Upload
wesley-king
View
217
Download
0
Tags:
Embed Size (px)
Citation preview
1
®
Overview
• Benefits of a Good Construction Schedule
• Baseline Schedule Development
• Schedule Updating and Maintenance
• Managing Project Changes
• USACE – Specific Schedule Requirements
• Conclusion
Construction Schedule Best Practices
2
® Requires thinking the project through prior to starting the work
Provides a structured approach to executing the project
Provides a means of communicating Scope and planned work sequence to stakeholders
Identification of problems before they arise
Identification of long-lead procurement/fabrication items
Assessment of resource requirements
Forecasting of cash flow requirements
Serves as primary documentation for modeling delay impacts
Benefits of a Construction Schedule
3
®
Key Considerations
• Scheduling Software
• Project WBS (Work Breakdown Structure)
• Contract Milestones
• Submittal Requirements
• Activity Coding Requirements
• Project Stakeholders
• Cost & Resources Loading Requirements
• Updating & Reporting Requirements
• Testing & Startup Requirements
• Project Closeout Requirements
Baseline Schedule Development
4
®
• Interior Finishes
• Interior MEP Finishes
• Testing & Turnover
• Project Close-out
Baseline Schedule Development (Cont.)
Key Elements
• Milestones
• Design Phase
• Pre-Construction Submittals/Review
• Construction Submittals/Review
• Procurement Activities
• Fabrication & Delivery Activities
• Site Work & Utilities
• Foundations & Structural
• Exterior Finishes
• Interior MEP Rough-ins
5
®
Baseline Schedule Development (Cont.)
Key Configuration/Control
• CPM with “Retained Logic”
• No open ended activities (Pred/Succ)
• Activity Durations <20 days
• Activity Calendars (Work Days vs. Calendar Days, Weather Days)
• Total Float based on “Longest Path”
• Limited use of Constraints
• Supports contract required completion date
6
® Key Considerations
• Contract Requirements
• Backup to Pay Requests
• Submittal Updates
• Procurement Updates
• Subcontractor Updates
• Impacts / Delays
• Contract Changes
• Reporting Requirements
Schedule Updating / Maintenance
7
® Key Elements
• Schedule Update “Data Date”
• Update to reflect actual period progress / status
» Actual Start Dates
» Actual Finish Dates
» % Complete (Physical)
» Remaining Duration
• Activity Relationship Changes
• Activities Added / Deleted
• Update Narrative Report
Schedule Updating / Maintenance
8
® Key Configuration/Control
• Schedule “Data Date”
• Correct “Out of Sequence” Progress
• No open ended activities (Pred/Succ)
• Total Float based on “Longest Path”
• Incorporates all known Impacts and Delays
• Incorporates Contract Changes
• Updated/Revised Critical Path
• Includes Update Narrative Report
Schedule Updating / Maintenance
9
®
Key Elements• Add Changes to the schedule as they
occur.
• Change activities need to be tied to activities that are or will be impacted.
• Changes and projected impacts need to be discussed in the Update Narrative report.
• Change Notification needs to be made early and in accordance with Contract requirements.
• Impact analysis should be performed as early as possible.
Managing Project Changes
10
®
USACE Requirements
USACE – Project Schedule Requirements
Unified Facility Guide Specification
• UFGS – 01 32 01.00 10, Project Schedule
Contract Specification Section
• 01 32 01.00 ??, Project Schedule
USACE Regulation
• ER 1-1-11, Progress, Schedules, and Network Analysis Systems
11
®
USACE Requirements
3.1 - General Requirements
Contractors proposed sequencing of the project work scope.
Forward planning and project monitoring tool.
Includes dates on which the Contractor contemplates starting and completing all scheduled activities.
Represents entire project including design, procurement, construction, and turnover.
Includes participation by contractor management, designers, subcontractors, suppliers.
12
®
USACE Requirements
3.1 - General Requirements (continued)
3.1.1 - Approved Project Schedule
• Must be Cost Loaded
• Must have all required activity coding
• Used to measure work progress
• Forms basis for progress payments
• Aids in evaluating time impacts and extensions
• Approval of Progress Payments may be withheld without schedule submission
13
®
USACE Requirements
3.2 - Basis for Payment and Cost Loading
Activity cost loading shall be reasonable
Activity cost loading must balance with contract CLIN values
Basis for determining period contract earnings/progress payments
Lack of approved schedule will impact processing of progress payments
Retainage may be withheld if changes/revisions have not been incorporated into the updated schedule
14
®
USACE Requirements
3.3 - Project Schedule Detail Requirements 3.3.1 - Critical Path Method
3.3.2 - Level of Detail Required
3.3.3 - Scheduled Project Completion and Activity Calendars
3.3.4 - Interim Completion Dates
3.3.5 - Default Progress Data – Not Allowed
3.3.6 - Out-of-Sequence Progress – Not Allowed
3.3.7 - Negative Lags and Start to Finish Relationships – Not Allowed
3.3.8 - Calculation Mode – Retained Logic
3.3.9 - Milestones
15
®
USACE Requirements
3.4 - Project Schedule Submissions 3.4.1 - Preliminary Project Schedule Submission
» Submit within 15 calendar days of NTP» Used for basis of Progress Payments during first 90 days after NTP
3.4.2 - Initial Project Schedule Submission » Submit within 42 calendar days of NTP» Used for basis of all remaining Progress Payments» Once approved, becomes the Baseline Schedule
3.4.3 – Design Package Schedule Submission» Extracted from the then current Preliminary, Initial, or Updated schedule
3.4.4 - Periodic Schedule Updates» Required to support estimate upon which progress payments may be made
16
®
Project Schedule
3.4 - Project Schedule Submissions (continued) 3.4.5 - Standard Activity Coding Dictionary
• SDEF (ER 1-1-11, Appendix A)
• Exact structure is mandatory
Activity
Field Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible Patry (e.g. GC, Subcontractor, USACE)
3 AREA 4 Area of Work
4 MODF 6 Modification or REA number
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of Work
7 CATW 1 Category of Work
8 FOW1 10 Feature of Work (used up to 10 charactures in length)
9 FOW2 10 Feature of Work (used up to 20 charactures in length)
10 FOW3 10 Feature of Work (used up to 30 charactures in length)
17
®
USACE Requirements
3.5 - Submission Requirements 3.5.1 - Data CD’s
3.5.2 - Narrative Report Description of activities on Critical Path Description of current/anticipated problem areas Description of delay factors and their impacts Explanation of corrective actions taken Communicate Contractors analysis of the schedule and its plans to compensate for any
problems
3.5.3 - Approved Change Verification
3.5.4 - Schedule Report
3.5.5 - Network Diagram
18
®
USACE Requirements
3.6 - Periodic Schedule Update Meeting 3.6.1 - Update Submission following Progress Meeting
3.6.2 - Status of Activities
3.7 – Request For Time Extensions
3.7.1 - Justification of Delay
3.7.2 - Submission Requirements
3.7.3 - Additional Submission Requirements
Start and Finish Dates Remaining Durations Activity Percent Complete
Logic Change Other Change
19
®
Project Schedule
3.8 - Directed Changes
3.9 - Weekly Progress Meetings
3.10 - Ownership of Float
3.11 - Transfer of Schedule Data into RMS/QCS
20
®
The schedule communicates the Scope and Work Plan of the project
It all starts with the project Baseline schedule
Periodic (monthly) updating is a must
Minimum configuration control must be followed to retain validity of the schedule
The schedule documents what actually happened through-out the life cycle of the project
The schedule is the primary tool used for documenting and modeling time related impacts/delays
Conclusion