Upload
alfredo-collantes
View
26
Download
2
Embed Size (px)
DESCRIPTION
From Internet
Citation preview
Paste Thickener Design and Operation Selected to Achieve
Downstream Requirements
J. S. Slottee PasteThick Associates, USAJ. Johnson PasteThick Associates, USA
Introduction
Paste thickener design is determined by requirements for
1. Deposition 2. Pumping3. Process feed rate and characteristics
This paper describes experience supporting the design of a paste tailings system as a system
Paste Stacking Flowsheet
Paste Thickener
TransferPump
UnderflowPump
Stack
TailingsFeed
Considerations Downstream of the Paste Thickener
Disposal foot print, capacity Dam construction to contain thickened
tailings Distribution of paste to optimize capacity Site environmental requirements (i.e.
deposit permeability to groundwater)
Surface Stacking
5% slope
Flume Tests to Determine SlopeIron ore tailings
Deposition Profiles
0
5
10
15
20
25
0 1 2 3 4
Distance from leading edge, m
Mud
hei
ght,
cm
~ 20 Pa yield stress~ 55 Pa yield stress~ 280 Pa yield stress
280 Pa20 Pa
55 Pa
Pumping Paste & Thickened Tailings
Pumping requirements of paste from plant to impoundments site
Potential for gravity flow Customer preference pump choice (i.e.
centrifugal only)
Inside thickener150 Pa 35%
Thickenerdischarge
80 Pa 35% Deposition50 Pa 35%
Shear Frequently Affects Rheology
Pumped Paste: Same wt% solids, Different Yield Stress
% solids
Yie
ld S
tress
Paste Thickener DesignBased on Yield Stress
Curve
% solids
Yie
ld S
tress
Inside thickener150 Pa 35%
Shear Frequently Affects Rheology
Same Yield Stress, Different % SolidsSpecific Gravity of Solid
Example #1
Pilot Testing Demonstrated
Potential
iron ore tailings80 wt% solids
A low yield stress selected Lower pumping costs Area available for
lower stacking angle
Example #1
Plant Requirements
Example #1
Design
450 tph design throughput Varying feed t/hr 18 m dia, 12 m sidewall
height paste thickener 3 centrifugal pumps in
series for transportation
Example #2
Glass Sands Tailings
Example #2Deposit Slope
Example #2
Pilot Shear Loop Tests
Example #2Varying Feed Particle Size and Rheology
Example #2Design
High Density Recommended
Deep Bed High Density
Diameter, m (ft) 18 (59) 15 (49) 18 (59) Sidewall ht, m (ft) 7.2 (24) 15 (59) 7.2 (24) Floor Slope, degree 20 30 20 K-Factor 300 300 150
The Paste System Design Process
Summary
Downstream requirements determine underflow target and therefore type of paste thickener.
Installed paste projects repeatedly demonstrate the correct approach of a team of the thickener supplier, pumping/pipeline and geotechnical consultants.
Conclusions
Sharing rheology data between the team is essential
Rheology is greatly influenced by particle size all parties need the same awareness of particle size range
Design to a target yield stress, not wt% solids
Paste Thickener Design and Operation Selected to Achieve Downstream RequirementsIntroductionPaste Stacking FlowsheetConsiderations Downstream of the Paste ThickenerSurface StackingFlume Tests to Determine SlopeIron ore tailingsPumping Paste & Thickened TailingsShear Frequently Affects Rheology Pumped Paste: Same wt% solids, Different Yield StressPaste Thickener DesignBased on Yield Stress CurveShear Frequently Affects Rheology Same Yield Stress, Different % SolidsExample #1Pilot Testing Demonstrated PotentialExample #1Plant RequirementsExample #1 Design Example #2Glass Sands TailingsExample #2Deposit SlopeExample #2Pilot Shear Loop TestsExample #2Varying Feed Particle Size and RheologyExample #2DesignThe Paste System Design ProcessSummaryConclusions