Project Preparation - Week 08

Embed Size (px)

Citation preview

  • 7/28/2019 Project Preparation - Week 08

    1/20

    1

  • 7/28/2019 Project Preparation - Week 08

    2/20

    2

    Activities (1)

    An activity is an element of the project that consumes time and

    which may or which in some cases may not consume any

    resources

    Activities can be divided into tasks

    Depending on the nature of the project, It is conceivable that awork package may be comprised of several activities, of a single

    activity or that two or more work packages may constitute a

    activity

    Activities are the building blocks of the project schedule. Aprojects activity list shows all activities and provides supporting

    information including resource consumption levels, expertise

    required, assumptions, constraints, expected deliverables activity

    manager etc.

  • 7/28/2019 Project Preparation - Week 08

    3/20

    3

    Activity Sequencing &

    Activity Duration Estimating

    Activity Sequencing involves identifying and documenting the

    logical precedence relationships between project activities.

    Activities must be logically sequenced with proper precedence

    relationships to support the subsequent development of a realistic

    and achievable schedule. This can be accomplished manually or

    with the aid of appropriate software

    Activity Duration Estimating involves making an assessment of the

    likely number of work periods that will be required to complete a

    project activity. Ideally, an activity duration estimate should

    include an indication of the range of possible time that an activity

    will take to complete

  • 7/28/2019 Project Preparation - Week 08

    4/20

    4

    How is Activity Duration Estimated? (1)

    Estimating activity durations is best done by individuals who arefamiliar with the work content. The quality of duration estimates

    hinges largely on the quality of the available information. There are

    several methods which are used for estimating activity duration in

    projects:

    Expert Judgment Individuals with specialized knowledge and

    experience in resource planning and duration estimating

    Analogous Duration Estimating Using similar activities asindicators of duration of an activity . Good in situations where

    information is lacking

  • 7/28/2019 Project Preparation - Week 08

    5/20

    5

    How is Activity Duration Estimated? (2)

    Quantitative Assessments For example: Work x Productivity Rate

    Three-Point Estimates Takes risk into consideration (most likely,

    optimistic, pessimistic)

    Reserve Time In the event of contingencies

  • 7/28/2019 Project Preparation - Week 08

    6/20

    6

    How are Activity Resource

    Requirements Estimated?

    Estimating the resource requirements of activities involves

    determining the type of physical resources (i.e. manpower,

    materials, machinery), the quantity required and the specific time

    when they will be required. Various methods are used for

    estimating activity resource requirements in projects, including,for example:

    Expert Judgment Individuals with specialized knowledge and

    experience in resource planning and duration estimating

    Published Estimating Data Available data on production rates,

    unit resource costs for labor, materials etc.

    Bottom-Up Estimating Decomposition of complex activities and

    corresponding assessment

  • 7/28/2019 Project Preparation - Week 08

    7/20

    7

    Project Activity Sequencing

    and Scheduling

    Project Activity Sequencing is the prerequisite for developing the

    project schedule. The project schedule determines the planned

    start and finish dates for all project activities. It requires duration

    estimates for each project activity, and is most conveniently

    depicted pictorially in the form of a bar chart (the Gantt Chart), orthe more informational and much more complex - form of a

    Network Diagram

    There are two network diagramming techniques which are used in

    project management the precedence diagramming method and

    the arrow-on-node method. The precedence method tends to be

    preferred by project managers over the arrow-on-node method

    which has some inherent structural drawbacks

  • 7/28/2019 Project Preparation - Week 08

    8/20

    8

    Basic Considerations in Developing

    Project Network Diagrams (1)

    Networks and their containing project activities flow from left to

    right

    Arrows on networks indicate precedence and flow and can cross

    each other

    Each project activity should have a unique identification number

    Looping of activities is not permissible

    Conditional statements (if then ) are impermissible

    Each activity in a project network have at least one predecessor

    and successor activity, except the first and last project activities

  • 7/28/2019 Project Preparation - Week 08

    9/20

    9

    Basic Considerations in Developing

    Project Network Diagrams (2)

    An activity can start only when all preceding connected activities

    have been completed

    If there are multiple start and end activities, a single node should

    be used to depict a start activity of a network diagram and a

    single node should be used to depict a end activity

  • 7/28/2019 Project Preparation - Week 08

    10/20

    10

    The Gantt Chart

    Named after the American Henry Gantt, the chart pictorially

    depicts project activities in the form of rectangular horizontalbars, with the length of the bar corresponding to the duration ofthe activity in question

    The main advantage of the Gantt Chart lies in its visual simplicity,but at the same time, it has a number of inherent drawbacks

    which are not present in network diagramming methods andwhich hence decrease its value as a project management tool:

    It does not provide adequate information on activities andresource requirements

    It does not provide any indication whether the resulting projectschedule represents the least attainable project completion time

    It allows the project manager to arbitrarily set the projectschedule

    It is unsuitable for large, more complex projects

  • 7/28/2019 Project Preparation - Week 08

    11/20

    11

    Example of a Gantt Chart

    Activity

    Identifier

    Activity Description Duration

    (workdays)

    1.1.2DY Work Package 1

    (Design and Build

    Component X)

    100

    1.1.3BXY Work Package 2

    (Design and BuildComponent Y)

    50

    1.1.4TXY Work Package 3

    (Test Components Xand Y)

    25

    1.1.5IXY Work Package 4

    (Integrate ComponentsX and Y)

    50

    P1 P2 P3 P4 P5

    Project Schedule Time Frame

  • 7/28/2019 Project Preparation - Week 08

    12/20

    12

    The Precedence Diagramming Method

    Precedence diagramming is a method of constructing project

    schedule network diagrams using boxes or rectangles known as

    nodes to represent individual project activities, and connects

    them with arrows to depict the dependencies between the project

    activities

    Activity A Activity B Activity C Activity A precedes

    Activity B which

    precedes Activity C

    Activity X

    Activity Y

    Activity Z

    Activity X precedes

    both Activities Y and Z

  • 7/28/2019 Project Preparation - Week 08

    13/20

    13

    The Four Basic Types of

    Precedence Relationships

    Activity A Activity BFS: Finish-to-Start

    Activity A must finish before

    Activity B can start

    Activity A

    Activity B

    SS: Start-to-Start

    Activity B may start onceActivity A has started

    Activity A Activity B

    SF: Start-to-Finish

    Activity B may finish once

    Activity A has started

    Activity A

    Activity B

    FF: Finish-to-Finish

    Activity B cannot finish until

    Activity A has finished

  • 7/28/2019 Project Preparation - Week 08

    14/20

    14

    Dependency Constraints

    In identifying and depicting dependencies between project

    activities, a number of constraints must be taken intoconsideration. Basically, there are four types of dependencies that

    may influence the sequencing and time schedule of project

    activities:

    Technical Constraints One or more project activities provide

    input for one or more other project activities

    Inter-Project Constraints The deliverables from one project

    serve as inputs for activities in another project (subprojects,

    geographical dispersion)Date Constraints Imposition of start and finish dates on

    project activities (no later than / earlier than / on this date)

    Management Constraints As specified by project managers or

    other primary stakeholders

  • 7/28/2019 Project Preparation - Week 08

    15/20

    15

    ACTIVITY

    DESCRIPTION

    ACTIVITYIDENTIFIER

    ACTIVITYDURATION

    ES EF

    LS LF

    SLA

    CK

    The CRITICAL PATH of a project is the

    sequence of activities that determine the project

    completion date any delay in an activity or

    activities comprising the critical path will delay

    the project by a corresponding amount of time

    Project Network Diagrams: The Node

    EARLY START: When can the activitystart at the earliest?

    EARLY FINISH: When can the activityfinish at the earliest?

    LATE FINISH: When can the activityfinish at the latest?

    LATE START: When can the activitystart at the latest?

    SLACK: The time forwhich the activity canbe delayed (also called

    float)

  • 7/28/2019 Project Preparation - Week 08

    16/20

    16

    Constructing a Project Network Diagram:(Example of Network Components and Details)

    Koll Business Information Center

    Activity Description Preceding Activity

    Activity Duration

    A Approval of Application None 5

    B Construction Plans A 15

    C Traffic Study A 10

    D Service Availability Check A 5

    E Staff Report B, C 15F Commission Approval B, C, D 10

    G Wait for Construction F 170

    H Occupancy E, G 35

  • 7/28/2019 Project Preparation - Week 08

    17/20

    17

    The Basic

    Network

    Structure

    Merge

    Activities

    Burst

    Activities

    A

    Approval of

    Application

    C

    Traffic Study

    D

    Service Avail-

    ability Check

    E

    Staff Report

    F

    Commission

    Approval

    B

    Construction

    Plans

    H

    Occupancy

    G

    Wait for

    Construction

    Constructing a Project Network Diagram:(Graphical Depiction of the Network Components)

  • 7/28/2019 Project Preparation - Week 08

    18/20

    18

    Constructing a Project Network Diagram:(Determining the Forward Pass)

    Application

    Approval

    Construction

    Plans

    Traffic

    Study

    Service

    Check

    Commission

    Approval

    Staff

    Report

    Wait for

    Construction

    Occupancy

    A

    B

    C

    D

    F

    E

    G

    H

    5

    15

    10

    5

    10

    15

    170

    35

    50

    205

    155

    105

    3020

    3520

    20030

    235200

    Forward PassES + Duration = EF

    20

    15

    10

    20

    15

    200

    35

    5

    5

    5

    30

  • 7/28/2019 Project Preparation - Week 08

    19/20

    19

    Application

    Approval

    A

    5

    Constructing a Project Network Diagram:(Determining the Backward Pass)

    Construction

    Plans

    B

    15

    Traffic

    Study

    C

    10

    Service

    Check

    D

    5

    Commission

    Approval

    F

    10

    Staff

    Report

    E

    15

    Wait for

    Construction

    G

    170

    Occupancy

    H

    35

    50

    205

    155

    105

    3020

    3520

    20030

    235200

    Backward PassLS + Duration = LF

    50 10 20

    205

    2015

    3020

    200185

    20030

    235200

    20

    20

    20

    200

    5

    10

    15

    30

    200185

    185

  • 7/28/2019 Project Preparation - Week 08

    20/20

    20

    Application

    Approval

    A

    5

    Constructing a Project Network Diagram:(Determining Slack and the Critical Path)

    Construction

    Plans

    B

    15

    Traffic

    Study

    C

    10

    Service

    Check

    D

    5

    Commission

    Approval

    F

    10

    Staff

    Report

    E

    15

    Wait for

    Construction

    G

    170

    Occupancy

    H

    35

    50

    205

    155

    105

    3020

    3520

    20030

    235200

    50 10 20

    205

    2015

    3020

    200185

    20030

    235200

    Slack = LS ESSlack = LF - EF

    0

    0

    5

    10

    0

    165

    0

    0