Project Management Oversight Prepared by the Department of Finance, Innovation & Technology June 2018

Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

Project Management Oversight

Prepared by the Department of Finance, Innovation & Technology

June 2018

Page 2: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

 

Executive Summary   This  semi‐annual  Report  on  Project Management  Oversight  details  Service  Board  efforts  in implementing  their  capital  programs.  Included  are  details  on  all  state‐funded  projects, regardless  of  budget,  and  all  systemwide  projects  with  budgets  of  $10  million  or  more, regardless  of  funding  source.  Information  in  this  report was  collected  by  direct  interviews, project  meetings,  and  documented  submissions  from  Service  Board  project  management teams.  The State of Good Repair backlog for the region currently stands at $19.4 billion, and the 10‐year capital need for normal reinvestment is $18.3 billion, which results in total 10‐year capital need of $37.7 billion. The 60 projects detailed in this report together represent $3,861,547,183 worth  of  construction, maintenance,  and  procurement. Many  of  these  projects will  address outstanding capital needs, while others are directed to compliance with federal requirements or enhancing customer experience, safety, and security.  The majority of state funded projects are within budget, one project  is under budget.   80% of the state funded projects are on schedule.  Regarding change orders, some of the added budget came  from  decisions  by  the  Service Boards  to  add  value  to  projects  or  comply with  federal requirements.  Other  change  orders  were mostly  for  unforeseen  conditions,  and  a minimal amount was due to errors and omissions.  There were also change orders that provided credit for value engineering and for unused allowance and deleted work.  Although the progress being made on these projects  is significant, current capital funding will not  support  much  needed  renewal  of  the  region’s  aging  transit  infrastructure.  Deferring infrastructure maintenance  and  replacement  has  negative  impacts  on  the  quality  of  service provided, including deteriorating service reliability. RTA, in accordance with the Strategic Plan, is  committed  to  seeking  stable,  long‐term  capital  funding  solutions  critical  to  renewing  and maintaining the region’s transit system. RTA and the Service Boards must collectively work to educate the public on the region’s transit needs and advocate for funding.  RTA  recognizes  the  commitment,  collaboration,  cooperation, and  level of effort each Service Board  provided  for  the  Report  on  Project Management  Oversight  to  be  a  success.  RTA  is appreciative  and pleased  to note  the exemplary  and ongoing  commitment of  transit  agency personnel  during  this  process.  RTA will  continue  to work with  the  CTA, Metra,  and  Pace  to advocate  for more  capital  funding  at  both  the  state  and  federal  level  to  ensure  our  transit system continues to prioritize and work towards a State of Good Repair. 

Page 3: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

 

Table of Contents    

Section I – State‐Funded Projects  .........................................................................1 Project List  ................................................................................................2 CTA  ............................................................................................................3 Metra  .......................................................................................................12 Pace  .........................................................................................................21 Budget Performance  ...............................................................................26 Schedule Performance  ............................................................................27 Change Orders  ........................................................................................28  

Section II – Systemwide Projects over $10,000,000  ...........................................30 Systemwide  .............................................................................................31 CTA  ..........................................................................................................38 Metra  ......................................................................................................50 Pace  .........................................................................................................68 

Page 4: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

 

Section I State‐Funded Projects 

1

Page 5: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Systemwide  STATE‐FUNDED PROJECTS  SERVICE BOARD  PROJECT TITLE  BUDGET

CTA  Wilson Transfer Station  $169,959,391 

CTA  95th Street Terminal Improvements  $90,000,000 

CTA  Perform Rail Car Overhaul (3200 Series)  $53,182,149 

CTA  Jefferson Park & Belmont Intermodal Facility Renovations  $15,236,957 

CTA  North Red Line Stations – Sheridan  $11,300,000 

CTA  Dearborn Subway Station Improvements – Grand, Chicago, and Division 

$11,028,240 

CTA  98th Shop – Replace Hoist and Spin Jacks  $5,323,426 

CTA  Rail Shop Roofs and Washer Replacements  $3,073,202 

Metra  Positive Train Control – System Integrator  $85,000,000 

Metra  Rail Car & Locomotive Rehab  $56,428,075 

Metra  Union Pacific West Line Expansion  $44,500,000 

Metra  Deering Bridge  $19,800,000 

Metra  Union Pacific North Line Bridges and Ravenswood Station  $12,668,903 

Metra  Healy Station – Milwaukee District North Line  $7,709,200 

Metra  Hazel Crest Station – Metra Electric District  $4,868,483 

Pace  Purchase 40’ Compressed Natural Gas Buses  $49,000,000 

Pace  Purchase 40’ Fixed Route Buses  $7,891,804 

Pace  Purchase Approximately 85 Paratransit Vehicles  $7,290,500 

Pace  Construct Toyota Park Transportation Center  $2,000,000 

Pace  Bus Stop Improvements – Joliet Multi‐Modal Transportation Center  $1,709,500 

  Note: Amounts shown represent only the IDOT/RTA‐funded portions of overall project budgets. 

2

Page 6: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of April 2018. 

Wilson Transfer Station (Final)  

Description: The Wilson Street Station and elevated track structure from Montrose Avenue to Leland Avenue was replaced with  a  four  track  station  and  platforms  between  the express  and  local  tracks.  The  elevated  track  structure between  Sunnyside  Avenue  on  the  south  to  Leland Avenue on  the north was replaced with steel columns and  concrete  track  bed.  The  elevated  track  structure over Broadway  Street  is  a  full  span, which eliminated piers  in  the  street  right‐of‐way.  The  architectural facades of historic buildings were preserved. 

Status:   The station is in operation and the project is in closeout. A contractor submitted closeout plan has been  accepted  and  is  being  implemented.  Project  activities  have  been  to  perform  punch  list, change order work, prepare and submit record documents.  This is the final report on this project.   

Budget:   The project was completed under budget.  Cost savings from value engineering were in the amount of  $1.18M.  CTA  also  saved  $1.18M  by  purchasing  revenue  equipment  for  the  station  directly instead of through the general contractor.   

  Budget  Obligated*  Expended*  Expended % 

State‐Funded Budget  $169,959,391  $169,831,548 $168,577,236  99% 

Overall Project Total  $206,070,539 $202,677,771 $190,458,787  92% 

Schedule:   The project was completed on schedule.  

 

Milestone  Baseline Schedule  Actual (A) / Forecast 

Advertise for Proposals  March 2014  March 2014 A 

Environmental Clearance  April 2013  June 2014 A 

Notice to Proceed  July 2014  July 2014 A 

Start Three‐Track Operations  March 2015  March 2015 A 

End Three‐Track Operations  March 2017  March 2017A 

Substantial Completion  January 2018  January 2018 A 

Highlights: The $206 million dollar project is one of the largest elevated track projects performed by CTA: 

Covered platforms have been provided on all tracks. 

Commuters have access between Purple Line express trains and Red Line local trains.  

Station access is being provided to persons with disabilities in accordance with ADA. 

Station entrances are on both sides of Wilson Avenue have as well as Sunnyside Avenue 

3

Page 7: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of April 2018. 

95th Street Terminal Improvements  

Description: This  project  will  expand  and  greatly improve  the  95th/Dan  Ryan  Red  Line station  as well  as  its  bus  terminal with  a new  stationhouse  comprising  north  and south bus terminal facilities for the 14 CTA and  5  Pace  bus  routes  that  serve  the station,  in addition to  improved pedestrian access.  This  station  serves over  1,000 CTA and Pace buses daily. 

Status:   The main terminal design‐build contract has continued design, bid and construction activities.  For design,  the  north  bus  bridge  package  is  undergoing  a  quality  review  by  the  designer  prior  to submission  and  the  pedestrian  bridge  package  is  being  advanced.  Bidding  and  award  of construction work orders is on‐going.  For the south terminal, the space is in operation and punch list work is being performed.  For the north terminal, demolition activities are being performed. 

Budget:   The project is on budget.   

  Budget Obligated * Expended *  Expended %State‐Funded Budget  $90,000,000  $89,954,566 $88,864,562  99%Overall Project Total  $280,000,000 $277,682,134 $195,047,076  70%

Schedule:   Project  schedule  updates  continue  to  show  construction  of  the  south  terminal  to  be  behind schedule and project completion on schedule.  

 

Milestone  Baseline Schedule  Actual (A) / Forecast 

Prime Contract Award  March 2015  December 2015 A 

Complete Construction Phase 1  January 2018  April 2018 A 

Substantial Completion  December 2018  December 2018 

Highlights: The terminal design features improvements in safety and amenities for CTA and Pace customers: 

Pedestrian overpass bridge between terminals to avoid the need for street level crossings. 

Wider bus lanes and increased spacing between bus bays for upgraded traffic flow.  

Expanded platforms and wider sidewalks to ease passenger congestion. 

Bright, airy and glass enclosed station for clear sightlines in a comfortable space. 

Additional escalators, elevators and pay area space for reduced wait times. 

Sound panels at platform level to provide noise mitigation. 

4

Page 8: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of April 2018. 

Rail Car Overhaul and Mid‐Life Rehabilitation  

Description: A  programmed  rail  car  overhaul  program  will provide  for  renewal  of  truck,  propulsion,  and other  subsystem equipment on  rail  cars  in  the 3200‐Series rail car fleets to maintain a state of good  repair.  CTA  is  also  retrofitting  the  3200 Series  cars  with  new  air  conditioning  units, auxiliary  power  supply,  destination  signs,  LED lighting, and security cameras. 

Status:   The  3200  Series  project  covers  257  cars.    The component  rebuild,  car  overhaul  work,  and equipment  installation  is  being  done  by  CTA Skokie  Shop  staff.    As  for  cars  that  have undergone  the  overhaul  and  returned  to revenue service, 234 of the 257 were completed as of May 22, 2018.  There has been an increase in the scope of repairs based on car condition observed during the program.   CTA has begun to bring some cars back that have some work remaining.   80 cars still need to come back to have the air‐conditioning replaced and other work completed. 

Budget:   The project is on budget. 

  Budget  Obligated*  Expended*  Expended % 

State‐Funded Budget  $53,182,149  $53,165,835 $48,122,693  90% 

Overall Project Total  $185,000,000 $168,646,369 $170,611,048  92%  

Schedule:   The Yellow Line closure disrupted and delayed the project about 12 months. To mitigate this delay and maintain continuous employment of the staff assigned to this project, CTA assigned some staff to work in the maintenance shops to get an early start on some modifications.   Reliability  issues  with  some  subsystems  have  impacted  production  but  solutions  have  been developed and production has returned to the expected rate of 8 cars per month.   However, the effect of delays has caused the completion date, based on this production rate, to be delayed. 

 

Milestone  Baseline Schedule  Actual (A) / Forecast 

First 3200‐Series Kits Received    March 2015  March 2015 A 

Complete 257 3200‐Series Cars  July 2017  January 2019 

 

5

Page 9: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of April 2018. 

Rail Car Overhaul and Mid‐Life Rehabilitation (continued)  

Highlights: 

In addition to the purchase of new rail cars, CTA has embarked on an aggressive rail car overhaul program to restore these cars to a state of good repair.  Performing overhauls as scheduled reduces unscheduled  maintenance,  improves  reliability,  and  preserves  comfort  and  ride  quality. Many underfloor components will not require overhaul for another 12 to 15 years.  A Quality Assurance process  is  in place both at the Contractor and at CTA for this project.   CTA’s  innovative use of an outside contractor to provide kitted material has reduced the workload on CTA Procurement and Materials Management and has avoided mixing program material with CTA spare parts.  All material was procured  from CTA pre‐approved vendors.   For  the 3200 Series project, CTA  is modernizing subsystems to increase reliability and security including:  

Air Conditioning System o New Air Conditioning Unit o New AC Controller 

Propulsion System o Rebuilt Cam Control Group o New Resistor Bank 

Trucks o New Wheels o Rebuilt Motors, new Armatures 

Interiors  o New LED Lighting o End Door Floor Panels o New Ribbed Flooring 

Doors o New Door Motors o New Door Hangers o New Thresholds 

Cab o Rebuilt Master Controller o Rebuilt Hydraulic Pressure Control 

Auxiliary Power Supply 

Systems  o Security Cameras o Programmable Message Signs  o LED Side and End Signs o Digital Route Number Signs 

CTA has found that they needed to increase the scope of the floor renewal and is renewing most of the ribbed flooring on the car in addition to floor panels near the end doors.   

CTA needed to rebid the replacement air‐conditioning units and controls.   Notice to proceed was given in September 2015.  Prototype units were received in September 2016 and the first production units arrived in November 2016.  The delay in receiving new air‐conditioning units has necessitated returning 100 cars to Skokie Shop to complete the installation of that system and its controls. 

An issue discovered recently with deterioration of some undercar wiring has caused renewal of that wiring to be added to the scope of work and a modification to be made to the Auxiliary Power Supply. 

 

6

Page 10: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

 

 

*Obligated and Expended amounts as of April 2018. 

Belmont & Jefferson Park Station Improvements  

Description: The  proposed  scope  of  work  includes upgrades  on  Blue  Line  Stations.    Belmont Station improvements include a new station canopy,  site  improvements,  enlarged  bus prepaid  boarding  area,  renovated  station electrical  and  finishes  and  refurbished platform  furniture.  Jefferson  Station improvements  include  reconstructed  bus turnaround  pavement  and  canopies, renovated  entrance  and  customer  waiting areas, enhanced lighting, improved signage, new public art, updated communication elements, lead abatement and repaired roofing, platform edge & curtain wall. 

Status:   This is a design‐build project that is in the design phase.  There are 3 design packages:  the Belmont canopy,  Jefferson Station  improvements and Belmont Station  improvements.     The  final Belmont canopy design is complete.  The final station improvement designs were submitted.  Coordination with  the City and State departments, utilities and Alderman’s office and scoping, pricing,  letting, bidding and awarding of construction trade work packages is on‐going.  

Budget:   The project is on budget.   

  Budget  Obligated*  Expended*  Expended % 

State‐Funded Budget  $15,236,957  $15,236,957 $1,804,359  12% 

Overall Project Total  $42,226,054 $27,970,447 $3,195,556  8% 

Schedule:   The project is on schedule.   

 

Milestone  Baseline Schedule  Actual (A) / Forecast 

Design‐Build Notice to Proceed  October 2017  October 2017 A 

Design Complete  April 2018  April 2018 A 

Complete Station Work  December 2018  December 2018 

Substantial Completion  July 2019  July 2019 

Highlights: This project  is part of a  larger  capital  improvement program known as  “Your New Blue”  for  the O’Hare  Blue  Line, which  includes  additional  track  and  station  renewal  projects.  The  estimated overall budget for the entire program  is $492 million. Jefferson Park  is a multi‐modal station that provides a vital link between CTA rail, CTA bus, Metra, and Pace. 

7

Page 11: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of April 2018. 

North Red Line Stations – Sheridan (Final)  

Description: Improvements will be made to Sheridan Station and adjacent  track  structure  to  provide  safe  and  dry conditions  and  aesthetic  improvements.  Various components  will  be  renewed,  including  lighting, roofs and canopies, platform decking, painting, and accessibility features. 

Status:   CTA Structure Maintenance forces are finishing up the  structure  renewal work.    This work  included replacing 162 track and platform stringers, 11 cross girders,  18  platform  canopy  channels,  4 platform structural  sections,  and  other  various  secondary structural components.  Due to changes in the availability of state funding, only the structure renewal work was completed as part of this project.  Improvements to the station have been deferred.  This is the final report on this project. 

Budget:   The project is on budget.  Expenditures are for CTA force account work.  

  Budget  Obligated*  Expended*  Expended % 

Project Total  $11,300,000  $11,941,068 $11,221,909  99% 

Schedule: The  project  is  on  schedule  for  the  structure  renewal work. Milestones  have  been modified  to coordinate with the Red and Purple Modernization and Wilson Transfer Station. 

 

Milestone  Baseline Schedule  Actual (A) / Forecast 

Started Structure Renewal   July 2015  July 2015 A 

Structure Renewal Completion  December 2017  May 2018 A 

Highlights: Sheridan is one of the oldest stations in the CTA system and is exhibiting signs of deterioration, having reached the end of its useful life. The station structure was built in the 1920s. Historic preservation measures are being taken to maintain the stationhouse façade.  

8

Page 12: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of April 2018. 

Dearborn Subway Station Improvements – Grand, Chicago, and Division 

 

Description: The proposed work  includes  improvements at  the street, mezzanine, and platform levels. At the street level, new entry canopies will be  installed at each stair opening with repairs to the stairs, new glazed tile walls, new lighting and repainted ceilings. At the mezzanine  level,  improvements  include  new finishes,  lighting,  and  exit  roto‐gates.  At  the platform level, improvements include new finishes, lighting, and furniture. Additional scope may include repairs  to  the  elevators  and  stairs  between  the mezzanine and platform levels. 

Status:   The Project Master Plan was finalized in October 2016.  A bid package for a design‐build contractor was prepared and advertised on February 5, 2018.   Bids were  received on May 1, 2018 and are currently being evaluated.   

Budget:   The project is on budget.  

  Budget  Obligated*  Expended*  Expended % 

State‐Funded Budget  $11,028,240  $961,099 $324,508  3% 

Overall Project Total  $39,000,000 $1,563,705 $430,769  1% 

Schedule:   The scheduling for this project needs to be coordinated with other “Your New Blue” projects for track access time.  Milestone dates will be developed once the contract is awarded.  CTA plans to take this contract to their July Board. 

 

Highlights: The Dearborn Subway opened in 1951, and these stations are in need of upgrades and improvements to improve operations and customer experience. This project is part of a larger capital improvement program known as “Your New Blue”  for  the O’Hare Blue Line, which  includes additional projects involving track and station renewal. The estimated overall budget  for  the entire program  is $492 million. 

9

Page 13: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

* Obligated and Expended amounts as of April 2018. 

98th Shop – Replace Hoist and Spin Jacks (Final)  

Description: CTA  replaced  the  existing  carriage  hoists,  spin  posts, body hoists, turntables, and associated controls on two tracks, each of which can accommodate up to two cars at  a  time.  This  equipment  is  used  to  elevate  and support  rail  cars  during  standard  and  special maintenance procedures. 

Status:   Equipment was delivered,  installed and commissioned.  The  shop  was  shut  down  for  90  days  to  perform construction  activities:  demolition,  reconstruction  and equipment installation.  Substantial completion was achieved in July 2017.  All punchlist items have been  completed.    Submittals  and  Operations  and  Maintenance  Manuals  as  well  as  training materials  have  been  received.    The  project  is  being  closed  out.    This  is  the  final  report  on  this project.  

Budget:   The project is on budget.   

  Budget  Obligated*  Expended*  Expended % 

State‐Funded Budget  $5,323,426  $5,323,426 $5,323,426  100% 

Overall Project Total  $8,535,000 $8,346,233 $7,510,637  88% 

Schedule:   The project was completed on schedule.   

 

Milestone  Baseline Schedule  Actual (A) / Forecast 

Work Order Award  April 2015  April 2015 A 

Construction Start  April 2016  April 2016 A 

Substantial Completion  July 2017  July 2017 A 

Highlights: The  equipment  at  98th  Shop  was  installed  when  the  shop  was  opened  in  1967,  and  was considerably past  its useful  life,  and was difficult  for CTA  to maintain  and  repair. Replacing  the equipment not only improved reliability, but also provided flexibility, as both tracks used to service rail cars have the same equipment after the project was completed. 

10

Page 14: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

 *Obligated and Expended amounts as of April 2018. 

Rail Shop Roofs and Washer Replacements Design  

Description: This  project  will  provide  for  improvements  at  the Green Line Harlem Rail Shop and Blue Line Des Plaines Rail  Shop.    The  roofing  component  replaced  existing roofs at Harlem and Des Plaines Shops.   A design  for the new  exterior  rail  car washer  at  the Harlem  Shop will be completed as part of this project.   Funding for construction of the washer still needs to be secured. 

Status:   Construction work on  rail  shop  roofs  at both Harlem and  Des  Plaines  Shops  are  complete.  Design  is  on‐going  for  the  rail  car washer  replacement  at Harlem shop.  Track and yard design documents are being advanced from 30% to 60% complete.    

Budget:   The project is on budget.    

  Budget Obligated* Expended*  Expended %State‐Funded Budget  $3,073,202 $3,073,202 $1,963,858  64% 

Overall Project Total  $4,966,103 $4,966,103 $2,900,499  58%

Schedule:   The project  is on schedule and has phases for the 2 shop elements being replaced:   roofs and rail washers design. 

 

Milestone  Baseline Schedule Actual (A) / ForecastRoof Replacement Start  June 2015 June 2015 A Roof Replacement Complete June 2016 June 2016 A Rail Washer Design Complete November 2018 November 2018 

Highlights: The existing roofs at the Harlem and Des Plaines Shops were approaching the end of their useful lives,  both  having  been  installed  when  the  rail  shops  were  first  opened.  Harlem  Shop  was constructed in 1965 and Des Plaines Shop was constructed in 1960.    Rail car washers at Harlem Shop are located exterior to the rail shop and are in poor condition, with much of their structures coated  in rust.   The Harlem Shop  is to be expanded for the addition of a new rail car washer.  The yard will be reconfigured with track that leads into the new, interior rail car washer. 

11

Page 15: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of March 2018. 

Union Pacific West Line Expansion  

Description:  

Status: 

Budget: The  project  is  on  budget.  RTA/IDOT  funding will  provide  for  portions  of  the  project  design, environmental study,  land acquisition, and construction.    Including additional  federal and  local funding, as well as other components of the UP West Line Expansion, the total overall budget is $204,970,663. Metra and the Union Pacific Railroad are sharing these costs.  

  Budget  Obligated*  Expended*  Expended % 

State‐Funded Budget  $44,500,000 $15,102,256 $2,054,934  5%

Overall Project Total  $204,970,663 $152,612,471 $136,842,407  67% 

Schedule: The project is on schedule.  

 Milestone 

Baseline Schedule

Actual (A) /Forecast

  Design Completion  March 2016  March 2016 A 

Eastern Section Construction  Notice to Proceed  November 2017  November 2017 A 

Eastern Section Construction  Substantial Completion September 2019  September 2019 

Highlights: The addition of a  third main  line  track will eliminate key bottlenecks and allow Metra  to add more service,  including more express trains, on the  line. The potential for freight  interference will  also  be  mitigated.    The  expanded  parking  deck  in  Geneva  and  the  new  pedestrian underpass  in Lombard were completed through separate projects as part of the overall Union Pacific West Line program. 

 

This  project  is  part  of  a  public‐private partnership  between  Metra  and  the  Union Pacific  Railroad  to  construct  a  new  third main line  track.  The  segments  funded  under  this project are  located between mileposts 10.0 and 11.8  in  Maywood  and  Melrose  Park  (eastern section) and between mileposts 32.1 and 38.4 in West Chicago and Geneva (western section). 

The project design and environmental work have been completed. Construction cost estimatesfor both segments,  including  land acquisition, have been prepared.  An  Invitation  for bids was issued  for  the  construction of east portion of  the  track  in May 2017.   Notice  to Proceed was issued in November 2017.  The construction project is currently 10% complete.   Metra plans to go out for bid on the western section construction in the fall of 2018. 

12

Page 16: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of March 2018. 

Positive Train Control – System Integrator  

Description: The Positive Train Control (PTC) system is comprised of wayside, onboard, and central equipment, including signals, GPS, computer hardware and software, and various other communications components. The system integrator functions to combine these components through design, testing, and implementation. 

Status: 

Budget: The project is on budget.  The state‐funded budget amount is dedicated to the System Integrator. The overall project  total  includes additional  federal and  local  funding and  is expected  to  reach over $350 million:   

  Budget  Obligated*  Expended*  Expended % 

State‐Funded Budget  $85,000,000 $85,000,000 $41,102,937  48% 

Overall Project Total  $331,200,747 $277,328,360 $198,179,113  60%  

Schedule: The  project  is  on  schedule.  The  federally‐mandated  revised  implementation  plan  allowed  for  a substantial completion  time extension  to December 2018.    It also allows  for a  time extension  to December  2020,  which  is  being  pursued  by Metra.   Metra must  have  one Metra‐owned  line operating with PTC in order to apply for the extension to December 2020.   

Milestone  Baseline Schedule Actual (A) /Forecast Contract Award  August 2015  August 2015 A 

Begin Implementation  August 2015  August 2015 A 

Subdivision Service Initiated  ‐‐‐  July 2018 

Substantial Completion  December 2018  June 2020   

Metra  is  responsible  for  PTC  implementation  on  the  five  corridors  on  which  it  owns/leases. Activities  include  on‐board  vehicle,  wayside,  communications  and  Back  Office  Segment  (BOS) hardware and software design, construction/installation,  testing, Revenue Service Demonstration (RSD) and implementation of the PTC system in compliance with regulatory requirements. 

System  integrator planning  and work  activities  support PTC  implementation.   Development of communication architecture, back office configuration, on board equipment reviews and testing plans &  reports  continue.   Configuration management documents & policies  and  the  revenue service  demonstration  application  are  being  written.   Personnel  are  undergoing  on‐board mechanical, wayside  and  locomotive  engineer  training.    Coordination  is  underway with  other host railroads to plan communications between networks for PTC operations. 

13

Page 17: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of March 2018. 

Positive Train Control – System Integrator (continued)  Metra operates as a  tenant on  three  lines on which PTC will be  implemented by  the other host railroads. Activities include on‐board vehicle hardware and software installations, testing, RSD, and interoperability with the host railroad PTC system in compliance with regulatory requirements.  Finally,  Union  Pacific  Railroad  (UP)  hosts  Metra  rail  operations  on  three  corridors.  PTC implementation  is  the  responsibility  of  the  UP,  in  which  UP  will  host  Metra’s  BOS  for  PTC operations. 

  

Line Name  Owner Party Responsible to Lead 

PTC Installation BNSF Railway (BNSF)  BNSF  BNSF 

Heritage Corridor (HC)  Canadian National  Canadian National 

Milwaukee District North (MD‐N)  Metra  Metra 

Milwaukee District West (MD‐W)  Metra  Metra 

Metra Electric District (MED)  Metra  Metra 

North Central Service (NCS)  Canadian National  Canadian National 

Rock Island District (RID)  Metra  Metra 

SouthWest Service (SWS)  Norfolk Southern  Metra 

Union Pacific North (UP‐N)  Union Pacific  Union Pacific 

Union Pacific Northwest (UP‐NW)  Union Pacific  Union Pacific 

Union Pacific West (UP‐W)  Union Pacific  Union Pacific  

Highlights: There are 4 core elements of the PTC system: 

Prevent train‐to‐train collisions. 

Stop over speed derailments 

Inhibit movement of a train through a switch left in the “wrong” position. 

Block unauthorized incursion into roadway work zones.  

14

Page 18: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of April 2018. 

Rehabilitation of Rolling Stock  

Description: Metra  is  rehabilitating  locomotives  and  bi‐level commuter  rail  cars.  The  locomotives  are  being rebuilt  with  complete  renovation  of  the  diesel engine,  overhaul  of  the  traction  alternator,  head end power alternator and gear box, replacement of the  control  system,  coupler  and  draft  gears, revamping of the trucks,  including traction motors, body  repair  and  modifications,  installation  of secondary engine room door and painting.  The rail cars  are  being  renovated  with  replacement  of couplers, yokes, draft gears, weather stripping, seats, floors, walls, window and door mechanisms, application of tube style diaphragms, renewal of the 480‐volt and control train  lines and repair of heating and lighting systems. 

Status:   Project  locomotive  and  rail  car  units  are  being  rebuilt  as  part  of  an  ongoing  rolling  stock rehabilitation  program.  18  of  the  42  F40PH‐2  locomotives  are  complete.    15  of  the  27 MP36 locomotives are complete.  40 of the 302 Nippon Sharyo rail cars are complete. 18 of the 41 Budd rail cars are complete.  

Budget:   The project is on budget.   

  Budget  Obligated*  Expended*  Expended % 

Locomotives  $30,000,000 $30,000,000 $9,019,174  30%Rail Cars  $26,428,075 $26,428,075 $6,788,620  26%

Overall Project Total  $56,428,075 $56,428,075 $15,807,794  28%

Schedule:   The project is on schedule.  Progress is being measured with production rates.  There were slips in production rates due to material shortages, extended deterioration repair and labor shortages. 

 

Vehicle  Baseline Production Actual Production F40PH‐2 Locomotive  24 weeks 29‐33 weeks MP36 Locomotive  70 days 99 days Nippon  Sharyo  Rail  28 days 28 days Budd Rail Car  100 days 120 days 

Highlights: This project will lower maintenance costs.   For locomotive rehabs, fuel costs will, also, be lowered and  air  pollution  and  the  regional  economy  health will  be  improved.    For  rail  car  rehabs,  the reliability and quality of service for commuters will be improved. 

15

Page 19: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of March 2018. 

Union Pacific North Line Bridges and Ravenswood Station  

Description: The  project  scope  includes  the construction  of  a  new  station  for  the inbound  half  of  the  Ravenswood Station  and  the  replacement  of  11 bridges  on  the  UP  North  Line.  The work  will  emulate  that  of  the outbound  section  of  the  station.  The station will have  longer platforms that are  covered,  lighting,  stairs,  ramps, warming  shelters,  and  landscaping. Work  on  the  bridges  includes replacement  of  existing  stone abutments,  retaining  wall construction, steel spans, and decks. 

Status:   Construction on the Ravenswood station is ongoing. Video surveillance of the sewers is required and the general contractor is proceeding forward with surveillance. A temporary access ramp was constructed to allow the general contractor to proceed with work. Installation of the earth retaining system (ERS) and tie backs are ongoing.  Work will proceed with drilled shafts, abutments, and precast beams.    On  the  bridge  project,  work  began around  the Winnemac  Ave,  Lawrence Ave, and Balmoral Ave bridges related to contractor mobilization,  lead abatement, tuck‐pointing, and demolition of superstructure steel, temporary support columns, and bridge deck clean up at all 11 bridges. This project is 9% complete.      

16

Page 20: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of March 2018. 

Union Pacific North Line Bridges and Ravenswood Station (continued)  

Budget:   The project is on budget.  

  Budget  Obligated*  Expended*  Expended % 

State‐Funded Budget  $12,668,903 12,668,903 $295,861  2%

Overall Project Total  $38,095,843 $38,095,843 $614,557  2%

Schedule:   The Ravenswood station project is behind schedule due to additional time needed by Union Pacific to review and approve the project drawings.  An updated schedule is being developed.  The bridge project is on schedule.  

Milestone  Baseline Schedule  Actual (A) / Forecast 

Design Completion  February 2013  December 2013 A 

Notice of Award – Station  July 2017  July 2017 A 

Notice to Proceed – Station  August 2017  August 2017 A 

Substantial Completion – Station  January 2020  June 2020 

Notice of Award – Bridges  September 2017  September 2017 A 

Notice to Proceed – Bridges  November 2017  November 2017 A 

Substantial Completion – Bridges  March 2020  March 2020  

Highlights: The  existing  bridges  are  over  100  years  old  and  can  no  longer  be  economically  repaired  and maintained.   Thus, they have reached the end of their useful  life.   Construction for the outbound tracks over the same 11 streets was completed  in 2015.   The new bridges will  last for more than 100  years.    At  Ravenswood  station,  the  current  structure  for  the  inbound  side  is  just  a  bare platform.  The  design  and  construction will  deliver  riders  a  new  station  to  provide  convenience, safety, and security.  This station will also be ADA accessible. 

17

Page 21: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of May 2018. 

Reconstruction of Deering Bridge  

Description: The  project  scope  consists  of  the rehabilitation  of  the  Deering  bridge over  the North Branch of  the Chicago River. It also includes the rehabilitation of  the  Webster  Avenue  bridge  just south of the Deering bridge and the fill of  the  bridge  over  the  former Milwaukee Road  just north of Deering bridge. 

Status:   Construction  is  ongoing  with  this project.  Webster  bridge  north  side column  base  repair  work  has  been started  by  the  general  contractor. Backfilling  and  repairing  on  the  east and west  side  is  in  progress.  Additionally,  assembly  of  shoring  for  the  east  side  counterweight repair work  is  in progress. Work  is also being performed on the column  foundations  for Webster bridge.  As of May 2018, the project is 7% complete.  

Budget:   The project is on budget.  

  Budget  Obligated*  Expended*  Expended % 

Project Total  $19,800,000 $18,706,499 $664,338  3%

Schedule:   This  project  is  behind  schedule  due  to  additional  time  needed  by  Union  Pacific  to  review  and approve the project drawings as well as FRA review and approval for signal relocation. 

 

Milestone  Baseline Schedule  Actual (A) / Forecast 

Notice of Award  July 2017  July 2017 A 

Notice to Proceed  August 2017  August 2017 A 

Substantial Completion  July 2018  July 2019 

Highlights: The Deering bridge and Webster bridge represent a major  investment of the Union Pacific North Line.     The rehabilitation of  the bridges  includes replacement of various bridge components with similar  materials  in  an  effort  to  maintain  the  original  design  intent.    Rehabilitating  outdated infrastructure will reduce operating maintenance costs.   

18

Page 22: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of May 2018. 

Healy Station  

Description: This project includes the elimination of the existing at‐grade  railway  crosswalk,  rehabilitation  of  inbound platform access and shelter facilities, construction of a new ADA‐compliant  ramp  to  the  outbound  platform, and  rehabilitation  of  the  outbound  shelter.    In addition, the adjacent bridge over Fullerton Ave will be refurbished. 

Status:   Construction  of  this  project  is  ongoing.    Work completed has been predominantly on  the east  side. The  work  includes  construction  of  the  ramp  wall where concrete was poured and cured.   Conduit  raceways,  light pole  foundations, and Voice‐of‐Metra concrete pads were also  installed along with associated plumbing. Work on  the west side involved demolition of the old brick shelter. 

Budget:   The project is on budget.  

  Budget  Obligated*  Expended*  Expended % 

Project Total  $7,709,200  $7,709,199 $2,340,442  30% 

Schedule:   The  project  is  expected  to  be  completed  on  schedule.    The  construction  activities  are  slightly behind due to weather but the delay is expected to be recovered.   

 

Milestone  Baseline Schedule  Actual (A) / Forecast 

Design Completion  May 2012  March 2013 A 

Substantial Completion  July 2018  July 2018 

Highlights: The project  scope also  includes  relocation of  the outbound  shelter and  stairs which will provide greater  street  visibility.  The  addition  of  the  ramp  on  the  east  side will  allow  both  sides  of  the station to be ADA accessible.   Removal of the at‐grade pedestrian crossing will  increase safety at this station for riders. 

 

19

Page 23: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of May 2018. 

Hazel Crest Station  

Description: The  project  scope  includes  the  rehabilitation  of the station and north and south entrances. It will also  include the addition of an elevator to make the  station  ADA  accessible.  The  project  will remove  the  old  brick  house  and  ground  level garage adjacent to the station. The empty space will be used  to  allow  for  vendor  space,  a  ticket booth, and restrooms at street level. 

Status:   Construction on the station is ongoing. The brick house  on  the  north  entrance  and  garage  have both been demolished. A temporary access ramp was created beyond the north end of the station to  allow  trucks  and  equipment  access  to  track level. The retaining wall for the temporary access ramp was built  to  support  the  ramp. The  south entrance  to  the  station  had  been  sectioned  off with stairs being completely demolished and new stairs framed and poured.  

Budget:   The project is on budget.  

  Budget  Obligated*  Expended*  Expended % 

Project Total  $4,868,483 $4,559,045 $526,893  11%

Schedule:   This  project  is  currently  behind  schedule  due  to  delays  of  initial  kick‐off  and  initial  existing conditions  that  differed  from  drawings.    A  time  extension  request  and  a  revised  schedule  is currently under review by Metra.  

 

Milestone  Baseline Schedule  Actual (A) / Forecast 

Design Completion  February 2013  December 2013 A 

Notice to Proceed  April 2015  August 2017 A 

Substantial Completion  July 2018  October 2018 

Highlights: Design for this station was completed under budget.  The rehabilitation of the station will provide full ADA accessibility to the platforms.      

20

Page 24: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of March 2018. 

Purchase 40’ Compressed Natural Gas Buses  

Description:  Purchase  new  40’  Compressed  Natural  Gas (CNG) buses for fixed route service. The current grant will  provide  for  a minimum  of  91  CNG buses. Fueling for these buses will be provided through  a  retrofit  at  Pace  South  Division  in Markham,  funded  through  other  sources  and completed in March 2016. 

Status:   Pace  awarded  a  production  contract  in February 2015. The first 20 buses have been delivered and received by Pace. The second order of 28 buses has been placed in August 2016 and these buses have been delivered to Pace on April 25, 2017.  The third order of the remaining 43 buses has been delivered between August 4, 2017 and October 13, 2017.  All of those buses have been placed in service.  A Change Order for another 11 buses, funded by 3 FTA grants, have been executed for this contract.     Of those 11 buses, 5 have been delivered in May 2018 and the remaining 6 are expected to be delivered in June 2018.   

Budget:   The project is on budget.  

  Budget  Obligated*  Expended*  Expended % 

Project Total  $49,000,000  $45,422,879 $45,422,779  93% 

Schedule:   Uncertainty of state capital funding has delayed this project as orders have been put on hold after the delivery of the first 20 buses.   The project was re‐started the remaining buses were delivered on schedule.  At this time all 91 buses have been delivered and placed in service.  

 

Milestone  Baseline Schedule  Actual (A) / Forecast 

Contract Award  February 2015  February 2015 A 

CNG Retrofit Complete  June 2015  March 2016 A 

91 Bus Delivery  June 2016  October 2017 A 

Highlights: Pace has initiated service out of the South Division for these buses, and long‐term operational cost savings are expected. Although initially more expensive to procure, CNG buses have been shown to make up the cost difference prior to the end of their useful lives. 

21

Page 25: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of March 2018. 

Purchase 40’ Fixed Route Buses (Final)  

Description: Purchase new 40’ Fixed Route Buses.  This project is part of a larger bus procurement.  State funding was originally allocated  to  fund 13 of  the Fixed Route buses.    Pace  has  reallocated  some  unused  state funds to this grant to purchase an additional 6 buses with state funds. 

Status:   The original 13 Fixed Route Buses funded with state funds have been delivered and placed in service in 2013.  An order for the additional 6 buses has been placed on December 29, 2016.  The additional 6 buses have been delivered and placed in service.  This is the final report on this project. 

Budget:   The project was completed on budget.  

  Budget  Obligated*  Expended*  Expended % 

State‐Funded Budget  $7,891,804  $7,880,428 $7,878,029  100% 

Schedule:   This project was completed on schedule.  

 

Milestone  Baseline Schedule  Actual (A) / Forecast 

Contract Award  January 2012  January 2012 A 

First Bus Delivery  October 2012  October 2012 A 

13 Bus Delivery Complete  February 2013  February 2013 A 

6 Additional Bus Delivery  July 2017  July 2017 A 

Highlights: The new buses will replace the existing 15‐18 year old buses to reduce maintenance and  increase reliability and comfort, providing cleaner, newer equipment to riders. 

22

Page 26: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of March 2018. 

Purchase Approximately 85 Paratransit Vehicles  

Description:  

Status:  

Budget: The project is on budget.  

 

  Budget  Obligated*  Expended*  Expended % 

Project Total  $7,290,500  $5,260,240 $940,633  13%  

Schedule: Uncertainty  of  state  capital  funding  has  delayed  this  project  initially.   Once  the  contract was awarded the vehicles have been delivered on schedule. 

 

Milestone  Baseline Schedule  Actual (A) /Forecast 

First Vehicle Delivery  November 2015  March 2018 A 

Last Vehicle Delivery  May 2016  June 2018  

Highlights: Cost savings from previous paratransit vehicle purchases have been reallocated to this project, allowing  Pace  to  purchase  more  vehicles  under  the  executed  indefinite  delivery/indefinite quantity contract once the funding becomes available.  

 

State funding under this project will provide for the  purchase  of  new  15‐passenger  paratransit vehicles  under  an  indefinite  delivery/indefinite quantity contract, with orders placed as funding becomes available. 

A  contract was  executed with Midwest  Transit for  the  purchase  of  85  paratransit  vehicles  in August 2017.  Of the 85 total, 29 vehicles are at the manufacturer, 37 are at  the dealer, and 19 are  at  the  Pace  South  Holland  Acceptance Facility.    The  final  delivery  is  expected  to  be completed by the end of the 2nd quarter in 2018. 

23

Page 27: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of March 2018. 

Toyota Park Transportation Center  

Description: Construct  new  bus  turnaround  and  passenger facility near Toyota Park in the Village of Bridgeview. 

Status:   Phase 1,  site and underground work,  is  complete. Phase  2, building  and  canopy work, was  re‐bid  in early 2015 after  initially receiving high bids from a previous solicitation. The 2015  low bid was within estimates, Pace had planned to award a contract in late 2015. That award was placed on hold due  to unavailability of  state  capital  funding.   Once  state funding became available, Pace  re‐reviewed  the plans and specifications  that were completed  in 2015 for code compliance, completed a bid package and advertised for bids in February 2018.  Pace Board approved the contract in April 2018 and a Notice to Proceed was issued on May 2, 2018. 

Budget:   The project is on budget.  

  Budget  Obligated*  Expended*  Expended % 

State‐Funded Budget  $2,000,000  $1,241,556 $1,241,556  62% 

Overall Project Total  $2,475,000 $1,241,556 $1,241,556  50% 

Schedule:   The project is on schedule.  It was initially delayed due to additional duration required for multiple re‐designs and a  subsequent  re‐bid process.  It was also delayed due  to  the uncertainty of  state funding.  Once state funding became available the project bid package was prepared and a schedule was developed.  

Milestone  Baseline Schedule  Actual (A) / Forecast 

Advertise for Proposals  February 2018  February 2018 A 

Notice to Proceed  May 2018  May 2018 A 

Substantial Completion  February 2019  February 2019 

  

Highlights: State Bond  funding  is providing  for  the construction phase only. Design  services are  funded and managed by the Village of Bridgeview. 

24

Page 28: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

*Obligated and Expended amounts as of March 2018. 

Bus Stop Improvements – Joliet Gateway Center  

Description: Construct a new bus turnaround facility to serve the nine Pace routes that will connect with the upgraded transportation  center  in  downtown  Joliet  on  the Metra  Rock  Island  District  and  Heritage  Corridor lines, as well as Amtrak routes. 

Status:   The overall Joliet Gateway Terminal project is being managed by the City of Joliet.  The design is complete and  prepared  for  bid  advertisement.  The  bus  stop component is currently on hold. 

Budget:   The project is on budget with zero expenditures.  

  Budget  Obligated*  Expended*  Expended % 

Project Total  $1,709,500  $0 $0  0% 

Schedule:   The overall Joliet Gateway Center is currently on hold. Milestone dates will be established once the project becomes active. 

 

Highlights: The overall Multi‐Modal Transportation Center project is being managed by the City of Joliet. Pace has committed this project budget as pass‐through funding to improve the bus turnaround facility. As the project is bid and constructed, Pace will not be responsible for any additional funding, but will realize cost savings if the work is completed under budget. 

25

Page 29: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Systemwide  STATE FUNDED PROJECTS – BUDGET PERFORMANCE  

STATUS  QUANTITY

On Budget  19

Under Budget  1

Over Budget  0

95%

5%

PERCENTAGE OF TOTAL PROJECTS

On Budget

Under Budget

Over Budget

   

26

Page 30: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Systemwide  STATE FUNDED PROJECTS – SCHEDULE PERFORMANCE  

STATUS  QUANTITY

On Schedule  15

Behind Schedule  5

Ahead of Schedule  0

 

75%

25%

PERCENTAGE OF TOTAL PROJECTS

On Schedule

Behind Schedule

Ahead of Schedule

  Projects Behind Schedule    

SB  PROJECT  REASON 

CTA  Rail Car Overhaul Yellow Line closure, increased scope of repairs, reliability issues with some subcomponents 

Metra  Deering Bridge Additional time needed by Union Pacific to review and approve project drawings and submittals, as well as FRA review time for signal relocation 

Metra  Hazel Crest Station Delay in scheduling kick‐off meetings and initial conditions that differed from drawings 

Metra Union Pacific North Line Bridges and Ravenswood Station 

Additional time needed by Union Pacific to review and approve project drawings and submittals 

Pace Bus Stop Improvements – Joliet Gateway Center 

Project is on hold 

   

   

27

Page 31: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

 

Systemwide  STATE FUNDED PROJECTS – CHANGE ORDERS  

STATUS  QUANTITY

Projects With Change Orders  6

Projects Without Change Orders  14

 Note: Some projects may have executed multiple change orders.  

70%

30%

PERCENTAGE OF TOTAL PROJECTS

Projects WithoutChange Orders

Projects WithChange Orders

    Projects With Change Orders  

SB  PROJECT NUMBER OF CHANGE ORDERS 

CTA  95th Street Terminal Improvements  9 

CTA  Wilson Transfer Station  10 

CTA  Rail Car Overhaul  1 

CTA  Rail Shop Roofs and Washer Replacement  2 

CTA  98th Shop – Replace Hoist and Spin Jacks  2 

Metra  Positive Train Control  2 

 

28

Page 32: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Systemwide  STATE FUNDED PROJECTS – CHANGE ORDER REASONS  

REASON  QUANTITY COST

Added Value  5 $12,827,139

Unforeseen Conditions  16 $8,941,827

Errors and Omissions  1 $193,395

Value Engineering  1 ($1,177,000)

Credits  2 ($1,819,396)

Time Extensions  1 $0

TOTAL  26 $18,965,966

  The  change  order  quantities  and  cost  amounts  represent  the  cumulative  total  for  the  20 currently ongoing state‐funded projects.   The total cost of change orders represents  less than 1% of the overall total budget of the state funded projects.   All change orders were executed within  the  project  budgets.    The  change  orders  executed  during  this  reporting  period  are described below.   For  the Wilson Transfer Station Project,  three change orders under  the construction  services contract are in‐process due to changed conditions and multiple allowance adjustments.  Work scope modifications were made to maintain the project schedule, customer safety and security and transit services as well as to realize actual work performed.   These change orders capture utility work performed  to  complete  construction  stages. To manage  and  improve  safety  and security, cameras, platform gates, signage, emergency power and public address systems were installed.   Also, credits were given for unused allowance to purchase revenue equipment and for deleted work.   The revenue equipment was purchased directly by CTA.  A  change order was executed  for  the 95th  Terminal  Improvements Project.  The  construction services contract was adjusted to add value.  Updates were for an enhanced building envelope system,  traffic  control,  traffic  signal  &  traction  power  infrastructure  and  foundation.    The upgraded  building  envelope  and  traffic  control  &  signal  provide  customer  facing  and transportation  improvements.    The  traction  power  infrastructure  and  foundation  upgrades resolved a field‐discovered conflict to maintain project progress and design intent.  Rail Shop Washer Replacements Project  change orders were executed  for added value.   The engineering services contract work scope was modified  to add document preparation, survey and  field  investigations  for  yard  track  reconfiguration  and  update  interior  pit  geometry, sequence of operations and washer controls.    Improvements  to  the yard reduce construction costs, enhance washer maintenance access and improve safety.   The washer element updates accommodate user group needs and provide a system‐wide compatible end product. 

29

Page 33: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

 

Section II Systemwide Projects over $10,000,000 

30

Page 34: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Systemwide  PROJECTS OVER $10,000,000  SERVICE BOARD  PROJECT TITLE  BUDGET

CTA  Purchase Rail Cars ‐ Series 7000  $632,000,000 

Metra  Positive Train Control  $331,200,747 

CTA  95th Street Terminal Improvements  $280,000,000 

CTA  Blue Line Signal Improvement  $207,100,000 

CTA  Wilson Transfer Station  $206,070,539 

Metra  UP West Line Expansion  $204,970,663 

CTA  Perform Rail Car Overhaul and Mid‐Life Rehabilitation  $185,000,000 

Pace  Purchase 40' Fixed Route Buses  $167,974,976 

Metra  Replace Bridges, 18th to 55th ‐ Rock Island District  $120,481,995 

Pace  Purchase CNG Buses  $119,913,100 

CTA  Red Purple Modernization (RPM) Phase 1  $113,704,135 

CTA  East Lake, Milwaukee, and Illinois Substation Construction  $68,987,861 

Metra  Locomotive Rehabilitation ‐ F40 (Option 1)  $67,226,124 

Metra  Lake Street Interlocker Modernization  $66,869,804 

CTA  Articulated Hybrid Bus Overhaul  $60,000,000 

Metra  Rehabilitation of Rolling Stock  $56,428,075 

CTA  Ravenswood‐Loop Connector Signal Renewal  $50,000,000 

Metra  Fiber Optic Cable  $46,547,942 

CTA  Belmont and Jefferson Park Stations Improvements  $42,226,054 

CTA  Garfield Green line Station Renovation  $42,000,000 

Metra  Locomotive Purchase  $41,420,000 

Metra  Financial System Replacement  $39,469,931 

CTA  Dearborn Subway Station Renovations ‐ G/C/D  $39,000,000 

Metra  Union Pacific North Line Bridges and Ravenswood Station  $38,095,843 

CTA  Bus State‐of‐Good‐Repair (SOGR)  $37,186,698 

Metra  Traction Power System Augmentation ‐ MED  $36,789,036 

Metra  Bridge Z‐100 Replacement  $34,000,000 

Metra  Locomotive Rehabilitation ‐ MP36  $31,459,842 

Metra  Lake Street Interlocker    $31,334,966 

Pace  Purchase Paratransit Buses for Suburban Dial‐A‐Ride  $30,098,869 

Metra  Car Rehabilitation ‐ Nippon Sharyo ‐ Phase 1  $29,050,000 

Pace  Purchase 40' Over The Road Buses  $28,872,150 

Metra  Commuter Car Rehab ‐ Budd  $26,751,093 

Metra  Yard Improvements  $23,159,000 

CTA  Illinois Medical District Station Rehabilitation  $23,000,000 

CTA  Lake Line ‐ Laramie to Harlem ‐ Trackwork Improvements  $21,391,986 

Pace  Purchase Vanpool Vehicles  $20,011,499 

Metra  Deering Bridge  $19,800,000 

31

Page 35: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Metra  New Bi‐Level Cars  $19,200,000 

CTA  Quincy Loop Station Upgrades  $18,234,808 

Metra  Revenue Accounting System  $17,770,000 

Metra  Car Rehabilitation – Amerail  $15,780,583 

Metra  IT Components and Services  $13,664,967 

Metra  Van Buren St Station  $13,500,000 

Metra  Car Rehabilitation ‐ Nippon Sharyo ‐ Phase 2  $13,125,000 

Metra  Head‐End Power Modification  $12,925,891 

Metra  Infrastructure Engineering  $12,688,284 

CTA Lake Line Stations Rehabilitation ‐ 51st, Halsted, Cottage Grove, and Kedzie 

$11,932,128 

Metra  47th Street Yard Improvements  $11,702,369 

CTA  North Red Line Stations ‐ Sheridan  $11,300,000 

Pace  Purchase Vanpool Minivans  $11,076,439 

Metra  Locomotive Rehabilitation ‐ F40 (Option 2)  $11,000,000 

Metra  Locomotive Rehabilitation ‐ F59  $10,500,000 

32

Page 36: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Systemwide  PROJECTS OVER $10,000,000 BY SERVICE BOARD – QUANTITY AND BUDGET  

SERVICE BOARD  PROJECTS  BUDGET

CTA  18  $2,049,134,209

Metra  29  $1,396,912,155

Pace  6  $377,947,033

TOTAL  54  $3,823,993,397

 

55%34%

11%

PERCENTAGE OF TOTAL PROJECTS

Metra

CTA

Pace

  

36%

54%

10%

PERCENTAGE OF TOTAL BUDGET

Metra

CTA

Pace

  

33

Page 37: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Systemwide  PROJECTS OVER $10,000,000 BY SERVICE BOARD – BUDGET RANGE  

0 1 2 3 4 5 6 7 8 9 10 11 12 13

10M‐19M

20M‐49M

50M‐99M

100M‐249M

250M‐499M

500M+

Metra

CTA

Pace

     

34

Page 38: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Systemwide  PROJECTS OVER $10,000,000 BY BUDGET RANGE  

BUDGET RANGE  PROJECTS

Projects over $500,000,000  1

Projects between $250,000,000 and $499,999,999  2

Projects between $100,000,000 and $249,999,999  8

Projects between $50,000,000 and $99,999,999  6

Projects between $20,000,000 and $49,999,999  20

Projects between $10,000,000 and $19,999,999  16

 

35

Page 39: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Systemwide  PROJECTS OVER $10,000,000 BY SERVICE BOARD – BUDGET RANGE  

BUDGET RANGE  CTA METRA  PACE

Projects over $500,000,000  1 0  0

Projects between $250,000,000 and $499,999,999  1 1  0

Projects between $100,000,000 and $249,999,999  4 2  2

Projects between $50,000,000 and $99,999,999  3 3  0

Projects between $20,000,000 and $49,999,999  6 11  3

Projects between $10,000,000 and $19,999,999  3 12  1

 

36

Page 40: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Systemwide  PROJECTS OVER $10,000,000 BY TYPE OF PROJECT  

TYPE OF PROJECT  QUANTITY COMBINED BUDGET

Construction  20 $1,398,640,346

Maintenance / Rehabilitation  18 $846,132,431

Procurement  15 $1,579,220,620

  

CTA  

TYPE OF PROJECT  QUANTITY TOTAL BUDGET

Construction  11 $895,155,525

Maintenance / Rehabilitation  5 $464,978,684

Procurement  2 $692,000,000

TOTAL  18 $2,049,134,209

  

Metra  

TYPE OF PROJECT  QUANTITY TOTAL BUDGET

Construction  9 $503,484,821

Maintenance / Rehabilitation  13 $384,153,747

Procurement  7 $509,273,587

TOTAL  29 $1,396,912,155

  

Pace  

TYPE OF PROJECT  QUANTITY TOTAL BUDGET

Construction  0 $0

Maintenance / Rehabilitation  0 $0

Procurement  6 $377,947,033

TOTAL  6 $377,947,033

 

37

Page 41: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

CTA  PROJECTS OVER $10,000,000  SERVICE BOARD  PROJECT TITLE  BUDGET

CTA  Purchase Rail Cars ‐ Series 7000  $632,000,000 

CTA  95th Street Terminal Improvements  $280,000,000 

CTA  Blue Line O'Hare Signals  $207,100,000 

CTA  Wilson Transfer Station  $206,070,539 

CTA  Perform Rail Car Overhaul and Mid‐Life Rehabilitation  $185,000,000 

CTA  Red Purple Modernization (RPM) Phase 1  $113,704,135 

CTA  East Lake, Milwaukee, and Illinois Substation Construction  $68,987,861 

CTA  Articulated Hybrid Bus Overhaul  $60,000,000 

CTA  Ravenswood‐Loop Connector Signal Renewal  $50,000,000 

CTA  Belmont and Jefferson Park Stations Improvements  $42,226,054 

CTA  Garfield Green line Station Renovation  $42,000,000 

CTA  Dearborn Subway Station Renovations ‐ G/C/D  $39,000,000 

CTA  Bus State‐of‐Good‐Repair (SOGR)  $37,186,698 

CTA  Illinois Medical District Station Rehabilitation  $23,000,000 

CTA  Lake Line ‐ Laramie to Harlem ‐ Trackwork Improvements  $21,391,986 

CTA  Quincy Loop Station Upgrades  $18,234,808 

CTA Lake Line Stations Rehabilitation ‐ 51st, Halsted, Cottage Grove, and Kedzie 

$11,932,128 

CTA  North Red Line Stations ‐ Sheridan  $11,300,000 

 

38

Page 42: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Purchase Rail Cars – Series 7000  

SCOPE:  Purchase up to 846 rail cars to replace the 2600 and 3200 series fleet.  The current project budget is for the base order of 400 cars. CTA may exercise options to increase the budget and purchase additional cars if funding is available. A design consultant will assist with quality control. 

BUDGET:  $632,000,000 (Budget for base quantity only – 400 cars); on budget. 

SCHEDULE:  On schedule; estimated completion December 2024. 

HIGHLIGHTS:  Notice to Proceed was given to the manufacturer in April 2016. The Chicago Assembly Facility is in progress with the north office building in the interior decoration phase. The main workshop concrete floor and track are in progress. Installation of the electrical switch gear and power systems are in the installation phase.  The first prototype cars are expected in 2019, with full production to begin in 2020. 

  

 

PROJECT:  95th Street Terminal Improvements  

SCOPE:  This project will rehabilitate the 95th/Dan Ryan station on the CTA Red Line and its bus terminal, which currently serves 11 CTA and Pace routes. The new design will feature an improved layout for bus and rail customers as well as improved and updated amenities. 

BUDGET:  $280,000,000; on budget. 

SCHEDULE:  On schedule; estimated completion December 2018. 

HIGHLIGHTS:  The main terminal design‐build contract has continued design and construction activities.  The south terminal opened to the public in April 2018.  The south terminal has all new signage, lights, platforms, and artwork. Punch list work is ongoing.  The north terminal currently has demolition activities ongoing.  The pedestrian bridge is being advanced for design and has been submitted for permitting. 

  

39

Page 43: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  O’Hare Line – Signal Upgrades & Special Trackwork 

SCOPE:  This project is for the replacement of the signal system from the Jefferson Park station to the O'Hare station. The existing signal system was implemented with the O'Hare Extension in 1984, and has become obsolete. Following the WMATA incident in 2009, NTSB analyzed systems across the country, including CTA's signal systems. NTSB uncovered a similar design flaw with this generation system, and recommended that a slow zone be added. Phase five work will address these issues, allowing the slow zone to be lifted, and improving safety and reliability on the branch overall. Replacement of two special track‐work elements to facilitate train movements and allow for increased operational flexibility and reduced maintenance. 

BUDGET:  $207,100,000; on budget. 

SCHEDULE:  On schedule; estimated completion May 2021. 

HIGHLIGHTS:  Design/Build contract was approved by CTA Board on 4/18/18. Execution of the contract is underway. Notice to Proceed is expected in May 2018. 

  

PROJECT:  Wilson Transfer Station (Final) 

SCOPE:  Wilson Station on the north branch of the CTA Red Line was rehabilitated. The new facility features reconstructed platforms, elevated track structure, and tracks. The facility now has entrances on both the north and south sides of Wilson Avenue, as well as an auxiliary entrance at Sunnyside Avenue, all of which is fully accessible. 

BUDGET:  $206,070,539; under budget. 

SCHEDULE:  On schedule; completed February 2018. 

HIGHLIGHTS:  The project achieved substantial completion in February 2018.  A final observation was performed by IDOT, RTA, and CTA to observe the project elements and confirm the project was substantially complete in accordance with grant agreement project scope.  CTA preserved historical building elements and brought back the original Gerber building facade.  Final close‐out is expected to be completed in the next few months.  This will be the final report on this project. 

  

40

Page 44: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Perform Rail Car Overhaul and Mid‐Life Rehabilitation  

SCOPE:  To reduce maintenance costs, 2600 Series cars are undergoing a 3/4 life overhaul and 3200 Series cars will receive a mid‐life overhaul. The project budget represents only the first year of a multi‐year overhaul program. 

BUDGET:  $185,000,000; on budget. 

SCHEDULE:  Behind schedule; estimated completion January 2019. 

HIGHLIGHTS:  Skokie Shop has completed all 100 cars in the 2600 Series cars project.  The 3200 Series project covers 257 cars.  The component rebuild, car overhaul work, and equipment installation is being done by CTA Skokie Shop staff.  As of May 2018, 234 of the 257 cars have undergone the overhaul and returned to revenue service.  There has been an increase in the scope of repairs based on car condition observed during the program. 

   

  

PROJECT:  Red Purple Modernization (RPM) – Phase 1  

SCOPE:  The RPM project will completely rebuild the northern portion of the Red Line from Belmont to Howard station and the Purple Line, which extends to Linden station in Wilmette.  The RPM Phase 1 project consists of the following elements:  Red‐Purple Bypass, Lawrence to Bryn Mawr Modernization, Corridor Signal Improvements, Advance Systems Work and Broadway Substation Upgrade. 

BUDGET:  $113,704,135; on budget. 

SCHEDULE:  On schedule; estimated completion January 2020. 

HIGHLIGHTS:  The draft RFP was issued at the end of 2017 and received comments from shortlisted proposers.  Efforts continue pertaining to utilities, real estate acquisitions, and property management services contract work. The permit was issued for work on the Broadway substation upgrade project. Finally, demolition work started after NTP was issued on Midcon RPM Phase One Adjacent Property Demolition Package work. 

  

41

Page 45: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  East Lake, Milwaukee, and Illinois Substation Construction  

SCOPE:  This project will provide for upgrades to the building envelopes as well as upgrades to interior finishes, AC power, lighting, alarms, heating, ventilation and plumbing systems at all three substations.  At East Lake substation the routing of cables from the substation to the elevated structure will be coordinated around a very congested area underground.  The East Lake building will be purchased from ComEd.  At Milwaukee substation the project will provide for new traction power equipment with greater capacity. 

BUDGET:  $68,987,861; on budget. 

SCHEDULE:  On schedule; estimated completion March 2020. 

HIGHLIGHTS:  The construction contract was awarded to Clark Construction and had the NTP issued in April 2017.  Traction power equipment is being manufactured. Electrical conduit and supports were installed at Illinois and Milwaukee. Permit was issued for work at East Lake. 

 

   

PROJECT:  Articulated Hybrid Bus Overhaul  

SCOPE:  Provide for the Mid‐Life Overhaul of up to 208 Articulated Buses. 

BUDGET:  $60,000,000; on budget. 

SCHEDULE:  Behind schedule; estimated completion February 2019. 

HIGHLIGHTS:  The rehabilitation of the articulated hybrid buses are being performed by an outside vendor. A total of 43 overhauled buses were delivered and accepted by CTA. It is expected that the vendor is to deliver the remaining 12 buses by end of Q2 2018 in order to complete milestone #2.   

       

42

Page 46: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

    

PROJECT:  Ravenswood‐Loop Connector Signal Renewal  

SCOPE:  Replace obsolete signal equipment beyond its useful life with new state‐of‐the‐art equipment, which will increase safety and livability in the Chicago metropolitan area and surrounding region. 

BUDGET:  $50,000,000; on budget. 

SCHEDULE:  On schedule; estimated completion December 2018. 

HIGHLIGHTS:  CTA is implementing this project through a design‐build contract. The contractor continued cable pulling operations. The interior wiring is in progress for the Cleveland and Illinois Houses. The Permit application for Illinois Relay House foundation continued. 

   

   

PROJECT:  Belmont and Jefferson Park Stations Improvements  

SCOPE:  The work scope is for station upgrades. Belmont station work includes a new station canopy, site improvements, enlarged bus prepaid boarding area, renovated station electrical and finishes, and refurbished platform furniture. Jefferson station improvements include reconstructed bus turnaround pavement and canopies, renovated entrance and customer waiting areas, enhanced lighting, improved signage, new public art, updated communication elements, and repaired roofing, platform edge, and curtain wall. 

BUDGET:  $42,226,054; on budget. 

SCHEDULE:  On schedule; estimated completion December 2018. 

HIGHLIGHTS:  The Jefferson Park Intermodal Facility is one of the few locations in the region that is served by all three Service Boards.  The procurement for this project was combined with the Belmont Gateway Project.  The Belmont canopy advance package final design is complete. Final design package for the station improvements was submitted. 

43

Page 47: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

   

PROJECT:  Garfield Green Line Station Renovation  

SCOPE:  The scope of this project is to enhance key elements to the current Garfield station located on the South Mainline that consists of the following:  the existing operational station and bus turnaround, the historic 1892 former ‘Alley L’ station that is no longer in use and associated historic track structure spanning Garfield Boulevard, and the roadway, median, and Greenspace. 

BUDGET:  $42,000,000; on budget. 

SCHEDULE:  On schedule; estimated completion July 2019. 

HIGHLIGHTS:  This project was awarded as a Design/Build and the selected contractor continued the design process and started working on the Intermediate Design Package. Construction Management Task Order was executed on January 26, 2018. DBC submitted 3D renderings of proposed Garfield Station. 

  

  

PROJECT:  Dearborn Subway Station Improvements  

SCOPE:  The proposed scope of work includes improvements at the street, mezzanine, and platform levels. New entry canopies will be installed at each stair opening with new glazed tile walls, lighting, and repainted ceilings. Mezzanine and platform improvements will include new finishes, lighting, furniture, and exit roto‐gates. Elevators and stairs will also be replaced. 

BUDGET:  $39,000,000; on budget. 

SCHEDULE:  On schedule; estimated completion December 2019. 

HIGHLIGHTS:  The Blue Line subway was originally opened in 1951. These three stations date back to that time and are in need of renewal to restore them to a state of good repair.  The Project Master Plan was finalized in October 2016.  A bid package for a design‐build contractor was prepared and advertised on February 5, 2018.  Bids 

were received on May 1, 2018 are currently being evaluated.   

   

44

Page 48: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

  PROJECT:  Bus State‐of‐Good‐Repair (SOGR)  

SCOPE:  This project provides rehabilitation work at existing bus garage and bus facilities across the CTA system. 

BUDGET:  $37,186,698; on budget. 

SCHEDULE:  On schedule; estimated completion September 2018. 

HIGHLIGHTS:  The following projects were completed: Employee Comforts at Bus Maintenance & Bus Turnarounds; Forest Glen Oil/Water Separator; Concrete Repair at South Shops Unit 9; System wide Bus Garage Exterior Lightning, 77th Garage Fuel System & Remediation; Forest Glen Chassis Wash Pit; Unit 6 Pit Replacement; 103 Garage Heating; 77th Unit 4 Tire Shop; South Shops Unit 4 Brake Stripping.  The only project remaining is the 77th Bus Garage Washer Replacement which is currently in progress with preparations for masonry tuck‐pointing and underground utilities.  

   

 

PROJECT:  Illinois Medical District Station Rehabilitation  

SCOPE:  Improvements to the station facilities will provide a new elevator at the Ogden Avenue stationhouse and renovations to the Damen Avenue and Paulina Street entrances with upgraded finishes throughout.  Existing ramps will be modified to become ADA compliant.  The platform canopy will also be repaired. Bus & Train trackers will be added as well. 

BUDGET:  $23,000,000; on budget. 

SCHEDULE:  On schedule; estimated completion January 2019. 

HIGHLIGHTS:  Improvements to this station will provide for ADA access to nearby medical facilities.  Construction contract was awarded and Notice to Proceed was issued in September 2016.  Demolition and salvaging of canopy completed.  Concrete repairs and demolition of remaining stationhouse concrete structure are ongoing.  Funding is provided by City of Chicago TIF and CTA. 

   

45

Page 49: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Lake Line – Laramie to Harlem – Tactical Ballasted Trackwork Improvements (Final) 

SCOPE:  This project will renew track, including ties, plates, and fasteners, on the ballasted portion of the Lake Branch of the Green Line from Latrobe Abutment to Harlem Yard. 

BUDGET:  $21,391,986; on budget. 

SCHEDULE:  Project was completed January 2017. 

HIGHLIGHTS:  All work completed. This will be the final report. 

       

  

PROJECT:  Quincy Loop Station Upgrades  

SCOPE:  Improvements to the station include: two elevators for both the inner loop and outer loop platforms; repair, repainting, and refinishing of interior and exterior elements of the stationhouse; and upgrades to lighting and canopy repairs. 

BUDGET:  $18,234,808; on budget. 

SCHEDULE:  On schedule; estimated completion September 2018. 

HIGHLIGHTS:  Quincy Station has been designated as CTA’s historic station on the elevated Loop and certain elements will be preserved.  Construction contract was awarded and Notice to Proceed was issued in July 2016. New steel elevator towers, bridge steel and bridge canopy steel have been installed on both east and west sides. New east elevator foundation build‐out and floor installation were completed. Build out of the east and west station houses continue.  Funding is provided by City of Chicago TIF and CTA. 

   

46

Page 50: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Lake Line Stations Rehabilitation – 51st, Halsted, Cottage Grove, and Kedzie  

SCOPE:  The purpose of this project is to rehabilitate the station’s customer‐facing elements with enhancements that include, but are not limited to: CTA sign replacement, stair repairs/replacement, stainless steel handrails, ADA compliant stainless steel station doors, station flooring, platform furniture refurbishment, LED lighting, painting, polishing of stainless steel surfaces, and power washing. 

BUDGET:  $11,932,128; on budget. 

SCHEDULE:  On schedule; estimated completion March 2019. 

HIGHLIGHTS:  The kickoff meeting was hosted by CTA and held on Friday, March 30th, 2018. HNTB is the Construction Management team. Construction Contractor, FH Paschen, is setting up E‐Builder accounts. Process plans and coordination issues were discussed after a site visit was conducted. 

   

 

PROJECT:  North Red Line Stations – Sheridan (Final) 

SCOPE:  Improvements to the station facilities will provide for improved maintenance, passenger comfort, and security. The project scope will include lighting, roofs and canopies, platform decking, painting, accessibility features, and structural repairs. 

BUDGET:  $11,300,000; on budget. 

SCHEDULE:  On schedule; estimated completion May 2018. 

HIGHLIGHTS:  Project is currently closing out with CTA Structure Maintenance forces finishing up with the structure renewal work, which is part of the project scope.  Detailing complete and finalized for all track and platform stringers.  Bent girder and stringer bracing were fabricated for installation.  Due to changes in the availability of state funding, only the structure renewal work will be completed.  Improvements to the station are deferred.  This is the final report on this project. 

    

47

Page 51: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

CTA  PROJECT BUDGET BY PERCENTAGE OF ENTIRE BUDGET AND PERCENTAGE OF PROJECTS  

BUDGET  QUANTITY % OF BUDGET  % OF PROJECTS

Projects over $500,000,000  1  30.9  5.6 

Projects between $250,000,000 and $499,999,999  1  13.7  5.6 

Projects between $100,000,000 and $249,999,999  4  34.7  22.1 

Projects between $50,000,000 and $99,999,999  3  8.7  16.7 

Projects between $20,000,000 and $49,999,999  6  10.0  33.3 

Projects between $10,000,000 and $19,999,999  3  2.0  16.7 

  

0

5

10

15

20

25

30

35

40

500M+ 250M‐499M 100M‐249M 50M‐99M 20M‐49M 10M‐19M

% of Budget

% of Projects

  

48

Page 52: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

CTA  

TYPE OF PROJECT  QUANTITY TOTAL BUDGET

Construction  11 $895,155,525

Maintenance / Rehabilitation  5 $461,978,684

Procurement  2 $692,000,000

 

61%

28%

11%

PERCENTAGE OF TOTAL PROJECTS

Construction

Maint./Rehab.

Procurement

  

44%

22%

34%

PERCENTAGE OF TOTAL BUDGET

Construction

Maint./Rehab.

Procurement

    

49

Page 53: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Metra  PROJECTS OVER $10,000,000   SERVICE BOARD  PROJECT TITLE  BUDGET

Metra  Positive Train Control  $331,200,747 

Metra  UP West Line Expansion  $204,970,663 

Metra  Replace Bridges, 18th to 55th ‐ Rock Island District  $120,481,995 

Metra  Locomotive Rehabilitation ‐ F40 (Option 1)  $67,226,124 

Metra  Lake Street Interlocker Modernization  $66,869,804 

Metra  Rehabilitation of Rolling Stock  $56,428,075 

Metra  Fiber Optic Cable  $46,547,942 

Metra  Locomotive Purchase  $41,420,000 

Metra  Financial System Replacement  $39,469,931 

Metra  Union Pacific North Line Bridges and Ravenswood Station  $38,095,843 

Metra  Traction Power System Augmentation ‐ MED  $36,789,036 

Metra  Bridge Z‐100 Replacement  $34,000,000 

Metra  Locomotive Rehabilitation ‐ MP36  $31,459,842 

Metra  Lake Street Interlocker    $31,334,966 

Metra  Car Rehabilitation ‐ Nippon Sharyo ‐ Phase 1  $29,050,000 

Metra  Commuter Car Rehab ‐ Budd  $26,751,093 

Metra  Yard Improvements  $23,159,000 

Metra  Deering Bridge  $19,800,000 

Metra  New Bi‐Level Cars  $19,200,000 

Metra  Revenue Accounting System  $17,770,000 

Metra  Car Rehabilitation ‐ Amerail  $15,780,583 

Metra  IT Components and Services  $13,664,967 

Metra  Van Buren St Station  $13,500,000 

Metra  Car Rehabilitation ‐ Nippon Sharyo ‐ Phase 2  $13,125,000 

Metra  Head‐End Power Modification  $12,925,891 

Metra  Infrastructure Engineering  $12,688,284 

Metra  47th Street Yard Improvements  $11,702,369 

Metra  Locomotive Rehabilitation ‐ F40 (Option 2)  $11,000,000 

Metra  Locomotive Rehabilitation ‐ F59  $10,500,000 

 

50

Page 54: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Positive Train Control (PTC)  

SCOPE:  Pursuant to the US Rail Safety Improvement Act of 2008, the United States railroad network, which includes all Metra lines, is required to implement PTC. In addition to this legislative mandate, justification for PTC also involves several safety improvements.  

BUDGET:  $331,200,747; on budget. 

SCHEDULE:  On schedule; estimated completion June 2020. 

HIGHLIGHTS:  System integrator planning and work activities support PTC implementation.  Development of communication architecture, back office configuration, on board equipment reviews, testing plans and reports continue.  Configuration management documents, policies and the revenue service demonstration application are being written.  Personnel are undergoing on‐board mechanical, wayside and locomotive engineer training.  Coordination is underway with other host railroads to plan communication between networks for PTC operations. 

 

 

PROJECT:  UP West Line Expansion  

SCOPE:  This project, a Public‐Private Partnership funded 50% by Metra and 50% by the Union Pacific Railroad, involves the expansion and extension of the UP West Line, including the addition of a third main line track. 

BUDGET:  $204,970,663; on budget. 

SCHEDULE:  Behind schedule; estimated completion December 2019. 

HIGHLIGHTS:  The project design and environmental work have been completed. Construction cost estimates for both segments, including land acquisition, have been prepared.  An Invitation for bids was issued for the construction of east portion of the track in May 2017.  Notice to Proceed was issued in November 2017.  The construction project is currently 10% complete.   Metra plans to go out for bid on the western section construction in the fall of 2018. 

   

51

Page 55: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Replace Bridges, 18th to 55th Streets – Rock Island District  

SCOPE:  Project funding provides for the replacement of bridges between 18th Street and 60th Street on the Rock Island District, and will also include new track and signal systems. 

BUDGET:  $120,481,995; on budget. 

SCHEDULE:  On schedule; estimated completion December 2020. 

HIGHLIGHTS:  Phase 1 design and construction is complete.  Phase 2 construction is 98% complete, with only final punch list items and final bills remaining.  The Phase 3 design task was submitted and is waiting on a NTP. The Phase 3 design is estimated to be completed in 2019, with estimated completion of construction in 2020. 

    

 

PROJECT:  Locomotive Rehabilitation – F40 (Option 1)  

SCOPE:  The locomotives, originally delivered between 1989 and 1992, will undergo a second rehabilitation to include complete rebuilding of the diesel engine, replacement and overhaul of various traction, electrical, and control components, and body repair and painting. These locomotives are the first batch of their fleet to undergo the rehabilitation process. 

BUDGET:  $67,226,124; on budget. 

SCHEDULE:  On schedule, estimated completion December 2018. 

HIGHLIGHTS:  Rehabilitation of these locomotives includes fuel emission upgrades to a higher environmental standard.  Eleven locomotives have completed the rehab process.  The contractor is currently working on five more locomotives.  Some of the locomotives will be rehabilitated under a different project number to use state funds. 

  

 

52

Page 56: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Lake Street Interlocker Modernization  

SCOPE:  This project features the modernization and upgrading of the Lake Street Interlocker north of Chicago Union Station. The current task is to modify the overhead ceiling plenum to provide clearance. 

BUDGET:  $66,869,804; on budget. 

SCHEDULE:  Behind schedule; estimated completion December 2018. 

HIGHLIGHTS:  Final Plan Set and Specifications were submitted, and Amtrak has awarded a 3rd party construction contract to start with the plenum removal in the summer of 2018. Turnout and switch replacement work is expected to start in June 2018. 

      

 

PROJECT:  Rehabilitation of Rolling Stock 

SCOPE:  Metra is rehabilitating locomotives and bi‐level commuter rail cars. The locomotives are being rebuilt with complete renovation of the diesel engine, overhaul of the traction alternator, head end power alternator and gear box, replacement of the control system, coupler and draft gears, revamping of the trucks, including traction motors, body repair and modifications, installation of secondary engine room door and painting. The rail cars are being renovated with replacement of couplers, yokes, draft gears, weather stripping, seats, floors, walls, window and door mechanisms, application of tube style diaphragms, renewal of the 480‐volt and control train lines and repair of heating and lighting systems. 

BUDGET:  $56,428,075; on budget. 

SCHEDULE:  Project completed in December 2017. 

HIGHLIGHTS:  This project will lower maintenance costs. For locomotive rehabs, fuel costs will, also, be lowered and air pollution and the regional economy health will be improved. For rail car rehabs, the reliability and quality of service for commuters will be improved. 

53

Page 57: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Fiber Optic Cable (Final) 

SCOPE:  This project consists of the installation of fiber optic cable at LaVergne MP 7.1 to Lisle MP 24 and between MP 23.0 and 26.0, including intermediate signals, and at grade crossings between mileposts 14.77 and 16.37 on the BNSF line.  The cable, used with logic controllers, will provide signal communication and control system for interlocking and crossings, as well as provide the infrastructure for PTC.  The project also includes the installation of Illinois Commerce Commission (ICC) mandated constant warning time equipment and signal upgrades. 

BUDGET:  $46,547,942; on budget. 

SCHEDULE:  Project completed in December 2017. 

HIGHLIGHTS:  Insulated joint removal and the Wi‐Fi installation at intermediate points were completed in 2017. Final billing remains.  This will be the final report on this project. 

PROJECT:  Locomotive Purchase  

SCOPE:  This project involves the purchase of at least 12 and up to 42 new and/or remanufactured diesel locomotives.  

BUDGET:  $41,420,000; on budget. 

SCHEDULE:  On schedule; estimated completion December 2022. 

HIGHLIGHTS:  Metra has recently given a Notice‐to‐Proceed for the purchase of 20 F59 locomotives from Amtrak and at the same time prepared a requisition for additional new or remanufactured diesel locomotive with the bid due date by the end of May 2018.  Metra anticipates these locomotives to have increased horsepower, lower emissions, and more fuel efficiency than the locomotives in the current fleet. 

54

Page 58: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Financial System Replacement  

SCOPE:  This project will provide funding for Metra to implement and Enterprise Resource Planning (ERP) system that will be compliant with current financial system “Best Practices”.  This system will support electronic data interchange, be fully extensible and upgradeable, use integrated highly flexible analytical reporting tools and support microcomputer/network based software productivity tools. 

BUDGET:  $39,469,931; on budget. 

SCHEDULE:  On schedule; estimated completion March 2020. 

HIGHLIGHTS:  Phase 1 went live in January 2016 for Charts of Accounts and General Ledger modules.  Phase 2, which includes Budget, Procurement, Inventory, Projects and Grants, Accounts Payable and Receivable Modules went live in June 2017.  Phase 3, which is the Payroll Module, is projected to go live in June 2018. 

   

 

PROJECT:  Union Pacific North Line Bridges and Ravenswood Station 

SCOPE:  The project scope includes the construction of a new station for the inbound half of the Ravenswood Station and the replacement of 11 bridges on the UP North Line. The work will emulate that of the outbound section of the station. The station will have longer platforms that are covered, lighting, stairs, ramps, warming shelters, and landscaping. Work on the bridges includes replacement of existing stone abutments, retaining wall construction, steel spans, and decks. 

BUDGET:  $38,095,843; on budget.  

SCHEDULE:  Behind schedule; estimated completion June 2020. 

HIGHLIGHTS:  Construction on the Ravenswood station is ongoing. A temporary access ramp was constructed to allow the general contractor to proceed with work. Installation of the earth retaining system (ERS) and tie backs are ongoing.  On the bridge project, work began at Winnemac, Lawrence, and Balmoral bridges related to contractor mobilization, lead abatement, tuck‐pointing, and demolition of superstructure steel, temporary support columns, and bridge deck clean up at all 11 bridges.  

 

55

Page 59: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Traction Power System Augmentation – Metra Electric District  

SCOPE:  Four existing tie stations (51st Street, 95th Street, Riverdale, and Homewood) will be converted into power substations with substantially greater power capacity and installing a new prefabricated substation at 31st Street. 

BUDGET:  $36,789,036; on budget. 

SCHEDULE:  On schedule; estimated completion December 2018. 

HIGHLIGHTS:  Converting the tie stations into substations and installing a new substation will increase capacity and reliability on the Metra Electric District.  Construction is moving from north to south. Construction at 31st Street and 51st Street are complete. Design for 95th Street and Riverdale are 100% complete. Construction contract is out for bid for 95th and Riverdale substations.  

    

 

PROJECT:  Bridge Z‐100 Replacement  

SCOPE:  This project is an infrastructure replacement and expansion project that will replace the Milwaukee District West Line’s Fox River Bridge with a new, double‐track structure, which will also include a modern, PTC‐compliant signal system. The project scope includes completing the design process, purchasing a permanent easement, and a two‐phase construction process. 

BUDGET:  $34,000,000; on budget. 

SCHEDULE:  On schedule; estimated completion March 2020. 

HIGHLIGHTS:  Construction work started in April 2018, which is 6% complete. Environmental permits to relocate mussel survey is in process. River work will start June 2018.  

      

56

Page 60: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Locomotive Rehabilitation – MP36  

SCOPE:  This project involves the mid‐life rehabilitation of 26 locomotives that were delivered between 2003 and 2004. 

BUDGET:  $31,459,842; on budget. 

SCHEDULE:  On schedule; estimated completion February 2019. 

HIGHLIGHTS:  Work is ongoing and being performed in‐house. Locomotives are being strategically removed from service to undergo rehabilitation with minimal impact to revenue service.  Requisition of materials is in process.  Materials are released from Master Purchase Orders as needed.  Fifteen locomotives have been completed and two are currently in Metra’s shop undergoing rehabilitation. 

     

 

PROJECT:  Lake Street Interlocker (Final) 

SCOPE:  This project features the renewal of turnouts at Lake Street Interlocking, including the purchase and installation of a new interlocking control machine. 

BUDGET:  $31,334,966; on budget. 

SCHEDULE:  On schedule; completed September 2017. 

HIGHLIGHTS:  The design work on interlocking control machine is ongoing and is at 89% completion.  Materials for interlocking control machine are being received and installation will follow.  Overall track work is currently at 100% completion.  Design work on interlocking control machine will be completed in a new programmed project. The scope for this project has been completed, and only final bills remain.  This is the final report on this project. 

     

57

Page 61: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Car Rehabilitation – Nippon Sharyo ‐ Phase 1 (Final) 

SCOPE:  This phase of the project involves the mid‐life rehabilitation of 30 commuter rail cars built by Nippon Sharyo and delivered between 2002 and 2005. This is the first major rehabilitation of these cars, and is the first phase in a multi‐year program to complete the rehabilitation of all 300 cars. 

BUDGET:  $29,050,000; on budget. 

SCHEDULE:  On schedule; completed in January 2018. 

HIGHLIGHTS:  Current scope of the project has been completed. Final bills remain related to current scope.  This is the final report on this project. 

     

  

PROJECT:  Commuter Car Rehabilitation – Budd  

SCOPE:  This project involves the life‐extending rehabilitation of up to 41 commuter cars, originally built by the Budd Company between 1974 and 1978, last rehabilitated between 1990 and 1993. The rehab includes, but is not limited to, replacement and/or repair to electrical and control lines, heating and lighting systems, replacement of seats, floors, walls, AC units, overhaul of trucks, replacement of all windows, door mechanisms, and emergency lighting requirements, etc. 

BUDGET:  $26,751,093; on budget. 

SCHEDULE:  On schedule; estimated completion December 2018. 

HIGHLIGHTS:  This project will improve the overall state of good repair for Metra rolling stock.  As with the locomotive rehabilitation projects, rolling stock are being removed from service in such a manner as to not disrupt operations.  Requisition of materials is ongoing and master purchase order is being released as needed.  Eighteen cars have been completed and rehabilitation continues with another car underway. 

 

58

Page 62: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Yard Improvements  

SCOPE:  This project includes, but not limited to, the rehabilitation of the 49th Street Car Shop on the Rock Island line to enable additional shift work for rail car and locomotive rehabilitation. Work could also include but not be limited to expanding office space, crew facilities, and locker rooms. A transfer table could also be added. 

BUDGET:  $23,159,000; on budget. 

SCHEDULE:  On schedule; estimated completion November 2019. 

HIGHLIGHTS:  Construction on this project started on April 1, 2018 and is currently in progress. 

      

 

PROJECT:  Deering Bridge  

SCOPE:  This project consists of rehabilitating the Deering bridge over the North Branch of the Chicago River. It also includes the rehabilitation of the Webster Avenue bridge just south of the Deering bridge and the fill of the bridge over the former Milwaukee Road just north of Deering Bridge. 

BUDGET:  $19,800,000; on budget. 

SCHEDULE:  Behind schedule; estimated completion July 2019  

HIGHLIGHTS:  Construction is ongoing with this project. Webster bridge north side column base repair work has been started by the general contractor. Backfilling and repairing on the east and west side is in progress. Additionally, assembly of shoring for the east side counterweight repair work is in progress. Work is also being performed on the column foundations for Webster bridge.  As of May 2018, the project is 7% complete.  

   

59

Page 63: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  New Bi‐Level Cars  

SCOPE:  The long‐term proposed rail car program will purchase 367 new diesel cars to replace 318 cars with an average age of 43 years and increase the number of spare cars by 49. 

BUDGET:  $19,200,000; on budget. 

SCHEDULE:  On schedule; estimated completion December 2021. 

HIGHLIGHTS:  Metra has completed final specification in early 2017 and issued an RFP in mid‐2017. Currently, Metra is completing the technical evaluation phase with the vendor and expects to proceed with the procurement in summer of 2018. This project will extend over multiple years. 

     

 

PROJECT:  Revenue Accounting System  

SCOPE:  Metra will implement a new and updated revenue accounting system and will also provide funding for Metra to scope and release an RFP to integrate its current financial system into an Enterprise Resource Planning (ERP) system that will be compliant with current best practices. 

BUDGET:  $17,770,000; on budget. 

SCHEDULE:  On schedule; estimated completion December 2020. 

HIGHLIGHTS:  Consultants are continuing implementation and support services for Oracle Point‐of‐Sale Projects and Phase 3 of ERP, which is the Revenue Accounting Module. Requisition is in process for ticket vending machines. 

      

60

Page 64: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Commuter Car Rehabilitation – Amerail (Final) 

SCOPE:  This project is the last of six phases in a rehabilitation and mid‐life overhaul program of 26 cars. The entire rehabilitation program includes all 176 commuter cars built by Morrison‐Knudsen/Amerail. These cars were originally placed into service between 1994 and 1998. 

BUDGET:  $15,780,583; on budget. 

SCHEDULE:  On schedule; completed in July 2017. 

HIGHLIGHTS:  This project was being performed in‐house at Metra’s 49th Street Shop on the Rock Island District.  All rehabilitation of 26 cars for have been completed.  This is the last report on this project. 

     

 

PROJECT:  IT Components and Services  

SCOPE:  This project will provide for purchase of various types of computer hardware and software that will be utilized at Metra Headquarters and outlying areas.  Purchases will include, but are not limited to, mainframe terminal and printer replacement, mainframe tape system, replacement of obsolete network switches, computers, printers, copiers and new servers. 

BUDGET:  $13,664,967; on budget. 

SCHEDULE:  On schedule; estimated completion December 2019. 

HIGHLIGHTS:  Purchase orders have been awarded for various computer hardware and software.  Hardware has been delivered and installed.  Requisitions are being prepared for hardware and software. 

     

61

Page 65: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Van Buren St Station  

SCOPE:  This project involves rehabilitation of the Van Buren Street station facility. Work to be performed includes, but is not limited to, rehabilitating the access tunnel, stairs, elevators, and other related facilities. 

BUDGET:  $13,500,000; on budget. 

SCHEDULE:  On schedule; estimated completion December 2021. 

HIGHLIGHTS:  Consultant contract has been awarded for station concept design. Currently concept design is at 99% completion. Design package is under final review. 

       

 

PROJECT:  Car Rehabilitation – Nippon Sharyo ‐ Phase 2  

SCOPE:  The overall project involves the mid‐life rehabilitation of 302 Bi‐Level commuter cars delivered between 2002 and 2008. This portion of the project involves the mid‐life rehabilitation of 11 cab cars and 19 trailer/coach cars built by Nippon Sharyo and delivered between 2002 and 2005. This is the first major rehabilitation of these cars, and is the second phase in a multi‐year program to complete the rehabilitation of all 300 cars. 

BUDGET:  $13,125,000; on budget. 

SCHEDULE:  On schedule; estimated completion November 2019. 

HIGHLIGHTS:  Eight cab cars and four trailer/coach cars have completed rehab. Four cars are currently undergoing rehabilitation, three being cabs and one being a trailer/coach car. 

    

62

Page 66: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Head‐End Power Modification  

SCOPE:  This project will modify 12 locomotives by replacing the main engine‐driven generator and inverter combination that provides power to the train consist with a separate engine/generator set on Metra’s Model MP36 passenger locomotives. 

BUDGET:  $12,925,891; on budget. 

SCHEDULE:  On schedule; estimated completion December 2018. 

HIGHLIGHTS:  One of twelve locomotives is completed. Two locomotives are in progress.  Improved fuel efficiency and reduced emissions are expected on locomotives upon completion completed of project. 

      

 

PROJECT:  Infrastructure Engineering  

SCOPE:  This project funds engineering of capital projects in Metra’s Engineering Department. Most of the work anticipated will support projects in the structural, signal, electrical, communications, and support facilities categories. The associated professional services will include design and/or construction management in a variety of fields. The project will fund the work of engineering consultants. 

BUDGET:  $12,688,284; on budget. 

SCHEDULE:  On schedule; estimated completion December 2018. 

HIGHLIGHTS:  Completed engineering design services for cost/benefit analysis for MWD Bridge Z100, Metra/BNSF Aurora Platforms and Parking Lots, Completion of RID Bridge Rehab over 89th, Vincennes, and Halsted Streets, Rehab of 211th Street Station (MED), and Platform Reconstruction at LaGrange Stone Avenue Station (BNSF). Kenny and HNTB contract work are ongoing. Flagging for BNSF will be performed under this project by a 3rd part contractor. 

 

63

Page 67: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  47th Street Yard Improvements (Final) 

SCOPE:  This project is part of an ongoing program to make improvements to the facilities at the 47th Street Yard and Shops.  The highest priority projects will provide for the installation of a new ventilation system in the diesel shop and the replacement of the sand tower in the yard. 

BUDGET:  $11,702,369; on budget. 

SCHEDULE:  On schedule; completed in December 2017. 

HIGHLIGHTS:  Project completed on December 31, 2017.  Final bills remain.  This will be the final report for this project. 

      

 

PROJECT:  Locomotive Rehabilitation – F40 (Option 2)  

SCOPE:  Ten locomotives, originally delivered between 1989 and 1992, will undergo a second rehabilitation to include complete rebuilding of the diesel engine, replacement and overhaul of various traction, electrical, and control components, and body repair and painting. These locomotives are the second batch of their fleet to undergo the rehabilitation process. 

BUDGET:  $11,000,000; on budget. 

SCHEDULE:  On schedule, estimated completion July 2019. 

HIGHLIGHTS:  Rehabilitation of these locomotives includes fuel emission upgrades to a higher environmental standard. Project funds were awarded in August 2016.  These funds are for Option 2 execution for rehabilitation of 10 locomotives. Two locomotives are currently being rehabbed. 

    

64

Page 68: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Locomotive Rehabilitation – F59  

SCOPE:  This project involves the purchase of used locomotives, as well as additional parts, for the life extension of the used locomotives. This project includes, but is not limited to, overhaul of the air compressor, main generator, traction motors, electrical control systems, replacement of couplers and gears, and body repairs/modifications. 

BUDGET:  $10,500,000; on budget. 

SCHEDULE:  On schedule; estimated completion August 2020. 

HIGHLIGHTS:  Metra has prepared a requisition for outsourcing the rehab of the used locomotives and is expecting bids due by end of May 2018. 

     

65

Page 69: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Metra  PROJECT BUDGET BY PERCENTAGE OF ENTIRE BUDGET AND PERCENTAGE OF PROJECTS  

BUDGET  QUANTITY % OF BUDGET  % OF PROJECTS

Projects over $500,000,000  0  0  0 

Projects between $250,000,000 and $499,999,999  1  23.7  3.4 

Projects between $100,000,000 and $249,999,999  2  23.3  6.9 

Projects between $50,000,000 and $99,999,999  3  13.6  10.4 

Projects between $20,000,000 and $49,999,999  11  27.1  37.9 

Projects between $10,000,000 and $19,999,999  12  12.3  41.4 

 

0

5

10

15

20

25

30

35

40

45

50

500M+ 250M‐499M 100M‐249M 50M‐99M 20M‐49M 10M‐19M

% of Budget

% of Projects

   

66

Page 70: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Metra  

TYPE OF PROJECT  QUANTITY TOTAL BUDGET

Construction  9 $503,484,821

Maintenance / Rehabilitation  13 $384,153,747

Procurement  7 $509,273,587

 

31%

45%

24%

PERCENTAGE OF TOTAL PROJECTS

Construction

Maint./Rehab.

Procurement

 

36%

28%

36%

PERCENTAGE OF TOTAL BUDGET

Construction

Maint./Rehab.

Procurement

    

67

Page 71: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Pace  PROJECTS OVER $10,000,000  SERVICE BOARD  PROJECT TITLE  BUDGET

Pace  Purchase 40’ Fixed Route Buses  $167,974,976 

Pace  Purchase CNG Buses  $119,913,100 

Pace  Purchase Paratransit Buses for Suburban Dial‐A‐Ride  $30,098,869 

Pace  Purchase 40' Over The Road Buses  $28,872,150 

Pace  Purchase Vanpool Vehicles  $20,011,499 

Pace  Purchase Vanpool Minivans  $11,076,439 

68

Page 72: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Purchase 40’ Fixed Route Buses (Final) 

SCOPE:  This project involves a five‐year indefinite delivery/indefinite quantity contract for 40 foot buses. The minimum quantity to be purchased under this contract is 24 buses and the total number of buses procured will not exceed the maximum amount of 416. 

BUDGET:  $167,974,976; on budget. 

SCHEDULE:  Project completed in January 2018.  

HIGHLIGHTS:  To date, 408 buses have been ordered under this contract. This number includes the last order for an additional 86 buses, which are all currently in service. The contract has expired.  This will be the final report for this project.  

     

 

PROJECT:  Purchase 40’ Compressed Natural Gas Buses  

SCOPE:  This project involves a five‐year indefinite delivery/indefinite quantity contract for 40’ compressed natural gas buses. The minimum quantity to be purchased under this contract is 91 buses and the total number of buses procured will not exceed the maximum amount of 250. 

BUDGET:  $119,913,100; on budget. 

SCHEDULE:  On schedule; estimated completion August 2018. 

HIGHLIGHTS:  The first 20 buses have been delivered and received by Pace. The second order of 28 buses has been placed in August 2016 and the busses have been delivered to Pace on April 25, 2017.  The third order of the remaining 43 buses has been delivered between August 4, 2017 and October 13, 2017.  All of those buses have been placed in service.  A Change Order for another 11 buses, funded by 3 FTA grants, has been executed.  Of those 11 buses, 5 have been delivered in May 2018 and the remaining 6 are expected to be delivered in June 2018.   

   

69

Page 73: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

   

PROJECT:  Purchase Paratransit Buses for Suburban Dial‐A‐Ride Service  

SCOPE:  This project involves a five‐year indefinite delivery/indefinite quantity contract for 15‐passenger Paratransit buses. The minimum quantity to be purchased under this contract is 20 gasoline engine and/or diesel engine buses.  The total number of buses procured will not exceed the maximum amount of 432. 

BUDGET:  $30,098,869; on budget. 

SCHEDULE:  On schedule; estimated completion March 2019. 

HIGHLIGHTS:  To date, a total of 355 vehicles, including the most recent new orders for a total additional 148 paratransit vehicles to be executed.  Of the additional 148, an order of 35 are all in service and delivery for an order of 85 is currently in process and expected to be completed by June 2018.  Pace staff will be meeting with the contractor to finalize a schedule for the remaining 28, but expects deliveries to be completed by March 2019. 

 

  

PROJECT:  Purchase 40’ Over The Road Buses (Final) 

SCOPE:  This project involves a five‐year indefinite delivery/indefinite quantity contract for 40’ Over The Road buses. The minimum quantity to be purchased under this contract is 14 buses and the total number of buses procured will not exceed the maximum amount of 50. 

BUDGET:  $28,872,150; on budget. 

SCHEDULE:  On schedule; completed in December 2017. 

HIGHLIGHTS:  A total of 30 forty foot Over The Road Buses have been ordered.  An order of 5 buses was executed in October 2016, the buses have been delivered and are now in service.  A new order of 3 buses was executed in February 2017 and were delivered in December 2017.  This contract has expired and is now closed.  This will be the final report for this project. 

    

70

Page 74: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

PROJECT:  Purchase Vanpool Vehicles  

SCOPE:  The vanpool procurement for conversion vehicles allowed for multiple awards based on van types. Therefore, this procurement was awarded to two vendors, each with a five year indefinite delivery/indefinite quantity contract. They have a combined minimum of 70 and maximum of 525 conversion vans. The contracts are for purchasing of 7, 10, and 14 passenger conversion vans. 

BUDGET:  $20,011,499; on budget. 

SCHEDULE:  On schedule; estimated completion June 2020. 

HIGHLIGHTS:  To date a total of 219 conversion vans have been ordered, including three additional new orders totaling 94 conversion vans.  All orders were placed in December 2017, March 2018, and April 2018.  Deliveries for all 94 will begin by July 2018 and are expected to be completed by September 2018. 

   

 

PROJECT:  Purchase Vanpool Minivans  

SCOPE:  A 5‐year contract with a third vendor was awarded on October 9, 2016 for the vanpool procurement of minivans with a minimum quantity of 124 and maximum of 421.  On October 26, 2016, FTA granted Pace a Buy America Waiver for domestic content and final assembly requirement for up to 188 Dodge Caravans. 

BUDGET:  $11,076,439; on budget. 

SCHEDULE:  On schedule; estimated completion October 2021. 

HIGHLIGHTS:  To date a total of 208 minivans have been ordered and delivered.  Pace is in the process of initiating a new order for an additional 122 minivans.   This new order of 122 was processed in May 2018 but is pending Purchasing action.  Pace will be reviewing the order of 122 minivans and may need to submit for another federal Buy America Waiver.  Research activity has begun to determine the type of Buy America waiver needed.  This complication will take time and delay this order from being finalized. 

  

71

Page 75: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Pace  PROJECT BUDGET BY PERCENTAGE OF ENTIRE BUDGET AND PERCENTAGE OF PROJECTS  

BUDGET  QUANTITY % OF BUDGET  % OF PROJECTS

Projects over $500,000,000  0  0  0 

Projects between $250,000,000 and $499,999,999  0  0  0 

Projects between $100,000,000 and $249,999,999  2  76.2  33.3 

Projects between $50,000,000 and $99,999,999  0  0  0 

Projects between $20,000,000 and $49,999,999  3  20.9  50.0 

Projects between $10,000,000 and $19,999,999  1  2.9  16.7 

 

0

20

40

60

80

100

500M+ 250M‐499M 100M‐249M 50M‐99M 20M‐49M 10M‐19M

% of Budget

% of Projects

  

72

Page 76: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

    

 REPORT ON PROJECT MANAGEMENT OVERSIGHT – JUNE 2018 

  

Pace  

TYPE OF PROJECT  QUANTITY TOTAL BUDGET

Construction  0 $0

Maintenance / Rehabilitation  0 $0

Procurement  6 $377,947,033

 

100%

PERCENTAGE OF TOTAL PROJECTS

Construction

Maint./Rehab.

Procurement

 

100%

PERCENTAGE OF TOTAL BUDGET

Construction

Maint./Rehab.

Procurement

   

 

73

Page 77: Project June 2018 Management Oversight · 2018-07-19 · The majority of state funded projects are within budget, one project is under budget. 80% of the state funded projects are

175 West Jackson Boulevard, Suite 1650 Chicago, Illinois 60604

Phone: 312-913-3200

RTAChicago.org

Follow us on

Chicago Transit Authority567 W. Lake St.Chicago, IL 60661888-968-7282www.transitchicago.com

Metra547 W. Jackson Blvd.Chicago, IL 60661312-322-6777www.metrarail.com

Pace550 W. Algonquin Rd.Arlington Heights, IL 60005847-364-7223www.pacebus.com