Projecttitel: BLUE Piling TechnologyJasper Winkes
Project partners: Van Oord OWP BV, TNO, Fistuca BV
17 mei 2013 Titel 2
The challenge
↑ Hammer size
↑ Noise mitigation €€
Pile driving damage critical
↑ Turbine size
↑ Water depth
↑ Foundation size
17 mei 2013 Titel 3
The challenge
17 mei 2013 Titel 4
Working principle BLUE Piling Technology
17 mei 2013 Titel 5
Development timeline
Phase 1
Q3 2011 – Q1 2012
Ø0.16 m
35 kN
0.2 kJ
Phase 2
Q1 2012 - Q3 2012
Ø0.6 m
1,200 kN
10 kJ
Phase 3
Q4 2012 - Q3 2013
Ø 2.2 m
12,000 kN
250 kJ
Phase 3 X
Q4 2013 – Q3 2014
Driving concrete pile
>500 kJ
Phase 4
Q2 2015 – Q1 2016
Ø5 m
>5 MJ Measured!
17 mei 2013 Titel 6
Video of demonstration on testpile
17 mei 2013 Titel 7
Results: Noise
130
140
150
160
170
180
0 1 2 3 4 5
Leve
l at
750
m d
ista
nce
, dB
re
1 μ
Pa
Pile diameter, m
SEL Values Hydraulic hammers vs BLUE hammer
BSH Noise limit
Typical operation
• BLUE Hammers can drive piles without requiring noise mitigation
• Equals (tens of) millions savings noise mitigation costs
17 mei 2013 Titel 8
Results: Fatigue
• The application of a BLUE Hammer allows savings of more than 85% on the installation fatigue.
• Further investigation by RAMBOLL shows that fully assembled monopiles can be driven, with boat landing, anodes etc. welded onto the pile.
0.5% - 5%
0.5% - 5%
0.0% - 0.2%
0.4% - 4%
39%
21%
6%
3%
Hydraulic Hammer
BLUEHammer
Fatigue damage
17 mei 2013 Titel 9
Future steps
Currently is Fistuca BV building the most powerful, most quiet and most gentle hammer in the world.
This will allow the industry to save tens of millions per project by reduced noise emissions, fatigue and the possibility of using larger and fully assembled piles.
Hammer will be available for rent by the end of 2017.
15 februari 2017 Match Making Day TKI Wind op Zee en Lancering Tenders 2017 10
Fistuca BV
Jasper Winkes
+31627367351
BLUE Piling Technology;
Driving down the costs of offshore foundations!
With thanks to our project partners: