Process Plant Site - Layout 1 CIL Tanks Gold Room Primary Crusher Process Water Ponds Power Station Site Ball / SAG Mills Drainage Pond Coarse Ore Stockpile Vault Workshops / Offices Reagent Storage Pre-leach Thickener Pebble Crusher Jupiter Mine Service Area

Process Plant Site - Layout - Corporate · PDF fileReagent Storage Pre-leach Thickener ... High voltage and low voltage electrical reticulation complete ... Slide 1 Author: Mark Raats

  • Upload
    vokien

  • View
    220

  • Download
    3

Embed Size (px)

Citation preview

Process Plant Site - Layout

1

CIL Tanks

Gold Room

Primary Crusher

Process Water Ponds

Power Station Site

Ball / SAG Mills

Drainage Pond

Coarse Ore Stockpile Vault

Workshops / Offices

Reagent Storage

Pre-leach Thickener

Pebble Crusher

Jupiter Mine Service Area

2

TSF Cell 1

Process Plant Site – Tailings Storage Facility

3

Process Plant Site – Wingwall, Primary Crusher & Transfer Station

4

Process Plant Site – Transfer Vault Underlying Coarse Ore Stockpile

5

Process Plant Site – Ball and SAG Mill Plinths

6

Process Plant Site – CIL Tanks

7

TavernKitchen / Dining

Accommodation Blocks

RO Plant

Admin

Gym

Accommodation Village – Layout

Waste Water Treatment

8

Westralia Mine Service Area – Layout

Changerooms

DCN & RUC Offices

First Aid / Mines Rescue

Powerline Corridor

Diesel-fired Power Station

ROM Pad

Heavy Vehicle WorkshopLight Vehicle Workshop

9

MMGP Site Infrastructure Progress

Tailings Storage Facility at 30% completion

2,500m3 of concrete poured (of 3,900m3 total):

ROM pad wingwall and primary crusher vault completed

Ball mill and SAG mill plinths completed

Coarse ore stockpile reclaim vault and conveyor tunnel civils completed

Structural steel assembly commenced

Pebble crusher delivered to site

First components of grinding mills due in Fremantle within 2 weeks

Construction of all water bores to supply raw water completed

Construction of all ponds completed

Treatment Facility Site Progress at 26% Completion – On Time and Budget

10

MMGP Site Infrastructure Progress

288 rooms completed and occupied (of total 400)

Kitchen / dining room and tavern completed and operational

All buildings on site and installed

Completion scheduled for late September

All buildings on site and installed

High voltage and low voltage electrical reticulation complete

Workshops completed

MSA completion scheduled for late September

Accommodation Village

Westralia Mine Service Area (MSA)

11

Westralia Mine Development Progress

Mine development passes 1,000m, 235m ahead of Feasibility Study schedule

Underground grade control drilling has commenced with 2 rigs

First underground electrical sub-station installed

Beresford Underground