Saudi Aramco Prequalification Questionnaire, General Bid Slates (GBS). Version: March 2015
PROJECT MANAGEMENT
GENERAL BID SLATES (GBS)
PREQUALIFICATION QUESTIONNAIRE
PART-B
Electrical Systems Group
Electrical & Instrumentation
Cathodic Protection & Transmission Lines
Contents
Instructions: GBS Experience Section .......................................................................................................... 2
Area Of Expertise .......................................................................................................................................... 3
Exhibit F: Summary Of Work Experience ..................................................................................................... 4
Exhibit G: Human Resources ........................................................................................................................ 7
Exhibit H: Equipment ................................................................................................................................... 38
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 2/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 2 of 40
INSTRUCTIONS: GBS EXPERIENCE SECTION
Part B of the Prequalification Questionnaire (PQQ) supplements Part A and requests information specific to the scope of work ofthe General Bid Slate (GBS) including relevant work experience, human resources, and equipment.
Saudi Aramco manages 15 Project GBS which are categorized into 7 groups. Each group has a unique Part B questionnaire.This Part B of the PQQ for the Electrical Systems Group is for companies requesting prequalification for the Electrical &Instrumentation GBS and the Cathodic Protection & Transmission Lines GBS. You will have an opportunity to identify areas ofspecialized expertise on these GBS, as well as your company’s financial capacity for these projects.
You are required to provide detailed experience and construction resource information for each GBS listed below that you arerequesting prequalification under. The Prequalification Evaluation Team (PQET) will use the information submitted in the Exhibitsof this Part B to verify that you possess the required experience, and resources to be part of the GBS.
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 3/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 3 of 40
AREA OF EXPERTISE Identify Areas of Expertise/Specialty
# General Bid Slate Description of Scope of WorkCompanySpecialty?(Yes/No)
Value ofLargest Project
Completed
(in USD)1) Electrical Systems & Instrumentation:
a) ElectricalSubstations
Construction of: Electrical Substations, Power distribution grids,installation of transformers and circuit breakers/ switchgear, andall associated instrumentation and interconnections.
YES
b) ElectricalTransmission Lines
Construction of: power transmission lines, and all associated sitepreparation and earth works.
NO
2) Cathodic Protection & Transmission Lines:
a) Cathodic Protection& TransmissionLines
Construction of galvanic anodes, Impressed Current CathodicProtection (ICCP) system installation, power transmission lines,and all associated site preparation and earth works.
NO
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 4/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 4 of 40
EXHIBIT F: SUMMARY OF WORK EXPERIENCE Projects Completed and Ongoing
List all completed and ongoing projects within the last 10 years, which are related to selected GBS(s) scope of work.
Project Type ProjectTitle
ContractValue in
US $
AwardDate
CompletionDate
Status(Completed
/Ongoing)
LSTK/LSPB/
other
Prime orSub-
Contract
Location(Country &
City)
ElectricalSubstations
Sadaba 11,100,250 Nov 8,2007
June 2008 Completed LSTK Prime Spain, Aragon
ElectricalSubstations
Espejo I 5,600,000 Dec,2007
June 2008 Completed LSTK Prime Spain, Andalucia
ElectricalSubstations
Lucaiena 3,000,000 2009 Completed LSTK Prime Spain, Andalucia
ElectricalSubstations
Espejo II 6,540,075 July ,2008
February2009
Completed LSTK Prime Spain, Andalucia
ElectricalSubstations
Espejo III 5,000,000 2009 Completed LSTK Prime Spain, Andalucia
ElectricalSubstations
Sevilla PV 3,500,000 Nov,2007
April 2008 Completed LSTK Prime Spain, Andalucia
ElectricalSubstations
CordobaPV
8,000,000 Oct,2007
September2008
Completed LSTK Prime Spain, Andalucia
ElectricalSubstations
Parque FVCiudadReal
10,000,000 2008 Completed LSTK Prime Spain, CiudadReal
ElectricalSubstations
Almonacid
PV Plant
5,600,000 Dec 10,
2007
July 2008 Completed LSTK Prime Spain, Aragon
ElectricalSubstations
Seat AlSol 5
1,943,040 May 16,2012
November2012
Completed LSTK Prime Spain,Cataluna
ElectricalSubstations
Seat AlSol 6
852,580 May 16,2012
November2012
Completed LSTK Prime Spain,Cataluna
ElectricalSubstations
FrioLimpio
446 July 10,2012
December2012
Completed LSTK Prime Spain, Aragon
ElectricalSubstations
PlantaFotovoltaica
Curbans
32,952,560 Feb, 5,2010
September2011
Completed LSTK Prime France,Hautes Alpes
ElectricalSubstations
BatillyFotovoltaique
10,372,000 June 6,2011
December2011
Completed LSTK Prime France,Creuse
ElectricalSubstations
PVPanamericana
20,000,000 July 6,2012
December2012
Completed LSTK Prime Peru, Tacna
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 5/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 5 of 40
Complete the following form for each ongoing project or projects completed in the last ten (10) years. Duplicate the below formfor each project. Provide copies of completion certificates, performance evaluation reports (signed/stamped by client) and copiesof the contract showing signature pages, contract value, type, scope of work and contract duration. A project will not beconsidered as part of your experience if above back-up documents are not provided.
GBSSpecialty
Select one or more GBS specialty related to the scope of work of this project.
GBS Specialty
1 Electrical Substations
2 Choose an item.
3 Choose an item.
Contract Info Title: SADABA Number:
Award Date: 2007 Contract Value (US$): 11,100,250
Contractual Completion Date: June 2008 Actual Completion Date: June 2008
Planned % Complete: Actual % Complete:
Value of Supplied Material (US$): X Value of Subcontracts (US$):
Client's
CompanyInfo
Client Name: Parques FV Del Espartal
Client Address: Spain, AragonRepresentative Name/Tel & Email:
ContractType
☒ Primary☐ Subcontractor ☒ Sole Contractor☐ Consortium☐ JV, with share %:
☒ LSTK☐ LSPB☐ Unit Rate☐ Construction Management☐ Others, specify: _______________________
Designer LSTK Detailed Design was done:☒ In-House Design Office☐ Outsourced☐ Not LSTK
Scope ofWork
Project’s Location: Spain, Aragon Country: Spain City: Aragon
Project’s Brief Description (related to your scope of work only) :
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 6/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 6 of 40
Sub-contracts
If applicable, list your main four (4) subcontracts under this project:
Scope of Work Value US$ Subcontractor Name
1
2
3
4
HumanResources
Provide human resources details for this project:
Position Number of Resources
1 Management & Administration
2 Project Cost & Scheduling
3 Project Managers
4 Senior Design Engineers
5 Design Engineers
6 Project Engineers
7 Procurement Personnel
8 Quality Department Personnel
9 Construction Supervisors
10 Construction Skilled Labor
11 Construction Unskilled Labor
Total
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 7/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 7 of 40
Complete the following form for each ongoing project or projects completed in the last ten (10) years. Duplicate the below formfor each project. Provide copies of completion certificates, performance evaluation reports (signed/stamped by client) and copiesof the contract showing signature pages, contract value, type, scope of work and contract duration. A project will not beconsidered as part of your experience if above back-up documents are not provided.
GBSSpecialty
Select one or more GBS specialty related to the scope of work of this project.
GBS Specialty
1 Choose an item.
2 Choose an item.
3 Choose an item.
Contract Info Title: ESPEJO I Number:
Award Date: Dec, 2007 Contract Value (US$): 5,600,000
Contractual Completion Date: June 2008 Actual Completion Date: June 2008
Planned % Complete: X Actual % Complete: X
Value of Supplied Material (US$): X Value of Subcontracts (US$): X
Client's
CompanyInfo
Client Name: IDECON
Client Address: Spain, AndaluciaRepresentative Name/Tel & Email:
ContractType
☒ Primary☐ Subcontractor ☒ Sole Contractor☐ Consortium☐ JV, with share %:
☒ LSTK☐ LSPB☐ Unit Rate☐ Construction Management☐ Others, specify: _______________________
Designer LSTK Detailed Design was done:☒ In-House Design Office☐ Outsourced☐ Not LSTK
Scope ofWork
Project’s Location: Spain, Andalucia Country: Spain City: Andalucia
Project’s Brief Description (related to your scope of work only) :
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 8/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 8 of 40
Sub-contracts
If applicable, list your main four (4) subcontracts under this project:
Scope of Work Value US$ Subcontractor Name
1
2
3
4
HumanResources
Provide human resources details for this project:
Position Number of Resources
1 Management & Administration
2 Project Cost & Scheduling
3 Project Managers
4 Senior Design Engineers
5 Design Engineers
6 Project Engineers
7 Procurement Personnel
8 Quality Department Personnel
9 Construction Supervisors
10 Construction Skilled Labor
11 Construction Unskilled Labor
Total
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 9/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 9 of 40
Complete the following form for each ongoing project or projects completed in the last ten (10) years. Duplicate the below formfor each project. Provide copies of completion certificates, performance evaluation reports (signed/stamped by client) and copiesof the contract showing signature pages, contract value, type, scope of work and contract duration. A project will not beconsidered as part of your experience if above back-up documents are not provided.
GBSSpecialty
Select one or more GBS specialty related to the scope of work of this project.
GBS Specialty
1 Choose an item.
2 Choose an item.
3 Choose an item.
Contract Info Title: LUCAIENA Number:
Award Date: X Contract Value (US$): 3,000,000
Contractual Completion Date: 2009 Actual Completion Date: 2009
Planned % Complete: X Actual % Complete: X
Value of Supplied Material (US$): X Value of Subcontracts (US$): X
Client's
CompanyInfo
Client Name: FIRST SOLAR
Client Address: Spain, AndaluciaRepresentative Name/Tel & Email:
ContractType
☒ Primary☐ Subcontractor ☒ Sole Contractor☐ Consortium☐ JV, with share %:
☒ LSTK☐ LSPB☐ Unit Rate☐ Construction Management☐ Others, specify: _______________________
Designer LSTK Detailed Design was done:☒ In-House Design Office☐ Outsourced☐ Not LSTK
Scope ofWork
Project’s Location: Spain, Andalucia Country: Spain City: Andalucia
Project’s Brief Description (related to your scope of work only) :
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 10/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 10 of 40
Sub-contracts
If applicable, list your main four (4) subcontracts under this project:
Scope of Work Value US$ Subcontractor Name
1
2
3
4
HumanResources
Provide human resources details for this project:
Position Number of Resources
1 Management & Administration
2 Project Cost & Scheduling
3 Project Managers
4 Senior Design Engineers
5 Design Engineers
6 Project Engineers
7 Procurement Personnel
8 Quality Department Personnel
9 Construction Supervisors
10 Construction Skilled Labor
11 Construction Unskilled Labor
Total
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 11/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 11 of 40
Complete the following form for each ongoing project or projects completed in the last ten (10) years. Duplicate the below formfor each project. Provide copies of completion certificates, performance evaluation reports (signed/stamped by client) and copiesof the contract showing signature pages, contract value, type, scope of work and contract duration. A project will not beconsidered as part of your experience if above back-up documents are not provided.
GBSSpecialty
Select one or more GBS specialty related to the scope of work of this project.
GBS Specialty
1 Choose an item.
2 Choose an item.
3 Choose an item.
Contract Info Title: ESPEJO II Number:
Award Date: July , 2008 Contract Value (US$): 6,540,075
Contractual Completion Date: February 2009 Actual Completion Date: February 2009
Planned % Complete: X Actual % Complete: X
Value of Supplied Material (US$): X Value of Subcontracts (US$): X
Client's
CompanyInfo
Client Name: IDECON
Client Address: Spain, AndaluciaRepresentative Name/Tel & Email:
ContractType
☒ Primary☐ Subcontractor ☒ Sole Contractor☐ Consortium☐ JV, with share %:
☒ LSTK☐ LSPB☐ Unit Rate☐ Construction Management☐ Others, specify: _______________________
Designer LSTK Detailed Design was done:☒ In-House Design Office☐ Outsourced☐ Not LSTK
Scope ofWork
Project’s Location: Spain, Andalucia Country: Spain City: Andalucia
Project’s Brief Description (related to your scope of work only) :
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 12/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 12 of 40
Sub-contracts
If applicable, list your main four (4) subcontracts under this project:
Scope of Work Value US$ Subcontractor Name
1
2
3
4
HumanResources
Provide human resources details for this project:
Position Number of Resources
1 Management & Administration
2 Project Cost & Scheduling
3 Project Managers
4 Senior Design Engineers
5 Design Engineers
6 Project Engineers
7 Procurement Personnel
8 Quality Department Personnel
9 Construction Supervisors
10 Construction Skilled Labor
11 Construction Unskilled Labor
Total
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 13/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 13 of 40
Complete the following form for each ongoing project or projects completed in the last ten (10) years. Duplicate the below formfor each project. Provide copies of completion certificates, performance evaluation reports (signed/stamped by client) and copiesof the contract showing signature pages, contract value, type, scope of work and contract duration. A project will not beconsidered as part of your experience if above back-up documents are not provided.
GBSSpecialty
Select one or more GBS specialty related to the scope of work of this project.
GBS Specialty
1 Choose an item.
2 Choose an item.
3 Choose an item.
Contract Info Title: ESPEJO III Number:
Award Date: X Contract Value (US$): 5,000,000
Contractual Completion Date: 2009 Actual Completion Date: 2009
Planned % Complete: X Actual % Complete: X
Value of Supplied Material (US$): X Value of Subcontracts (US$): X
Client's
CompanyInfo
Client Name: IDECON
Client Address: Spain, AndaluciaRepresentative Name/Tel & Email:
ContractType
☒ Primary☐ Subcontractor ☒ Sole Contractor☐ Consortium☐ JV, with share %:
☒ LSTK☐ LSPB☐ Unit Rate☐ Construction Management☐ Others, specify: _______________________
Designer LSTK Detailed Design was done:☒ In-House Design Office☐ Outsourced☐ Not LSTK
Scope ofWork
Project’s Location: Spain, Andalucia Country: Spain City: Andalucia
Project’s Brief Description (related to your scope of work only) :
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 14/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 14 of 40
Sub-contracts
If applicable, list your main four (4) subcontracts under this project:
Scope of Work Value US$ Subcontractor Name
1
2
3
4
HumanResources
Provide human resources details for this project:
Position Number of Resources
1 Management & Administration
2 Project Cost & Scheduling
3 Project Managers
4 Senior Design Engineers
5 Design Engineers
6 Project Engineers
7 Procurement Personnel
8 Quality Department Personnel
9 Construction Supervisors
10 Construction Skilled Labor
11 Construction Unskilled Labor
Total
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 15/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 15 of 40
Complete the following form for each ongoing project or projects completed in the last ten (10) years. Duplicate the below formfor each project. Provide copies of completion certificates, performance evaluation reports (signed/stamped by client) and copiesof the contract showing signature pages, contract value, type, scope of work and contract duration. A project will not beconsidered as part of your experience if above back-up documents are not provided.
GBSSpecialty
Select one or more GBS specialty related to the scope of work of this project.
GBS Specialty
1 Choose an item.
2 Choose an item.
3 Choose an item.
Contract Info Title: SEVILLA PV Number:
Award Date: November 2007 Contract Value (US$): 3,500,000
Contractual Completion Date: April 2008 Actual Completion Date: April 2008
Planned % Complete: X Actual % Complete:X
Value of Supplied Material (US$): X Value of Subcontracts (US$): X
Client's
CompanyInfo
Client Name: SEMI
Client Address: Spain, AndaluciaRepresentative Name/Tel & Email:
ContractType
☒ Primary☐ Subcontractor ☒ Sole Contractor☐ Consortium☐ JV, with share %:
☒ LSTK☐ LSPB☐ Unit Rate☐ Construction Management☐ Others, specify: _______________________
Designer LSTK Detailed Design was done:☒ In-House Design Office☐ Outsourced☐ Not LSTK
Scope ofWork
Project’s Location: Spain, Andalucia Country: Spain City: Andalucia
Project’s Brief Description (related to your scope of work only) :
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 16/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 16 of 40
Sub-contracts
If applicable, list your main four (4) subcontracts under this project:
Scope of Work Value US$ Subcontractor Name
1
2
3
4
HumanResources
Provide human resources details for this project:
Position Number of Resources
1 Management & Administration
2 Project Cost & Scheduling
3 Project Managers
4 Senior Design Engineers
5 Design Engineers
6 Project Engineers
7 Procurement Personnel
8 Quality Department Personnel
9 Construction Supervisors
10 Construction Skilled Labor
11 Construction Unskilled Labor
Total
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 17/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 17 of 40
Complete the following form for each ongoing project or projects completed in the last ten (10) years. Duplicate the below formfor each project. Provide copies of completion certificates, performance evaluation reports (signed/stamped by client) and copiesof the contract showing signature pages, contract value, type, scope of work and contract duration. A project will not beconsidered as part of your experience if above back-up documents are not provided.
GBSSpecialty
Select one or more GBS specialty related to the scope of work of this project.
GBS Specialty
1 Choose an item.
2 Choose an item.
3 Choose an item.
Contract Info Title: CORDOBA PV Number:
Award Date: October, 2007 Contract Value (US$): 8,000,000
Contractual Completion Date: September 2008 Actual Completion Date: September 2008
Planned % Complete: X Actual % Complete:X
Value of Supplied Material (US$): X Value of Subcontracts (US$): X
Client's
CompanyInfo
Client Name: SEMI
Client Address: Spain, AndaluciaRepresentative Name/Tel & Email:
ContractType
☒ Primary☐ Subcontractor ☒ Sole Contractor☐ Consortium☐ JV, with share %:
☒ LSTK☐ LSPB☐ Unit Rate☐ Construction Management☐ Others, specify: _______________________
Designer LSTK Detailed Design was done:☒ In-House Design Office☐ Outsourced☐ Not LSTK
Scope ofWork
Project’s Location: Spain, Andalucia Country: Spain City: Andalucia
Project’s Brief Description (related to your scope of work only) :
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 18/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 18 of 40
Sub-contracts
If applicable, list your main four (4) subcontracts under this project:
Scope of Work Value US$ Subcontractor Name
1
2
3
4
HumanResources
Provide human resources details for this project:
Position Number of Resources
1 Management & Administration
2 Project Cost & Scheduling
3 Project Managers
4 Senior Design Engineers
5 Design Engineers
6 Project Engineers
7 Procurement Personnel
8 Quality Department Personnel
9 Construction Supervisors
10 Construction Skilled Labor
11 Construction Unskilled Labor
Total
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 19/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 19 of 40
Complete the following form for each ongoing project or projects completed in the last ten (10) years. Duplicate the below formfor each project. Provide copies of completion certificates, performance evaluation reports (signed/stamped by client) and copiesof the contract showing signature pages, contract value, type, scope of work and contract duration. A project will not beconsidered as part of your experience if above back-up documents are not provided.
GBSSpecialty
Select one or more GBS specialty related to the scope of work of this project.
GBS Specialty
1 Choose an item.
2 Choose an item.
3 Choose an item.
Contract Info Title: PARQUE FV CIUDAD REAL Number:
Award Date: X Contract Value (US$): 10,000,000
Contractual Completion Date: 2008 Actual Completion Date: 2008
Planned % Complete: X Actual % Complete:X
Value of Supplied Material (US$): X Value of Subcontracts (US$): X
Client's
CompanyInfo
Client Name: RENOVALIA
Client Address: Spain, Ciudad RealRepresentative Name/Tel & Email:
ContractType
☒ Primary☐ Subcontractor ☒ Sole Contractor☐ Consortium☐ JV, with share %:
☒ LSTK☐ LSPB☐ Unit Rate☐ Construction Management☐ Others, specify: _______________________
Designer LSTK Detailed Design was done:☒ In-House Design Office☐ Outsourced☐ Not LSTK
Scope ofWork
Project’s Location: Spain, Ciudad Real Country: Spain City: Ciudad Real
Project’s Brief Description (related to your scope of work only) :
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 20/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 20 of 40
Sub-contracts
If applicable, list your main four (4) subcontracts under this project:
Scope of Work Value US$ Subcontractor Name
1
2
3
4
HumanResources
Provide human resources details for this project:
Position Number of Resources
1 Management & Administration
2 Project Cost & Scheduling
3 Project Managers
4 Senior Design Engineers
5 Design Engineers
6 Project Engineers
7 Procurement Personnel
8 Quality Department Personnel
9 Construction Supervisors
10 Construction Skilled Labor
11 Construction Unskilled Labor
Total
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 21/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 21 of 40
Complete the following form for each ongoing project or projects completed in the last ten (10) years. Duplicate the below formfor each project. Provide copies of completion certificates, performance evaluation reports (signed/stamped by client) and copiesof the contract showing signature pages, contract value, type, scope of work and contract duration. A project will not beconsidered as part of your experience if above back-up documents are not provided.
GBSSpecialty
Select one or more GBS specialty related to the scope of work of this project.
GBS Specialty
1 Choose an item.
2 Choose an item.
3 Choose an item.
Contract Info Title: ALMONACID PV PLANT Number:
Award Date: December 10, 2007 Contract Value (US$): 5,600,000
Contractual Completion Date: July 2008 Actual Completion Date: July 2008
Planned % Complete: X Actual % Complete:X
Value of Supplied Material (US$): X Value of Subcontracts (US$): X
Client's
CompanyInfo
Client Name: PAGOLA, S.A.
Client Address: Spain, AragonRepresentative Name/Tel & Email:
ContractType
☒ Primary☐ Subcontractor ☒ Sole Contractor☐ Consortium☐ JV, with share %:
☒ LSTK☐ LSPB☐ Unit Rate☐ Construction Management☐ Others, specify: _______________________
Designer LSTK Detailed Design was done:☒ In-House Design Office☐ Outsourced☐ Not LSTK
Scope ofWork
Project’s Location: Spain, Aragon Country: Spain City: Aragon
Project’s Brief Description (related to your scope of work only) :
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 22/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 22 of 40
Sub-contracts
If applicable, list your main four (4) subcontracts under this project:
Scope of Work Value US$ Subcontractor Name
1
2
3
4
HumanResources
Provide human resources details for this project:
Position Number of Resources
1 Management & Administration
2 Project Cost & Scheduling
3 Project Managers
4 Senior Design Engineers
5 Design Engineers
6 Project Engineers
7 Procurement Personnel
8 Quality Department Personnel
9 Construction Supervisors
10 Construction Skilled Labor
11 Construction Unskilled Labor
Total
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 23/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 23 of 40
Complete the following form for each ongoing project or projects completed in the last ten (10) years. Duplicate the below formfor each project. Provide copies of completion certificates, performance evaluation reports (signed/stamped by client) and copiesof the contract showing signature pages, contract value, type, scope of work and contract duration. A project will not beconsidered as part of your experience if above back-up documents are not provided.
GBSSpecialty
Select one or more GBS specialty related to the scope of work of this project.
GBS Specialty
1 Choose an item.
2 Choose an item.
3 Choose an item.
Contract Info Title: SEAT AL SOL 5 Number:
Award Date: May 16, 2012 Contract Value (US$): 1,943,040
Contractual Completion Date: November 2012 Actual Completion Date: November 2012
Planned % Complete: X Actual % Complete:X
Value of Supplied Material (US$): X Value of Subcontracts (US$): X
Client's
CompanyInfo
Client Name: GESTAMP SOLAR
Client Address: Spain, CatalunaRepresentative Name/Tel & Email:
ContractType
☒ Primary☐ Subcontractor ☒ Sole Contractor☐ Consortium☐ JV, with share %:
☒ LSTK☐ LSPB☐ Unit Rate☐ Construction Management☐ Others, specify: _______________________
Designer LSTK Detailed Design was done:☒ In-House Design Office☐ Outsourced☐ Not LSTK
Scope ofWork
Project’s Location: Spain, Cataluna Country: Spain City: Cataluna
Project’s Brief Description (related to your scope of work only) :
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 24/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 24 of 40
Sub-contracts
If applicable, list your main four (4) subcontracts under this project:
Scope of Work Value US$ Subcontractor Name
1
2
3
4
HumanResources
Provide human resources details for this project:
Position Number of Resources
1 Management & Administration
2 Project Cost & Scheduling
3 Project Managers
4 Senior Design Engineers
5 Design Engineers
6 Project Engineers
7 Procurement Personnel
8 Quality Department Personnel
9 Construction Supervisors
10 Construction Skilled Labor
11 Construction Unskilled Labor
Total
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 25/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 25 of 40
Complete the following form for each ongoing project or projects completed in the last ten (10) years. Duplicate the below formfor each project. Provide copies of completion certificates, performance evaluation reports (signed/stamped by client) and copiesof the contract showing signature pages, contract value, type, scope of work and contract duration. A project will not beconsidered as part of your experience if above back-up documents are not provided.
GBSSpecialty
Select one or more GBS specialty related to the scope of work of this project.
GBS Specialty
1 Choose an item.
2 Choose an item.
3 Choose an item.
Contract Info Title: SEAT AL SOL 6 Number:
Award Date: May 16, 2012 Contract Value (US$): 852,580
Contractual Completion Date: November 2012 Actual Completion Date: November 2012
Planned % Complete: X Actual % Complete:X
Value of Supplied Material (US$): X Value of Subcontracts (US$): X
Client's
CompanyInfo
Client Name: GESTAMP SOLAR
Client Address: Spain, CatalunaRepresentative Name/Tel & Email:
ContractType
☒ Primary☐ Subcontractor ☒ Sole Contractor☐ Consortium☐ JV, with share %:
☒ LSTK☐ LSPB☐ Unit Rate☐ Construction Management☐ Others, specify: _______________________
Designer LSTK Detailed Design was done:☒ In-House Design Office☐ Outsourced☐ Not LSTK
Scope ofWork
Project’s Location: Spain, Cataluna Country: Spain City: Cataluna
Project’s Brief Description (related to your scope of work only) :
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 26/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 26 of 40
Sub-contracts
If applicable, list your main four (4) subcontracts under this project:
Scope of Work Value US$ Subcontractor Name
1
2
3
4
HumanResources
Provide human resources details for this project:
Position Number of Resources
1 Management & Administration
2 Project Cost & Scheduling
3 Project Managers
4 Senior Design Engineers
5 Design Engineers
6 Project Engineers
7 Procurement Personnel
8 Quality Department Personnel
9 Construction Supervisors
10 Construction Skilled Labor
11 Construction Unskilled Labor
Total
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 27/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 27 of 40
Complete the following form for each ongoing project or projects completed in the last ten (10) years. Duplicate the below formfor each project. Provide copies of completion certificates, performance evaluation reports (signed/stamped by client) and copiesof the contract showing signature pages, contract value, type, scope of work and contract duration. A project will not beconsidered as part of your experience if above back-up documents are not provided.
GBSSpecialty
Select one or more GBS specialty related to the scope of work of this project.
GBS Specialty
1 Choose an item.
2 Choose an item.
3 Choose an item.
Contract Info Title: FRIO LIMPIO Number:
Award Date: July 10,2012 Contract Value (US$): 446
Contractual Completion Date: December 2012 Actual Completion Date: December 2012
Planned % Complete: X Actual % Complete:X
Value of Supplied Material (US$): X Value of Subcontracts (US$): X
Client's
CompanyInfo
Client Name: SOLAVANTI, S.L.
Client Address: Spain, AragonRepresentative Name/Tel & Email:
ContractType
☒ Primary☐ Subcontractor ☒ Sole Contractor☐ Consortium☐ JV, with share %:
☒ LSTK☐ LSPB☐ Unit Rate☐ Construction Management☐ Others, specify: _______________________
Designer LSTK Detailed Design was done:☒ In-House Design Office☐ Outsourced☐ Not LSTK
Scope ofWork
Project’s Location: Spain, Aragon Country: Spain City: Aragon
Project’s Brief Description (related to your scope of work only) :
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 28/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 28 of 40
Sub-contracts
If applicable, list your main four (4) subcontracts under this project:
Scope of Work Value US$ Subcontractor Name
1
2
3
4
HumanResources
Provide human resources details for this project:
Position Number of Resources
1 Management & Administration
2 Project Cost & Scheduling
3 Project Managers
4 Senior Design Engineers
5 Design Engineers
6 Project Engineers
7 Procurement Personnel
8 Quality Department Personnel
9 Construction Supervisors
10 Construction Skilled Labor
11 Construction Unskilled Labor
Total
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 29/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 29 of 40
Complete the following form for each ongoing project or projects completed in the last ten (10) years. Duplicate the below formfor each project. Provide copies of completion certificates, performance evaluation reports (signed/stamped by client) and copiesof the contract showing signature pages, contract value, type, scope of work and contract duration. A project will not beconsidered as part of your experience if above back-up documents are not provided.
GBSSpecialty
Select one or more GBS specialty related to the scope of work of this project.
GBS Specialty
1 Choose an item.
2 Choose an item.
3 Choose an item.
Contract Info Title: PLANTA FOTOVOLTAICA CURBANS Number:
Award Date: Feb, 5 ,2010 Contract Value (US$): 32,952,560
Contractual Completion Date: September 2011 Actual Completion Date: September 2011
Planned % Complete: X Actual % Complete:X
Value of Supplied Material (US$): X Value of Subcontracts (US$): X
Client's
CompanyInfo
Client Name: GDF
Client Address: France, Hautes AlpesRepresentative Name/Tel & Email:
ContractType
☒ Primary☐ Subcontractor ☒ Sole Contractor☐ Consortium☐ JV, with share %:
☒ LSTK☐ LSPB☐ Unit Rate☐ Construction Management☐ Others, specify: _______________________
Designer LSTK Detailed Design was done:☒ In-House Design Office☐ Outsourced☐ Not LSTK
Scope ofWork
Project’s Location: France, Hautes Alpes Country: France City: Hautes Alpes
Project’s Brief Description (related to your scope of work only) :
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 30/40
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 31/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 31 of 40
Complete the following form for each ongoing project or projects completed in the last ten (10) years. Duplicate the below formfor each project. Provide copies of completion certificates, performance evaluation reports (signed/stamped by client) and copiesof the contract showing signature pages, contract value, type, scope of work and contract duration. A project will not beconsidered as part of your experience if above back-up documents are not provided.
GBSSpecialty
Select one or more GBS specialty related to the scope of work of this project.
GBS Specialty
1 Choose an item.
2 Choose an item.
3 Choose an item.
Contract Info Title: BATILLY FOTOVOLTAIQUE Number:
Award Date: June 6, 2011 Contract Value (US$): 10,372,000
Contractual Completion Date: December 2011 Actual Completion Date: December 2011
Planned % Complete: X Actual % Complete:X
Value of Supplied Material (US$): X Value of Subcontracts (US$): X
Client's
CompanyInfo
Client Name: GESTAMP SOLAR
Client Address: France, CreuseRepresentative Name/Tel & Email:
ContractType
☒ Primary☐ Subcontractor ☒ Sole Contractor☐ Consortium☐ JV, with share %:
☒ LSTK☐ LSPB☐ Unit Rate☐ Construction Management☐ Others, specify: _______________________
Designer LSTK Detailed Design was done:☒ In-House Design Office☐ Outsourced☐ Not LSTK
Scope ofWork
Project’s Location: France, Creuse Country: France City: Creuse
Project’s Brief Description (related to your scope of work only) :
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 32/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 32 of 40
Sub-contracts
If applicable, list your main four (4) subcontracts under this project:
Scope of Work Value US$ Subcontractor Name
1
2
3
4
HumanResources
Provide human resources details for this project:
Position Number of Resources
1 Management & Administration
2 Project Cost & Scheduling
3 Project Managers
4 Senior Design Engineers
5 Design Engineers
6 Project Engineers
7 Procurement Personnel
8 Quality Department Personnel
9 Construction Supervisors
10 Construction Skilled Labor
11 Construction Unskilled Labor
Total
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 33/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 33 of 40
Complete the following form for each ongoing project or projects completed in the last ten (10) years. Duplicate the below formfor each project. Provide copies of completion certificates, performance evaluation reports (signed/stamped by client) and copiesof the contract showing signature pages, contract value, type, scope of work and contract duration. A project will not beconsidered as part of your experience if above back-up documents are not provided.
GBSSpecialty
Select one or more GBS specialty related to the scope of work of this project.
GBS Specialty
1 Choose an item.
2 Choose an item.
3 Choose an item.
Contract Info Title: PV AMERICANA Number:
Award Date: June 6, 2011 Contract Value (US$): 20,000,000
Contractual Completion Date: December 2012 Actual Completion Date: December 2012
Planned % Complete: X Actual % Complete:X
Value of Supplied Material (US$): X Value of Subcontracts (US$): X
Client's
CompanyInfo
Client Name: GESTAMP SOLAR
Client Address: Peru, TacnaRepresentative Name/Tel & Email:
ContractType
☒ Primary☐ Subcontractor ☒ Sole Contractor☐ Consortium☐ JV, with share %:
☒ LSTK☐ LSPB☐ Unit Rate☐ Construction Management☐ Others, specify: _______________________
Designer LSTK Detailed Design was done:☒ In-House Design Office☐ Outsourced☐ Not LSTK
Scope ofWork
Project’s Location: Peru, Tacna Country: Peru City: Tacna
Project’s Brief Description (related to your scope of work only) :
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 34/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 34 of 40
Sub-contracts
If applicable, list your main four (4) subcontracts under this project:
Scope of Work Value US$ Subcontractor Name
1
2
3
4
HumanResources
Provide human resources details for this project:
Position Number of Resources
1 Management & Administration
2 Project Cost & Scheduling
3 Project Managers
4 Senior Design Engineers
5 Design Engineers
6 Project Engineers
7 Procurement Personnel
8 Quality Department Personnel
9 Construction Supervisors
10 Construction Skilled Labor
11 Construction Unskilled Labor
Total
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 35/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 35 of 40
EXHIBIT G: HUMAN RESOURCES
1.1 Project Management Key Personnel
Provide information of company’s key project management personnel in the table below and provide copies ofeducational academic degrees and resumes for each management personnel:
Name Job Title Years withCompany
Total ExperienceYears inDiscipline
Education: Graduate,Undergrad., Diploma
1 Jose Luis Celorrio General Manager 12 24
2 Jose Igancio del BarrioProject ControlsManager
3 Construction Manager
4 Engineering Manager
5 Alona Ibisate QA/QC Manager
6 Mrs. Raquel Bueno Safety Manager
7 Jose Ruiz Sanjoaquin Procurement Manager
8 Pre-commissioning Manager
1.2 Project Construction Workforce
In the tables below, provide numbers of resources In-Kingdom (IK) and/or Out-of-Kingdom (OOK). Provide scannedcopies of IK Labor Office approved block visas and General Organization for Social Insurance (GOSI) Certificates,which is mandatory for your IK resources.
1.2.1 Provide numbers of your company project management personnel in the table below.
No TitleCurrent Number of Resources Number of unused
block visas for work IKIK OOK
1 Project Engineers
2 Cost Engineers3 Estimators
4 Schedules /Planners
Sub Total
1.2.2 Provide numbers of your company engineering and construction field personnel.
# TitleCurrent Number of Resources Number of unused
block visas for work IKIK OOK
1 Civil Engineers
2 Mechanical Engineers
3 Electrical Engineers
4 Process & Control Engineers
5 Instrumentation & Control Engineers
6 Communications Engineers
7 QA/QC Engineer
8 Control System Engineers
9 Superintendent (Piping/Mech.)
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 36/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 36 of 40
# TitleCurrent Number of Resources Number of unused
block visas for work IKIK OOK
10 Superintendent (Civil)
11 Superintendent (Elect. /Instr.)
12 Foremen/Supr. (Piping/Mech.)
13 Foremen/Supr. (Civil)14 Foremen/Supr. (Elect/Instrument)
15 Safety Engineers
16 Others (Specify)
Sub Total
1.2.3 In the table below, provide numbers of skilled/ craft personnel resources.
# Skilled Labor SpecialtyCurrent Number of Resources Number of unused
block visas for work IKIK OOK
1 Masons
2 Carpenters
3 Surveyors
4 Iron Workers
5 Pipe Fitters
6 Mech. technicians
7 Elect. Technicians
8 Steel Fixers
9 Painters
10 Millwrights
11 Painters
12 Scaffolders13 Sand Blasters
14 Structural Steel Fabricator
15 Welders Structural
16 Welders Piping
17 Pipe Fabricators
18 Riggers
19 Electricians (LV/HV)
20 Instr. & Control Technicians
21 Certified Cable Splicers
22 NDT Technicians23 Cathodic Protection Technicians
24 Side Booms Operators
25 Rock Breakers
26 Light Crane Operators
27 Heavy Crane Operators
28 Bulldozer Operator
29 Grader Operators
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 37/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 37 of 40
# Skilled Labor SpecialtyCurrent Number of Resources Number of unused
block visas for work IKIK OOK
30 Backhoe/Excavator Operator
31 Truck Drivers
32 Others (Specify)
Subtotal
1.2.4 In the table below, provide numbers of unskilled/ labors personnel resources.
# Unskilled LaborsCurrent Number of Resources Number of unused
block visas for work IKIK OOK
1 Laborers
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 38/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 38 of 40
EXHIBIT H: EQUIPMENT
Construction Equipment
Equipment Types: in the table below, provide information about company currently owned and leased equipment relevant to thescope of work of the GBS you are requested to be prequalified for. Equipment types may be lifting such as cranes, tower cranesetc., transportation equipment such as trucks, civil work equipment such as excavators and leveling etc.
Equipment Type Current Number of Units
1 Hammer Drill 1
2 Hammer Drill 1
3 Hammer Milwaukee 2
4 Cordless Hammer Drill Hilti TE6A 15
5 Rotary Hammer 6
6 Fence 60
7 Truck Iveco ML120E18Bas 1
8 Crane Palfinger PK 15002 SE 1
9 Hydraulic Pressure Pipe Bender Vas CH4 MOD 8 110 Generator Set 2
11 Angle Grinder Bosch 230 1900 1
12 Generator G-5000 1
13 Floor Saw Lux-13 1
14 Rotary Hammer Hilti TE 6S 1
15 Rotary Hammer Hilti TE 6C 1
16 Magnetic Base Drill 1
17 Generator M 2,25 Gasoline 1
18 Jointing Kit 1
19 Cordless Drill 12V Hilti or Battery 1
20 Generator M 25 Gasoline 1
21 Kit Hilti 1
22 Ditect Fastening System Tools 1
23 Cable Stripper 1
24 Hydraulic Pump 1
25 Cable Stripper 1
26 Hydraulic Pump 1
27 Coil Support 1
28 Coil Support 1
29 Reel Stand 1
30 RDSI Tester Analyzer 1
31 TV Cable Inc. Tester Analyzer 1
32 Tester for Cable Quality 133 Professional Kit Fujikura 1
34 Tachymeter TC1105 1
35 Set HP-Calan 3010R 1
36 Set Calan 3010R 1
37 Site Master 25 MHZ – 4GHZ 1
38 Laser Rot PR16 1
39 Plotter HP Desingjet 105 1
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 39/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Saudi Aramco: Public
Page 39 of 40
Equipment Type Current Number of Units
40 Digitizing Tablet 1
41 Digital Camera Mavicva F 2
42 Digital Camera Mavicva M 1
43 Digital Camera Sony Mavi 244 Plotter HP Desingjet 105 1
45 Plotter Canon BJ W-3000 1
46 Plotter IPF500 1
47 FO Slices Machine 1
48 Reflectometer 1
49 Wiring Certification 1
50 Sound Level Meter 1
51 Multi Gas Detector 1
52 Laser Detector 1
53 ADSL-ISDN Meter 1
54 ADSL Meter. Module ISDN 1
55 ADSL Meter. Module ADSL 1
56 Field Meter mediamax 1
57 Sweep Analyzer CATV Agilent 1
58 Impedance Meter 1
59 Cable Tester 1
60 Cable Explorer TDR 1
61 Field Meter cablrlab 1
62 Sweep Analyzer 1
63 Measuring Forward and Contact Systems Meter 1
64 ELCB Tester 1
65 Earth Meter 1
66 Thermal Graphic Camera 167 Torque Wrench 1
68 Torque Wrench 1
69 Clamp Meter 1
70 Clamp Meter 1
71 Process Meter Multifunction 1
72 Process Meter Multifunction 1
73 Insulation Tester 1
74 Power Supply 1
75 Process Meter Multifunction 1
76 Insulation Tester High Voltage Mkoban 0775823 (MG-146-2) 9053087 1
77 Insulation Tester Koban KRA 2550 0775032 (9676789) 1
78 Process Multimeter 11950345 179 Process Multimeter 12250490 1
80 Process Multimeter 10780329 1
81 Process Multimeter 12220664 1
82 Process Multimeter 13130271 1
83 Process Multimeter 98540130 1
84 High Voltage Insulation Tester Koban KRA 2804 (8951976) 1
85 Insulation Tester Koban KRA 2550 9053087 1
7/23/2019 Project Management PQQ Part B - Electrical Systems Group
http://slidepdf.com/reader/full/project-management-pqq-part-b-electrical-systems-group 40/40
Saudi Aramco Prequalification Questionnaire – General Bid Slates (GBS) Part - B
Equipment Type Current Number of Units
86 Process Multimeter 12220664 1
87 Process Multimeter Fluke. 289 15460280 1
88 Thermal Graphical Camera 1
89 Thickness Meter 190 Measuring Forward and Contact Systems Meter 1
91 Hart Emerson 475 Communicator 1
92 Multi Gas Detector. Drugger X-AM 2000 (8318911) 1
93 Hexafasic Tester 1
94 Megaohmeter 1
95 Network Analyzer 1
96 Dynamometer 1
97 Total Station 1
98 Digital Tellurometer 1
99 Portable Turbidity Meter 1
100 Turbidity Meter 1
Equipment Maintenance: Describe or attach your equipment maintenance/fleet management program and yourcompany’s maintenance facilities, including the size of each facility and number of maintenance technicians.