign

    BuildTest

    DesignBuild

    Test

    DesignBuild

    Test

    The Schedule According to Engineering 

    The Schedule According to Manufacturing 

    The Schedule According to System Test 

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    12/23

    Develop The Project Schedule

     Mid-Atlantic Operations

    Contract

    Award

    Design

    ProcureLong Lead

    Fabrication

    Assembly

    0 days

    START ON

    8/1/01

    100 days

    120 days

    30 days

    15 days 25 days

    FS

    FS

    FS

    FS

    FS

    FS

    8-1-01

    8-1-01

    8-1-01

    12-18-01

    8-1-011-15-02

    12-19-01

    1-29-02

    1-30-02

    2-19-03

    2-20-02

    3-26-03

    12-7-01 = Early Start

    10-10-02 = Early Finish

    Test

    Parts

    Deliver 

    0 days

    5-1-01

    5-1-01

    FNET

    5/1/01

    FS

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    13/23

    “Freeze” The Baseline ScheduleID Task Name Duration Total Slack  1 Contract Award 0 d 26 d

    2 Design 100 d 26 d

    3 Procure Long Lead Parts 120 d 36 d

    4 Fabrication 30 d 26 d

    5 Assembly 15 d 26 d

    6 Test & Delivery 25 d 26 d

    7 Contract Delivery 0 d 0 d

    8/1

    8/1 12/18

    8/1 1/15

    12/19 1/29

    1/30 2/19

    2/20 3/26

    5/1

    Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

    2001 2002

    REV: Baseline 8-1-01

     Mid-Atlantic Operations

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    14/23

    Controlling the BaselineSchedule

     Mid-Atlantic Operations

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    15/23

    Schedule ControlSchedule Control is the process of changing the project schedule in a

    timely, disciplined manner in response to a) new work scope, b) the

    need for a new schedule baseline, and c) recovery from actual project 

     problems.

    Baseline

    Revisions

    Workaround

    Planning

    ScheduleControl

    Replanning

     Mid-Atlantic Operations

    REV A, REV B New Baseline Recovery Schedule  

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    16/23

    Baseline Schedule RevisionsThe revision process consists of modifying the baseline schedule with

    the incorporation of new authorized work scope.

    ØBaseline schedule

    ØContract

      deliverables

    Ø New scopeØChange Requests

    ØCustomer 

      authorization

    ØBaseline schedule

      revisions ~ REV A,

      REV B, etc.

    ØContract delivery

      date modifications

    INPUT PROCESS OUTPUT

    Incorporate the

    change into the

     baseline schedule and

    issue a revised

    schedule

     Mid-Atlantic Operations

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    17/23

    Schedule Revision Guidelines• Lock the baseline schedule away . . . but keep the key handy!

    • Customer contractual authorization needed before incorporating newscope into baseline schedule

    • Assume existing baseline schedule is in “on track” at the time customer 

    authorizes new scope change• Incorporate the change into the existing “unstatused” baseline schedule

    • Do not use schedule reserve or slack to absorb impact of new scopechanges

    • Review schedule revision with project team, change board and customer 

    • Release formal baseline schedule revision to the project team

    • Continue management process: authorize work and budget to CAMs,submit claim proposal, modify contract, etc.

     Mid-Atlantic Operations

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    18/23

    The Customer Makes A Change

     Mid-Atlantic Operations

    On 10-1-01, the customer adds a requirement for RF

    Testing to the contract

    Contractor estimates RF

    Testing will take 10 days

    1 2

    3 4   R   E  V A

    “Unstatused” baseline

    schedule is modified with

    new RF Test

    Revision A of the baseline

    schedule is issued

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    19/23

    Baseline Schedule – REV A

     Mid-Atlantic Operations

    ID Task Name Duration Total Slack  

    1 Contract Award 0 d 26 d

    2 Design 100 d 26 d

    3 Procure Long Lead Parts 120 d 36 d

    4 Fabrication 30 d 26 d

    5 Assembly 15 d 26 d

    6 Test 25 d 26 d

    7 RF Test & Delivery 10 d 26 d

    8 Contract Delivery 0 d 0 d

    8/1

    8/1 12/18

    8/1 1/15

    12/19 1/29

    1/30 2/19

    2/20 3/26

    3/27 4/9

    5/15

    Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul

    2001 2002

    REV A: 10-1-01

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    20/23

    Baseline Schedule Comparison

     Mid-Atlantic Operations

    +26 days+26 daysTotalFloat

    5-15-025-1-02

    Contract

    Delivery

    4-9-023-26-02PlannedDelivery

    REV ABaseline

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    21/23

    Baseline Schedule Revision Matrix

     Mid-Atlantic Operations

    5-15-02

    4-9-02

    REV B

    (12-6-01)

     Add UV 

    Coating 

    6-17-2

    5-11-02

    REV C

    (2-4-02)

    Delete Spec

    1.5.3

    5-15-025-1-02

    Contract

    Delivery

    4-9-023-26-02

    Planned

    Delivery

    REV A

    (10-1-01)

     Add RF 

    Test 

    Baseline

    (8-1-01)

    The baseline revision matrix helps both customer and 

    contractor maintain visibility of the effect of new scope

    changes.

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    22/23

    Without An Accurate Baseline Schedule

    • Projects may lose sight of their schedule

    objectives and commitments

    • Credibility and relevance of schedule performanceand forecasts is questionable

    • Projects could lose schedule integration with cost plan

    • Contractors may have difficulty segregating theimpact (schedule & cost) of new scope from the

    impact of technical or performanceproblems

     Mid-Atlantic Operations

  • 8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf

    23/23

    Summary & Conclusions• The baseline schedule is a tool that should be

    modified as new work scope is authorized

    • An accurate baseline schedule is necessary toassess actual performance, put forecasts in

     perspective, and determine the significance of 

    variances

    • A structured revision process is required to

    maintain an accurate baseline schedule

     Mid-Atlantic Operations