10
Projecttitel: BLUE Piling Technology Jasper Winkes Project partners: Van Oord OWP BV, TNO, Fistuca BV

Projecttitel: BLUE Piling Technology

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Projecttitel: BLUE Piling Technology

Projecttitel: BLUE Piling TechnologyJasper Winkes

Project partners: Van Oord OWP BV, TNO, Fistuca BV

Page 2: Projecttitel: BLUE Piling Technology

17 mei 2013 Titel 2

The challenge

↑ Hammer size

↑ Noise mitigation €€

Pile driving damage critical

↑ Turbine size

↑ Water depth

↑ Foundation size

Page 3: Projecttitel: BLUE Piling Technology

17 mei 2013 Titel 3

The challenge

Page 4: Projecttitel: BLUE Piling Technology

17 mei 2013 Titel 4

Working principle BLUE Piling Technology

Page 5: Projecttitel: BLUE Piling Technology

17 mei 2013 Titel 5

Development timeline

Phase 1

Q3 2011 – Q1 2012

Ø0.16 m

35 kN

0.2 kJ

Phase 2

Q1 2012 - Q3 2012

Ø0.6 m

1,200 kN

10 kJ

Phase 3

Q4 2012 - Q3 2013

Ø 2.2 m

12,000 kN

250 kJ

Phase 3 X

Q4 2013 – Q3 2014

Driving concrete pile

>500 kJ

Phase 4

Q2 2015 – Q1 2016

Ø5 m

>5 MJ Measured!

Page 6: Projecttitel: BLUE Piling Technology

17 mei 2013 Titel 6

Video of demonstration on testpile

Page 7: Projecttitel: BLUE Piling Technology

17 mei 2013 Titel 7

Results: Noise

130

140

150

160

170

180

0 1 2 3 4 5

Leve

l at

750

m d

ista

nce

, dB

re

1 μ

Pa

Pile diameter, m

SEL Values Hydraulic hammers vs BLUE hammer

BSH Noise limit

Typical operation

• BLUE Hammers can drive piles without requiring noise mitigation

• Equals (tens of) millions savings noise mitigation costs

Page 8: Projecttitel: BLUE Piling Technology

17 mei 2013 Titel 8

Results: Fatigue

• The application of a BLUE Hammer allows savings of more than 85% on the installation fatigue.

• Further investigation by RAMBOLL shows that fully assembled monopiles can be driven, with boat landing, anodes etc. welded onto the pile.

0.5% - 5%

0.5% - 5%

0.0% - 0.2%

0.4% - 4%

39%

21%

6%

3%

Hydraulic Hammer

BLUEHammer

Fatigue damage

Page 9: Projecttitel: BLUE Piling Technology

17 mei 2013 Titel 9

Future steps

Currently is Fistuca BV building the most powerful, most quiet and most gentle hammer in the world.

This will allow the industry to save tens of millions per project by reduced noise emissions, fatigue and the possibility of using larger and fully assembled piles.

Hammer will be available for rent by the end of 2017.

Page 10: Projecttitel: BLUE Piling Technology

15 februari 2017 Match Making Day TKI Wind op Zee en Lancering Tenders 2017 10

Fistuca BV

Jasper Winkes

[email protected]

+31627367351

BLUE Piling Technology;

Driving down the costs of offshore foundations!

With thanks to our project partners: