Upload
ikram-jasra
View
218
Download
0
Embed Size (px)
Citation preview
7/28/2019 Project Preparation - Week 08
1/20
1
7/28/2019 Project Preparation - Week 08
2/20
2
Activities (1)
An activity is an element of the project that consumes time and
which may or which in some cases may not consume any
resources
Activities can be divided into tasks
Depending on the nature of the project, It is conceivable that awork package may be comprised of several activities, of a single
activity or that two or more work packages may constitute a
activity
Activities are the building blocks of the project schedule. Aprojects activity list shows all activities and provides supporting
information including resource consumption levels, expertise
required, assumptions, constraints, expected deliverables activity
manager etc.
7/28/2019 Project Preparation - Week 08
3/20
3
Activity Sequencing &
Activity Duration Estimating
Activity Sequencing involves identifying and documenting the
logical precedence relationships between project activities.
Activities must be logically sequenced with proper precedence
relationships to support the subsequent development of a realistic
and achievable schedule. This can be accomplished manually or
with the aid of appropriate software
Activity Duration Estimating involves making an assessment of the
likely number of work periods that will be required to complete a
project activity. Ideally, an activity duration estimate should
include an indication of the range of possible time that an activity
will take to complete
7/28/2019 Project Preparation - Week 08
4/20
4
How is Activity Duration Estimated? (1)
Estimating activity durations is best done by individuals who arefamiliar with the work content. The quality of duration estimates
hinges largely on the quality of the available information. There are
several methods which are used for estimating activity duration in
projects:
Expert Judgment Individuals with specialized knowledge and
experience in resource planning and duration estimating
Analogous Duration Estimating Using similar activities asindicators of duration of an activity . Good in situations where
information is lacking
7/28/2019 Project Preparation - Week 08
5/20
5
How is Activity Duration Estimated? (2)
Quantitative Assessments For example: Work x Productivity Rate
Three-Point Estimates Takes risk into consideration (most likely,
optimistic, pessimistic)
Reserve Time In the event of contingencies
7/28/2019 Project Preparation - Week 08
6/20
6
How are Activity Resource
Requirements Estimated?
Estimating the resource requirements of activities involves
determining the type of physical resources (i.e. manpower,
materials, machinery), the quantity required and the specific time
when they will be required. Various methods are used for
estimating activity resource requirements in projects, including,for example:
Expert Judgment Individuals with specialized knowledge and
experience in resource planning and duration estimating
Published Estimating Data Available data on production rates,
unit resource costs for labor, materials etc.
Bottom-Up Estimating Decomposition of complex activities and
corresponding assessment
7/28/2019 Project Preparation - Week 08
7/20
7
Project Activity Sequencing
and Scheduling
Project Activity Sequencing is the prerequisite for developing the
project schedule. The project schedule determines the planned
start and finish dates for all project activities. It requires duration
estimates for each project activity, and is most conveniently
depicted pictorially in the form of a bar chart (the Gantt Chart), orthe more informational and much more complex - form of a
Network Diagram
There are two network diagramming techniques which are used in
project management the precedence diagramming method and
the arrow-on-node method. The precedence method tends to be
preferred by project managers over the arrow-on-node method
which has some inherent structural drawbacks
7/28/2019 Project Preparation - Week 08
8/20
8
Basic Considerations in Developing
Project Network Diagrams (1)
Networks and their containing project activities flow from left to
right
Arrows on networks indicate precedence and flow and can cross
each other
Each project activity should have a unique identification number
Looping of activities is not permissible
Conditional statements (if then ) are impermissible
Each activity in a project network have at least one predecessor
and successor activity, except the first and last project activities
7/28/2019 Project Preparation - Week 08
9/20
9
Basic Considerations in Developing
Project Network Diagrams (2)
An activity can start only when all preceding connected activities
have been completed
If there are multiple start and end activities, a single node should
be used to depict a start activity of a network diagram and a
single node should be used to depict a end activity
7/28/2019 Project Preparation - Week 08
10/20
10
The Gantt Chart
Named after the American Henry Gantt, the chart pictorially
depicts project activities in the form of rectangular horizontalbars, with the length of the bar corresponding to the duration ofthe activity in question
The main advantage of the Gantt Chart lies in its visual simplicity,but at the same time, it has a number of inherent drawbacks
which are not present in network diagramming methods andwhich hence decrease its value as a project management tool:
It does not provide adequate information on activities andresource requirements
It does not provide any indication whether the resulting projectschedule represents the least attainable project completion time
It allows the project manager to arbitrarily set the projectschedule
It is unsuitable for large, more complex projects
7/28/2019 Project Preparation - Week 08
11/20
11
Example of a Gantt Chart
Activity
Identifier
Activity Description Duration
(workdays)
1.1.2DY Work Package 1
(Design and Build
Component X)
100
1.1.3BXY Work Package 2
(Design and BuildComponent Y)
50
1.1.4TXY Work Package 3
(Test Components Xand Y)
25
1.1.5IXY Work Package 4
(Integrate ComponentsX and Y)
50
P1 P2 P3 P4 P5
Project Schedule Time Frame
7/28/2019 Project Preparation - Week 08
12/20
12
The Precedence Diagramming Method
Precedence diagramming is a method of constructing project
schedule network diagrams using boxes or rectangles known as
nodes to represent individual project activities, and connects
them with arrows to depict the dependencies between the project
activities
Activity A Activity B Activity C Activity A precedes
Activity B which
precedes Activity C
Activity X
Activity Y
Activity Z
Activity X precedes
both Activities Y and Z
7/28/2019 Project Preparation - Week 08
13/20
13
The Four Basic Types of
Precedence Relationships
Activity A Activity BFS: Finish-to-Start
Activity A must finish before
Activity B can start
Activity A
Activity B
SS: Start-to-Start
Activity B may start onceActivity A has started
Activity A Activity B
SF: Start-to-Finish
Activity B may finish once
Activity A has started
Activity A
Activity B
FF: Finish-to-Finish
Activity B cannot finish until
Activity A has finished
7/28/2019 Project Preparation - Week 08
14/20
14
Dependency Constraints
In identifying and depicting dependencies between project
activities, a number of constraints must be taken intoconsideration. Basically, there are four types of dependencies that
may influence the sequencing and time schedule of project
activities:
Technical Constraints One or more project activities provide
input for one or more other project activities
Inter-Project Constraints The deliverables from one project
serve as inputs for activities in another project (subprojects,
geographical dispersion)Date Constraints Imposition of start and finish dates on
project activities (no later than / earlier than / on this date)
Management Constraints As specified by project managers or
other primary stakeholders
7/28/2019 Project Preparation - Week 08
15/20
15
ACTIVITY
DESCRIPTION
ACTIVITYIDENTIFIER
ACTIVITYDURATION
ES EF
LS LF
SLA
CK
The CRITICAL PATH of a project is the
sequence of activities that determine the project
completion date any delay in an activity or
activities comprising the critical path will delay
the project by a corresponding amount of time
Project Network Diagrams: The Node
EARLY START: When can the activitystart at the earliest?
EARLY FINISH: When can the activityfinish at the earliest?
LATE FINISH: When can the activityfinish at the latest?
LATE START: When can the activitystart at the latest?
SLACK: The time forwhich the activity canbe delayed (also called
float)
7/28/2019 Project Preparation - Week 08
16/20
16
Constructing a Project Network Diagram:(Example of Network Components and Details)
Koll Business Information Center
Activity Description Preceding Activity
Activity Duration
A Approval of Application None 5
B Construction Plans A 15
C Traffic Study A 10
D Service Availability Check A 5
E Staff Report B, C 15F Commission Approval B, C, D 10
G Wait for Construction F 170
H Occupancy E, G 35
7/28/2019 Project Preparation - Week 08
17/20
17
The Basic
Network
Structure
Merge
Activities
Burst
Activities
A
Approval of
Application
C
Traffic Study
D
Service Avail-
ability Check
E
Staff Report
F
Commission
Approval
B
Construction
Plans
H
Occupancy
G
Wait for
Construction
Constructing a Project Network Diagram:(Graphical Depiction of the Network Components)
7/28/2019 Project Preparation - Week 08
18/20
18
Constructing a Project Network Diagram:(Determining the Forward Pass)
Application
Approval
Construction
Plans
Traffic
Study
Service
Check
Commission
Approval
Staff
Report
Wait for
Construction
Occupancy
A
B
C
D
F
E
G
H
5
15
10
5
10
15
170
35
50
205
155
105
3020
3520
20030
235200
Forward PassES + Duration = EF
20
15
10
20
15
200
35
5
5
5
30
7/28/2019 Project Preparation - Week 08
19/20
19
Application
Approval
A
5
Constructing a Project Network Diagram:(Determining the Backward Pass)
Construction
Plans
B
15
Traffic
Study
C
10
Service
Check
D
5
Commission
Approval
F
10
Staff
Report
E
15
Wait for
Construction
G
170
Occupancy
H
35
50
205
155
105
3020
3520
20030
235200
Backward PassLS + Duration = LF
50 10 20
205
2015
3020
200185
20030
235200
20
20
20
200
5
10
15
30
200185
185
7/28/2019 Project Preparation - Week 08
20/20
20
Application
Approval
A
5
Constructing a Project Network Diagram:(Determining Slack and the Critical Path)
Construction
Plans
B
15
Traffic
Study
C
10
Service
Check
D
5
Commission
Approval
F
10
Staff
Report
E
15
Wait for
Construction
G
170
Occupancy
H
35
50
205
155
105
3020
3520
20030
235200
50 10 20
205
2015
3020
200185
20030
235200
Slack = LS ESSlack = LF - EF
0
0
5
10
0
165
0
0