Upload
kirk-ponton
View
213
Download
0
Embed Size (px)
Citation preview
Production Capacity of Truck and Loader Teams
©Dr. B. C. Paul 2003
Production Can be Limited by Either the Truck or Loader
Example• 6 Cat 773 trucks work 10 hours/day 6
days/ week and 40 weeks/year• 10 minutes moving cycle• Loaded in 4 passes with 992
• Drive by with no spot time 2.8 minutes• 12.8 min total cycle
Calculating the Truck Production
144,000 minutes/year at 12.8 minutes/cycle• 11,250 trips at 57.98 tons/trip• 652,275 tons/truck per year
Trucks breakdown • Say they run 85% of the time• 652,275*0.85 = 554,434 tons
More Truck Production
Workers not running equipment all shift• Say 50 minutes/hour or 0.83• 554,434*0.83 = 460,180 tons
Loader won’t work all the time• Say it runs 85% of the time 0.85• 460,180*0.85 = 391,153 tons
Finishing? Truck Production
May not utilize equipment all the time it is available• Say 95% utilized of available• 391,153*0.95 = 371,595 tons
Off course we know we may have to worry about trucks bunching but lets say we ignore that
For 6 trucks I could haul out 2.23 million tons per year• Obviously ignoring any bunching up at the
loader
Now Lets Look at My Loader’s Production
144,000 minutes with 0.7 minutes/pass• Loader could do 205,714 cycles/year• At 14.495 tons/pass 2.982 million
tons Loader only runs 85%
• 2.535 million tons
More Loader Production
Loader Operator working 50 min/hour• 2.104 Million
Utilized of Available 95%• 1.998 Million tons
This of course assumes there is always a truck there to be loaded
Question of the Day
How did my trucks haul out 2.23 million tons of rock if the loader could only load 1.998 million tons under best conditions?
Of course the answer is that loader was limiting
Check of Over-trucked• 12.8 minutes/truck cycle/2.8 minutes/loader• 4.57 trucks/loader (ie 6 trucks is more than
the loader can possibly handle)
Conclusion
When one is over-trucked it is the loader that determines production
How to Handle Bunching
If I have 6 trucks and 1 loader Calculate my Match Factor
• 6*2.8/(1*12.8) = 1.3125• Number greater than 1 indicates over-
trucked Look up my bunching factor
• 0.952• Trick is that bunching is applied to the
limiting part of the system (ie the loader)
Calculating Production
Theoretically could do 1.998 million tons/year• 1,998,496 * 0.952 = 1,902,568
What 0.952 bunching meant was that 95.2% of the time when the loader had a scoop of material it would have a truck there waiting (even over-trucked its not always there)
What We Haven’t Considered
I just assumed that I had 6 trucks ready to go whenever my loader was• Reality is that trucks could be broken
too. Noted that all my examples so far
were based on trucks with only 1 loader that was conveniently there or not there
How to Handle Truck Break-downs
Binomial Probability gives me the odds on any number of trucks working• Not too scary with the spreadsheet to do all
the work• 6 trucks 37.71%• 5 trucks 39.93%• 4 trucks 17.62%• 3 trucks 4.14%• 2 trucks 0.55%• Lower numbers have little chance
Solution Approach
I have 5 truck fleets that have some chance of happening• 37.71% chance of 6 trucks to one loader
• This fleet could produce 1.903 Million tons per year
Find What I could produce with the other 4 fleets and what there probability is
Do a weighted average of my production rates to see what my fleet could most likely produce
5 Trucks to One Loader
Match Factor• 5*2.8/(1*12.8) = 1.09375• Still over-trucked ie the loader is the limit to which
bunching is applied Bunching Factor is 0.886
• Note that as # trucks went down the chances that one would be waiting went down
• Production• Loader Full Production 1.998 Million tons * 0.886 =
1.771 Million tons Probability is 39.93%
4 Trucks to 1 Loader
Calculate Match Factor 0.875• Note this is under 1 which means that
trucks are now the limiting step Bunching Factor is 0.885 Production per Truck without bunching
is 371,595 tons• 371,595*0.885 = 328,862 tons/truck
For 4 trucks 1,315,000 tons• Probability is 17.62%
3 Trucks and 1 Loader
Match Factor 0.656 Bunching is 0.931 applied to trucks Production per truck is 345,955
tons/year (with 0.931 bunching)• For 3 Trucks 1,038,000 tons/year with
4.14% probability
2 Trucks and 1 Loader
Match Factor = 0.4375 Bunching = 0.979 Production/Truck = 363,792
tons/year Two Trucks 727,582 tons/year
• With 0.55% Probability
Doing the Weighted Average
1,903,000 * 0.3771 + 1,771,000 * 0.3993 + 1,315,000 *0.1762 + 1,038,000 * 0.0441 + 727,582 * 0.0055 = 1,703,000 tons per year is the expected
production of 6 truck and 1 loader• Note that probability of the loader being down was
the 0.85 used in both the loader and the truck capacity