Presented by: Smt. Jopilin L. Nonglait Programme Manager, FFDA Directorate of MAWTHADRAISHAN & MAIRANG C&RD BLOCK FIELD VERIFICATION OF THE SCHEME SPA (2010-11), VALUE CHAIN (2010-11) & RKVY CORPUS FUND (2011- 12) IMPLEMENTED UNDER MSAM

Presented by: Smt. Jopilin L. Nonglait Programme Manager, FFDA Directorate of Fisheries, Shillong MAWTHADRAISHAN & MAIRANG C&RD BLOCK FIELD VERIFICATION

Embed Size (px)

Citation preview

Presented by: Smt. Jopilin L. NonglaitProgramme Manager, FFDADirectorate of Fisheries, Shillong

MAWTHADRAISHAN & MAIRANG C&RD BLOCK

FIELD VERIFICATION OF THE SCHEME SPA (2010-11), VALUE CHAIN (2010-11) & RKVY CORPUS FUND (2011-12) IMPLEMENTED UNDER

MSAM

Name of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.1 Ha

Pond identification Number (PIN)

2531391254

Bundh

Crest width >1.5M

Bottom width < 3 M

Slope 1:1

Depth < 1 M

Overflow pipe 2-4 inch

Drain pipe 8 inch

Percentage of completion 100

Remarks:They will try to raise the pond depth. Previously the pond size is less but now they have constructed another two small ponds to meet the specification.

1. Christian UP School, Nongkasen

MAIRANG BLOCK

Remarks:He has already constructed 6 ponds but 3 are meant for value chain. Seed had been stocked with own expenditure, still waiting for the Departmental fish seed.

2. Shri Emkwingshon Marngar, NongkasenName of the scheme

Value Chain

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.12 Ha

Pond identification Number (PIN)

2530991254

Bundh

Crest width 1-1.5M

Bottom width < 5 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe No overflow

Drain pipe 8 inch

Percentage of completion 100

MAIRANG BLOCK

3. Shri Bankitbok Lyngkhoi, Nongkasen

Remarks:Work is in progress, only first installment received.

Name of the schemeValue Chain

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.12 Ha

Pond identification Number (PIN)

2531091254

Bundh

Crest width > 1.5M

Bottom width > 5 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe No overflow

Drain pipe 4-6 inch

Percentage of completion 50

MAIRANG BLOCK

4. Smti. Triansinoris Iawphniaw, Langlew

Remarks:Fish seeds had been stocked borne from her own expenditure. Still waiting for the Departmental fish seed.

Name of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.1 Ha

Pond identification Number (PIN)

2528591256

Bundh

Crest width > 1.5M

Bottom width < 3 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe No overflow

Drain pipe 4-6 inch

Percentage of completion 100

MAIRANG BLOCK

5. Shri. Kesparlin Syiemlieh, Marngor

Remarks:Fish seeds had been stocked with own expenditure, 2nd installment received, loan has not clear yet.

Name of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.15 Ha

Pond identification Number (PIN)

2527491256

Bundh

Crest width > 1.5M

Bottom width > 5 M

Slope 1:1

Depth > 1.5 M

Overflow pipe No overflow

Drain pipe 4-6 inch

Percentage of completion 100

MAIRANG BLOCK

6. Shri Hoben Sohshang, Marngor

Remarks:Fish seeds had been stocked with own expenditure, 2nd installment received, pond constructed through diversion of the river.

Name of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.1 Ha

Pond identification Number (PIN)

2527691259

Bundh

Crest width > 1.5 M

Bottom width > 5 M

Slope 1:1

Depth > 1.5 M

Overflow pipe No overflow

Drain pipe 4-6 inch

Percentage of completion 100

MAIRANG BLOCK

Remarks:There is no water in the pond due to leakage, therefore he constructed with cemented wall and work is in progress.

7. Shri Finder Lyngdoh, LanglewName of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.2 Ha

Pond identification Number (PIN)

2528991254

Bundh

Crest width > 1.5 M

Bottom width 3-5 M

Slope 1:1

Depth > 1.5 M

Overflow pipe No overflow

Drain pipe 4-6 inch

Percentage of completion 100

MAIRANG BLOCK

Remarks:He conveyed the message to the Department to extend the supply of feed and fertilizers in the second year also.

8. Shri Welphang Marngar, LaitksehName of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.1 Ha

Pond identification Number (PIN)

2530191246

Bundh

Crest width > 1.5M

Bottom width > 5 M

Slope 2:1

Depth 1-1.5 M

Overflow pipe No overflow

Drain pipe 4-6 inch

Date of stocking 5-09-2013

Percentage of completion 100

MAIRANG BLOCK

Remarks:The water quality is good since he followed what he learnt from the training given to him. He is ready to construct another pond with his own expenditure.

9. Shri Ristarkhos Marngar, LaitksehName of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.1 Ha

Pond identification Number (PIN)

2530091244

Bundh

Crest width 1-1.5M

Bottom width < 3 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe 4-5 inch

Drain pipe 4-6 inch

Date of stocking 5-09-2013

Percentage of completion 100

MAIRANG BLOCK

Remarks:The pond is situated in the market place; his interest is to convert it into a tourist spot.

10. Shri Spailin Sohlang, MarkasaName of the scheme

Value Chain

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.1 Ha

Pond identification Number (PIN)

2531891259

Bundh

Crest width > 1.5 M

Bottom width > 5 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe 4-5 inch

Drain pipe 4-6 inch

Percentage of completion 100

MAIRANG BLOCK

11. Shri Planningstar Lyngdoh Mawnai, Mawroh

Remarks: The farmer takes interest on pond construction even though the subsidy could not meet his excess expenditure. Pond reconstructed with cement since the wall collapse due to penetration of water.

Name of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.1 Ha

Pond identification Number (PIN)

2536191388

Bundh

Crest width 1-1.5 M

Bottom width 3-5 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe 2-4 inch

Drain pipeNot yet installed

Percentage of completion 80

MAWTHADRAISHAN BLOCK

Remarks:Water quality is good since application of cow dung is followed up properly. She wanted to expand her pond little bit bigger. Waiting for the departmental seed.

12. Smt. Drelin Jana, MawrohName of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.1 Ha

Pond identification Number (PIN)

2536091385

Bundh

Crest width 1-1.5 M

Bottom width 3-5 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe 4-5 inch

Drain pipe 4-6 inch

Percentage of completion 100

MAWTHADRAISHAN BLOCK

Remarks:Stocked with 2 quintal of Fish seed purchased from Umsning. Still waiting for the departmental seed since the pond is already exceed 0.1 ha.

13. Smt. Mali Nongbri, MawlumkohkhrangName of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.4 Ha

Pond identification Number (PIN)

2535091333

Bundh

Crest width > 1.5 M

Bottom width 3-5 M

Slope 1:1

Depth > 1.5 M

Overflow pipe No overflow

Drain pipe 4-6 inch

Percentage of completion 100

MAWTHADRAISHAN BLOCK

Remarks:Stocked with 2 quintal of Fish seed from own expenditure.

14. Smt. Jrolmai Jana, Phudbah

Son in photo

Name of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.38 Ha

Pond identification Number (PIN)

2535991341

Bundh

Crest width > 1.5 M

Bottom width > 5 M

Slope 2:1

Depth > 1.5 M

Overflow pipe No overflow

Drain pipe 4-6 inch

Percentage of completion 100

MAWTHADRAISHAN BLOCK

Remarks:He cleared up the bank loan immediately.

15. Shri Stendro Rani, PhudbahName of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.1 Ha

Pond identification Number (PIN)

2536191341

Bundh

Crest width > 1.5 M

Bottom width > 5 M

Slope 1:1

Depth > 1.5 M

Overflow pipe 2-4 inch

Drain pipe 4-6 inch

Percentage of completion 100

MAWTHADRAISHAN BLOCK

Remarks:Fish seeds had been stocked borne from own expenditure. Still waiting for the departmental seed.

16. Shri Richardpower Lyngdoh Mawnai, Mawshut

Grand father in photo

Name of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.1 Ha

Pond identification Number (PIN)

2535091369

Bundh

Crest width > 1.5 M

Bottom width 3-5 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe 2-4 inch

Drain pipe 8 inch

Percentage of completion 100

MAWTHADRAISHAN BLOCK

Remarks:Fish seeds had been stocked borne from her own expenditure, repayment of loan is completed.

17. Smt. Patricia Lyngdoh Mawnai, Mawshut

Husband in photo

Name of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.1 Ha

Pond identification Number (PIN)

253509136

Bundh

Crest width > 1.5 M

Bottom width > 5 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe > 5 inch

Drain pipe 4-6 inch

Percentage of completion 100

MAWTHADRAISHAN BLOCK

18. Smt. Krossmolin Ryntathiang, Langstiehrim

Remarks: 250 kg of Fish seeds had been stocked borne from her own expenditure, now there many fingerlings hatched from the old brood fish; she also contributed table sized fish during the 1st Aqua fest. Water quality is good.

Husband in photo

Name of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.1 Ha

Pond identification Number (PIN)

2534291376

Bundh

Crest width 1-1.5 M

Bottom width 3-5 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe 2-4 inch

Drain pipe No drain pipe

Percentage of completion 100

MAWTHADRAISHAN BLOCK

19. Smt. Wahidir Wahlang, Sangshong

Remarks:

Fish seeds had been stocked borne from her own expenditure, repayment of loan is completed.

Husband in photo

Name of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.1 Ha

Pond identification Number (PIN)

2533291379

Bundh

Crest width 1-1.5 M

Bottom width 3-5 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe 4-5 inch

Drain pipe 4-6 inch

Percentage of completion 100

MAWTHADRAISHAN BLOCK

20. Shri Bakerlang Marbaniang, Sangshong

Remarks:

Repayment of loan is completed; the cost of labour is more since the pond is quite big.

Name of the scheme SPA

Area of the pond to be Constructed

0.1 Ha

Actual area of the pond constructed

0.88 Ha

Pond identification Number (PIN)

2532991379

Bundh

Crest width -

Bottom width -

Slope -

Depth -

Overflow pipe No overflow

Drain pipe 4-6 inch

Percentage of completion 80

MAWTHADRAISHAN BLOCK