Upload
duongdang
View
214
Download
0
Embed Size (px)
Citation preview
NaturaFill © 2013, TEAM 13, CALVIN COLLEGE Last Updated: 4/1/2014
PROJECT BRIEF NaturaFill: Fuel for Thought
Team 13 Karl Bratt Jonathan Haines Brandon Koster
Project Brief Last Updated: 4/1/2014
1
1 Project Overview
1.1 Problem Statement There is scarcity in the residential applications for compressed natural gas (CNG) in the United States
transportation landscape. Currently, only 605 public CNG refueling stations exist, compared to the
168,000 gasoline stations.1 In response, a few small companies, such as BRC Fuelmaker, have
developed home refueling units that run on electricity and connect to existing natural gas lines.2
Unfortunately, these models begin at $5,000 before installation.3
1.2 Project Objective The objective of NaturaFill is to design, build, and test a natural gas home refueling appliance that is
lower cost and more reliable than the appliances currently on the market.
1.3 Design Requirements
1.4 Team Organization:
Karl Bratt 1.4.1.1
Bratt is a Mechanical concentration engineering student also in pursuit of a business
minor. Bratt is primarily responsible for the organizational components of the
project. This includes, but is not limited to, the planning and scheduling of team
meetings, review and on-time delivery of project deliverables, and work breakdown
of tasks among the team member using Microsoft Project.
Jonathan Haines 1.4.1.2
Haines is a Mechanical concentration engineering student also in pursuit of a
mathematics minor. Haines’s experience with thermodynamics and manufacturing,
along with his knowledge of Autodesk CFD simulator, has been valuable in the design
and testing of the system. In addition, Haines has used his experience in
manufacturing to machine the system’s metal components and parts
Brandon Koster 1.4.1.3
Koster is a Mechanical concentration engineering student also in pursuit of a
business minor. Koster has significant background knowledge in the industry, which
has served to connect the team with companies and individuals able to provide
guidance and support throughout the project. In addition, his experience with
compression systems has helped in performing design calculations, ordering parts,
and forecasting the overall cost of the system.
1 http://www.afdc.energy.gov/fuels/natural_gas_locations.html
2 http://www.cngnow.com/vehicles/refueling/Pages/refueling-at-home.aspx
3 Jimmy Moerdyk, Moerdyk Energy Inc. (MEI), 9/27/13, 9:00AM
Project Brief Last Updated: 4/1/2014
2
2 Design Decisions
2.1 Hydraulic System A hydraulic system will be used to convert electrical energy into mechanical work that will drive the
pistons a therefore compress the gas. An overview of the proposed hydraulic system is shown below
in Figure 1: Hydraulic System Schematic. The images describe current
Project Brief Last Updated: 4/1/2014
3
2.2 Natural Gas System
Small Parker Hydraulic Cylinder
(testing only). Full-scale
cylinder still to be purchased.
Ashcroft 5000 psi
Pressure Gauge(s)
D03 Solenoid-Operated
Hydraulic Control Valve
5000 psi Tubing w/ 3/8”
SAE Straight Thread Fittings
1.25 Gallon Hydraulic Pump & Reservoir
Monarch Hydraulics Inc.
Figure 1: Hydraulic System Schematic
Project Brief Last Updated: 4/1/2014
4
The natural gas system will move the gas from a residential natural gas line, through each of the two
compression cylinders, and ultimately into the tank of a natural gas vehicle. It also is designed to
prevent backflow at every possible point and monitor the thermodynamic state of the natural gas
using thermocouples, pressure gages, and a pressure transducer. A schematic of the natural gas
system is shown below in Figure 2: Natural Gas System Schematic.
2.3 Sealing System
2.3.1 PTFE Coated Cylinder Walls PTFE (Teflon) coated cylinder walls will provide an excellent low-friction surface for the piston rings to
move along. This coating will protect against provide an excellent low-friction seal and protection
against excessive wear on both the cylinder wall surface and the rings. This coating is most common
in oil-less compressor designs.
2.3.2 PTFE Seal Rings Two PTFE (Teflon) seal will be used to seal the gas
inside the compression chamber. These rings
provide an excellent, low fiction seal. These rings
will be located to the inside of the two rider rings,
as displayed below in Figure 37.
2.3.3 PTFE Rider Rings Two PTFE (Teflon) rings will be used to stabilize
the piston as it moves up and down the cylinder
walls. These rings will be located to the outside of
the two seal rings, as displayed below in Figure
37. Figure 2. Sealing System Schematic
Project Brief Last Updated: 4/1/2014
5
Figure 3: Control System
2.4 Control System The controls for the system will be managed by
National Instruments: LabVIEW 8.5. Using
National Instruments input, output, thermocouple,
power supply, and Ethernet modules, the team
will monitor the temperatures and pressures at
each stage in the system and program emergency
stops if either exceed safe operating conditions
(see Figure 4: Control System). Work is currently
underway to have the control system programmed
and operating by mid-March.
3 Significant Issues
3.1 Loss of an Electrical Engineer At the beginning of February 2014, our team was notified that our fourth member, the only electrical
engineer in the group, was dropping out of engineering. This was shocking news. Discussions arose
over which of us three mechanical engineers would take his place. Having purchased a Raspberry Pi
development board, the team began researching how to program it. We realized this was beyond our
technical knowledge and began looking into other control module alternatives.
3.2 Lead Time on Seals Finding appropriate seals for the compression cylinders has been a challenge. Recognizing that they
must withstand high pressures and temperatures, there are few suitable models available. After
reaching out to Zatkoff Seals & Packaging in Grand Rapids, the team eventually found a Parker seal
that that would satisfy the system’s requirements. Unfortunately, on February 26, the team was
informed of a 6-8 week lead-time on such seals. This development has modified the team’s original
plan of constructing a fully-functional preliminary prototype before the final. In addition, it moved up
the final design decision deadline so that the final prototype seals may be ordered in the next few
days.
Project Brief Last Updated: 4/1/2014
6
Figure 4: CFD Pressure Distribution
Figure 6: Preliminary Prototype CAD Model
4 Current Status
4.1 Modeling In order to determine the size requirements for the
natural gas compression cylinders along with the tubing
connecting the cylinders, the team has used a
combination of Engineering Equation Solver (EES) and
Autodesk CFD simulator, as shown in Figure 5. These
have enabled the team to monitor the pressure and
temperature distribution throughout the compression
cylinders.
In addition, the team has modeled the preliminary
prototype in Autodesk Inventor and Algor to understand
the system’s stress distribution during operation (See
Figure 6). The final has been shown in the Appendix.
4.2 Prototype Construction of the final prototype is underway.
Currently, the team has obtained 140 pounds of plate
steel, of which the manifolds are being machined out of.
In addition, the team plans to have the hydraulic system working with a test hydraulic cylinder by
March 10.
4.3 Controls As shown in Figure 4, the team is currently programming a VI in LabVIEW 8.5 with the appropriate
input and output controls necessary for the final prototype. Once the pressure transducers arrive, the
team will be able to begin testing the VI for functionality.
4.4 Budget