Mid-Atlantic Operations
Managing The Baseline Schedule
Walter MajerowiczPlanning & Schedule Manager
Polar Operational Environmental Satellites Program
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
2/23
Objective
Provide an overview of proven baseline schedule
control concepts and practices by:
• Summarizing the steps for developing the baselineschedule
• Highlighting the elements of schedule control
• Illustrating the schedule revision process based on lessons-
learned from major projects/contracts
Mid-Atlantic Operations
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
3/23
Agenda
• Introduction
• Developing the Baseline Schedule• Controlling the Baseline Schedule
• Example Baseline Schedule Revision
• Summary & Conclusions
Mid-Atlantic Operations
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
4/23
Introduction
Mid-Atlantic Operations
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
5/23
Time / Schedule Management• Project Schedule Management consists of the processes
required to ensure timely completion of the project: – Activity definitionè what needs to be done
– Activity sequencingè the order things need to occur – Activity duration estimatingè the number of work periods needed
– Schedule developmentè creating the roadmap
– Schedule status accountingè getting the facts
– Schedule analysisè what is the schedule telling us
– Schedule performance reporting è how are we doing and where arewe going
– Schedule controlè managing change
• Project Scheduling is the application of these processes
Mid-Atlantic Operations
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
6/23
Focus on the Baseline Schedule• Premise
– Baseline schedules can, will and should change
– Projects emphasize accurate current operating schedules
– Projects do not always maintain accurate baseline schedules
• Approach
– Freeze the baseline schedule at the start of the project
– Modify the “unstatused” baseline schedule for new scope changes
– Issue baseline schedule revisions
• Findings – A disciplined schedule control process identifies the impact of scope
changes on project/contract deliverables and objectives
– Without schedule control, the schedule impact of new scope changesare difficult to distinguish from performance problems
Mid-Atlantic Operations
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
7/23
Mid-Atlantic Operations
The Baseline Schedule• Represents the project team’s schedule commitment• Establishes target dates and time spans for the
accomplishment of activities
• Documents the project’s schedule assumptions
• “Freezes” the original plan at the completion of the initial project planning, but . . . – Will and should change over the life of the project (e.g. new scope)
– Should not be changed to match performance
• Provides a time perspective to the project team
• Sets a benchmark against which schedule performance ismeasured and forecasts projected ~ in order to better determine future courses of action
• Correlates to project’s original cost estimate / budget
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
8/23
Developing the BaselineSchedule
Mid-Atlantic Operations
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
9/23
Drawing Tree
WBS
3.0
Instruments
1.0 System
Engineering
Total Program
2.0 Spacecraft
S O W
Planning Meetings With Project Team
Previous Projects’ History
Identify the Project Activities
Mid-Atlantic Operations
Activity List
• Design
• Build• Test
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
10/23
Determine the Activity Sequence
Activity List
• Design• Build
• Test
Mid-Atlantic Operations
Mandatory
Dependencies
External
Dependencies
Assumptions
Constraints
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
11/23
Mid-Atlantic Operations
Estimate Activity DurationsDesign
BuildTest
DesignBuild
Test
DesignBuild
Test
The Schedule According to Engineering
The Schedule According to Manufacturing
The Schedule According to System Test
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
12/23
Develop The Project Schedule
Mid-Atlantic Operations
Contract
Award
Design
ProcureLong Lead
Fabrication
Assembly
0 days
START ON
8/1/01
100 days
120 days
30 days
15 days 25 days
FS
FS
FS
FS
FS
FS
8-1-01
8-1-01
8-1-01
12-18-01
8-1-011-15-02
12-19-01
1-29-02
1-30-02
2-19-03
2-20-02
3-26-03
12-7-01 = Early Start
10-10-02 = Early Finish
Test
Parts
Deliver
0 days
5-1-01
5-1-01
FNET
5/1/01
FS
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
13/23
“Freeze” The Baseline ScheduleID Task Name Duration Total Slack 1 Contract Award 0 d 26 d
2 Design 100 d 26 d
3 Procure Long Lead Parts 120 d 36 d
4 Fabrication 30 d 26 d
5 Assembly 15 d 26 d
6 Test & Delivery 25 d 26 d
7 Contract Delivery 0 d 0 d
8/1
8/1 12/18
8/1 1/15
12/19 1/29
1/30 2/19
2/20 3/26
5/1
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2001 2002
REV: Baseline 8-1-01
Mid-Atlantic Operations
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
14/23
Controlling the BaselineSchedule
Mid-Atlantic Operations
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
15/23
Schedule ControlSchedule Control is the process of changing the project schedule in a
timely, disciplined manner in response to a) new work scope, b) the
need for a new schedule baseline, and c) recovery from actual project
problems.
Baseline
Revisions
Workaround
Planning
ScheduleControl
Replanning
Mid-Atlantic Operations
REV A, REV B New Baseline Recovery Schedule
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
16/23
Baseline Schedule RevisionsThe revision process consists of modifying the baseline schedule with
the incorporation of new authorized work scope.
ØBaseline schedule
ØContract
deliverables
Ø New scopeØChange Requests
ØCustomer
authorization
ØBaseline schedule
revisions ~ REV A,
REV B, etc.
ØContract delivery
date modifications
INPUT PROCESS OUTPUT
Incorporate the
change into the
baseline schedule and
issue a revised
schedule
Mid-Atlantic Operations
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
17/23
Schedule Revision Guidelines• Lock the baseline schedule away . . . but keep the key handy!
• Customer contractual authorization needed before incorporating newscope into baseline schedule
• Assume existing baseline schedule is in “on track” at the time customer
authorizes new scope change• Incorporate the change into the existing “unstatused” baseline schedule
• Do not use schedule reserve or slack to absorb impact of new scopechanges
• Review schedule revision with project team, change board and customer
• Release formal baseline schedule revision to the project team
• Continue management process: authorize work and budget to CAMs,submit claim proposal, modify contract, etc.
Mid-Atlantic Operations
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
18/23
The Customer Makes A Change
Mid-Atlantic Operations
On 10-1-01, the customer adds a requirement for RF
Testing to the contract
Contractor estimates RF
Testing will take 10 days
1 2
3 4 R E V A
“Unstatused” baseline
schedule is modified with
new RF Test
Revision A of the baseline
schedule is issued
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
19/23
Baseline Schedule – REV A
Mid-Atlantic Operations
ID Task Name Duration Total Slack
1 Contract Award 0 d 26 d
2 Design 100 d 26 d
3 Procure Long Lead Parts 120 d 36 d
4 Fabrication 30 d 26 d
5 Assembly 15 d 26 d
6 Test 25 d 26 d
7 RF Test & Delivery 10 d 26 d
8 Contract Delivery 0 d 0 d
8/1
8/1 12/18
8/1 1/15
12/19 1/29
1/30 2/19
2/20 3/26
3/27 4/9
5/15
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2001 2002
REV A: 10-1-01
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
20/23
Baseline Schedule Comparison
Mid-Atlantic Operations
+26 days+26 daysTotalFloat
5-15-025-1-02
Contract
Delivery
4-9-023-26-02PlannedDelivery
REV ABaseline
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
21/23
Baseline Schedule Revision Matrix
Mid-Atlantic Operations
5-15-02
4-9-02
REV B
(12-6-01)
Add UV
Coating
6-17-2
5-11-02
REV C
(2-4-02)
Delete Spec
1.5.3
5-15-025-1-02
Contract
Delivery
4-9-023-26-02
Planned
Delivery
REV A
(10-1-01)
Add RF
Test
Baseline
(8-1-01)
The baseline revision matrix helps both customer and
contractor maintain visibility of the effect of new scope
changes.
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
22/23
Without An Accurate Baseline Schedule
• Projects may lose sight of their schedule
objectives and commitments
• Credibility and relevance of schedule performanceand forecasts is questionable
• Projects could lose schedule integration with cost plan
• Contractors may have difficulty segregating theimpact (schedule & cost) of new scope from the
impact of technical or performanceproblems
Mid-Atlantic Operations
8/15/2019 PS0504 Managing the Baseline Schedule, Majerowicz.pdf
23/23
Summary & Conclusions• The baseline schedule is a tool that should be
modified as new work scope is authorized
• An accurate baseline schedule is necessary toassess actual performance, put forecasts in
perspective, and determine the significance of
variances
• A structured revision process is required to
maintain an accurate baseline schedule
Mid-Atlantic Operations