Process: Permit to Work PS-OP-RC-2011 Prepared by: Property Services Printed copies are considered uncontrolled Rev: 9.0 Page: Page 1 of 25 Contents Objective .......................................................................................................... 2 1.0 Scope .............................................................................................................. 2 2.0 Implementation ................................................................................................ 3 3.0 3.1. Permit Application ........................................................................................ 4 Risk Assessment ................................................................................... 5 3.1.1. 3.2. Permit Administration ................................................................................... 6 RMIT Internal Consultation .................................................................... 7 3.2.1. 3.3. Permit Authorisation ..................................................................................... 8 3.4. Working under Permit Conditions ................................................................. 8 Permit Handover ................................................................................... 9 3.4.1. 3.5. Monitoring Permit to Work Activities ............................................................. 9 3.6. Permit Close Out ........................................................................................ 10 3.7. Emergency Works ...................................................................................... 10 3.8. Permits ....................................................................................................... 11 Hot Work Permit (PS-FORM-RC-2031) ............................................... 11 3.8.1. Work at Height Permit (PS-FORM-RC-2010) ...................................... 11 3.8.2. Hazardous Materials Permit (PS-FORM-RC-2037) ............................. 12 3.8.3. Service & Fire Isolation Permit (PS-FORM-RC-2036).......................... 13 3.8.4. Excavation/Penetration Permit (PS-FORM-RC-2030).......................... 15 3.8.5. Responsibilities .............................................................................................. 16 4.0 Definitions ...................................................................................................... 19 5.0 Supporting Documents................................................................................... 20 6.0 Revision ......................................................................................................... 21 7.0

Process: Permit to Work PS-OP-RC-2011mams.rmit.edu.au/8775xw4mtva11.pdf · PS-OP-RC-2011 Prepared by: ... works are performed safely, ... Safe Work Method Statement (SWMS) or risk

Embed Size (px)

Citation preview

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 1 of 25

Contents

Objective .......................................................................................................... 2 1.0

Scope .............................................................................................................. 2 2.0

Implementation ................................................................................................ 3 3.0

3.1. Permit Application ........................................................................................ 4

Risk Assessment ................................................................................... 5 3.1.1.

3.2. Permit Administration ................................................................................... 6

RMIT Internal Consultation .................................................................... 7 3.2.1.

3.3. Permit Authorisation ..................................................................................... 8

3.4. Working under Permit Conditions ................................................................. 8

Permit Handover ................................................................................... 9 3.4.1.

3.5. Monitoring Permit to Work Activities ............................................................. 9

3.6. Permit Close Out ........................................................................................ 10

3.7. Emergency Works ...................................................................................... 10

3.8. Permits ....................................................................................................... 11

Hot Work Permit (PS-FORM-RC-2031) ............................................... 11 3.8.1.

Work at Height Permit (PS-FORM-RC-2010) ...................................... 11 3.8.2.

Hazardous Materials Permit (PS-FORM-RC-2037) ............................. 12 3.8.3.

Service & Fire Isolation Permit (PS-FORM-RC-2036) .......................... 13 3.8.4.

Excavation/Penetration Permit (PS-FORM-RC-2030) .......................... 15 3.8.5.

Responsibilities .............................................................................................. 16 4.0

Definitions ...................................................................................................... 19 5.0

Supporting Documents................................................................................... 20 6.0

Revision ......................................................................................................... 21 7.0

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 2 of 25

Objective 1.0

The objective of this procedure is to explain the Property Services permit to work

(PTW) process for the management of nominated high risk work activities, completed

by Property Service engaged contractors.

Scope 2.0

The scope of the permit to work process applies to the following nominated high risk

work activities, completed by contractors engaged by Property Services:

Hot works

Service and fire isolations

Work at heights

Excavations/penetrations

Hazardous materials

This process is applicable to all works managed by Property Services. Works

engaged or conducted by RMIT staff or students currently falls outside of the scope of

this process, as such all works are to be safely managed by existing risk

management processes and in consultation with relevant Senior Advisor Health,

Safety & Wellbeing.

Contractors within this process are deemed as any external parties performing works

at RMIT.

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 3 of 25

Implementation 3.0

Appendix B & C graphically outlines the process flow for permit to work process,

including application; review and approval; and close out. It includes roles for

Contractor, Permit Office, FM, PM, Technical review and Third Party Service Provider

e.g. Airmaster, Fire technician or Security services.

The Property Services representative engaging the works is responsible to

ensure that all relevant RMIT and Property Services requirements are met and

works are performed safely, including adherence with the permit to work

process. Property Services Safety Team and Permit Office will facilitate the

administration of the permit to work process. The Contractor will be

responsible for any additional costs associated with an OHS incident or

building outage/damage caused by not isolating services.

Additionally, It is encouraged that isolations which are being planned for

projects that Airmaster is engaged as soon as practicable, this will allow a

technical review and therefore ensure the review does not impact on the permit

timeframe. Airmaster have provided a schedule of rates Appendix D, to assist in

project budgeting.

Certain tasks undertaken by Property Services have been identified as having an

elevated risk to health, safety or property and require formal review and approval by

appropriate nominated RMIT personnel before being undertaken. To achieve this,

Property Services has developed a permit to work system that enables a controlled

approach to effectively manage risk.

It is the responsibility of the relevant Property Services representative (Facilities

Manager/Coordinator or Project Manager/Officer) to ensure that contractors are:

appropriately inducted into RMIT and Property Services;

aware of the Property Services permit to work system;

comply with the permit to work; and

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 4 of 25

comply with all other safety and Property Services requirements.

All Contractors are directed to the Property Services Safety Management website at:

http://www1.rmit.edu.au/propertyservices for most recent copy of ‘Property Services

Contractor Induction Booklet’.

The permit to work process is a mandatory Property Services requirement. Steps to

be taken in the event of an emergency situation are referenced in Section 3.7 below.

3.1. Permit Application

Appendix B & C graphically outlines the process flow for permit to work process for

application, including roles for Contractor, Permit Office, PM, FM, Technical Review

and Third Party Service Providers.

All Contractors are directed to the Property Services Safety Management website at:

http://www1.rmit.edu.au/propertyservices for most recent copy of Property Services

permit to work forms. Questions should be directed to the Property Services

representative engaging the works, or Property Services Permit Office via email to

[email protected].

All permit applications are to be received by the Permit Office, at least five (5)

business days prior to commencement of works. Contractors are to complete all white

(no colour) sections of the permit form. Green/grey sections will be completed by

authorised RMIT officers through the review and approval process. The permit

applicant is the individual requesting the permit application and is to be listed on the

front page of each permit application.

The contractor is responsible for completing the relevant permit forms in consultation

with the Property Services representative engaging the works. The Property Services

representative is responsible for verifying the content, work description and timeline of

the works nominated in the permit application. All applications and associated

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 5 of 25

documentation are to be submitted to the Permit Office for administration, via the

following email address [email protected].

With the exception of the Hot Work Permit, the contractor must nominate on the

permit, the individual (permit holder) who will be in direct control of the works for the

duration outlined on the permit form. Where the permit holder changes, a separate

permit applications is to be submitted, nominating relevant permit holder and duration.

The Permit Holder will be responsible for ensuring that the work is undertaken in

accordance with the permit conditions and must actively monitor the works performed

under the permit.

The contractor must include relevant supporting documentation in permit applications,

along with completed permit form(s). This documentation may include:

Safe Work Method Statement (SWMS) or risk assessment;

Licenses and/or competencies for personnel undertaking the work;

Emergency response procedures/plans;

Relevant regulatory authority approvals or notifications; and

Reports from other service providers, such as service location reports.

The contractor and Property Services representative must consider all implications of

the work/task to be performed e.g. hot works should consider fire isolations,

excavation should consider service isolations. All relevant permit forms required to

safely conduct the task, are to be registered in one application, if this does not occur

permit applications will likely be delayed.

Where third party service providers e.g. Airmaster, fire engineer or Security are

required to assist with permitted works, the Property Service representative engaging

the works is responsible to ensure the third party is scheduled and provided with

adequate notice of the works.

Risk Assessment 3.1.1.

Where applicable, SWMS or risk assessment will be completed by the Contractor and

provided to Permit Office for review prior to permit approval.

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 6 of 25

The SWMS or risk assessment must be site/task specific and clearly identify the

hazards associated with all activities associated with the work: including site set up,

demobilisation and any potential impacts on the surrounding facilities or persons. The

SWMS or risk assessment will follow a logical sequence for the work and will include

provision of sign off by site personnel prior to commencement of approved works.

Control measures will be specified in accordance with the hierarchy of control

methodology.

Note: A SWMS is a mandatory requirement for high risk construction work, as

defined by health and safety regulations.

3.2. Permit Administration

On receipt of the permit and associated information, the Permit Office shall review the

documentation to ensure completeness. Where it is deemed that the information is

incomplete, the Permit Office will return the application to the relevant Contractor and

Property Services representative and indicate data gaps and request additional

information.

Where it is deemed that the permit application is complete, the Permit Office shall

process the application, assign a unique application number and log into the permit

register. The permit and associated documentation will be forwarded to the relevant

Permit Authoriser or for Technical Review (Refer to Section 3.3). Upon approval of

the permit, the Permit Office will consult with the relevant Property Services

representative engaging the works and the relevant Facilities Asset Management

representative and record on the permit application. The Permit Office is responsible

to ensure the permit register is updated at appropriate stages of the permit to work

process.

Upon approval the permit will then be issued to the relevant stakeholders, so that

works can commence. This may include Airmaster, Security or a third party service

provider for completion of fire or service isolations. Where third parties involvement is

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 7 of 25

required (as indicated on fire/service isolation permit e.g. sprinkler, mechanical,

electrical etc.) the Property Services representative must raise a work order and liaise

with the relevant third party to schedule isolations with advance notice. This work

order number is to be provided on the isolations permit application. Once permit is

approved Permit Office will advise relevant third party that permit is approved and

isolations can be conducted. The Permit Office is responsible for ensuring that the

Permit, and associated documentation, is maintained in accordance with this

Procedure.

RMIT Internal Consultation 3.2.1.

Prior to issuing the permit to the contractor, the Permit Office will consult with:

FM to confirm that the works do not impact or conflict with other works

planned on the campus. This consultation will be indicated on the relevant

permit.

PS Representative to confirm that they are aware of planned works and have

discussed with Contractor. In addition, confirmation will be sought to confirm

that a Works Notification will be issued by the Property Services

representative where there may be disruption to occupants. This consultation

will be indicated on the relevant permit. Additionally, the PS Representative

must communicate with ITS any permits that may impact them, particularly

electrical isolations, the PS Representative will need to ensure there is an

applicable IT Servicenow number for these isolations.

Technical Review 3.2.2.

Isolation permits will be sent to [email protected] for technical

review. This will not include smoke and thermal isolations that are not all

level/all building impacting

Airmaster will confirm they have received the request for Technical Review

and keep the Permit Office updated on any delays

The Technical Review will be completed using the agreed template by

Airmaster and RMIT. This is retained by the Project Team and Permit Office.

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 8 of 25

3.3. Permit Authorisation

Appendix B &C graphically outlines the process flow for permit to work process for

permit review and approval, including roles for Permit Office, FM, PM and Technical

review.

The Permit Authoriser is responsible for reviewing the permit and any attached

information, such as SWMS or risk assessments. Where the Permit Authoriser is

satisfied with the information presented, the permit may be authorised. This will

include recording:

Any additional permit conditions; and

Permit validity period (noting a maximum 30 days only).

Where the Permit Authoriser is not satisfied with the information presented, the

Permit Authoriser will liaise directly with the relevant contractor Property Services

representative to obtain the necessary additional information. The permit will not be

authorised until the appropriate information has been made available and reviewed by

the Permit Authoriser.

The validity period of all permits will not exceed 30 days. Following expiry, the permit

will be considered to be cancelled.

Property Services Safety Team are available to assist Authorisers in the review and

approval of any permit.

3.4. Working under Permit Conditions

The person (Contractor representative) in direct control of the work and present on

site (Permit Holder), will be indicated on the permit, there is to be only one Permit

Holder per shift and no more than two Permit Holders for any permit. This person is

responsible for ensuring that the work is being undertaken in accordance with the

permit conditions. Where it is deemed that the permit does not adequately address

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 9 of 25

the task risks, the contractor must cease work and notify the relevant Property

Services representative.

The work will not resume until the task has been reviewed and the permit revised, as

necessary. Any amendments to an approved permit are to be recorded on the permit,

initialled by the contractor and Permit Authoriser; or a new permit is applied for and

issued.

It is the responsibility of the Permit Holder to communicate any changes to the permit

to all relevant team members, specifically all members of the permitted workforce.

A copy of the permit must be readily available at the location of the works for review

and sign on by those completing the works (Permit workforce) and Property Services

representatives, during monitoring activities. All workers performing works under the

permit (Permit workforce) must sign on to the permit prior to commencement of

works.

Permit Handover 3.4.1.

Where the person controlling the work (Permit Holder) changes, the work will cease

until such time as a permit handover is completed. A permit handover will require

attendance of the ‘new’ Permit Holder, Contractor representative (preferably Permit

Requestor) and Property Services representative and/or Permit Authoriser, as a

minimum. The handover process is to be completed and documented on the permit.

3.5. Monitoring Permit to Work Activities

Permit Holder and Contractor are responsible for monitoring and ensuring

compliance of the permit for duration of works.

The Property Services Safety Team will conduct ad-hoc or scheduled contractor

inspections. These inspections may include viewing of permits, where relevant. Any

incidents or hazards observed will be recorded in RMITs incident and hazard

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 10 of 25

reporting tool (PRIME) in accordance with Global Safety Management (GSM)

requirements.

Permit to Work activities may be informally monitored on an ad-hoc basis by the

relevant Property Services representative or RMIT Security.

Permits may be cancelled at any time where the permit conditions are not being

adhered to or if it is deemed that the permit conditions do not adequately address the

task hazards.

3.6. Permit Close Out

Appendix B & C graphically outlines the process flow for permit to work process for

close out, including roles for Contractor and Permit Office.

At the completion of works or expiry of the permit duration, the contractor must review

the work site/location and confirm:

That all personnel, tools and equipment are accounted for; and

The site has been made good and/or returned to a safe condition.

Following satisfactory review of the work site/location the contractor must sign off on

the permit as being closed out and return the permit to the Permit Office via

[email protected].

It is expected that all permits will be closed out and returned to the Permit Office

within 24 hours of expiry.

3.7. Emergency Works

In the event that emergency works are required, these may be directed to proceed in

a safe manner consistent with the intent of this process and with approval of the

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 11 of 25

Executive Director Property Services (EDPS) or nominated delegate. Emergency

service or fire isolations may be performed as required to make safe, and/or minimise

damage to assets/property, or as directed by Emergency Services e.g. MFB.

Note: Due to insurance notification requirements, a Fire Isolation Permit is a

mandatory requirement. However, in the event of an emergency, this permit may be

completed and issued to the Permit Office, immediately after the site has been made

safe.

3.8. Permits

Hot Work Permit (PS-FORM-RC-2031) 3.8.1.

Contractors are expected to have their own hot work permit process in place, as a

result, the RMIT Hot Work Permit is used to verify that the contractor’s hot work

permit process meets a number of minimum requirements.

The Permit Approver will review the relevant contractor’s hot work permit against the

requirements of Section 2 of the RMIT Hot Work Permit and record outcomes

accordingly.

The hot work permit review process may be undertaken during periodic contractor

management processes, such as quarterly contract meetings or capital works project

meetings.

Work at Height Permit (PS-FORM-RC-2010) 3.8.2.

The Work at Height permit is applied where the relevant contractor intends to utilise

RMIT maintained height access infrastructure, for example:

Anchor points;

Life lines; and

Davit arms.

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 12 of 25

It is RMIT’s responsibility to ensure that RMIT height access infrastructure is

appropriately maintained, however maintenance details, e.g. inspection/test dates,

must be recorded by the contractor on the Work at Height Permit.

As part of the approval process, the Permit Authoriser must review the following

attached permit documentation:

Site and task specific SWMS or risk assessment;

Work at height competencies; and

Work at height rescue plan.

The minimum competency requirement for work at height is the National recognised

course – RIIWHS204D – Work safely at heights.

Documented rescue plans must be established to enable the safe rescue of a

suspended person within a reasonable timeframe, to reduce the risk of suspension

trauma and to enable the application of first aid, should it be required. Contractors

must have the capacity to safely rescue a worker from height without assistance from

public emergency services.

Hazardous Materials Permit (PS-FORM-RC-2037) 3.8.3.

The Hazardous Materials Permit is applied where contractor works are being

conducted in Building 108, Building 201, where works have the potential to disturb

Asbestos/Lead Containing Materials and works that will disturb SMF within the ceiling

void of Building 11 Level 3.

The Hazardous Materials Permit may be valid for the duration of the specific work

activity, however the validity period will not exceed 30 days.

As part of the approval process, the Permit Authoriser must review the following

attached permit documentation:

Asbestos Management Plan/ Scope of Works (where applicable);

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 13 of 25

Site and task specific SWMS or risk assessment; and

Evidence of appropriate competency of workers.

Where a hygienist has been engaged to facilitate the work, specific documentation

must be obtained by the relevant Property Services representative on close out of the

permit, including:

Air monitoring certificates;

Clearance certificates;

Environmental waste transfer dockets; and

Updated asbestos register.

Note: The Hazardous Materials Permit is required to be completed for all works

undertaken in Buildings 108 and 201 and all works that will disturb SMF within the

ceiling void of Building 11 Level 3.

Service & Fire Isolation Permit (PS-FORM-RC-2036) 3.8.4.

The Service & Fire Isolation Permit is applied where a contractor is undertaking works

that may impact on services, such as:

Fire (includes work that may generate heat, smoke, dust or odours);

Mechanical;

Gas;

Electrical; and

Hydraulic/water.

The contractor will record the specific dates and times the isolation is required in

Section 3 of the Permit, however this will be reviewed and amended at the discretion

of the Permit Authoriser. Service & Fire Isolations (not localised / smaller scale smoke

and thermal isolations) will require a technical review, it is encouraged that Airmaster

is engaged prior to the Permit Process so that this review does not impact the

timeline of the Permit Application. The process for Service & Fire Isolations is shown

in Appendix C.

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 14 of 25

The contractor and Property Services representative are to be copied into emails

where Service and Fire Isolation Permits are issued to a service provider for

completion of isolations.

It is the responsibility of the relevant Property Services representative to engage with

and schedule third party service providers for completion of isolations and raise a

purchase order. The service and fire isolation permits denotes services that may

require third party isolation. Who can be engaged for these services are outlined in

Figure 1 below -

Figure 1 Service Provider for Service and Fire Isolations

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 15 of 25

Additionally, please refer to Appendix D for schedule of rates to allow project

budgeting.

Excavation/Penetration Permit (PS-FORM-RC-2030) 3.8.5.

The Excavation/Penetration Permit is applied where a contractor is required to break

or penetrate the ground.

The Excavation/Penetration Permit may be valid for the duration of the specific work

activity, however the validity period will not exceed 30 days.

Prior to authorisation of the permit, the Permit Authoriser must ensure that the

contractor has made every reasonable attempt to identify services. This will include

completion of service location activities, such as:

Review of existing service maps or plans;

Dial before you dig;

Underground service location detection; and

Slab/wall scanning.

As part of the approval process, the Permit Authoriser must review the following

attached permit documentation:

Site and task specific SWMS or risk assessment;

Evidence of appropriate competency of plant and equipment operators; and

Emergency response plan.

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 16 of 25

Responsibilities 4.0

Position Responsibilities

Executive Director Property Services

Ensure Property Services stakeholders are provided

adequate support and resource to allow for compliance

with this procedure

Senior Manager, Hazardous Materials and Safety

Confirm and document that Permit Authorisers have

acquired through training, qualification or experience the

knowledge and skills to carry out the task

Ensure that the permit to work process is reviewed

auditing and updated driving continuous improvement

Provide information, instruction and/or training on the

permit to work process to relevant stakeholders

Provide resource, technical support and guidance to

Permit Office as required

Permit Office

Monitor the Permit Office email and process permits in

accordance with agreed timeframes

Review permits to ensure that information is complete

Liaise with contractors, Property Services representatives,

FM and Technical Services or other relevant stakeholder

to facilitate the Permit to Work Process

Maintain the Permit and Isolations Register

Maintain the permit and associated documentation in

accordance with this Procedure

Escalate any Permit to Work procedural issues to the

Senior Manager Hazardous Materials & Safety

Participate in information, instruction and/or training with

regard to the Permit to Work Process

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 17 of 25

Position Responsibilities

Permit Authoriser

Authorise permits relevant to their area of competency

and where authorised to do so

Review the completed permit and associated

documentation prior to permit authorisation

Liaise with contractors or PS representatives or other

relevant stakeholder to facilitate the Permit to Work

Process

Authorise permits by signing the relevant section of the

permit

Escalate any Permit to Work procedural issues to the

Senior Manager Hazardous Materials & Safety

Participate in information, instruction and/or training with

regard to the Permit to Work Process

Property Services Representative

Communicate Permit to Work requirements to contractors

Liaise with the contractor, Permit Office, Technical Team

and Permit Authoriser for the facilitation of the Permit to

Work Process

Monitor the work site/location to verify that the permit

conditions are being complied with and that the permit is

relevant for the works

Report any Permit to Work related issues to the Manager

Hazardous Materials & Safety

Participate in information, instruction and/or training with

regard to the Permit to Work Process

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 18 of 25

Position Responsibilities

Contractor (including Permit Requester, Holder and workforce)

Completing the permit application in consultation with the

relevant Property Services representative

Providing the appropriate risk management

documentation with the relevant Permit application

Working in accordance with permit conditions and

ensuring all associated employees, contractors and sub-

contractors comply with permit conditions

Scheduling and completing permit handovers as required

Closing out permits and returning the completed permit to

the Permit Office

Reporting permit to work issues to the relevant Property

Services representative

Participating in information, instruction and/or training on

the permit to work process

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 19 of 25

Definitions 5.0

Defines any key terms and acronyms relating to the process where they apply.

Term Definition

Asbestos

Varieties of mineral silicates belonging to the serpentine or amphibole groups of rock-forming minerals, including actinolite asbestos, grunerite (or amosite) asbestos (brown), anthophyllite asbestos, chrysotile asbestos (white), crocidolite asbestos (blue) and tremolite asbestos.

Asbestos Containing Materials

Any material that, as part of its design, contains asbestos.

Emergency Works Work where if not completed immediately, may result in unacceptable harm to people, property or the environment.

Excavation Any work that involves the digging of holes, pits or trenches in the ground.

Contractor Contractor Controlling the works, if not Principal

Hot Work

Work that has the potential to create a source of ignition. This may include, but is not limited to, grinding, welding, thermal or oxygen cutting or heating and other related heat or spark producing operations.

Lead Lead is a naturally occurring metal. Pure lead can combine with other substances to form various lead compounds.

Penetration

The breaking or penetration of the ground where there is a risk of impacting services.

For the purpose of this procedure, penetration does not include routine screwing or driving of fixing items, such as nails or screws.

Permit Authoriser The RMIT nominated approver who has appropriate skills, training and competence to approve works.

Permit Handover Requires attendance of the ‘new’ Permit Holder, Contractor representative and Property Services representative and/or Permit Authoriser (as a minimum)

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 20 of 25

Term Definition

Permit Holder

The person (Contractor representative) in direct control of the work, this may be Principal Contractor or subcontractor. There is to be only one Permit Holder per shift and no more than two Permit Holders for any permit.

Permit Applicant /Requester

The individual requesting the permit application, usually the Site Manager or Project Manager. The permit applicant will be the primary contact should RMIT have any questions with regard to the application.

Permit Workforce All workers performing works under the conditions of the permit.

Principal Contractor Individual person or Company in charge of the work area

Safe Work Method Statement (SWMS)

A document that sets out the work activities to be carried out, the hazards arising from these activities and the measures to be put in place to control the risks.

SMF Synthetic Mineral Fibres

Suspension Trauma

Can occur with a fall arrest system when a person has an arrested fall and is suspended in an upright, vertical position with the harness straps causing pressure on the leg veins.

Supporting Documents 6.0

Document Number Document Name

PS-FORM-RC-2031 Hot Work Permit

PS-FORM-RC-2010 Work at Height Permit

PS-FORM-RC-2037 Hazardous Materials Permit

PS-FORM-RC-2030 Excavations/Penetrations Permit

PS-FORM-RC-2036 Fire & Service Isolations Permit

PS/WI/RC/2044 SMF Contractor Minimum Requirements

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 21 of 25

Revision 7.0

Rev No.

Issue Date

Nature of Amendment Page No(s)

Author Department

8.0 April 2018

Holistic review of process and permit forms

- TW Property Services / Safety

9.0 July 2018

Holistic review of process and permit forms

- BM Property Services / Safety

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 22 of 25

Appendix A: Permit Authorisers

Permit Type

Permit Authoriser

Work at heights Authorised RMIT Representative engaging works (or Line Manager)

Service & Fire Isolation

Senior Facilities Co-ordinator

Hazmat Not disturbing hazmat Risk of disturbing hazmat

Senior Facilities Co-ordinator Safety Team

Hot works Safety Team

Excavation/Penetration

Authorised RMIT Representative engaging works (or Line Manager)

*FM includes: Senior Facilities Co-ordinators, Facilities Co-ordinators and Technical

Services

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 23 of 25

Appendix B: Permit to Work Process Flow

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 24 of 25

Appendix C: Isolation Permit Request Work Flow

Process: Permit to Work

PS-OP-RC-2011

Prepared by:

Property Services

Printed copies are considered uncontrolled

Rev: 9.0

Page: Page 25 of 25

Appendix D – Schedule of Rates

Internal Link to Schedule of Rates