36
Language: English Original: French PROJECT : Rural Infrastructure Development Support Project (PADIR). COUNTRY : DEMOCRATIC REPUBLIC OF CONGO PROJECT APPRAISAL REPORT Date : August 2011 Appraisal Team Project Team Team Leader M. AYACHI 3380 OSAN.3 Team Members K. LAAJILI 2760 OSAN.3 T. AHMED 3028 OSAN.3 Rita N. BA 2590 OSAN.2 B.D KADIATA, 6333 CDFO V. LOSSOMBOT 6335 CDFO C. AHOSSI 6811 CMFO P. MARINI 6334 CDFO Médo LO Consultant Division Manager J. M. MWANGI 2375 OSAN.3 (Ag.) Sector Director A.BEILEH 2039 OSAN Regional Director M. KANGA 2251 ORCE Peer Reviewers M. MOUMNI, Chief Water and Sanitation Engineer 2344 OWAS.2 H. FELLAH, Agronomist 2262 OSAN.2 M. RAFAA, Agricultural Economist 2252 OSAN.1 A. DIAW, CPO 2580 ORCE N. KACEM, Agricultural Economist 2489 OSAN.2 V. GUINEO, Rural Development Specialist 6205 TDFO AFRICAN DEVELOPMENT FUND

PROJECT APPRAISAL REPORT - African … : Rural Infrastructure ... DEMOCRATIC REPUBLIC OF CONGO PROJECT APPRAISAL REPORT Date : August 2011 ... will also facilitate the marketing …

  • Upload
    dinhnga

  • View
    214

  • Download
    0

Embed Size (px)

Citation preview

Language: English

Original: French

PROJECT : Rural Infrastructure Development Support Project

(PADIR).

COUNTRY : DEMOCRATIC REPUBLIC OF CONGO

PROJECT APPRAISAL REPORT Date : August 2011

Appraisal Team

Project Team

Team Leader M. AYACHI 3380 OSAN.3

Team

Members

K. LAAJILI 2760 OSAN.3 T. AHMED 3028 OSAN.3 Rita N. BA 2590 OSAN.2

B.D KADIATA, 6333 CDFO

V. LOSSOMBOT 6335 CDFO

C. AHOSSI 6811 CMFO

P. MARINI 6334 CDFO

Médo LO Consultant

Division Manager J. M. MWANGI 2375 OSAN.3

(Ag.) Sector Director A.BEILEH 2039 OSAN

Regional Director M. KANGA 2251 ORCE

Peer Reviewers

M. MOUMNI, Chief Water and Sanitation Engineer 2344 OWAS.2

H. FELLAH, Agronomist 2262 OSAN.2

M. RAFAA, Agricultural Economist 2252 OSAN.1

A. DIAW, CPO 2580 ORCE

N. KACEM, Agricultural Economist 2489 OSAN.2

V. GUINEO, Rural Development Specialist 6205 TDFO

AFRICAN DEVELOPMENT FUND

TABLE OF CONTENTS Page

Currency Equivalents, Fiscal Year, Weights and Measures, Acronyms and Abbreviations, Project Information

Sheet, Project Summary, Logical Framework, Implementation Schedule, Report and Recommendation to Board of

Directors i-vii

I. STRATEGIC ORIENTATION AND JUSTIFICATION

1.1 Project Linkages with Country Strategy and Objectives ....................................................... 1

1.2 Justification for Bank Involvement ....................................................................................... 1

1.3 Aid Coordination ................................................................................................................... 2

II. PROJECT DESCRIPTION

2.1 Project Components ............................................................................................................... 3

2.2 Technical Solutions Retained and Alternatives Explored ..................................................... 4

2.3 Project Type ........................................................................................................................... 5

2.4 Project Cost and Financing Arrangements ............................................................................ 6

2.5 Project Area and Beneficiaries .............................................................................................. 7

2.6 Participatory Approach to Project Identification, Design and Implementation ................. 8

2.7 Bank Group Experience and Lessons Reflected in Project Design ....................................... 9

2.8 Key Performance Indicators ................................................................................................ 10

III. PROJECT FEASIBILITY

3.1 Economic and Financial Performance ................................................................................. 10

3.2 Environmental and Social Impacts ...................................................................................... 10

IV. IMPLEMENTATION

4.1 Implementation Arrangements ............................................................................................ 12

4.2 Monitoring ........................................................................................................................... 15

4.3 Governance .......................................................................................................................... 16

4.4 Sustainability ...................................................................................................................... 16

4.5 Risk Management ................................................................................................................ 17

4.6 Knowledge Building ............................................................................................................ 17

V. LEGAL FRAMEWORK

5.1 Legal Instrument .................................................................................................................. 18

5.2 Conditions for Bank Intervention ........................................................................................ 18

5.3 Compliance with Bank Policies ........................................................................................... 18

VI. RECOMMENDATION…………………………………………………… 18 Appendix I: Country’s Comparative Socio-Economic Indicators 1

Appendix II: Table of ADB Portfolio in the Country 1

Appendix III: Major Related Projects Financed by Other Development Partners 1

Appendix IV: Map of Country and Project Area 1

Appendix V: Summary of Procurement Arrangements (in UA Thousand) 1

Appendix VI: Project Cost by Expenditure Category and Sources of Finance 1

Appendix VII: Examples of Physical Outputs of PRESAR and PARSAR 4

Volume II: Technical Annexes

A : Country’s Development Agenda, Sector Overview and Donor Support

B : Backup of Key Arguments of Report

B1 : Main Commitments

B2 : Detailed Project Costs

B3 : Implementation Arrangements

B4 : Financial Management and Disbursement Arrangements

B5 : Procurement Arrangements

B.6 : Audit Arrangements

B.7 : Economic and Financial Analysis

B8 : Environmental and Social Analysis

B9 : Project Preparation and Supervision

Currency Equivalents

(August 2011)

UA 1 = CDF 1461.29

UA 1 = US$ 1.5990

UA 1 = €1.1073

Fiscal Year

1 January - 31 December

Weights and Measures

1 metric tonne = 2204 pounds

1 kilogramme (kg) = 2.20 pounds

1 metre (m) = 3.28 feet

1 millimetre (mm) = 0.03937 inch

1 kilometre (Km) = 0.62 mile

1 hectare (ha) = 2.471 acres

Acronyms and Abbreviations

AFD French Development Agency MITPR Ministry of Infrastructure, Public Works and Reconstruction

ASS Agriculture Sector Study

BD Board of Directors NA Not Applicable

BD Bidding Documents No. Number

BTC Belgian Technical Cooperation NCB National Competitive Bidding

CARG Rural Agricultural Management Council NGO Non-Governmental Organization

CDF Congolese Franc NPV Net Present Value

CDFO DRC Regional Office PADIR Rural Infrastructure Development Support Project

CO2 Carbon Dioxide PARSAR Agriculture and Rural Sector Rehabilitation Support Project

CPSS Provincial Coordination and Monitoring Committee

DRC Democratic Republic of Congo PCR Project Completion Report

DVDA Agricultural Feeder Roads Directorate PGAI Aid and Investment Management Platform

DWS Drinking Water Supply PMU Project Management Unit

ERR Economic Rate of Return PNIA National Agricultural Investment Programme

ESMP Environmental and Social Management Plan PP Procurement Plan

EU European Union PRESAR Agricultural and Rural Sector Rehabilitation Project

F.E. Foreign Exchange PRGSP Poverty Reduction and Growth Strategy Paper

FONER National Road Maintenance Fund QCBS Quality-and Cost-Based Selection

GDP Gross Domestic Product

GEEC Congo Environmental Study Group SG Secretary-General

GEF Global Environment Facility SME Small and Medium-size Enterprises

ICB International Competitive Bidding SNHR National Rural Water Service

IEC Information, Education and Communication SNSA National Agricultural Statistics Service

L.C. Local Currency SSADR Agriculture and Rural Development Sector Strategy

LCS Least Cost Selection STD Sexually Transmitted Diseases

LEA Local Executing Agency T Tonne

LI Labour Intensive TA Technical Assistance

LRMC Local Road Maintenance Committee TG Thematic Group

MDG Millennium Development Goals TOR Terms of Reference

MFI Microfinance Institution UA Unit of Account

MGFE Ministry of Gender, Family and Children UC Unit Cost

MINAGRI Ministry of Agriculture USD United States Dollar

MINDR Ministry of Rural Development WB World Bank

iii

Project Information Sheet

Client Information

DONEE : DEMOCRATIC REPUBLIC OF CONGO

EXECUTING AGENCY : General Secretariat of the Ministry of Rural

Development Boulevard 30 juin Kinshasa / Gombe –

DRC

Financing Plan

Source Amount (UA) Instrument

ADF 49.46 million Grant

Government/Beneficiaries 1.41 million

TOTAL COST 50.87 million

Key ADB Financial Information_______________________________

Grant Currency Unit of Account (UA)

Type of Interest Not applicable

NPV (Baseline Scenario) US$15.68 million

ERR (Baseline Scenario) 18 %

Timeframe – Main Milestones (expected) _______________________________

Concept Note Approval July 2011

Project Approval November 2011

Effectiveness April 2012

Physical Completion Date of Activities June 2017

Deadline for Last Disbursement December 2017

iv

PROJECT SUMMARY

1. Project Overview: The Rural Infrastructure Development Support Project (PADIR) is

located in the south of DRC, in the provinces of Bas-Congo, Bandundu, Kasaï-Occidental,

Kasaï-Oriental and Katanga. These provinces have a population of about 36,000,000

inhabitants, 60% of whom are poor and live on less than one dollar per day. In addition to their

poverty, these provinces were selected for their high agricultural potential and constitute the

main sources of food supply to DRC’s major towns and cities. The major expected outputs

are: (i) the rehabilitation of 1,905 km of rural roads, 9 landing stages, 212 drinking water

points, 77 boreholes, 18 drinking water supply networks, 40 markets, 30 warehouses and 16

slaughtering areas; (ii) support to 10 Vocational Training Centres, 10 Social Reintegration

Centres (60% for women), 10 workshops for craftsmen and 10 workshops for processing

associations (60% for women); and (iii) training and retraining for 300 technical officers and

professionals and 500 infrastructure management committees and associations totalling 5000

members. The project cost is estimated at UA 50.87 million, and the project will be

implemented over a five-year period as from April 2012.

2. The main beneficiaries will be producer and trader associations, in particular, women

who are extremely active in markets, vocational training and social reintegration centres for

vulnerable youths, craftsmen, SMEs and rural development technical services. 6000

unemployed young men and women will benefit from vocational training to facilitate their

integration into working life. The estimated number of direct and indirect beneficiaries is

about 6 million inhabitants (16% of the population of the provinces concerned) 53% of whom

are women. The project will ensure the systematic representation of women and youths in all

the consultation and decision-making frameworks so that they can fully defend their interests.

3. The main benefits generated by the project outputs will be as follows: (i) the creation

of the equivalent of 23,300 permanent jobs, (ii) increase in traders’ monthly incomes from

US$150 to 250; and (iii) the marketing of additional agricultural production of 2.28 million

tonnes (T) of food crops and 20,000 T of meat and fish by facilitating the marketing of

produce and reducing post-harvest losses. To ensure ownership of outputs and their

sustainability, the priority activities have been identified, and their implementation and

management carried out in consultation with future users through workshops organized by the

different project preparation missions with the participation of all the stakeholders (farmers,

traders, technical services, provincial authorities, NGOs, SMEs, etc.). This approach has helped

to define specific responsibilities for future management of project outputs. Thus, the markets,

slaughtering areas and warehouses will be managed and maintained by Management

Committees to be trained under the project. The revenue generated by these facilities will

easily cover their maintenance. Rural road maintenance will be carried out by road menders

with support from the National Road Maintenance Fund (FONER). The PADIR infrastructure

management modalities have already been tested under the implementation of the Agricultural

and Rural Sector Rehabilitation Support Project (PARSAR) and the Agriculture and Rural

Sector Rehabilitation Project (PRESAR), financed by the Bank in DRC.

4. Needs Assessment: Despite the high potential and socio-economic importance of the

Congolese agriculture and rural sector, its productivity has fallen sharply, mainly due to the

remoteness of the production areas and the shortcomings of central government supervisory

services. Only 10% of the 87,000 km agricultural feeder road network is accessible.

Agricultural produce marketing and conservation infrastructure is in an advanced state of

degradation. Farmer technical supervisory services are virtually non-existent on the ground.

This situation has created a paradox in rural areas: no buyers for agricultural produce in the

v

fields, yet shortage of food products in the towns. The food deficit is estimated at over 30%.

The agriculture and rural sector investment gap was estimated at US$ 945.4 million (UA 590

million) for the 2011-2020 decade. In order to improve the population’s well-being in relation

to the Millennium Development Goals (MDGs), in particular the reduction of extreme poverty

and hunger, DRC is preparing a second generation Poverty Reduction and Growth Strategy

Paper (PRGSP) for the 2011-2015 period. Its objectives include agriculture sector recovery

and food security through improved access and marketing infrastructure, employment

promotion and human resource capacity building. PADIR activities (rural roads, markets,

drinking water, capacity building, and vocational training) will fully support the achievement

of these objectives.

5. Value Added for the Bank: The improvement of rural infrastructure and capacity

building for operators are consistent with the Bank’s objectives in its RMC development

mission and its 2010-2014 Agriculture Sector Strategy. In the project provinces, PADIR will

fulfill the development strategies identified under the 2008 ADF-financed Congolese

Agriculture Sector Study (ASS). It will also consolidate the rural development activities

financed by the Bank under the ongoing PARSAR and PRESAR. These projects have made

significant progress in rural infrastructure (1,500 km of rural roads with 200 road structures,

200 drinking water springs, 40 rural markets, and 60 storage warehouses), the distribution of

improved seeds (50,000 tonnes) and capacity building (training for 2,000 senior staff and

employees and 800 production and marketing, MFI and handicraft associations and groupings

totalling 30,000 members). These outputs have undoubtedly helped the population in their

daily lives, but fall short of the needs. Examples of the physical outputs of these projects are

presented in the attached Appendix VII and the Technical Annexes in Volume II. The PADIR

will also facilitate the marketing of agricultural produce from these projects and boost synergy

with the other projects in the region. With this operation, the Bank will also strengthen its

comparative advantage in the infrastructure sector, where it is closely involved at sub-regional

level, which gives it a lead role in the response to the country’s food crisis.

6. Knowledge Management: PADIR will, through the establishment of an adequate

monitoring-evaluation system, generate relevant information on the impact of rural

infrastructure on reducing travel time and transport costs, as well as on food product prices

and on poverty reduction in general, and youth employment, in particular. The experimental

introduction of solar energy at market and local community level will build knowledge of this

technology with a view to envisaging its expansion and reducing oil consumption and CO2

emissions. It will also provide an alternative solution in areas without electricity. The support

for Vocational Training and Social Reintegration Centres will help to enhance the technical

level of youths, who will be the drivers of the new technologies in their environment.

Sensitization on information, education and communication (IEC) themes for women and

youths will gradually help to improve their living conditions and their level of knowledge of

their environment. All this information will enable the Bank to learn lessons for future

operations, and to position itself as a key actor in development support.

VII. Results-Based Logical Framework Country and Project Name: Democratic Republic of Congo – Rural Infrastructure Development Support Project (PADIR)

Project Goal: Food security improvement and poverty reduction through the rehabilitation of rural infrastructure

RESULTS CHAIN

PERFORMANCE INDICATORS MEANS OF VERIFICATION RISKS AND MITIGATION MEASURES

Indicators (including CSIs) Baseline Situation Target

IMP

AC

T Contribution to improved food security

and poverty reduction for the Congolese

population

- Food requirement coverage rate

- Poverty rate

70% at present

60% at present

90% in 2017

40% in 2017

Sources

MINAGRI, Ministry of Trade and

FAO Statistical Reports

EF

FE

CT

S

1. Increase in marketed agricultural

produce

2. Improved living standards of the

beneficiaries

1.1 Marketed agricultural produce

2.1 Number of jobs created

2.2 Traders’ monthly incomes;

2.3 Population supplied with drinking

water

1.1Marketed produce:

20 million T of which

1% meat and fish

2.1 N.A

2.2- US$150/month

2.3 N.A

1.1 Marketed produce: 21 million T in 2014 and 22.3 million

T in 2017, of which 1% meat and fish

2.1 Equivalent of 10,000 permanent jobs created in 2014 and

a total of 23,300 by 2017, comprising 53% for women.

2.2 Traders’ incomes up to US$ 180 per month in 2014 and

US$250 in 2017.

2.3 At least 60,000 additional people in 2014 and 130,000 in

2017 comprising 53% women

- Annual Statistical Reports of

MINAGRI, the Ministry of Trade

and FAO - Quarterly Project and Mid-Term

Impact Reports and PCRs

Methods :

-Statistics, specific studies and

annual surveys

Risks

- Lack of qualified technical control services

and operational infrastructure maintenance and

management committees

Mitigation Measures

- Capacity building for the technical services

involved, and training of infrastructure

management services

OU

TC

OM

ES

1. Infrastructure Rehabilitation

1.1 Rural roads motorable, and landing

stages accessible

1.2 Agricultural produce markets and

slaughtering areas operational

1.3 Urban areas supplied with drinking

water

1.4 Agricultural Training and Social

Reintegration Centres and handicraft

mechanical and processing workshops

rehabilitated

1.5 Premises of rural development

services rehabilitated

2. Capacity Building

2.1 Agricultural Training and Social

Reintegration Centres, and Handicraft

Mechanical and Processing Workshops

operational

2.2 Farmer, MFI and SME organizations

and infrastructure management

committees set up.

2.3 Premises of rural development

services operational.

2.4 Rural development senior staff

qualified

2.5 IEC Programme (STD, gender

equality, nutrition and gender promotion)

carried out

3. Project Organization and

Management

3.1 Satisfactory Project Management

1.1 Length of rural roads and number

of additional landing stages

rehabilitated

1.2 Number of additional markets and

slaughtering areas constructed

1.3 Additional water points established

1.4 Number of additional premises

rehabilitated

1.5 Number of additional premises

rehabilitated and equipped

2.1.1 Number of centres equipped

2.1.2 Number of youths trained

2.2.1 Number of structures supported

and people trained

2.3 Number of premises equipped

2.4 Number of professionals

trained/retrained

2.5 Number of people affected

3.1.1- 4 Activity and audit reports

produced; 3.1.2 Monitoring system

operational; 3.1.3- % disbursed

1.1 N.A

1.2 Idem

1.1 - 800 km of rural roads and 4 landing stages in 2014 and

1,905 km and 9 landing stages in 2017.

1.2 - 25 markets,7 slaughtering areas and 15 warehouses in

2014 and 40, 16 and 30 respectively in 2017

1.3 Development of 100 springs, 35 boreholes and 10 DWS

networks in 2014 and 212, 77 and 18 respectively in 2017.

1.4.1 – 5 Vocational Training and 5 Social Integration

Centres in 2014, with 60% for women and 10 respectively in

2017; 1.4.2 –10 workshops and premises for handicraft and

processing associations in 2014 and 20 in 2017, with 60% for

women.

1.5– 8 premises for technical support services in 2014.

2.1.1 – 5 Vocational Training and 5 Social Reintegration

Centres in 2014 and 10 and 10 respectively in 2017, with

60% for women; 2.1.2 – 10 workshops for handicraft and

processing associations in 2014 and 20 in 2017, with 60% for

women; 2.1.3 – 3000 youths in 2014 and 6000 by 2017

(comprising 60% girls)

2.2.1 – 250 structures in 2014 and 500 in 2017 with 5000

members in 2017, comprising at least 50% women. 2.2.2 – 5

MFIs in 2014 and 10 in 2017

2.3 – 8 premises in 2014.

2.4 – 200 senior staff in 2014 and 300 in 2017, comprising

53% women

2.5 - 5000 people in 2014 and 10,000 in 2017, comprising

60% women

3.1.1 Four status reports and one audit per year

3.1.2 One monitoring-evaluation report/year; 3.1.3

Disbursement rate 20%/yr (50% in 2014 and 100% in 2017)

1.1 – Quarterly Project Activity,

Supervision, CDFO monitoring and

PCR Mid-Term Review Reports

- Idem

- Idem

- Idem

Risks

- Limited working resources for technical

control services involved

- Weak capacity of SMEs for works

- Lack of familiarity with financial

management and procurement rules of

procedure.

Mitigation Measures

- Training and equipping of services

- Training and retraining of SME managers

- Organization and training of Infrastructure

Management and Maintenance Committees

- Mobilization of expertise in International

Financial Management, and

- in procurement and organization of training

sessions by the Bank in these areas.

KE

Y A

CT

IVIT

IES

BY

CO

MP

ON

EN

T

1. Rehabilitation of Rural Infrastructure

Preparation of BDs and launching of competitive bidding for studies and works contractors

Implementation and monitoring of infrastructure rehabilitation (rural roads, markets, slaughtering areas, water points, etc.)

2. Institutional Capacity Building for Beneficiaries

Preparation of TORs for training sessions and BDs for different items of equipment for the structures concerned. Conduct of training and procurement of equipment (furniture,

computer and specific equipment)

3. Project Organization and Management

Equipment and training of project staff; establishment of the monitoring-evaluation system and preparation of the different reports (baseline, mid-term and final situation)

Preparation of annual audits and PCR

RESOURCES (in million UA)

ADB Loan : 49.46

Government/Beneficiaries : 1.41

Component 1 : 35.67

Component 2 : 8.85

Component 3 : 6.35

Total : 50.87

vii

PROJECT IMPLEMENTATION SCHEDULE

2011 2012 2013 2014 2015 2016 2017

Quarter (Q) Q

3

Q

4

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q

1

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3

Q4

1. Board Presentation/Grant Approval

2. Publication of General Procurement Notice

3. Signature and Effectiveness of Grant Agreement

4. Fulfillment of Conditions Precedent to First

Disbursement

5. Project Launching Mission

6. Preparation of TA Procedure Manuals and TORs and

BDs for Procurement

7. Procurement of PMU Equipment and Recruitment of TA

8. Recruitment of Local Executing Agencies (LEA)

9. Preparation of Engineering Designs

10. Recruitment of Works Contractors and Inspection Firms

11. Implementation and Inspection of Infrastructure Works

12. Rehabilitation and Equipping of Partners’ Premises

13. Training/Retraining of Senior Staff and Members of

Associations

14. Implementation of IEC Programme

15. Organization and Sensitization of Management Committees

16. Management of Environmental and Social Aspects

17. Project Coordination and Management

18. Mid-Term Review

19. Project Audit

20. Project Completion Report

Report and Recommendation of Bank Group Management to the Board of Directors

concerning the proposed grant to DRC to finance the RURAL INFRASTRUCTURE

DEVELOPMENT SUPPORT PROJECT

Management hereby submits this report and recommendations concerning a proposal for a grant of

UA 49.46 million to DRC to finance the Rural Infrastructure Development Support Project.

I. STRATEGIC ORIENTATION AND JUSTIFICATION

1.1 Project Linkages with the Country Strategy and Objectives

1.1.1 In order to improve the population’s well-being in line with the Millennium

Development Goals (MDGs), in particular, a reduction in extreme hunger and poverty, DRC is

preparing a Poverty Reduction and Growth Strategy Paper (PRGSP) for the 2011-2015 period.

It is underpinned by four pillars, two of which form the strategic anchor for this project: Pillar

II ‘Diversify the Economy, Accelerate Growth and Promote Employment’ comprising the

following six development focus areas: (i) agriculture sector recovery and food security; (ii)

basic infrastructure development; (iii) support for the production system (Focus Area 3), (iv)

improved marketing; (v) promotion of employment; and (vi) regional planning. All these areas

closely affect the agriculture and rural sector; and Pillar III ‘Facilitate Access to Basic Social

Services and Build Human Capital’ comprising the establishment of drinking water and

sanitation facilities, STD prevention, and training and retraining of human resources. These

different focus areas are included in DRC’s Agriculture and Rural Development Sector

Strategy for 2011-2015, which centres on the rehabilitation of agricultural feeder roads and

marketing infrastructure, overhaul of the production system and capacity building for support

services and rural communities. The PADIR actions support the national strategy through their

direct impact on food security and poverty reduction.

1.2 Justification for Bank Involvement

1.2.1 The Bank’s 2008-2012 RBCSP is focused on two pillars: (i) Support for Good

Governance and (ii) Promotion of Pro-Poor Growth. These Pillars concern the agriculture and

rural sector through human resource capacity building (Focus Area 3 of Pillar 1), and

improvement of agriculture and rural sector infrastructure (Focus Area 4 of Pillar II). More

specifically, Focus Area 4 targets the opening up of rural areas by improving agricultural feeder

roads and marketing channels, as well as capacity building for operators. This operation is also

consistent with the Bank’s Medium-Term Strategy (2008-2012) and its Agriculture Sector

Strategy (2010-2014), the common objectives of which are poverty reduction and food security

particularly through improved marketing and transport facilities, enhanced agricultural

productivity, support for the private sector and capacity building for the various partners. The

PADIR activities (rural roads, markets, warehouses, slaughtering areas, drinking water,

capacity building and vocational training) are fully in keeping with both the Bank and

Government objectives. In addition, the PADIR drinking water component will expand Bank

support in this area, which is currently confined to urban and peri-urban areas, to the rural areas

of the Congo.

1.2.2 The Congolese agriculture and rural sector has enormous possibilities of growth and

occupies a dominant position in the country’s economy. However, it is experiencing a sharp

decline in productivity, largely due to the dilapidated state of rural infrastructure and the

shortcomings of the central government support services. Less than 10% of the 87,000 km of

rural roads are suitable for motor vehicles and are virtually inaccessible in the rainy season.

Marketing infrastructure is extremely deficient. Apart from the ongoing project intervention

areas, technical supervisory services are practically non-existent. The food deficit is estimated

at over 30% and poverty affects 60% of the population. Against this backdrop, the DRC has

asked its partners, including the Bank, to support it in addressing this situation.

2

1.2.3 The PADIR is in line with the priorities of the Bank, which makes infrastructure the

engine of Africa’s economic development, and will further strengthen its comparative

advantage in the rural infrastructure sector where it is closely involved at sub-regional level.

Under the Bank’s strategy, infrastructure is also the engine of economic development for the

RMCs. Rural and agricultural infrastructure is part of this orientation. The ADF-financed

Agriculture Sector Study resulted in Provincial Development Master Plans (PDDP) and priority

projects for each region. These PDDPs are focused on opening up the agricultural areas,

rehabilitating the production system and providing support to the technical services concerned.

They served as basis for formulating this project, and will help the country negotiate other

financial support operations for the sector. Vocational training for the youths will promote

income-generating activities, which will have positive spinoff effects on employment that the

country greatly needs.

1.2.4 The PADIR will also help consolidate the achievements of Bank-financed rural

development projects in DRC, through the PARSAR and PRESAR projects, by facilitating

transportation of agricultural output from these project areas and expanding the intervention

areas to more specifically target the most vulnerable segments of the populations. The

achievements of these projects are significant, especially in the area of rural

infrastructure (1,500 km of rural roads with 200 road structures, 200 drinking water springs, 40

rural markets, 60 storage warehouses, and 50,000 tonnes of improved seeds) and capacity

building for technical services and community organizations (2,000 senior staff and 800

associations and groupings of producers, traders, MFIs and handicraft totaling over 3,000

members). These achievements have undoubtedly greatly assisted the populations in their daily

lives, but fall short of expectations. Examples of the project outputs are presented in the

attached Appendix VII and the Annex of Volume II.

1.3. Aid Coordination

1.3.1 In the wake of the Aid Effectiveness Forum, ‘Kinshasa Agenda’, the DRC established

mechanisms to ensure closer monitoring of development policies and programmes. Thus, an

Aid and Investment Management Platform (PGAI) was set up at the Ministry of Planning, and

20 thematic groups (TG) were organized. The Belgian Cooperation coordinates TG 15, which

covers agriculture and rural development. The CDFO represents the Bank in the TGs. These

TGs constitute a harmonized consultative framework for operations in the DRC. However, the

frequency of meetings and their coordination should be improved for there is no strict meeting

schedule. Consultation with the different TFPs, at the different stages of project formulation,

has helped offset these shortcomings. This project was presented to, and discussed with TG15

at its 9 June 2010 meeting. Furthermore, the steering mechanism set up by the Government in

2010, namely the National Steering Committee and Provincial Coordination and Monitoring

Committees for agriculture and rural sector projects and programmes will improve aid

coordination on the ground in future.

1.3.2 The ADF intervention will complement the other TFP operations. Indeed, the TFP

actions aim to increase agricultural production. The access and marketing infrastructure

planned under PADIR will facilitate transportation of the produce generated by their

interventions. Furthermore, several TFP projects are located in the north of the country. By

intervening in the south, the Bank will contribute to the harmonization of development country-

wide. The Belgian Cooperation is financing a project to develop agriculture, and open up

certain provinces covered by the PDIR. Consultative meetings on the intervention approach and

geographical location have been organized with this partner to harmonize operations.

Furthermore, in the selection of PADIR rural roads, links with accessible national roads or

those undergoing rehabilitation with AFD, ADF, EU and Chinese Cooperation support, were

taken into account. Relevant lessons were learnt from the TFP experiences, in particular, the

advanced state of dilapidation of infrastructure, which remains the prime concern. The desire to

3

remove this bottleneck is shared by all. In addition, sustainability of the infrastructure will

depend on the type of basic works carried out. Feeder roads rehabilitated by LI works are not

very durable because of the fragility of their environment. The current level of agriculture

sector aid is presented in the following table.

Sector or Sub-Sector* Importance

GDP Exports Labour

Agriculture and Rural Development, including forests [40%] [10%] [70%]

Stakeholders – Annual Public Expenditure (2005-2010 averages) *

Government (million US$) Donors Amount (millions US$) [%]

ADF 100 41

IFAD/OPEC 50 20

8 (2% of total expenditure) European Union 20 8

BTC 27 11

WB 20 8

USAID 15 6

Others (FAO, UNDP, GEF,

Nordic Fund) 15 6

TOTAL 247 100

Level of Aid Coordination

Existence of thematic working groups [Yes, set up under the PGAI]

Existence of an overall sector programme [No, a PNIA under preparation]

ADB role in aid coordination [M]

L : Leader ; M : member (not lead) : none: no involvement

(*) Sources: PRSP II, Agriculture and Rural Development Sector Strategy, March 2010, African Agriculture Development

Programme, February 2011, and list of Ministry of Planning projects.

II. PROJECT DESCRIPTION

2.1. Project Components

The following main actions have been retained in order to achieve the project objectives:

Components UA

Million

Description

I.

Rehabilitation

of Rural

Infrastructure

35.67

Rehabilitation of access routes: 1,905 km of rural roads and 9 landing stages will

be rehabilitated to open up the production areas.

Rehabilitation and development of product marketing and storage infrastructure:

40 rural markets, 16 slaughtering areas and 30 warehouses.

Improvement of drinking water points: 212 springs, 77 boreholes, and 18 drinking

water supply (DWS) networks.

Rehabilitation of Premises of Associations, Training Centres and Technical

Services: 10 workshops for artisans (mechanical, carpentry, crafts) ; 10

agricultural produce processing workshops ; 10 vocational training

centres/institutes (agriculture, livestock, fisheries, animal draught, etc.), 10 social

integration centres, 10 MFI and 8 premises for technical support services

(1/province, 1 in Kalemie in Katanga and 2 in Kinshasa (MINDR and

MINAGRI).

II. Capacity

Building

8.85 Building the capacities of structures concerned with the following activities:

Specific training for 500 agro-processing associations of women, artisans,

LRMCs, market management committees and PMEs totalling 5,000

members (comprising 60% women), in : trading, product processing,

mechanics, carpentry, market management, and feeder road maintenance.

Training and retraining of 300 senior staff from the technical ministries

(participatory planning, project management, agricultural statistics, works

supervision, IT, gender concept and environmental management).

Support for furniture, computer equipment and specific equipment for 10

workshops for artisans, 10 workshops for processing associations, and 10

vocational training and 10 social reintegration centres, 10 MFI and 8

administrative buildings with about 100 offices for the technical services.

IEC programme on gender equality, human rights, gender promotion,

4

prevention of HIV/AIDS, malaria control and nutrition based on locally

available foodstuffs, etc. This programme will affect 10,000 people 60% of

whom are women.

III- Project

Management

6.35

Management and coordination of activities and maintenance of project

assets;

Establishment of monitoring and evaluation system, and preparation of the

ESMP.

Audit of accounts and mid-term and final reviews.

2.2. Technical Solutions Retained and Alternatives Explored

2.2.1. The selection of activities and their technical design was based on participatory

consultations grouping together the grassroots communities, local authorities and government

technical services. These consultations helped to identify priority actions in line with the

population’s needs. Another factor taken into account was the need to harmonize PADIR

activities with the PRGSP and Provincial Development Plans. The technical design drew on the

lessons learnt from similar experiences in the region. Two aspects were prioritized: the

sustainability of outputs and the need to ensure their ownership by the beneficiaries. The issue

of sustainability, particularly of rural road management and maintenance, represents a critical

concern in project design, which created two integrated components concerning ‘physical

infrastructure’ and ‘capacity building for users’. This issue is also a cause for concern for the

Government, which has established a highways and road maintenance fund, regulated rainy

season roadblocks, and organized maintenance brigades.

2.2.2 The experience gained from the PRESAR and PARSAR projects has underscored the

importance of works quality at start-up, followed by the sensitization and organization of users.

Indeed, structures built of durable materials, which comply with quality standards, require little

maintenance and are more resistant to environmental uncertainties. Thus, the mechanical

compaction works on rural roads using adequate materials and the construction of reinforced

concrete bridges and culverts were preferred to manual works and masonry structures which

did not prove to be durable. The involvement of grassroots communities and local authorities in

subsequent management and maintenance improves their sustainability and enhances their

impact. The construction of all project infrastructures will be preceded by a written undertaking

signed by the beneficiaries to ensure the management and maintenance of future structures. The

aspect relating to the integration and complementarity of project activities in the area with those

of the Bank and other TFPs (road projects, drinking water projects, agricultural projects, etc.)

was also a decision-making factor for the PADIR in order to avoid overlapping and to facilitate

coordination of outputs on the ground. All the planned rural roads will connect with a year-

round, all-weather road, or one whose improvement is already scheduled.

5

Table 2.2: Alternative Solutions Explored and Reasons for their Rejection

Alternative Brief Description Reasons for Rejection

Intervene on all

degraded access and

marketing

infrastructure in the

provinces concerned or

else prioritize high

potential production

areas?

Most of the rural infrastructure is in

very poor condition and its complete

rehabilitation requires significant

resources which exceed those of this

project. Intervention over a broader area with

the available resources cannot resolve of

problem of access for resources would be

spread too thinly. Integrated and integral development is

the most suitable. Consequently,

intervention on priority sites is

necessary.

PADIR activities will primarily be located in

the high production potential basins of

each province:

Investments will be more effective for the

supply of local markets with agricultural

produce and the revival of the resultant

trade flows.

The concentration of activities on well-

defined sites will foster complementarity

of actions and enhance their impact on the

ground.

The rural roads must connect with the

provincial and national roads and TFP

road programmes in the region.

Distribute project

activities over all the

provinces as requested

by the Government, or

confine them to a few

provinces where the

Bank has a

comparative

advantage?

Some TFPs (IFAD, Belgian

Cooperation and the World Bank) mainly

intervene in the central and northern

provinces (Equateur, Orientale,

Maniema), and in rural Kinshasa. To

avoid overlapping, it is necessary to

intervene in other areas. ADF is

intervening in 5 southern DRC provinces

which have high untapped potential due

to their remoteness. The need for

development actions there is great, and

has not yet been met.

PADIR interventions have been confined to the

southern provinces for the following

reasons:

Need to consolidate the achievements of

the Bank’s interventions in the region in

order to improve their sustainability and

prevent the spreading of investments too

thinly country-wide.

The Bank has an advantage in this region:

knowledge of the area. Existence of

project management structures, the

capacity of which has been built up by the

Bank, which will facilitate

implementation of the new project.

Rehabilitate more rural

roads using LI works

with a low unit cost or

else opt for mechanical

and manual works, and

durable structures

(reinforced concrete)

on a limited network?

LI works are usually carried out on

roads where degradation is not serious

for these are light manual works.

For its part, machine use entails more

significant compaction works with hard

structures which combine labour and

mechanization. Infrastructure built in this

way is much more resistant.

Manual rehabilitation of rural feeder is not

suitable for DRC because:

Their state of degradation is extremely

advanced;

The physical environment (sandy soil and

heavy rainfall) fosters erosion and manual

works have shown their limitations;

Mechanized works are more durable and

easy to maintain. Even though they are

more costly, their cost can be offset by the

maintenance savings to be made.

2.3. Project Type

PADIR is an autonomous operation in the form of an investment project grant. The institutional

capacities of the sector Ministries require further strengthening and no single sector programme

has been adopted by all the donors. The Ministry of Agriculture is preparing a National

Agricultural Investment Programme (PNIA). Currently, most donor interventions in the sector

are made through this type of operation (investment projects). The project grant is, for the

moment, the most suitable instrument, since part of the funds will be used to build the

capacities of the services of the Ministries of Rural Development, Agriculture, Gender and

Environment at the decentralized level. The planned capacity building includes the following

themes: (i) formulation of policies and monitoring of their implementation; (ii) project

monitoring and evaluation; (iii) compilation of reliable statistics; and (iv) strategic and

organizational studies. This strengthening will help the country prepare its sector programme in

future.

2.4. Project Cost and Financing Arrangements

2.4.1 The total project cost, net of taxes and customs duties, is estimated at UA 50.869

million, i.e. US$ 81.428 million. This comprises UA 28.893 million in foreign exchange (US$

6

46.251 million) and UA 21.976 million in local currency (US$ 35.178 million). Average

provisions of 6% and 7% of the base cost have been made for physical and financial

contingencies respectively. The summary of the project cost estimates by component and by

expenditure category is presented in Tables 2.3 and 2.4 below.

Table 2.3

Summary Cost Estimates by Component

COMPONENTS In US$ Thousand In UA Thousand % %

F.E. L.C. TOTAL F.E. L.C. TOTAL F.E.

Base

Cost

Comp : Rural Infrastructure Rehabilitation 31.706 19.022 50.729 19.807 11.883 31.690 63 62

Comp : Capacity Building 8.342 4.449 12.791 5.211 2.779 7.991 65 16

Comp : Project Management and Coordination 2.051 8.101 10.152 1.282 5.061 6.343 20 12

Total Base Cost 42.100 31.573 73.672 26.300 19.724 46.024 57 90

Physical Contingencies 1.496 2.084 3.580 934 1.302 2.236 42 4 Financial Contingencies 2.655 1.521 4.176 1.659 950 2.609 64 5

Total Cost 46.251 35.178 81.428 28.893 21.976 50.869 57 100

Table 2.4

Summary Cost Estimates by Expenditure Category

Expenditure

Categories In US$ Thousand In UA Thousand % %

F.E. L.C. TOTAL F.E. L.C. TOTAL F.E. Base Cost

Works 25.613 17.501 43.114 16.000 10.933 26.934 59 53

Goods 5.428 1.517 6.945 3.391 948 4.338 78 9

Services 7.955 1.648 9.603 4.969 1.030 5.999 83 12

Operating costs 3.104 10.906 14.010 1.939 6.813 8.752 22 17

Base Cost 42.100 31.573 73.672 26.300 19.724 46.024 57 90

Physical Contingencies 1.496 2.084 3.580 934 1.302 2.236 42 4

Financial Contingencies 2.655 1.521 4.176 1.659 950 2.609 64 5

Grand Total 46.251 35.178 81.428 28.893 21.976 50.869 57 100

Table 2.5

Summary Project Cost Estimates by Source of Finance

Sources of Finance In US$ Thousand In UA Thousand %

F.E. L.C. TOTAL F.E. L.C. TOTAL

ADF 46.251 32.921 79.171 28.893 20.566 49.459 97

GOVERNMENT 0 2.257 2.257 0 1.410 1.410 3

TOTAL 46.251 35.178 81.428 28.893 21.976 50.869 100

2.4.2 The project will be financed by ADF, the Government and beneficiary structures. The

ADF grant, in an amount of UA 49.46 million, which represents 97% of the total project cost,

net of tax, will be used to finance all the goods, works and services as well as operation of the

PMU, including bank charges. The Government and beneficiaries will contribute UA 1.41

million (US$ 2.257 million to the financing of the project costs; i.e. about 3% of the project

cost. The contribution of beneficiaries concerns maintenance of their micro-projects

rehabilitated by PADIR (2% of the project cost). The Government’s contribution consists in

providing offices for the project (1% of the cost). The ADF financing in local currency will

support the Government’s efforts for the most vulnerable segments of the population so as to

reduce poverty. Expenditures relating to the various project components will be made in

conformity with the schedule in Table 2.6 below. The breakdown of project cost by category

and source of finance is presented in the attached Appendix VI. Details of the physical

quantities and project costs are summarized in the list of goods and services in Annex B2 of

Volume II.

7

Table 2.6

Expenditure Schedule by Component in UA Thousand

COMPONENTS 2012 2013 2014 2015 2016 Total

Component A: Rural Infrastructure Rehabilitation 200 5.008 9.994 11.639 4.850 31.691

Component B: Capacity Building 1.237 1.579 2.066 2.358 750 7.991

Component C: Management and Coordination 1.033 1.326 1.327 1.327 1.329 6.342

Total Base Cost 2.470 7.912 13.387 15.324 6.929 46.024

Physical Contingencies 79 369 688 798 303 2.236

Financial Contingencies 92 430 802 931 354 2.609

Total Cost 2.641 8.711 14.878 17.053 7.586 50.869

% 5% 17% 29% 34% 15% 100%

2.4.3 The national counterpart contribution was assessed in compliance with the Bank’s

Policy on Expenditure Eligibility as follows:

(i) the country’s commitment to implement its overall development programme:

Since July 2009, DRC has been implementing an economic programme backed

by the IMF Extended Credit Facility and aligned on the PRGSP, the objective of

which is to consolidate macroeconomic stability and growth. The conclusions of

the third review of this Programme in December 2010 confirm the shift towards

growth-bearing policies likely to reduce poverty;

(ii) the financing allocated by the country to sectors targeted by Bank assistance:

The agriculture and rural development sector budget is rising sharply. Since the

EHIPC Initiative completion point was reached in July 2010, the priority sector

budget, including agriculture, has risen considerably. In 2011, the budget of this

sector will increase by 10% in comparison to 2010. Selected as one of the

performance criteria of the IMF-backed economic programme, this trend will be

maintained in the short- and medium-term;

(iii) the country’s budget situation and debt level: Implementation of budgetary

policy was satisfactory in 2010. The domestic budget balance, which previously

posted a deficit, now shows a slight surplus (0.2% of GDP). The 2011 Budget is

being executed on the basis of a balanced annual cash flow plan, agreed upon

with the IMF on the expectation of current revenue of CDF 3,006.3 billion

against expenditure of CDF 3,172.5 billion. The negative balance is covered by

EU budget, the sale of a telecommunications license, and use of the banking

system. However, resource projections at end 2011 show a shortfall mainly due

to the failure to adjust petrol prices in efforts to protect the population’s

purchasing power, especially in an electoral period. DRC has received

considerable external debt relief. In 2010, the NPV of the external debt/exports

ratio was brought down from 182.5% to 57.5%. However, the country remains

vulnerable to a drop in exports and higher borrowing costs. The Government has

undertaken to pursue reforms aimed at promoting export growth and limiting

external borrowing to highly concessional resources.

2.5. Project Area and Beneficiaries

2.5.1 The PADIR activities are located in the south of DRC, in the provinces of Bas-Congo,

Bandundu, Kasaï-Occidental, Kasaï-Oriental and Katanga. These provinces cover 1,174,000

km2 and have a population of about 36 million inhabitants. It is a region with high agricultural

potential. It produces half of DRC’s food crops and supplies agricultural products to the main

Congolese towns and cities (Bandundu, Kananga, Lubumbashi, Mbuji-Mayi, Kinshasa and

8

Matadi). The resident population is 75% rural, with agriculture as the principal activity. Poverty

affects 60% of the inhabitants. The project intervenes directly in high production potential

basins to facilitate the transportation of products and supply of the local market. It will also

help consolidate and complement the outputs of the PARSAR and PRESAR projects in these

provinces. The sites directly concerned with the PADIR interventions comprise the project

areas of PARSAR and PRESAR activities, mainly towards the north of the provinces currently

affected.

2.5.2 The main beneficiaries are producer and trader associations, particularly women who

are highly active in trading, artisanal workers, SMEs, Vocational Training and Social

Reinsertion Centres, and the technical services of Ministries responsible for Rural

Development. Local authorities and private operators will also benefit from the basic

infrastructure and revival of economic activities. Thus, the number of direct and indirect

beneficiaries is estimated at 6 million inhabitants (about 17% of the population of the regions

concerned). The vulnerable groups are poor farmers, orphans, the handicapped and war victims.

Most of them live in semi-urban and rural areas, with little access to the formal employment

market and social infrastructure (reinsertion and vocational training centres, drinking water,

etc.). Their harsh living conditions justify the need to adopt special measures to save them from

social exclusion.

2.5.3. Capacity building, in the form of training, as well as office automation and specific

equipment, will benefit the Government technical services responsible for rural development.

These are : (i) MINDR (General Secretariat-SG, Agricultural Feeder Roads Department -

DVDA, National Rural Water Service - SNHR, National Animal Traction Service-SENATRA,

National Rural Housing Service-SENAHRU), National Cooperatives and Farmer Organization

Service-SNCOOP, National Rural Information Service – SNIR, National Appropriate

Technologies-SENATEC and Studies and Planning Department-DEP); (ii) MINAGRI (GS,

Agricultural Centres, community farms, National Agricultural Statistics Service-SNSA, and

(iii) the Ministry of Planning (Productive Services Directorate). Local authorities and other

partners involved in project implementation (Local Road Maintenance Committees –LRMC,

Market and Slaughterhouse Management Committees, associations of hauliers, traders,

artisans, Rural Agricultural Management Council-CARG, Small and Medium Enterprises

{SME) for works, Micro-Finance Institutions (MFI) are also among the beneficiaries of

capacity building. In all, 500 structures with about 5000 members will benefit from capacity

building. Furthermore, 300 senior staff from the sector ministries will benefit from capacity

building to enable them to provide high quality technical support to farmers and to the

implementation of PADIR activities.

2.5.4 The above-mentioned activities will generate the equivalent of 23,300 permanent jobs,

increase the incomes of traders retained as typical beneficiaries, from US$ 150 to US$ 250 per

month and the marketing of additional 2.3 million tonnes of agricultural production by

facilitating the transportation of produce and reducing post-harvest losses. In addition,

vocational training will lead to the integration of 6,000 young men and women into working

life.

2.6. Participatory Approach to Project Identification, Design and Implementation

2.6.1 During project formulation, all the stakeholders were closely involved, in consultation

workshops and working meetings, in the discussion of priority needs and provincial

development plans. Subsequently, depending on the available resources, meetings were held to

summarize and harmonize points of view with Government technical services, private

operators, NGOs and representatives of the beneficiaries. Concerns were raised about opening

up the production basins, the supply of drinking water and the rehabilitation of markets to

facilitate produce marketing. As regards the administration, the main concern was to train

9

personnel and provide them with working resources. In particular, the rural roads selected were

those that connected with the provincial or national road network and were prioritized by the

Government for annual DVDA maintenance. Field-level proposals were discussed and

validated with the Central Ministries. This approach helped to identify the most profitable

investments and clearly define responsibilities for the management and maintenance of

infrastructure to be handed over to the beneficiaries in order to ensure sustainability.

Consultations with the beneficiaries, private operators and TFPs will continue during project

implementation in order to enquire about the impacts and, if required, refocus the activities to

meet expectations. Information workshops will be organized by supervision missions from the

headquarters and CDFO to enhance project impacts.

2.7. Bank Group Experience and Lessons Reflected in Project Design

2.7.1 The Bank’s agriculture and rural sector portfolio comprises three national operations

(PARSAR, PRESAR, and an Agriculture Sector Study) and 2 regional projects (Lake

Tanganyika Integrated Management Support Project and the Congo Basin Ecosystems

Conservation Support Project) all of which are active. Their performance is fairly satisfactory.

Since there are no PCRs concerning this sector, the formulation and implementation

mechanism for the PADIR were based on lessons learnt from the DRC Portfolio Review and

the Mid-Term Reviews of the PARSAR and PRESAR projects carried out between 2008 and

2010, as well as the conclusions of other TFP monitoring reports. The main lessons concern the

positive impacts of rural roads on access to rural areas and the revival of marketing. Integration

of activities in the same project area has had a greater impact on development than thinly

spread interventions. Post-harvest losses have dropped significantly and agricultural produce

easily reaches the market. Food importing provinces have offset their deficit and have achieved

surpluses, which they export to the other provinces. Capacity building for technical senior staff

has resulted in improvement in the quality of their service delivery. The shortcomings concern

weaknesses of some service providers and the poor quality of manually implemented rural road

works, which impacted negatively on their durability. In addition, delays in the fulfillment of

the conditions precedent and difficulties in mobilizing counterpart funds have extended project

implementation periods.

2.7.2 The above-mentioned lessons were reflected in the PDIR design. Thus, to address the

challenges of opening up rural areas, priority has been given to access and marketing

infrastructure (69% of the project cost, excluding the cost of infrastructure-related capacity

building). The option taken to mechanize certain rural road works and train maintenance

committees and involve them in management will improve their sustainability. Capacity

building for SMEs will improve their qualifications, as well as the quality of their work.

Renewal of the contracts of structures with sound experience in the management of ongoing

projects (PRESAR and PARSAR) to assume responsibility for PADIR will speed up

implementation. The counterpart funds and conditions precedent are reduced to a strict

minimum. The conditions precedent are limited to two, which can be easily fulfilled. The

Government will pay the salaries of local staff and provide premises. Furthermore, preparation

of the procurement plan prior to project start-up and the Bank’s policy to delegate authority to

approve documents to the regional offices as well as RMC capacity building will help to ensure

the effectiveness of its assistance.

2.8 Key Performance Indicators

2.8.1 The outcomes identified in the logical framework and in the above paragraphs 2.5.3 to

2.5.5 were retained as project performance indicators. These will be measured during the first

year through the conduct, by a consultant, of a survey to determine the project baseline

situation. The related information will be incorporated in the monitoring-evaluation system to

be established for PADIR. Special emphasis will be placed on the monitoring of socio-

10

economic impacts on the target groups, disaggregated by women and youths (vocational

training, social reintegration, jobs created). Project management-related indicators will comply

with the Bank’s institutional indicators. These concern: (i) the period not exceeding 180 days

allowed for signing the grant agreement; (ii) the average disbursement rate of at least 18%/yr.;

and (iii) the project performance indicator (PI) based on14 indicators rated from 0 to 3 during

supervision missions.

2.8.2 The gathering and assessment of physical output indicators and the volume of produce

marketed will be based on the status and audit reports, the statistics of the Ministries of

Agriculture, Rural Development, Trade and the Economy, as well as on FAO food security

reports. An impact assessment will be conducted at mid-term and another on project

completion. These assessments will be conducted with Bank financing by specialized

consultants. The information will be gender disaggregated and analyzed in relation to the

expected project outputs and impacts. The related reports will be made available to the Project

Coordination, the Steering Committee, and the Bank supervision and mid-term review missions

for relevant lessons to be drawn. If required, these bodies will consult each other and refocus

the project in order to enhance its effectiveness. Monitoring of the indicators will also be used

by Congolese and Bank officials to improve the design of future projects.

III PROJECT FEASIBILITY

3.1. Economic and Financial Performance

An additional 2.3 million tonnes of food crops, meat and fish will be marketed at full

development, representing about 20% of current production of the project area. This will result

from access and marketing infrastructure (markets and others) which will facilitate the

transportation of food products, reduce post-harvest losses estimated at over 30% in DRC, and

encourage farmers to produce more. The monthly incomes of traders will rise from US$150 to

250. The net present value generated by the project is US$ 15.68 million. Other non-

quantifiable benefits will also be produced, for example travel time savings and impact on the

productivity of structures benefiting from capacity building. The project economic rate of

return (ERR) is estimated at 18%.

3.2 Environmental and Social Impacts

3.2.1 Environment: The PADIR is classified in Environmental Category II. Its activities,

focused on the rehabilitation of existing infrastructure and partner capacity building, should not

pose any threat to the environment. The major negative impacts concern quarries, dust and

health risks related mainly to waste around markets and slaughtering areas. Measures have been

recommended for the rehabilitation of quarries, reforestation to replace the cut vegetation and

create a dust filter, maintenance of markets, and STD knowledge building. There will be

positive social impacts: contribution to improved living conditions of beneficiaries through

higher incomes, improved transport conditions for produce and better hygiene in markets,

facilitation of access to drinking water, and capacity building for stakeholders.

3.2.2 Regarding the risks related to rural road works, the mitigation measures will be

incorporated into contractors’ terms of reference, especially the spraying of rural road work

sites with water to reduce dust, the planting of vegetation on embankments, the cleaning of

markets and sensitization of communities and training in waste management. Concerning the

other risks, IEC activities will be carried out to build the beneficiaries’ knowledge of

environmental conservation and STDs. Information campaigns on malaria control, hygiene and

nutrition will be conducted to raise the population’s awareness of these aspects. All the

environmental measures are detailed in the Environmental and Social Management Plan

(ESMP), the implementation of which will be supervised by the Government. The cost of

strengthening the environmental aspects is estimated at US$ 3.20 million.

11

3.2.3 Climate Change: Climate change, which is a global phenomenon (drought,

proliferation of epidemics, floods, etc.), constitutes a major problem for the survival of all

species, as well as the implementation of development works and must be taken into account.

The PDIR will not have any negative impacts on climate change. The traffic flow in the project

area will be improved. CO2 emissions of transport vehicles into the atmosphere will be reduced

due to shorter travel times. The rehabilitation of markets will reduce loading and unloading

times for transport vehicles. Though limited, these impacts will help to reduce the greenhouse

effect. The gradual introduction of solar power for motor pumps and lighting for markets and

training centres will also help to limit CO2 emissions. Reforestation of borrow areas for

materials and feeder road edges will help to control the effects of global warming. As regards

markets and slaughtering areas, shady areas will be created with perennial plants. All this

vegetation restoration represents an estimated 500 ha of green space.

3.2.4 Gender: The DR C has ratified many international and regional agreements relating to

human and, in particular, women’s rights, including the Convention on the Elimination of all

Forms of Discrimination against Women ratified in 2005. The Congolese Constitution prohibits

all forms of discrimination against women and guarantees the mainstreaming of gender issues

into all the development sectors (Article 14 of the DRC Constitution). However, customary

law, and the implementation of some legal texts do not comply with the principles of men and

women’s rights. The impunity observed for violence against women is not conducive to the

eradication of this phenomenon. Though women are responsible for virtually all petty trading

activities and most of the agricultural and stockbreeding work (60% of the agricultural work

force), they are little involved in resource management and control.

3.2.5 The project activities are intended to improve the living conditions and well-being of

all vulnerable people. The sensitization campaign on gender equality, the rights of both sexes

and conflict resolution, planned under the project in its IEC programme, will help to correct the

imbalance in this area. The project will also build the capacities of the decentralized services of

the Ministry of Women’s Affairs to help them to disseminate gender promotion texts, and

enhance supervision and assistance to women in their daily activities. Over 500 associations of

traders, agro-processing operators, and artisans totaling about 5,000 members, at least 60% of

whom are women, will be organized and trained to help them resume their economic activities.

Currently, women traders experience difficulties in obtaining agricultural supplies. With the

improvement of rural roads, mechanized transport will develop and their ordeal will be eased.

Concurrently, 10 MFIs will be supported to assist the various developers in financing their

activities.

3.2.6 Building the capacities of structures dominated by women will provide them with

opportunities to create income-generating activities and organize and consolidate their status

within rural communities usually dominated by men. The project will provide direct support to

women’s and youth associations through the transfer of agricultural product processing

technologies and the provision of kits of materials specific to each type of activity. The project

will ensure that the majority of the beneficiaries of the project outputs will be women in

accordance with the logical framework indicators. This aspect will appear in support

agreements for the different partners prior to commitment of the project investments. The

estimated cost for gender promotion and implementation of the activities specifically targeted

by this aspect is UA 6 million (training, specific equipment, rehabilitation of markets where

women are very active, organization of sensitization campaigns, teaching aids, etc.)

3.2.7 Social: The project will implement an IEC programme and will involve field staff of

the Ministries of Gender, Health and Environment in its implementation. This programme will

improve the level of knowledge on gender equality, decision-making participation, human

rights, gender promotion, health, particularly protection against HIV/AIDS and malaria, and

balanced nutrition based on locally sourced foodstuffs. Ten thousand (10,000) people will

12

benefit from this programme. The improved agricultural product marketing conditions and

hygiene of the food product points of sale will also help to reduce water-borne and food–related

diseases. The project will have significant positive social impacts, especially on vocational

training, trades and employment. It will equip the social reintegration and vocational training

centres, which will help to improve employment in the provinces and the living standards of the

population in general.

3.2.8 Involuntary Resettlement: The PADIR does not involve the displacement of any people

from the project area or their resettlement.

IV. IMPLEMENTATION

4.1 Implementation Arrangements

4.1.1 Executing Agency: The project will be implemented under the oversight of the

Ministry of Rural Development and attached to the General Secretariat for Rural Development.

Its implementation mechanism will rely on structures from the PARSAR and PRESAR. These

structures have acquired sound experience that will speed up project implementation. They also

have branches in the provinces concerned. A PADIR Management Unit (PMU) will be set up

based on these structures, and will comprise the National Coordination and five branches (one

per province). The composition of the PMU will be adapted to the specificity of the project

which is focused on infrastructure and capacity building, and the staff will be selected on a

performance basis. The Branches will comprise: (i) a branch manager; (ii) an infrastructure

expert; (iii) a gender specialist; (iv) a capacity-building specialist; (v) a monitoring and

evaluation specialist; (vi) an environmental specialist; (vii) an accountant; (viii) a cashier, (ix) a

secretary; (x) four drivers; (xi) two security guards; and (xii) a messenger. The Katanga

Province branch will be located in Kalemie, closer to the project intervention sites. A liaison

office will be established in Lubumbashi, the region’s capital, to be able to follow up files with

the administration. It will comprise a liaison officer and a driver.

4.1.2 The National Coordination (CN) will comprise: (i) a national coordinator; (ii) an

internal auditor; (iii) a capacity building specialist, (iv) a monitoring-evaluation specialist; (v)

a national procurement counterpart; (vi) an administrative assistant; (vii) a computer

programmer; (viii) a secretary; (ix) three drivers; (x) two security guards; and (xi) a messenger.

PADIR staff will be seconded to the project by the Government. The appointment of new staff

to the PMU, apart from the existing PARSAR and PRESAR staff, must have the prior approval

of ADB on the basis of 3 CVs per post. A Ministerial Order will be signed to set up the PADIR

structures. This document will constitute a condition precedent to first disbursement of the

grant resources. In order to build the PMU’s implementation capacity, there will be local

technical assistance (TA) in accounting (54 months), procurement (18 months) and financial

management (24 months). The procurement specialist will support the PMU in the preparation

of BDs, bid analysis, contract monitoring and the training of project staff. On completion of

his/her assignment, the national counterpart will take over. The financial management expert

will assist in the establishment and testing of the financial management manual and will train

the local staff. The CN will sign a performance contract, renewable every two years, which will

be binding on all the project staff. This contract forms part of the other conditions to be fulfilled

no later than six months after the first disbursement.

4.1.3 The PMU will see to the preparation of activity programmes and annual budgets, the

preparation of payment requests, monitoring of project activities, consolidation of accounts and

preparation of status reports. Implementation of the actual activities will be awarded to service

providers on the basis of competition. The decentralized services of the Ministries concerned

(Gender, Environment etc.) will be closely involved in works control and acceptance. The

different training courses will be carried out contractually by a specialized structure to be

13

recruited. It will be responsible for organizing all the training courses and related logistics. This

approach has been successfully tested under the PRESAR and PARSAR. Local executing

agencies (LEA) will also be responsible for the implementation of rural infrastructure and

sensitization and training programmes for the infrastructure management and maintenance

committees.

4.1.4 Institutional Arrangements: PADIR’s institutional mechanism is consistent with the

one established by the Government for the monitoring and coordination of development

projects. It concerns the National Steering Committee (SC) and Provincial Coordination and

Monitoring Committees (CPCS) for agriculture and rural sector programmes. The composition

of these Committees and their operating modalities are defined in their acts of establishment

(refer to Ministerial Orders No. 027 and 028 of 18 May 2011). These committees are composed

of representatives of the technical ministries involved in rural development, local communities

and TFPs (refer to Annex B.3 of Volume II). The SC, chaired by the MINDR Secretary-

General, ensures its consistency with the Government’s strategy. It coordinates TFP

interventions and approves the project annual work programmes and budgets. It meets on a

quarterly basis. The CPCS is responsible for monitoring project progress and the quality of its

outputs and coordination with other operators in the field. It is responsible for overall project

control, field supervision and ensures its consistency with the Provincial Development Plans. It

is chaired by the provincial rural development inspector in each province, and meets every two

months. The CPCS prepares the project monitoring reports and minutes of coordination

meetings for submission to the SC for information and consideration.

4.1.5 Successful project implementation will depend on smooth coordination with the

provincial authorities and decentralized structures concerned. The technical services of

MINDR, MINAGRI, and the other ministries concerned (gender, the environment,

infrastructure, etc.) at the central and decentralized levels must be closely involved in the

programming, control and acceptance of the planned works.

4.1.6 Procurement Arrangements: Procurement of goods, works and services financed on

ADF resources will be made in compliance with the Bank’s Rules of Procedure for the

Procurement of Goods and Works or, as the case may be, its Rules of Procedure for the Use of

Consultants using Bank standard bidding documents.

4.1.7 Procurement Plan (PP): The country will submit to the Bank for approval, prior to the

negotiations, the draft PP prepared during the project appraisal mission. The Bank will consider

the PP with a view to ensuring its compliance with the Grant Agreement as well as with the

relevant Rules. This PP will cover an initial period of at least 18 months, and will be updated

annually by the Donee, or as required. Any proposal for its revision will be submitted to ADF

for prior approval.

4.1.8 Financial Management and Disbursement: The existing financial management

mechanism for the PRESAR and PARSAR projects, which already have experience in project

administrative, financial and accounting management, will be adapted to the context of the new

project. In order to strengthen the mechanism, the team responsible for financial management

will be reinforced by the creation of positions for an internal auditor at the National

Coordination and a cashier for each branch, in addition to the accounting assistant. This

organization of the team takes into account both the scope of the project, which comprises five

provinces, and the lessons learnt from the two previous projects. The advantage of the proposed

structure is that it will make the mechanism efficient and operational at start-up, and result in

savings in terms of costs and time.

4.1.9 The National Coordination will be responsible for the administrative, financial and

accounting management of all the project activities, including those implemented by other

14

entities. To that end, it will ensure: (i) the assignment of personnel; (ii) the preparation of

procedure manuals; (iii) the strengthening of the internal control procedure; (iv) the

procurement of software and its configuration on the basis of the specific project data; (v) the

training of financial staff in the Bank’s financial management procedures; and (v) the

recruitment of the external auditor. An action plan to improve the project’s financial

management is presented in Annex B4 of Volume II.

4.1.10 Funds will be disbursed in accordance with the Bank’s rules and procedures. A

special account will be opened in a bank acceptable to ADF for the payment of the grant

resources. Disbursements will be made in accordance with the project expenditure schedule

and the list of goods and services. The first disbursement will be released following grant

effectiveness and fulfillment of the conditions precedent to first disbursement. Two

disbursement methods are proposed: (i) the special account method for the project management

team’s operating expenses and for payments of amounts not exceeding UA 20,000. The funds

will be disbursed in the form of advances to be paid into the special account opened for that

purpose. Replenishments will be made upon justification of the use of at least 50% of the

previous disbursement and the totality of previous disbursements, if required; and (ii) the

method of direct payment to service providers for amounts exceeding the equivalent of UA

20,000.

4.1.11 Audit: The project financial statements, the special account and certified expenditure

statements will be audited annually by an independent external audit firm acceptable to the

Bank. The auditor’s terms of reference (TOR) must be prepared on the basis of the Bank’s

standard model. They must specify that that the audit will be conducted in compliance with

international audit standards. The terms of reference will cover in detail the financial,

management, internal control and procurement aspects. They will specify that the auditor will

prepare, in addition to the audit report, a letter to Management in which it will present its

comments, identify any weaknesses observed and bring to the borrower’s attention any issues it

may consider relevant. The auditor must have access to all the legal documents, exchanges of

correspondence and other project-related information. The annual audit reports will be

submitted to the Bank not later than six months following the closure of each financial year,

otherwise disbursements will be suspended.

4.2 Monitoring

4.2.1 Project implementation will cover a period of five years, from April 2012 to March

2017. The PMU will assume the main responsibility for internal monitoring of the activities

and their impacts. It will prepare, in conformity with the Bank’s recommended format,

quarterly and annual reports focused on the monitoring of the project logical framework

indicators. The existing monitoring-evaluation system adopted by the PARSAR and PRESAR

structures, which will be used in implementing the PADIR, will help considerably in this area.

It is computerized and has information collection and processing tools to monitor the physical

outputs, disbursements and gender disaggregated socio-economic and environmental impacts.

This system will be adapted to the PADIR, and the staff in charge will be retrained from project

start-up. This will ensure the timely detection of any weakness and finding of adequate

solutions.

4.2.2 External monitoring will be conducted at the central level by the MINDR General

Secretariat and the SC, and at provincial level, by the CPCS, which is chaired by the provincial

rural development inspector. These structures are required to review project progress, assess its

performance and the quality of its management and outputs, and, if necessary, refocus it in

consultation with the Bank. Compliance of the ESMP implementation will be supervised by the

Congo Environmental Study Group (GEEC), which is the technical organ of the Ministry of

Environment responsible for ensuring compliance with environmental and social standards in

project implementation. A focal point of the Ministry of Environment in Kinshasa will be

involved in the coordination and consolidation of the ESMP across the entire project.

15

4.2.3 Specific surveys will be conducted at project start-up to establish a baseline situation,

at mid-term and on completion to assess the impacts in relation to the performance indicators

mentioned in the appraisal report. The Bank’s monitoring will be conducted through

supervision missions and the project technical and financial audits. The Bank’s Human

Development Division (OSHD.1) will be involved in these missions to assess the socio-

economic and poverty reduction impacts. CDFO will contribute through its close monitoring of

the project by providing the required assistance in the areas of technical monitoring,

procurement, disbursement and financial management. The project implementation schedule

presented at the beginning of the report can be summarized as follows:

Timeframe Milestones: Monitoring/Feedback Loop Activities:

November 2011 Grant Approval ADF

1st quarter (Qr) 2012 Signature and Effectiveness Government/ADF

1st Qr 2012 Establishment of PMU Government

3rd Qr 2012 Recruitment of TA PMU/monitored by GS MINDR and ADF

3rd Qr 2012-end 2015 Preparation of Engineering Designs PMU /LEA/monitored by GS MINDR and ADF

4th Qr 2012-2nd

Qr 2013 Equipment of PMU & partners PMU /LEA/monitored by GS MINDR and ADF

4th Qr 2012 Recruitment of LEA PMU/monitored by GS MINDR and ADF

4th Qr 2012-1st Qr. 2016 Recruitment of Contractors PMU /LEA/monitored by GS MINDR and ADF

2nd Qr 2013-end 2016 Training of Partners PMU/LEA/monitored by GS MINDR and ADF

2nd Qr 2013-end 2016 Works Implementation and Control PMU/LEA/monitored by GS MINDR and ADF

4th Qr 2014 Project Mid-Term Review PMU /Government/ADF

2nd Qr 2017 Project Completion Report PMU/Government/ADF

4.3 Governance

4.3.1 The socio-political conflicts of the nineties, characterized by the suspension of

investments and shortcomings of the development support services, especially affected the

human resources of the administration and rural and agricultural infrastructure. This situation

impacted negatively on the rational management of the country’s resources, project

implementation and financial resource management. With support from the different partners,

a more conducive business climate, in general, and better organization of the agriculture and

rural sector, in particular, have been perceptible since 2010. This trend is confirmed by the

following facts: (i) enactment, in February 2010, of the law authorizing ratification of the

Treaty establishing the Organization for the Harmonization of Business Law in Africa

(OHADA); (ii) US$ 12.3 billion debt relief for DR Congo comprising US$11.1 billion under

the EHIPC Initiative and US$ 1.3 billion under the Multilateral Debt Relief; (iii) reform of the

procurement system and the promulgation in 2010 of the Public Procurement Code; (iv) start of

restructuring of the administration with the Belgian Cooperation, FAO and MINDR support

with the Bank’s financial contribution; (v) Preparation of DRC’s Agriculture and Rural

Development Sector Strategy for the 2011-2015 period and the National Food Security Plan;

and (vi) preparation of the National Agricultural Investment Plan under the Global Agriculture

and Food Security Programme (GAFSP).

4.3.2 This project’s governance risks concern the goods and services procurement procedure

and financial resource management. These risks will be mitigated by the strict application of

the Bank’s procurement rules of procedure. The supervision and technical and financial audits

will ensure conformity and consistency between the resources committed and services actually

delivered. The Bank-organized training sessions for SMEs on the project cycle and

procurement for SMEs, as well as the scheduled technical assistance, will help to improve

project governance. As for the Government, involvement of the Ministries of Finance, Planning

and the Budget in the Steering Committee provides a guarantee of good governance in so far as

they have the right to inspect the project resources and quality of its outputs. Furthermore, the

establishment, by the Minister of Finance, of a Project Technical Monitoring Committee, which

holds monthly meetings chaired by him/her to review the implementation of activities and

budgets, has significantly improved operational governance.

16

4.4 Sustainability

4.4.1 The Government has included the PADIR in its development strategies (PRGSP and

Agriculture and Rural Strategy). Its implementation is backed by the sector ministries and the

population on the ground. All the actors concerned were involved in the project identification,

preparation and appraisal to facilitate subsequent ownership of project outputs. The project

selected profitable marketing infrastructure serving densely populated areas with high

agricultural production potential. These aspects will foster revenue collection by the local

authorities and management committees for infrastructure maintenance.

4.4.2 The rural roads selected are part of the DVDA priority maintenance programme,

which receives an annual allocation from the National Road Maintenance Fund (FONER),

established in 2008 and funded by the national budget, donors and parafiscal revenue (petrol,

road tolls, fines collected). Its budget for 2011 is estimated at US$ 50 million. The Roads

Agency will be allocated US$ 24 million of this amount for the maintenance of provincial and

national roads and the DVDA US$7.6 million (13% of the FONER Budget) for the

maintenance of 3,000 km of rural roads. The Government intends to gradually replenish this

fund even more in order to ensure maintenance of the entire priority network. The Local Road

Maintenance Committees (LRMC), which will be involved in the infrastructure work, will be

equipped and trained by the project and subsequently supported by DVDA with the financial

backing of FONER. To facilitate this operation, PADIR will carry out rural road maintenance

for the first two years after rehabilitation and provide the LRMCs with kits of maintenance

equipment and build DVDA’s capacity in terms of training and working resources. On the

other hand, adequate rural road rehabilitation at start-up and construction of durable road

structures will facilitate and contain subsequent maintenance costs.

4.4.3 Regarding markets, user associations will be responsible for managing the markets,

water points and latrines. Funds collected from traders will be distributed, as is customary,

between the local authorities and associations responsible for infrastructure maintenance and

cleanliness in the markets. As for the slaughterhouses, the taxes collected should ensure the

management and maintenance of water points, latrines and wastewater treatment ponds. For a

typical market, the recurrent costs were estimated at US$7,000 per year. These may be easily

covered by the additional expected revenue, estimated at US$19,300 per year. Infrastructure

implementation must be linked to the establishment of committees to manage it and the signing

of agreements to take over subsequent maintenance to ensure sustainability.

4.5. Risk Management

4.5.1 Risks: The infrastructure rehabilitation works do not pose any major implementation

risks. The planned technologies are well known in the region, and the PMU is very familiar

with them. Apart from the above-mentioned governance aspects, the main risks for the

achievement of project objectives are: (i) lack of qualified services for the technical control of

infrastructure; (ii) weak capacity of SMEs for the works; (iii) inadequate organization of

infrastructure management/users committees; and (iv) lack of familiarity with the Bank’s

financial management rules of procedure.

4.5.2 Mitigation Measures The following measures will be taken to mitigate the negative

impacts of the above-mentioned risks: (i) capacity building of technical services involved in

training and working resources; (ii) training and retraining of officials from Associations and

SMEs; and (iii) organization of Infrastructure Maintenance Committees. On completion of

their training, they will also be provided with batches of small materials and maintenance

equipment; and (iv) mobilization of international financial management and procurement

expertise, the training of senior staff and institutional and governance capacity building by the

Bank.

17

4.6. Knowledge Building

4.6.1 Through its monitoring and evaluation system, PADIR will provide information on the

impact of rural infrastructure on the reduction of travel time and transport costs, and their

effects on the prices of foodstuffs, food security and employment. The experimental

introduction of solar energy at local community level will improve knowledge of this

technology with a view to envisaging its extension and reducing oil consumption. It will

provide an alternative solution in areas without electricity. Support to the Vocational Training

and Social Reintegration Centres will enhance the technical level of young people, who will be

the drivers of the new technologies in their environment. The IEC themes in favour of the

population will in time build up their knowledge in the areas of nutrition, hygiene and disease

prevention. This information will provide relevant lessons for enhancing the effectiveness of

Bank operations.

4.6.2 The main lessons learnt from PADIR implementation will feed the database of the

Statistics Departments of the Ministries of Rural Development, Agriculture and Planning and

will serve as a reference for future operations. Summaries could be posted on the websites of

the Bank and the Government relating to the PRGSP. The capacity building component will

comprise technical training targeting national staff, which will enable them to improve their

qualifications. In addition, the technical staff of the PMU and provincial administration will be

involved in the different stages of the project’s implementation (definition of needs and

technical specifications, preparation of TORs, compliance control, works acceptance etc.).

Furthermore, the use of periodic reports in which performance indicators are analyzed

constitutes an attractive knowledge base regarding project impacts on the Bank and the Donee.

V. LEGAL FRAMEWORK

5.1 Legal Instrument

This is a grant which will be awarded to the Government of the Democratic Republic of Congo

to cofinance this project.

5.2 Conditions for Bank Intervention

A. Conditions Precedent to Grant Effectiveness: Effectiveness of the Grant Agreement

will be subject to its signature by the Donee and ADF.

B. Conditions Precedent to First Disbursement: In addition to effectiveness of the Grant

Agreement, the first disbursement will be subject to fulfillment, by the Donee and to the full

satisfaction of the Fund, of the following conditions:

(i) Provide ADF with the original copy of the Order signed by the Minister of Rural

Development concerning establishment of the PADIR PMU structures

(paragraph 4.1.2);

(ii) Provide ADF with evidence of the opening of a special account in the name of

PADIR in a bank acceptable to ADF for payment of the project grant resources

(paragraph 4.1.10).

C. Other conditions: In addition, the Donee will:

(i) Submit to ADF, for approval, no later than six months after the first

disbursement of the grant resources, the project implementation and

administrative and financial management procedure manuals (paragraph 4.1.9) ;

and

18

(ii) Submit to ADF, for approval, no later than six months after the first

disbursement of the grant, the Project Coordinator’s performance contract

(paragraph 4.1.2).

D. Undertaking: Through the PMU, the Donee undertakes to implement the

Environmental and Social Management Plan (paragraph 3.2.2).

5.3. Compliance with Bank Policies

The Rural Infrastructure Development Support Project complies with all the Bank’s applicable

rules.

VI. RECOMMENDATION

Management recommends that the Board of Directors should approve the proposal for an ADF

Grant of UA 49.46 million to DR Congo for the Rural Infrastructure Development Support

Project, subject to fulfillment of the conditions stipulated in this report.

Appendix I

Page 1/1

DRC

Comparative Socio-Economic Indicators.

YearCongo

(DRC)Africa

Develo-

ping

Countrie

Develo-

ped

CountrieBasic Indicators Area ( '000 Km²) 2 345 30 323 80 976 54 658Total Population (millions) 2010 67,8 1 031,5 5 659 1 117Urban Population (% of Total) 2010 35,2 39,9 45,1 77,3Population Density (per Km²) 2010 28,9 34,0 69,9 20,4GNI per Capita (US $) 2009 160 1 525 2 968 37 990Labor Force Participation - Total (%) 2010 38,0 40,1 61,8 60,7Labor Force Participation - Female (%) 2010 40,7 41,0 49,1 52,2Gender -Related Dev elopment Index Value 2007 0,370 0,433 0,694 0,911Human Dev elop. Index (Rank among 169 countries) 2010 168 n.a n.a n.aPopul. Liv ing Below $ 1 a Day (% of Population) 2006 59,2 42,3 25,2 …

Demographic Indicators

Population Grow th Rate - Total (%) 2010 2,7 2,3 1,3 0,6Population Grow th Rate - Urban (%) 2010 4,6 3,4 2,4 1,0Population < 15 y ears (%) 2010 46,4 40,3 29,0 17,5Population >= 65 y ears (%) 2010 2,9 3,8 6,0 15,4Dependency Ratio (%) 2010 96,2 77,6 55,4 49,2Sex Ratio (per 100 female) 2010 98,3 99,5 93,5 94,8Female Population 15-49 y ears (% of total population) 2010 22,6 24,4 49,4 50,6Life Ex pectancy at Birth - Total (y ears) 2010 48,0 56,0 67,1 79,8Life Ex pectancy at Birth - Female (y ears) 2010 49,6 57,1 69,1 82,7Crude Birth Rate (per 1,000) 2010 43,7 34,2 21,4 11,8Crude Death Rate (per 1,000) 2010 16,6 12,6 8,2 8,4Infant Mortality Rate (per 1,000) 2010 113,9 78,6 46,9 5,8Child Mortality Rate (per 1,000) 2010 193,7 127,2 66,5 6,9Total Fertility Rate (per w oman) 2010 5,8 4,4 2,7 1,7Maternal Mortality Rate (per 100,000) 2008 670,0 530,2 290,0 15,2Women Using Contraception (%) 2005-08 … … 61,0 …

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-09 11,0 58,3 109,5 286,0Nurses (per 100,000 people)* 2004-09 50,2 113,3 204,0 786,5Births attended by Trained Health Personnel (%) 2007 74,0 50,2 64,1 …Access to Safe Water (% of Population) 2008 46,0 64,5 84,3 99,6Access to Health Serv ices (% of Population) 2005-07 … 65,4 80,0 100,0Access to Sanitation (% of Population) 2008 23,0 41,0 53,6 99,5Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2005-09 3,2 4,9 0,9 0,3Incidence of Tuberculosis (per 100,000) 2009 372,0 294,9 161,0 14,0Child Immunization Against Tuberculosis (%) 2009 95,0 79,9 81,0 95,1Child Immunization Against Measles (%) 2009 86,0 71,1 80,7 93,0Underw eight Children (% of children under 5 y ears) 2007 28,2 30,9 22,4 …Daily Calorie Supply per Capita 2007 1 605 2 465 2 675 3 285Public Ex penditure on Health (as % of GDP) 2008 1,8 5,7 2,9 7,4

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2009 90,3 102,7 107,2 101,3 Primary School - Female 2009 83,0 99,0 109,2 101,1 Secondary School - Total 2009 36,7 37,8 62,9 100,1 Secondary School - Female 2009 26,2 33,8 61,3 99,6Primary School Female Teaching Staff (% of Total) 2009 26,3 47,0 60,5 81,4Adult literacy Rate - Total (%) 2008 66,6 64,8 80,3 98,4Adult literacy Rate - Male (%) 2008 77,5 74,0 86,0 98,7Adult literacy Rate - Female (%) 2008 56,1 55,9 74,8 98,1Percentage of GDP Spent on Education 2005 … 4,6 3,8 5,0

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2008 3,0 7,8 10,6 10,9Annual Rate of Deforestation (%) 2005-09 … 0,7 0,4 -0,2Annual Rate of Reforestation (%) 2005-09 … 10,9 … …Per Capita CO2 Emissions (metric tons) 2009 0,0 1,1 2,9 12,5

Sources : ADB Statistics Department Databases; World Bank: World Development Indicators; last update : May 2011

UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

0

20

40

60

80

100

120

140

20

03

20

04

20

05

20

06

20

07

20

08

20

09

Infant Mortality Rate( Per 1000 )

Cong o (DRC) Africa

0

200

400

600

800

1000

1200

1400

1600

1800

20

02

20

03

20

04

20

05

20

06

20

07

20

08

20

09

GNI per capita US $

Cong o (DRC) Africa

0,0

0,5

1,0

1,5

2,0

2,5

3,0

3,5

20

03

20

04

20

05

20

06

20

07

20

08

20

09

Population Growth Rate (%)

Congo (DRC) Africa

111213141516171

20

03

20

04

20

05

20

06

20

07

20

08

20

09

Life Expectancy at Birth (years)

Cong o (DRC)

Africa

Appendix II

Page 1/1

Table of ADB Portfolio in the Country

Project/Sector Amount (MUSD)

% Disbursed Key Dates of

Age (yr) Commitment Disbursed Approval Signature Closure

Agricultural and Rural Sector Rehabilitation

Support Project in Bas-Congo and Bandundu

Provinces (PARSAR)

25.00 19.94 80.00 19/05/04 25/5/04 31/03/12 7

Agriculture and Rural Sector Rehabilitation

Project in Katanga and the 2 Kasaï Provinces

(PRESAR)

35.00 28.05 80.14 12/12/05 2/2/06 31/01/13 5.5

Agriculture Sector Study (ASS) 1.85 1.50 81.23 28/06/06 11/10/06 30/06/11 5

Agriculture 61.85 49.49 80.41

Rehabilitation of the Nselé-Lufimi and

Kwango-Kenge Roads 52.45 34.02 64.86 19/12/05 29/12/05 31/12/11 6

Priority Air Safety Project (PPSA) 88.60 - 0.00 27/09/10 2/11/10 31/12/15 0.7

Project for the Rehabilitation and

Strengthening of the Inga Hydro-Power

Stations and Kinshasa Distribution Grid

(PMEDE)

35.70 - 0.00 18/12/07 10/4/08 31/12/14 3.6

Rural and Periurban Electrification Project

(PEPUR) 69.69 - 0.00 15/12/10 10/03/11 31/12/15 0.5

Drinking Water Supply and Sanitation

Project in Semi-Urban areas (PEASU) 70.00 20.88 29.83 6/6/27 9/8/07 31/12/12 4

Infrastructure 316.44 54.91 17.35

Orientale Province Health Development

Master Plan Support Project (PAPDDS) 25.00 8.27 33.08 17/03/04 25/05/04 31/03/12 7

Socio-Economic Reintegration Support

(PARSEC) 15.00 2.31 15.41 24/07/07 9/8/07 30/06/13 4

Social 40.00 10.58 26.45

Human Resources Revitalization and

Mobilization (PRM-RH) 20.00 - 0.00 19/01/11 4/05/11 31/12/15 0.5

Multisector 20.00 - 0.00

Total 438.3 114.98 26.23

4.6

Source: SAP (June 2011)

Appendix III

Page 1/1

Main Related Projects Financed by Other Development Partners Donor Project Name Location/Province COST

Million US$

World

Bank

Agriculture Sector Rehabilitation Support Project (PARRSA) Equateur, and Kinshasa (Maleba Pool)

120.00

IFAD

Integrated Agricultural Rehabilitation Project in Maniema Province (PIRAM) Maniema 23.33

Agricultural Rehabilitation Programme in Orientale Province (PRAPO) Orientale 14.73

Agricultural Revival Programme in Equateur Province (PRAPE) Equateur 16.00

Belgium

PRAPE and PRAPO in cofinancing with IFAD Orientale and Equateur 12.28

Rural Road Rehabilitation and Maintenance Bas-Congo, Bandundu, Kasaï-Oriental, 30.00

Rehabilitation of Agricultural Feeder Routes (land, river and quays) 75.00

Plant Production Support (APV) Bas-Congo, Bandundu, Kasaï-Oriental, Katanga, Orientale 4.90

Seed Selection Support (ASS) Bas-Congo, Bandundu, Katanga, Kasaï-Oriental 7.81

Artisanal Fisheries and Fish Farming (PRODEPAAK) Katanga, Bas-Congo, Katanga, Orientale 6.50

Urban and Periurban Horticulture Support (HUP) Bas-Congo, Bandundu 4.00

Technical and Organizational Support to Rural and Semi-Urban Initiatives of

Agricultural Associations

Katanga

2.17

Various other support operations for MINAGRI and in the rest of the country Various provinces. 31.23

EU Restoration of Agricultural and Fishery Product Distribution Channels through

Marketing Cooperatives in Tanganyika District

South Kivu 2.30

Food Security and Natural Resource Management Support Project in Bushi Region Orientale

1.80

Agricultural Product Marketing and Production Support in Ituri Bandundu ; Kinshasa City 2.05

Agricultural Revival in Bandundu Province to Supply Kinshasa Bandundu ; Kinshasa City 8.70

Various other operations All regions 74.53

USAID Food Production Processing and Marketing Bas-Congo, Kinshasa, Bandundu 35.00

Capacity Building of the National Agricultural Research Institute (INERA) Kinshasa – Bas Congo-Maniema-K. Oriental 10.00

Inter Food Policy and Research (or International Agricultural Policy Research

Institute) & Study on Improvement of the Agriculture Sector Business Climate

Country-wide, Kinshasa 2.60

Other

Donors

Periodic support to the different agricultural subsectors, capacity building and research

and extension.

All provinces of the country 148.79

ADB

Group

108.70

Total 742.42

Source: Ministry of Planning /Productive Sectors Department

Appendix IV

Page 1/1

Appendix IV

Map of Project Area

Annex 1 : PADIR Area of Intervention

Projet Area

This map is for use exclusively by readers of the report to which it relates. Names and boundaries shown in no way represent the

views of the Bank Group or its staff on the legal status of any territory; neither do they imply their approval or acceptance of its

boundaries.

Provincial

Boundaries

Appendix V

Page 1/1

Summary of Procurement Arrangements (in UA Thousand)

Expenditure Categories ICB NCB Other Shortlist Other Fin.

Gvt/Benef..

Total

1.

Goods

4.338 [4.338]

1.1 Rural Infrastructure Equipment 0.300 [0.300] 0.300 [0.300] 1.2 Office Equipment 0.456 [0.456] 0.456 [0.456]

1.3

1.4 1.5

1.6

1.7

2.

2.1

2.2

2.3 2.4

3.

Transport Equipment

IT Equipment Various Specific Materials

Various Teaching Aids

Specific Professional Equipment

Civil Works

Rehabilitation of Rural Infrastructure

Rehabilitation of Administrative Buildings

Rehabilitation of PMU Premises and Katanga branches Rehabilitation of Springs, DWS and Boreholes

Consultancy Services

0.993 [0.993]

0.596 [0.596]

21.408[21.408]

2.905 [2.905]

0.651 [0.651]

0.125 [0.125]

1.218 [1.218]

0.047 [0.047] 2.574 [2.574]

0.993 [0.993]

0.596 [0.596] 0.651 [0.651]

0.125 [0.125]

1.218 [1.218]

26.934 [26.934]

21.408 [21.408]

2.905 [2.905]

0.047 [0.047] 2.574 [2.574]

5.974 [5.974]

3.1 3.2

3.3

3.4 3.5

3.6

3.7 3.8

3.9

3.10 3.11

3.12

3.13 3.14

3.15

4. 4.1

4.2 4.3

4.4

4.5 4.6

4.7 4.8

Preliminary Sketches for Rural Infrastructure Preliminary Sketches for Administrative Buildings

Various Complementary Engineering Designs

Monitoring and Inspection of Infrastructure Works Sensitization, Training and Organization

Rural Outreach

Technical Assistance to PMU Preparation of Project Manual

Preparation of Rural Infrastructure Manual

Various TA and Short-Term Missions Various Sector Studies

Training Courses

Audit of Accounts and Procurements Mid-Term Review

Project Completion Report

Operating Costs

Maintenance of Buildings/Equipment Partners’

Structures

Operating costs of Equipment Partners’ Structures Office Rental

Focal Point Expenditure

PMU/ Branch Allowance Performance Bonus Operating costs of Provincial Coordination and

Steering Committees

Operating costs of PMU/Branches Headquarters Visit

Contingencies Physical

Financial

0..087 [0.087]

0.070 [0.070]

0.015 [0.015]

0.015 [0.015]

0.013[0.013]

0.013[0.013]

0.853 [0.853]

4.978 [4.978]

0.512 [0.512] 0.974 [0.974]

0.025 [0.025]

2.261 [2.261] 2.609 [2.609]

0.318 [0.318]

2.873 [2.873] 0.832 [0.832]

0.245 [0.245]

0.562 [0.562]

0.187 [0.187] 0.116 [0.116]

0.534 [0.534]

0.094 [0.094]

0.929

0.453

0.028

0.318 [0.318] 0.087 [0.087]

0.070 [0.070]

2.873 [2.873] 0.832 [0.832]

0.245 [0.245]

0.562 [0.562] 0.015 [0.015]

0.015 [0.015]

0.187 [0.187] 0.116 [0.116]

0.534 [0.534]

0.094 [0.094] 0.013 [0.013]

0.013 [0.013]

8.752 [7.342]

0.929 [0]

0.453[0]

0.028[0] 0.853 [0.853]

4.978 [4.978]

0.512 [0.512] 0.974 [0.974]

0.025 [0.025]

4.870 [4.870] 2.261[2.261]

2.609 [2.609]

TOTAL

2.045 [2.045]

24.613 [24.613]

17.040 [17.040]

5.761[5.761]

1.410

50.868 [49.458]

Others: * Shopping for Goods; ** Selection Process for Individual Consultancy Services, *** Community-based Works Contract

Appendix VI

Page 1/1

Project Cost by Expenditure Category and Sources of Finance Expenditure

Category In Dollars Thousand In Units of Account Thousand

GVT/Ben ADF TOTAL GVT/Ben ADF TOTAL

L.C. F.E. L.C. Total L.C. F.E. L.C. Total

Works 0 25.613 17.501 43.114 43.114 0 16.000 10.933 26.934 26.934

Goods 0 5.428 1.517 6.945 6.945 0 3.391 948 4.338 4.338

Services 0 7.955 1.648 9.603 9.603 0 4.944 1.030 5.974 5.974

Operating costs 2.257 3.104 8.649 11.753 14.010 1.410 1.939 5.403 7.342 8.752

Base Cost 2.257 42.100 29.316 71.415 73.672 1.410 26.274 18.314 44.588 45.998 Physical

Contingencies 0 1.496 2.084 3.580 3.580 0 959 1.302 2.261 2.261 Financial

Contingencies 0 2.655 1.521 4.176 4.176 0 1.659 950 2.609 2.609

Grand Total 2.257 46.251 32.921 79.171 81.428 1.410 28.892 20.566 49.458 50.868

Appendix VII

Page 1/4

Appendix VII: Examples of Physical Outputs of PRESAR and PARSAR

Rural Roads

Mbalaka Road, Kambové/ PRESAR

Bif Kasombo Road, Katanga /PRESAR

Bridges

Mabaya Bridge, Katanga / PRESAR

Appendix III

Page 2/4

Rural Markets

Sambwa Market, Katanga/PRESAR

Appendix III

Page 3/4

Kasansa Market/ Kasaï-Oriental/PRESAR

Springs

Kawama 2 Springs, Katanga /PRESAR

Mazembe Spring, Katanga

Administrative Building

Buildings of the Ministry of Gender, Family and Children, Kinshasa /PARSAR

Appendix III

Page 4/4

MINAGRI buildings, Kinshasa /PARSAR

Distribution of small items of processing equipment to associations/PARSAR Seed fields Bas Congo /PARSAR