Upload
hoangnga
View
259
Download
3
Embed Size (px)
Citation preview
© IFM Quality Services Pty Ltd Page 1
This report is only for the use of participating laboratories
Proficiency Testing FINAL REPORT Transformer Heating Test
50 HZ 16E32.2
August 2016
Proficiency Testing Provider Certificate Number 3189-02.
Program Coordinator: Ingrid Flemming IFM Quality Services Pty Ltd PO Box 877 Ingleburn NSW 2565 Australia Tel: +61 (0)2 9618 3311 Fax: +61 (0)2 9618 3355 Email: [email protected] Samples Dispatched: 1 July 2016 Results Due: 28 August 2016 Report Issued: 9 November 2016
We gratefully express our thanks to IECEE CTL WG2 for their support. In particular, thanks to Matej Žontar for his assistance.
© IFM Quality Services Pty Ltd Page 2
This report is only for the use of participating laboratories
Operational Summary
NUMBER OF ROUNDS AND FREQUENCY OF TESTING
Rounds are operated on an on-need basis. This is the third of 3 rounds operated in 2016.
APPLICABLE STANDARDS
IEC 61558-1.
Due to the similarities in test procedures, other product standards may be applicable, including: IEC 60335-
1; IEC 60598-1; IEC 61010-1; IEC 60065; IEC 60950-1, IEC 62368-1 and other standards requiring
temperature rise tests using change in winding resistance method.
SAMPLE MANUFACRURE AND ASSURANCE OF SAMPLE INTERGRITY
Participants received one transformer. The samples were sourced from a single commercial supplier’s
manufacturing batch. Prior to use in this program, each individual sample was screened by IFM’s Support
Division for damage and functionality. The winding resistances were measured for each sample, those
found to be outside the statistically acceptable range were removed from the pool of samples. A selection
of the remaining samples was sent to an ISO/IEC 17025 accredited contract testing laboratory to carry out
homogeneity tests. Samples met the required criteria for homogeneity.
METHOD OF DISPATCH
All samples were sent via express national/international courier.
ASSESSMENT PROCEDURE
Please refer to IFM’s Policies on the assessment of PTP results:
http://www.ifmqs.com.au/proficiency/references/QPL001-02_Assessment_of_Microbiological_PT_Results.pdf
Refer to the discussion for a description of the assessment procedure for relevant tests.
DISPUTE PROCEDURE
Participants wishing to dispute their assessment, or appeal an evaluation on other grounds should submit
their appeal in writing to the program coordinator.
Please refer to http://www.ifmqs.com.au/ifm_terms_and_conditions.htm for the detailed policy.
CONFIDENTIALITY
The identity of participants and any identifying information supplied by participants is treated as confidential.
Appropriate policies and procedures have been put into place to ensure this confidentiality is maintained.
Please refer to http://www.ifmqs.com.au/ifm_policy_on_confidentiality.htm for the detailed policy.
TEST INSTRUCTIONS
Instructions applicable to this testing round may be found at:
http://www.ifmqs.com.au/proficiency/instructions/16e32.2_Instructions.pdf
© IFM Quality Services Pty Ltd Page 3
This report is only for the use of participating laboratories
Participation Summary
⇒ 97 organisations enrolled
⇒ 87 organisations participated
⇒ 118 sets of results were submitted
⇒ 3362 individual test results were received
⇒ 348 results were assessed
⇒ 3014 results were not assessed
⇒ 51 results were assessed as outliers
Enumerative Tests Assessment Criteria
• Temperature rise of the primary winding at 50 Hz.
• Temperature rise of the secondary 1 winding at 50 Hz
• Temperature rise of the secondary 2 winding at 50 Hz.
Robust statistics are applied in order to determine a Z score for
each result. Acceptable Z scores are |Z|<3. Whenever possible
non-numeric results are assessed by applying simple pass/fail
assessments without issue of Z scores.
To ensure 1 laboratory could not unfairly bias the statistics
whenever multiple participants from a single laboratory submit
results, only the first 2 participants’ results are included in the data
population to be statistically analyzed.
Variations to the normal assessment procedure will be detailed in the discussion.
Available Tests
INDIVIDUAL RESULTS
Should individual test results be required, these will be provided upon request.
CORRECTIVE ACTIONS
IFM follows up on corrective actions of laboratories for a period of 3 months. Details for the closure
of actions will be at :
http://www.ifmqs.com.au/proficiency/references/QPF086-01_Corrective_Action_Management_for_Electrical_PT.pdf
© IFM Quality Services Pty Ltd Page 4
This report is only for the use of participating laboratories
Discussion
CALCULATED AND SUBMITTED TEMPERATURE RISES
Each participant’s reported temperature rise for the primary and secondary windings were plotted against a
calculated temperature rise based on the formula:
Where x = 234.5 for copper ∆t is the temperature rise R1 is the initial resistance, R2 is the final resistance t1 is the initial ambient temperature, t2 is the final ambient temperature
Most participant’s reported temperature rise was in agreement with the calculated rise for the primary and
secondary windings (Figure 1). Participants reporting a result >5K different to the value calculated by IFM
are required to explain why the results are different.
One laboratory used the equation Reported value= measured value– Ambient. The temperature rise
reported by this laboratory did not match that of the value calculated by IFM. It is unclear if this laboratory
is using a different method to determine temperature rise. This program was only for laboratories which
measure temperature rise using the change of resistance method.
NUMBER OF SIGNIFICANT FIGURES
It is a requirement of ISO17025 that laboratories know their measurement uncertainties and that they do
not report misleading results. Laboratories reporting results to more significant figures than is suitable for
their measurement uncertainty are reporting misleading results, the greater number of significant figures
implies greater confidence in the result precision. Similar to 16E32 and 16E32.1, some participants
reported results to 5 decimal places. It is unlikely that laboratories would have a measurement uncertainty
that would allow reporting this many significant figures. Appendix 1 of this report contains information that
laboratories may find useful when calculating their measurement uncertainty.
Members of working group 2 have recommended that laboratories should at most report results to 1
decimal place. However, this does not negate the need for laboratories to determine their measurement
uncertainty.
TEMPERATURE RISE SECONDARY 1 VS SECONDARY 2 WINDING
After investigating participant’s results it was found that their was a correlation between the secondary 1
temperature rise results and the secondary 2. This can be seen in Figure 2.
Standard applied (Figures 3-5), adjustment of the voltage, time taken to reach steady state as well as initial
and final; voltage, current to the temperature rises of the primary and secondary windings were compared
to temperature rise. No factor examined was found to affect the results of this round.
LOW RESISTANCES IN SECONDARY WINDINGS
The resistances of the secondary windings were measured reasonably consistently by participants at 0.2 -
0.3 ohm. However, the resistances of the primary windings were 2 orders of magnitude higher than this at
∆ = ( 2 − 1) 1 ( + 1) − ( 2 − 1)
© IFM Quality Services Pty Ltd Page 5
This report is only for the use of participating laboratories
10
20
30
40
50
60
70
20 25 30 35 40 45 50 55 60 65 70
Tem
pera
ture
Ris
e Se
cond
ary 2
(K)
Temperature Rise Secondary 1 (K)
16e32.2: Secondary Temperature 1 Rise vs Secondary Temperature 2 Rise
FIGURE 2
0
20
40
60
80
100
120
140
0 50 100 150
Subm
itted
tem
pera
ture
rise
(K)
Calculated temperature rise (K)
16E32.2: Submitted vs Calculated Temperature Rise
Primary winding
Secondary 1 winding
Secondary 2 winding
x=y
FIGURE 1
30 - 40 ohm. There are some implications to the choice of equipment with this variation. The relative
ability to accurately measure the lower resistances must be taken into account when considering the
precision with which the results are reported.
Further, when the measured resistances of the windings are small, attention must be paid to other variables
both in the temperature rise equation and the factors that might influence the resistance being measured,
particularly the connections of conductors to the windings and electronic influences. Please refer to the
discussion in Appendix 1.
© IFM Quality Services Pty Ltd Page 6
This report is only for the use of participating laboratories
0
2
4
6
8
10
12
14
16
35.43 38.43 41.43 44.43 47.43 50.43 53.43 56.43 59.43 more
Freq
uenc
y (pa
rticip
ants
)
Primary winding temperature rise (K)
16E38.2: Primary Winding: Temperature Rise by Standard
IEC60065
IEC60598
IEC60950
IEC60335
IEC60601
IEC61010
IEC61558
IEC62368
IEC60947
FIGURE 3
0
2
4
6
8
10
12
27.88 32.76 37.64 42.52 47.4 52.28 57.16 62.04 66.92 more
Freq
uenc
y (pa
rticip
ants
)
Secondary 1 winding temperature rise (K)
16E32.2: Secondary 1 Winding Temperature Rise by Standard
IEC60065
IEC60598
IEC60950
IEC60335
IEC60601
IEC61010
IEC61558
IEC62368
IEC60947
FIGURE 4
READING AND FOLLOWING INSTRUCTIONS GIVEN FOR TESTING
The instructions require an input voltage to be applied to the primary winding while a resistive load is
attached to both of the secondary outputs. Point 4 of the instructions states the test should be conducted at
50Hz. One of the participating laboratories tested their transformer at 40Hz. This participant reported
outlying results and consequently received fail assessments. It was also noted that a participant tested the
9 V winding when at point 9b in the instructions it specifies that the load must be placed between the
terminals marked 0 V and 12 V. While these laboratories may not have received outliers they are still
advised to perform corrective action to ensure that understanding customer instructions is part of their
contract review process.
© IFM Quality Services Pty Ltd Page 7
This report is only for the use of participating laboratories
0
2
4
6
8
10
12
14
30.15 34.53 38.91 43.28 47.66 52.04 56.41 60.79 65.17 more
Freq
uenc
y (pa
rticip
ants
)
Secondary 2 winding temperature rise (K)
16E32.2: Secondary 2 Winding Temperature Rise by Standard
IEC60065
IEC60598
IEC60950
IEC60335
IEC60601
IEC61010
IEC61558
IEC62368
IEC60947
FIGURE 5
© IFM Quality Services Pty Ltd Page 8
This report is only for the use of participating laboratories
16e32.2 Temp Rise Transformer 50HzQ20 Temp rise primary
(K)Number of Results Received 115Number of Results Analysed 115Quartile 1 44.4650Quartile 3 50.4670IQR 6.0020NIQR 4.4493Median 47.4300Acceptable High:Median + (3*NIQR) 60.7778Acceptable Low:Median - (3*NIQR) 34.0822Statistically Acceptable Range 26.6957
16e32.2 Temp Rise Transformer 50HzQ21a Temp rise secondary 1
(K)Number of Results Received 115Number of Results Analysed 115Quartile 1 42.4400Quartile 3 52.2000IQR 9.7600NIQR 7.2351Median 47.4000Acceptable High:Median + (3*NIQR) 69.1053Acceptable Low:Median - (3*NIQR) 25.6947Statistically Acceptable Range 43.4105
Results
TEMPERATURE RISE 50HZ FOR PRIMARY AND SECONDARY WINDINGS
16e32.2 Temp Rise Transformer 50HzQ21b Temp rise secondary 2
(K)Number of Results Received 115Number of Results Analysed 115Quartile 1 43.0000Quartile 3 51.7545IQR 8.7545NIQR 6.4897Median 47.6600Acceptable High:Median + (3*NIQR) 67.1291Acceptable Low:Median - (3*NIQR) 28.1909Statistically Acceptable Range 38.9383
0
5
10
15
20
25
30
35
35 38 41 44 47 50 53 56 59
Mor
e
Result (K)
Freq
uenc
y
16e32.2 Temp Rise Transformer 50HzQ20 Temp rise primary
Excluded
Included
0
5
10
15
20
25
30
35
28 33 38 43 47 52 57 62 67
Mor
e
Result (K)
Freq
uenc
y
16e32.2 Temp Rise Transformer 50HzQ21a Temp rise secondary 1
Excluded
Included
0
5
10
15
20
25
30
35
30 35 39 43 48 52 56 61 65
Mor
e
Result (K)
Freq
uenc
y
16e32.2 Temp Rise Transformer 50HzQ21b Temp rise secondary 2
Excluded
Included
© IFM Quality Services Pty Ltd Page 9
This report is only for the use of participating laboratories
Appendix 1
Estimating measurement uncertainty is a requirement of ISO17025. Laboratories should have their own
procedure in place to determine their measurement uncertainty. An explanation of how to determine
measurement uncertainty is outside of the scope of this report. Laboratories that have not calculated their
measurement uncertainty may find ISO/IEC Guide 98-3:2008 useful.
To aid laboratories in estimating their measurement uncertainty, IFM has calculated the change in
temperature rise of the primary and secondary windings with changes in the initial and final ambient
temperature and resistance. As base values IFM used the median values from participants reporting
results for 50 Hz. These values were R1 primary = 37.01, R2 primary = 43.95, R1 secondary1 = 0.26, R2 secondary1 =
0.311, t1 = 23 and t2 = 23.68. The temperature rise for the primary and secondary windings were then
calculated for these values. Each variable was then increased by the value indicated in Tables A.1 to A.6
and the absolute change in the temperature rise was calculated.
TABLE A.1
TABLE A.2
TABLE A.3
TABLE A.4
TABLE A.5
TABLE A.6
While IFM did not ask participants for their measurement uncertainty, it should be inferred by the number of
significant figures reported. As the majority of participants reported ambient temperature to 1 decimal
place, it should be possible to assume their measurement uncertainty for ambient temperature is between
approximately 0.9 and 0.1 °C. Assuming the measurement uncertainty of the ambient temperature is 0.1 °
C, there could be a 0.1 °C variation between the real ambient temperature and the measured ambient
temperature.
Based on tables A.5 and A.6 there could therefore be a difference of 0.2 °C (0.118+0.1) between the real
temperature rise and the measured temperature rise. This would mean that the majority of laboratories
should at most be reporting temperature rise to 1 decimal place. However, the above is based on
assumptions, simplified calculations of measurement uncertainty and only considers the uncertainty of the
ambient temperature. Laboratories need to ensure that they calculate their own measurement uncertainty
using a valid method, considering all variables.
Change in initial resistance of primary winding (Ohms) R1 primary + 1 R1 primary + 0.1 Change in temperature rise (K) 8.04 0.82
Change in final resistance of primary winding (Ohms) R2 primary +1 R2 primary +0.1
Change in temperature rise (K) 6.95 0.69
Change in initial resistance of secondary 1 winding (Ohms) R1 secondary + 0.001 R1 secondary + 0.0001 Change in temperature rise (K) 1.18 0.1184
Change in final resistance of secondary 1 winding (Ohms) R2 secondary + 0.01 R2 secondary + 0.001 Change in temperature rise (K) 0.99 0.099
Change in initial ambient temperature (°C) t1 + 1 t1 + 0.1 Change in temperature rise 1.187 0.118
Change in final ambient temperature (°C) t2 + 1 t2 + 0.1 Change in temperature rise 1 0.1
© IFM Quality Services Pty Ltd Page 10
This report is only for the use of participating laboratories
Even though an instrument may be calibrated to a high level of accuracy the measurements it makes may
not be as accurate as the calibration. For example a thermocouple probe may be calibrated to within 0.2 °
C. However, if there are warm and cool areas within a room and, depending on the manner of air flow and
other environmental influences, it may only be able to determine the true ambient temperature to within 2 °
C.
Some factors that may affect temperature determinations are:
• Hot and cold areas in a room
• Distance of the temperature measuring probe from the sample and / or possible influence of radiated
heat from the sample
• Sudden changes in temperature from air-conditioners/heaters or opening doors
Some factors that may affect resistance measurements
• Resistance of the probes
• Connection of the probes to the sample
• Sources of noise (e.g. EMF)
Figures A1 and A2 compare how the uncertainty in resistance and ambient temperature affect the
uncertainty in temperature rise for different winding resistances. From these charts it can be seen that;
• a 1% uncertainty in resistance leads to leads to an approximate 4 K uncertainty in temperature rise
0
1
2
3
4
5
6
0 0.2 0.4 0.6 0.8 1
Unc
erta
inty
in te
mpe
ratu
re ri
se (K
)
Winding resistance (ohm)
Uncertainty in temperature rise of a 50 K temperature rise for different winding resistances for a 1 K uncertainty in ambient
temperature
Uncertainty in R = 0.01
Uncertainty in R = 0.001
Uncertainty in R = 0.0001
FIGURE A1
© IFM Quality Services Pty Ltd Page 11
This report is only for the use of participating laboratories
0
1
2
3
4
5
6
0 0.2 0.4 0.6 0.8 1
Unc
erta
inty
in te
mpe
ratu
re ri
se (K
)
Winding resistance (ohm)
Uncertainty in temperature rise of a 50 K temperature rise for different winding resistances for a 0.0001 ohm uncertainty in
resistance
Uncertainty in temperature = 1
Uncertainty in temperature = 0.5
Uncertainty in temperature = 0.1
FIGURE A2
© IFM Quality Services Pty Ltd Page 12
This report is only for the use of participating laboratories
�End of Report�
Lab Code Reason Withdrawn / Comment Due DateAction Alert
Heating Test - Transformers - 16e32.2 (201607)
Electrical Program Status Report
1 CBTL - Certification Body Testing Laboratory
2 CBTL - Certification Body Testing Laboratory
3 CBTL - Certification Body Testing Laboratory
4 CBTL - Certification Body Testing Laboratory
5 CBTL - Certification Body Testing Laboratory
6 CBTL - Certification Body Testing Laboratory
7 CBTL - Certification Body Testing Laboratory
8 CBTL - Certification Body Testing Laboratory
9 CBTL - Certification Body Testing Laboratory
Y Y10 10 Feb 2017CTF - Customer’s Testing Facility
O 7/11/2016 Part01: 2 results assessed as outlying
11 CBTL - Certification Body Testing Laboratory
12 CBTL - Certification Body Testing Laboratory
13 CBTL - Certification Body Testing Laboratory
14 CBTL - Certification Body Testing Laboratory
15 CBTL - Certification Body Testing Laboratory
16 CBTL - Certification Body Testing Laboratory
17 Private
18 CBTL - Certification Body Testing Laboratory
19 Private
22 CBTL - Certification Body Testing Laboratory
23 CBTL - Certification Body Testing Laboratory
25 CTF - Customer’s Testing Facility
Y Y26 10 Feb 2017CTF - Customer’s Testing Facility
O 7/11/2016 Part01: 2 results assessed as outlyingO 7/11/2016 Part02: 2 results assessed as outlying
28 CBTL - Certification Body Testing Laboratory
29 CBTL - Certification Body Testing Laboratory
30 Private
31 CBTL - Certification Body Testing Laboratory
32 CTF - Customer’s Testing Facility
34 CTF - Customer’s Testing Facility
Y Y35 10 Feb 2017CBTL - Certification Body Testing Laboratory
O 7/11/2016 Part01: 1 result assessed as outlyingO 7/11/2016 Part02: 2 results assessed as outlying
37 CBTL - Certification Body Testing Laboratory
Y Y39 10 Feb 2017CTF - Customer’s Testing Facility
O 7/11/2016 Part02: 1 result assessed as outlyingO 7/11/2016 Part01: 1 result assessed as outlying
40 CTF - Customer’s Testing Facility
Y Y41 10 Feb 2017CTF - Customer’s Testing Facility
O 7/11/2016 Part01: 1 result assessed as outlying
9/11/2016 Page 1 of 4Produced by IFM Quality Services Pty Ltd
WWW.IFMQS.COM.AU - Ph: +61 2 9618 3311
Lab Code Reason Withdrawn / Comment Due DateAction Alert
Heating Test - Transformers - 16e32.2 (201607)
Electrical Program Status Report
43 CBTL - Certification Body Testing Laboratory
44 CTF - Customer’s Testing Facility
Y Y45 10 Feb 2017CBTL - Certification Body Testing Laboratory
O 7/11/2016 Part01: 1 result assessed as outlyingO 7/11/2016 Part02: 1 result assessed as outlying
46 CBTL - Certification Body Testing Laboratory
47 CTF - Customer’s Testing Facility
49 Private
Y Y50 10 Feb 2017Private
O 7/11/2016 Part01: 1 result assessed as outlying
51 CBTL - Certification Body Testing Laboratory
53 CBTL - Certification Body Testing Laboratory
54 CTF - Customer’s Testing Facility
Y Y56 10 Feb 2017CBTL - Certification Body Testing Laboratory
O 7/11/2016 Part02: 1 result assessed as outlying
Y Y57 10 Feb 2017Private
O 7/11/2016 Part01: 1 result assessed as outlyingO 7/11/2016 Part02: 1 result assessed as outlying
Y Y58 10 Feb 2017Private
O 7/11/2016 Part02: 3 results assessed as outlyingO 7/11/2016 Part01: 3 results assessed as outlying
59 CBTL - Certification Body Testing Laboratory
60 CBTL - Certification Body Testing Laboratory
Y Y61 10 Feb 2017CTF - Customer’s Testing Facility
O 7/11/2016 Part01: 3 results assessed as outlying
Y Y62 10 Feb 2017CBTL - Certification Body Testing Laboratory
O 7/11/2016 Part01: 1 result assessed as outlying
63 CTF - Customer’s Testing Facility
Y Y64 10 Feb 2017CBTL - Certification Body Testing Laboratory
O 7/11/2016 Part01: 3 results assessed as outlyingO 7/11/2016 Part02: 3 results assessed as outlying
65 CTF - Customer’s Testing Facility
66 CBTL - Certification Body Testing Laboratory
67 CBTL - Certification Body Testing Laboratory
68 CBTL - Certification Body Testing Laboratory
69 CTF - Customer’s Testing Facility
70 CBTL - Certification Body Testing Laboratory
Y Y71 10 Feb 2017CTF - Customer’s Testing Facility
O 7/11/2016 Part02: 3 results assessed as outlying
74 CBTL - Certification Body Testing Laboratory
Y Y75 10 Feb 2017Private
O 7/11/2016 Part01: 2 results assessed as outlying
76 CBTL - Certification Body Testing Laboratory
77 CBTL - Certification Body Testing Laboratory
9/11/2016 Page 2 of 4Produced by IFM Quality Services Pty Ltd
WWW.IFMQS.COM.AU - Ph: +61 2 9618 3311
Lab Code Reason Withdrawn / Comment Due DateAction Alert
Heating Test - Transformers - 16e32.2 (201607)
Electrical Program Status Report
78 Private
79 Private
80 CTF - Customer’s Testing Facility
81 CBTL - Certification Body Testing Laboratory
82 CTF - Customer’s Testing Facility
83 Private
84 CTF - Customer’s Testing Facility
85 Private
86 CBTL - Certification Body Testing Laboratory
Y Y87 10 Feb 2017Private
O 7/11/2016 Part01: 3 results assessed as outlyingO 7/11/2016 Part02: 3 results assessed as outlying
88 CTF - Customer’s Testing Facility
Y Y89 10 Feb 2017CTF - Customer’s Testing Facility
O 7/11/2016 Part02: 1 result assessed as outlying
90 Private
91 Private
92 Private
Y Y93 10 Feb 2017Private
O 7/11/2016 Part02: 1 result assessed as outlying
94 Private
95 CBTL - Certification Body Testing Laboratory
96 Private
97 Private
98 CTF - Customer’s Testing Facility
Program Results NOT submitted
99 Private
Y Y100 10 Feb 2017CBTL - Certification Body Testing Laboratory
O 7/11/2016 Part01: 3 results assessed as outlying
101 Private
Y Y102 10 Feb 2017Private
O 7/11/2016 Part01: 1 result assessed as outlying
103 Private
9/11/2016 Page 3 of 4Produced by IFM Quality Services Pty Ltd
WWW.IFMQS.COM.AU - Ph: +61 2 9618 3311
Lab Code Reason Withdrawn / Comment Due DateAction Alert
Heating Test - Transformers - 16e32.2 (201607)
Electrical Program Status Report
>> Report Indicator Columns and Action History Codes
- "Y" when a submitted result was determined to be an outlier requiring corrective action(s) or additional information is required to clarify a result. Action history will then follow.- "Y" when corrective or other action(s) have not been completed- Date by which corrective or other action(s) are required to be completed. This date is not set until the FINAL report has been issued.
X - Reminder sent to laboratoryC - Action Closed (Completed)F - Overdue action referred to IEC-EE
Action History Codes:
O - Action Opened by IFMN - Notification of action sent to laboratoryA - Acknowledgement received from laboratoryR - Response received from laboratory
Column:
Action
AlertDue Date
9/11/2016 Page 4 of 4Produced by IFM Quality Services Pty Ltd
WWW.IFMQS.COM.AU - Ph: +61 2 9618 3311