Upload
charuee
View
279
Download
4
Embed Size (px)
Citation preview
7/26/2019 Prefabricated Construction Blocks
1/31
Pre-Feasibility Study
PPrreeffaabbrriiccaatteeddCCoonnssttrruuccttiioonn BBlloocckkss
(((SSSMMMEEEDDDAAADDDOOOCCCUUUMMMEEENNNTTT)))
Small and Medium Enterprise Development Authority
7/26/2019 Prefabricated Construction Blocks
2/31
S a a d ed u te p se eve op e t ut o ty
Pre-Feasibility Report Prefabricated Construction Blocks
DISCLAIMER
The purpose and scope of this information memorandum is to introduce the subject
matter and provide a general idea and information on the said area. All the material
included in this document is based on data/information gathered from various sources and
is based on certain assumptions. Although, due care and diligence has been taken to
compile this document, the contained information may vary due to any change in any of
the concerned factors, and the actual results may differ substantially from the presented
information. SMEDA does not assume any liability for any financial or other loss
resulting from this memorandum in consequence of undertaking this activity. Therefore,
the content of this memorandum should not be relied upon for making any decision,
investment or otherwise. The prospective user of this memorandum is encouraged to
carry out his / her own due diligence and gather any information he/she considers
necessary for making an informed decision.
The content of the information memorandum does not bind SMEDA in any legal or other
form.
DOCUMENT CONTROL
7/26/2019 Prefabricated Construction Blocks
3/31
Pre-Feasibility Report Prefabricated Construction Blocks
PPRROOJJEECCTTPPRROOFFIILLEE
11..11 OOPPPPOORRTTUUNNIITTYYRRAATTIIOONNAALLEE
Construction sector has been registered with a growth rate of 7.9 percent1. Housing and
construction is one of the major drivers of growth in more than 40 allied industries anddirectly adds to the PREFABRICATED CONSTRUCTION BLOCKS industry. In
addition, for the building of roads, flyovers and bypasses there is a mass and consistentneed of prefabricated blocks across the country. Various construction and real estate
development projects are in progress and are continuously being commissioned whichwill have high demand of prefabricated construction material all over the country.
In order to make up the backlog and meet the shortfall in the next 20 years, overall
housing construction industry has to be raised to the level of 500,000 housing units perannum. This is the extent of the annual housing market in Pakistan which positively
predicts a permanent growth in construction sector which directly adds to the potential inprefabricated building blocks segment of the construction industry.
Massive construction in the public sector especially in Karachi also contributes to the
acceleration in construction sector and the quantum of work will continue at least for thenext two to three years at the same pace which surely predicts a great investment
opportunity in the proposed business.
The aforementioned statistics provide enough evidences and ensure a steep andcontinuous growth vis--vis investment opportunity in the PREFABRICATED
CONSTRUCTION BLOCKS business.
11..22 PPRROOJJEECCTT BBRRIIEEFF
7/26/2019 Prefabricated Construction Blocks
4/31
Pre-Feasibility Report Prefabricated Construction Blocks
economic feasibility of the venture. Determination of level of demand for blocks in thearea (how many per month) and degree of competition from other block yards are
important factors having a significant bearing on the feasibility of the venture. Thencomes the cost estimation based on various methods of production and output. Factors
which influence unit cost include:
Purchase price or rental of site
Cost of site improvements: fencing, paved areas for production and stockpiles,pathways, roadways and buildings
Cost of equipment: concrete mixer, block making machine and miscellaneousequipment
Cost of services: water and electricity
Material costs
Wastage
Maintenance costs of site and equipment
Output: number of blocks per day dimensions of block, solid or hollow.
Labor costs
Cost of finance etc.
11..33 MMAARRKKEETTEENNTTRRYYTTIIMMIINNGG
Blocks making business depends on activity and movement in construction industry.Housing and construction plus government initiated development projects demand mass
availability of blocks all over the year. Therefore, a block manufacturing unit could beestablished at any time of the year.
11..44 PPRROOPPOOSSEEDDBBUUSSIINNEESSSSLLEEGGAALLSSTTAATTUUSS
The legal status of business tends to play an important role in any setup; the proposed
bl k d i d S l P i hi b i
7/26/2019 Prefabricated Construction Blocks
5/31
Pre-Feasibility Report Prefabricated Construction Blocks
1. Solid Block
2. Hollow Block
3. Pavers
4. Kerb stone / Blocks
1.5.1 Raw Material Sourcing
Raw material to be used for the production of concrete based block is available in the
local market at reasonable price. Main production material components include: cementand sand/crushed stone. A number of suppliers are available for Sand and Crush in eachregion and area of Pakistan and could easily be contacted, whereas, cement could be
procured from any well known cement company. Cement suppliers could also be one ofthe sources for sand and crush supply reference. Low quality Chinese cement is also
available in the local market which has been declared substandard for consumption byPSQCA.
Volatility in cement prices is the biggest threat while working in construction industry.
7/26/2019 Prefabricated Construction Blocks
6/31
Pre-Feasibility Report Prefabricated Construction Blocks
S.
No. Block Type
Size/
Dimension Standard
Production(as % of
Total)
ColorSelling
Price/ unit
(Rs.)
1 Masonry Block
Solid Block 4x8x12 600-800 psi* 10% Natural Grey 15
Solid Block 5x8x12 600-800 psi 20% Natural Grey 16
Solid Block 6x8x12 600-800 psi 10% Natural Grey 17
Hollow Block 5x8x16 600-800 psi 10% Natural Grey 23
Fair Face Blocks
Solid Block 90x190x390 mm 600-800 psi 15% Natural Grey 28
2 Pavers 300x300x40mm 4000 psi 5% Natural Grey 40
3 Kerb Stone/Block 6x12x12 5000 psi 30% Natural Grey 90
* per square inch
11..88 RREECCOOMMMMEENNDDEEDDPPRROOJJEECCTTPPAARRAAMMEETTEERRSS
Capacity Human Resource Technology/Machinery Location
50% Capacity Utilisation
(based on 8 working hrs. daily17 Both Local and Imported
Nooriabad,
Sindh
Financial Summary
Project Cost IRR NPV Payback Period
Cost of
Capital
(WACC)
Rs. 43.04 million 26%14,127,743
4 Years 17.50%
11..99 PPRROOPPOOSSEEDDLLOOCCAATTIIOONN
P d l ti f tti f b t ti bl k ki it l l d d
7/26/2019 Prefabricated Construction Blocks
7/31
Pre-Feasibility Report Prefabricated Construction Blocks
developed cities and towns i.e. Karachi, Lahore, Multan, Faisalabad, Peshawar, Quettaetc.
11..1100 KKEEYYSSUUCCCCEESSSSFFAACCTTOORRSS//PPRRAACCTTIICCAALLTTIIPPSSFFOORRSSUUCCCCEESSSS
Prefab construction blocks business is dependent on the pricing and margins given tobuilders, suppliers and retail customers. It also depends on efficient supply of blocks to
the customer and communication facilities provided to the prospective clients, retailersand order booking agents.
1.10.1 Conventional Order Booking Arrangements Distribution
As we have discussed earlier, prefab construction blocks is one of the allied sectors ofconstruction industry. Therefore, all raw material suppliers to the construction industry
are considered to be the part of the distribution network for the prefab constructionblocks.
A block maker when setting up a block yard, institutes contacts with the constructionmaterial suppliers, retailers and signup a contract in order to appoint them as orderbooking agents. Generally, construction and building material supplier is the part of the
whole chain, and brings together the customers and suppliers. Sometimes the supplier hashis own delivery vehicles and in most of the cases, keeps arrangement with the
commercial vehicle operators, material manufacturers, and buyer, having a significanceof a pivoting point among them.
1.10.2 Ordering and Delivery Procedure:
Block maker appoints order booking agents (building material suppliers) with in the city
who entertain the customer Customers usually send someone or personally go to the
7/26/2019 Prefabricated Construction Blocks
8/31
Pre-Feasibility Report Prefabricated Construction Blocks
orders using hired delivery vehicles. Bulk deliveries typically account for around 30% ofthe total annual sales.
In the Prefab construction blocks industry, the role of the middle man is played by
building material suppliers at a nominal margin of 1% to 2% of the order booked.
11..1111 PPRROODDUUCCTTMMAARRKKEETTIINNGG
In the manufacturing industry, marketing is considered to be of significant importance. In
the Prefab construction blocks industry, marketing parameters are very limited andlargely associated with the construction sectors performance. Some of the marketing
promotion activities which should duly be rendered are given below:
Developing contacts with the building material suppliers, well known builders andcontractors.
Keep up to date information on civil and construction works initiated by local,provincial and central government.
Draw linkages with material suppliers to the housing industry at town level.
Emphasis on image development and building acquaintances across individualcontractors who are serving private sector.
Establish contacts with local civil engineering firms, individuals and professionals.
22.. SSEECCTTOORR&&IINNDDUUSSTTRRYY AANNAALLYYSSIISS
22..11 SSEECCTTOORRCCHHAARRAACCTTEERRIISSTTIICCSSAANNDDOOVVEERRVVIIEEWW
Construction sector is one of the largest economic sectors of Pakistan in terms of3
7/26/2019 Prefabricated Construction Blocks
9/31
Pre-Feasibility Report Prefabricated Construction Blocks
Prefab construction block have different categories from smallest size of a brick to a huge
sized pre-cast concrete bridges. However, for the purpose of this pre-feasibility, we havefocused on the manufacturing setups where various types of blocks are manufactured
with the help of automatic or semi-automatic plant and machinery. This sector is largelyunorganized and no statistics are available in terms of how many block manufacturing
units are working and their scale of operations. The prefab construction blocksmanufacturing sector can be divided into three categories:
Organized Sector Machine Blocks
Organized sector constitutes only three major players in Karachi: Envicrete Private
Limited, Hubcrete and Izhar Paver Blocks. Only Envicrete is working as a private limitedcompany; other two are operating as sole proprietorship companies. All companies use
imported plants and machinery due to their large scale of operations. Standard blocks aregenerally available in the sizes of 6x8x12, 5x8x12 and 4x8x12. Product quality
is defined in PSI (per squire inch pressure) which a block can survive. Generally itdepends on the use of block which varies from product to product. Housing construction
purpose block has a normal PSI of 400 and pavers are manufactured with 5000 PSIstrength. Except for Envicrete, other two manufacturers are concentrating only on pavers
and kerb stones.
Unorganized Sector Machine Blocks
This sector mainly includes block yards where hand operated mechanical machines areused to make concrete blocks which lay six and above blocks at a time. Therefore, their
operations are limited and usually work on the basis of area to area demand. Hundreds ofsuch setups could be seen in each area of the country where these setups are fulfilling the
local housing construction demand of blocks of three different sizes and strengths
7/26/2019 Prefabricated Construction Blocks
10/31
Pre-Feasibility Report Prefabricated Construction Blocks
22..22 EENNVVIIRROONNMMEENNTTAALL&&PPRROOTTEECCTTIIOONNAASSPPEECCTTSS
Block making results in persistent exposure to the asbestos (due to dust emission), whichis a natural fiber found in the dust particles of cement and blocks. To avoid its harmful
effect on human health, it is suggested to follow guidelines provided by the provincialagency of environment protection. These procedures do not particularly apply on theblock manufacturing industry, rather, a standard material, product and process handling
guidelines applicable to construction and allied industries are available on the website:www.environment.gov.pk
33.. MMAARRKKEETTIINNFFOORRMMAATTIIOONN
33..11 MMAARRKKEETTPPOOTTEENNTTIIAALL
Prefab construction blocks making units across the country are working mostly as
unorganized sector (about 80%) and no reliable data is available, precisely, for the
installed capacity and the number of units working etc. However, since it is an alliedindustry of the construction sector, growth in construction sector may be considered as aclose proxy for the growth in prefab construction blocks sector which is 7.9% (Economic
Survey of Pakistan 2006).
33..22 EEXXPPOORRTTSSAANNDDIIMMPPOORRTTSSOOFFPPRREEFFAABBCCOONNSSTTRRUUCCTTIIOONNBBLLOOCCKKSS
Prefabricated construction blocks or other products are heavy; hence there are limited
opportunities for export due to high cost of transportation. The market scope for prefabconstruction blocks is found to be encouraging in local market with the increased demand
from construction industry. There is also a sufficient demand from Govt. Contractors forlying of roads and construction of industries.
7/26/2019 Prefabricated Construction Blocks
11/31
Pre-Feasibility Report Prefabricated Construction Blocks
44.. PPRROODDUUCCTTIIOONNPPRROOCCEESSSS
44..11 PPRREEFFAABBCCOONNSSTTRRUUCCTTIIOONNBBLLOOCCKKSS--PPRROODDUUCCTTIIOONNPPRROOCCEESSSSFFLLOOWW
PPrreeffaabbccoonnssttrruuccttiioonnbblloocckkss
PPrroocceessssFFllooww
Ordering &
Stockpiling
Material
Batching
Mixing
Molding
Curing
7/26/2019 Prefabricated Construction Blocks
12/31
Pre-Feasibility Report Prefabricated Construction Blocks
The following steps are commonly used to manufacture concrete blocks.
Mixing
The sand and gravel are stored outside in piles and are transferred into storage bins inthe plant by a conveyor belt as they are needed. The Portland cement is stored outside
in large vertical silos to protect it from moisture.
As a production run starts, the required amounts of sand, gravel, and cement aretransferred by gravity or by mechanical means to a weigh batcher, which measures
the proper amounts of each material.
The dry materials then flow into a stationary mixer where they are blended togetherfor several minutes. There are two types of mixers commonly used. One type, called aplanetary or pan mixer, resembles a shallow pan with a lid. Mixing blades are
attached to a vertical rotating shaft inside the mixer. The other type is called ahorizontal drum mixer. It resembles a coffee can turned on its side and has mixing
blades attached to a horizontal rotating shaft inside the mixer.
After the dry materials are blended, a small amount of water is added to the mixer. Ifthe plant is located in a climate subject to temperature extremes, the water may first
pass through a heater or chiller to regulate its temperature. Admixture chemicals andcoloring pigments may also be added at this time. The concrete is then mixed for six
to eight minutes.
Molding
Once the load of concrete is thoroughly mixed, it is dumped into an inclined bucketconveyor and transported to an elevated hopper. The mixing cycle begins again for
the next load.
From the hopper, the concrete is conveyed to another hopper on top of the blockmachine at a measured flow rate. In the block machine, the concrete is forced
downward into molds. The molds consist of an outer mold box containing severalmold liners The liners determine the outer shape of the block and the inner shape of
7/26/2019 Prefabricated Construction Blocks
13/31
Pre-Feasibility Report Prefabricated Construction Blocks
Curing
The pallets of blocks are conveyed to an automated stacker or loader which placesthem in a curing rack. Each rack holds several hundred blocks. When a rack is full, it
is rolled onto a set of rails and moved into a curing kiln.
The kiln is an enclosed room with the capacity to hold several racks of blocks at atime. There are two basic types of curing kilns. The most common type is a low-
pressure steam kiln. In this type, the blocks are held in the kiln for one to three hoursat room temperature to allow them to harden slightly. Steam is then gradually
introduced to raise the temperature at a controlled rate of not more than 60F per hour
(16C per hour). Standard weight blocks are usually cured at a temperature of 150-165F (66-74C), while lightweight blocks are cured at 170-185F (77-85C). Whenthe curing temperature has been reached, the steam is shut off, and the blocks are
allowed to soak in the hot, moist air for 12-18 hours. After soaking, the blocks aredried by exhausting the moist air and further raising the temperature in the kiln. The
whole curing cycle takes about 24 hours.
Another type of kiln is the high-pressure steam kiln, sometimes called an autoclave.In this type, the temperature is raised to 300-375F (149-191C), and the pressure is
raised to 80-185 psi (5.5-12.8 bar). The blocks are allowed to soak for five to 10hours. The pressure is then rapidly vented, which causes the blocks to quickly release
their trapped moisture. The autoclave curing process requires more energy and a moreexpensive kiln, but it can produce blocks in less time.
Cubing
The racks of cured blocks are rolled out of the kiln, and the pallets of blocks are un-stacked and placed on a chain conveyor. The blocks are pushed off the steel pallets,
and the empty pallets are fed back into the block machine to receive a new set ofmolded blocks.
If the blocks are to be made into split-face blocks, they are first molded as two blocksj i d t th O th d bl bl k d th th h litt
7/26/2019 Prefabricated Construction Blocks
14/31
Pre-Feasibility Report Prefabricated Construction Blocks
Strength
Quality of blocks should be controlled so that strengths are adequate (to avoid breakagesor rejection by customers) and mixes are as economical as possible. Ideally, blocksshould be regularly tested for strength and mixes and production processes modified ifnecessary. If testing is impracticable or unaffordable, block strength should becontinually assessed by noting whether corners and edges, or even whole blocks, tend tobreak in handling. Strength can also be assessed by knocking two mature bricks together.
Dimensions
The length and width of the units are determined by the mould and will not vary greatly.However, the height can vary and should be monitored using a simple gauge. Units ofinconsistent height will lead to difficulties in the construction of masonry and possiblerain penetration.
Shrinkage
Concrete masonry units shrink slightly after manufacture. In order to avoid thishappening in the wall, blocks should be allowed to dry out for at least seven days beforebeing used for construction.
44..22 RRAAWWMMAATTEERRIIAALL RREEQQUUIIRREEMMEENNTT
Crushed Hard Lime Stone, Sand, Cement and Water will be used as raw material formanufacturing prefab construction blocks. Crushed raw stone and sand could be
purchased directly from the excavator (quarry lease holder) or supplier, whereas, cementcould be sourced from manufacturers by signing a regular supply contract which wouldlead to a controlled cost. For the purpose of this pre-feasibility, it is proposed to hold a
l t t ith th th t f t i l li t id ibl th t i
7/26/2019 Prefabricated Construction Blocks
15/31
Pre-Feasibility Report Prefabricated Construction Blocks
44..33 MMAACCHHIINNEERRYYRREEQQUUIIRREEMMEENNTT
Although small mixing and molding units are available in the local market, yet, completemechanized plants are not available and organized setups are using imported plant andmachinery for concrete block making. European and American plants are available which
give good quality output; however, these are very expensive and not generally preferredeven by the leading players due to high capital requirement. Therefore, Chinese or any
other machinery would be more appropriate for the proposed project which gives goodquality output and is relatively more economical.
Machinery with the following specification has been proposed for the project which will
cost around Rs. 30 million.
Detailed Plant Description
HCQ6-15III Concrete Block Machine:
With a solid and robust welded steel frame, this machine is operated using
an advanced control system. Has a compact size (6 x 3.5 x 2.95m), and overallweight of 9.6MT.
Compulsory Mixer with Skip Elevator:The mixer consists of a solid mixing trough and alloy steel rotary mixing
blade, 4 vertical supports with foot plates. The platform is adapted forservice and working. To mix light weight and high density concrete with
0.5cbm per batch.
Elevator:As the pallet and fresh block convey to the elevator, they are stacked to
a maximum height of 1metre which is equivalent to 2 2 ton
7/26/2019 Prefabricated Construction Blocks
16/31
Pre-Feasibility Report Prefabricated Construction Blocks
Control Panel with Touch Screen:Heart of the control is a PLC with a touch screen color flat display. The
operator can select the functions and change the parameter directly via thescreen. The recipe can be stored and the statistics data can be downloaded.
There are many Chinese and other suppliers available on the internet and could becontacted and easily accessible. For the purpose of this pre-feasibility, we have exploredthe following machinery suppliers:
11.. Quanzhou City Licheng Huangshi Machinery Co., Ltd. (Web Address:http://huangshimachinery.en.alibaba.com/ )
2. Fujian Quanzhou Honcha Machine Make Co., Ltd.
3. Concrete Pumps
7 Ballance Road, Durban, 4001, South Africa
P. O. Box 262, Westville, 3630, South AfricaTel +27 - 31 - 303 1397 Fax +27 - 31 - 312 0294E-mail address: [email protected] address: www.concretepumps.co.za
44..44 VVEEHHIICCLLEESSFFOORRTTRRAANNSSPPOORRTTAATTIIOONN
The proposed setup would require three to four vehicles (new machinery has beenconsidered for the proposed project) to carryout transportation of raw material andfinished products. Besides, dumping and loading vehicles for the transportation of
fi i h d d t t th t ki i t ld b i it D t il f i d
7/26/2019 Prefabricated Construction Blocks
17/31
Pre-Feasibility Report Prefabricated Construction Blocks
difference between rented and purchased machinery would be very close over a longperiod of time. Therefore it would be preferred to acquire own machinery rather than
obtaining these services on rent.
44..55 PPLLAANNTTAANNDDMMAACCHHIINNEERRYYMMAAIINNTTEENNAANNCCEE
Machinery is expected to be serviced on an annual basis. During the projected period,maintenance expenses are estimated to be around 3% of the total cost of machine.
55.. LLAANNDD&&BBUUIILLDDIINNGGRREEQQUUIIRREEMMEENNTT
55..11 SSIITTEEDDEEVVEELLOOPPMMEENNTT
The Prefab construction blocks project is estimated to require a total area of one acre,which will be used for stockpiling of raw material, production of blocks, cement storageand storage of finished product. Since heavy machinery and vehicles i.e. dumper, forklifters etc. would be used which require open space for the movement as well as there
will be frequent movement of heavy transportation and delivery vehicles; therefore, largeland requirement is being recommended. Moreover, the space would also be used formachinery installation, storage and vehicle parking and different services necessary forthe project.
55..22 LLAANNDD&&BBUUIILLDDIINNGGRREEQQUUIIRREEMMEENNTTSS
5.2.1 Selecting a site
In selecting a site, consider location, access, ground slope and size. Each of these isdiscussed below.
7/26/2019 Prefabricated Construction Blocks
18/31
Pre-Feasibility Report Prefabricated Construction Blocks
Ground slope
Ideally, the site should be level or nearly so. Steep slopes make handling and productiondifficult. Terracing a steep slope is expensive.
Size
The site should be big enough for aggregate stockpiles, cement storage, production (slab
or stationary machine) block stacking, staff facilities, an office and on-site access. Withall provisions for the business, one acre would be sufficient for the project.
5.2.2 Establishing the site
The site should have provision for stockpiling aggregates and storing cement, a
production area, a stacking area, staff facilities, an office, and access between differentareas and facilities. Each of these is discussed below.
5.2.2.1 Aggregate stockpiles
Aggregates must be stockpiled in such a way that: they do not become contaminated by
soil, leaves, etc; different aggregates are kept separate; and rainwater can drain away.Ideally therefore, aggregates should be stockpiled on a concrete slab. If this is not done,
the layer of aggregates in contact with the soil should not be used for production.Aggregates must not be stockpiled under trees. Partitions should be erected between
different types of aggregate. Stockpiles should be on a slight slope so that rainwater doesnot collect in the aggregates.
5.2.2.2 Cement store
7/26/2019 Prefabricated Construction Blocks
19/31
Pre-Feasibility Report Prefabricated Construction Blocks
The size of this area depends on the method of producing blocks. A stationary machine,which forms blocks on pallets, needs a relatively small area with space around it for
operators. A mobile egg-laying machine needs a fairly large slab on which blocks aremade. Details of such a slab are discussed below.
Construction of a production slab
Area
A flat concrete slab, big enough for at least one days production, is required. To
minimize breakages in cold weather, it is recommended to increase the cement content ofthe mix or the curing period before moving the blocks. As a guideline, an 80 x 80 ft. in
area is suitable for a production of 6000 blocks per day.
Slope
Normally block production is carried out in the open, and the concrete slab should have aminimum slope of 1 in 100 to ensure proper drainage.
Thickness
Large production machines require a minimum slab thickness of 150 mm.
Joints
To prevent uncontrolled cracking of the slab, it should be divided into panels which
should be square or as close to square as possible. The half round keyway preventsdifferential settlement of adjacent slabs. The maximum joint spacing depends on the
thickness of the slab and should not exceed 6 m for slab thicknesses of 150 and 200 mm.
7/26/2019 Prefabricated Construction Blocks
20/31
Pre-Feasibility Report Prefabricated Construction Blocks
DetailsSize/Area
(Sq. Ft.)
Civil Works
/Construction
Cost/Sq. Ft.
Total
Construction
Cost
Production & Stacking Area 15,000 150 2,250,000
Cement Store 2500 300 750,000
Office & Staff facilities 400 300 120,000
Storage Area (Sand/Crush) Not limited - 0
Water Tank 4000 200 800,000
Other Services (water plant, tool shop etc.) 500 300 150,000
Total Covered Area 18,400 4,070,000
The factory would be located atNooriabad, Sindh. The reason for the selection is thatutilities, water, electricity and skilled manpower are conveniently available, whereas,
comparatively low cost of land, proximity to the target market, good transport andcommunication facilities, also account for its selection.
66.. HHUUMMAANNRREESSOOUURRCCEERREEQQUUIIRREEMMEENNTT
Construction and allied industry is a labor intensive industry; therefore, a total 18 personswill be required to handle the production operations of a prefab construction blocks
making unit. The business unit will work on one shift basis (8 hours daily). Technicalstaff with relevant experience will be required for operating production plant. The staff
will be provided training by the plant & machinery supplier.
7/26/2019 Prefabricated Construction Blocks
21/31
Pre-Feasibility Report Prefabricated Construction Blocks
Total approximate manpower required for the business operations along with therespective salaries are given in the table below:
(Pak. Rs.)
Staff Title No of Persons Monthly
Salary
Annual
Salary
Owner (Business Unit Manager)
Production Staff (Quarry/Excavation Site)
2. Forklift Operator 1 8,000 96,000
3. Dumper/Truck Driver 1 8,000 96,000
4. Helper/Laborer 2 8,000 96,000
Production Staff (Crushing Factory)
5. Production Incharge / Plant Operator 1 10,000 120,000
6. Assistant Production Plant Operator 1 5,000 60,000
7. Production Laborers 8 32,000 384,000
Total Production Staff 14 71,000 852,000
General Administration/ Selling Staff
8. Office Assistant 1 5,000 60,000
9. Security Staff 2 10,000 120,000Total G A /S Staff 3 15,000 180,000
TOTAL 17 86,000 1,032,000
6.1 Experience Requirement for the Staff
One to two year of experience on mechanized block making plant would be necessary for
the person who will operate the prefab construction blocks plant. It is also suggested thatpreference should be given to literate persons so that they could understand the
significance of undertaking health and safety measures.
7/26/2019 Prefabricated Construction Blocks
22/31
Pre-Feasibility Report Prefabricated Construction Blocks
77..22 OOVVEERRAALLLLFFAACCTTOORRYY&&OOFFFFIICCEERREENNOOVVAATTIIOONN
To renovate the factory / office premises in Year 5 and Year 10, certain expenses will be
incurred for which an amount equivalent to 5% of the total site/office construction cost isestimated.
77..33 FFAACCTTOORRYY//OOFFFFIICCEEFFUURRNNIITTUURREE
A lump sum provision of Rs. 60,000 for procurement of office/factory furniture isassumed. This would include table, desk, chairs, and office stationery. The breakup of
Factory Office Furniture & Fixtures is as follows:
Item Number Total Cost
Table & Chair for Owner 1 5,000
Tables & Chairs for Admin. Staff 1 3,000
Waiting Chairs 4 6,000Curtains & Interior Decoration for office - 5,000
Chairs for Workers/Labor 6 5000
Electrical Fittings & Lights - 30,000
Others - 6,000
Total 60,000
77..44 DDEEPPRREECCIIAATTIIOONNTTRREEAATTMMEENNTT
The treatment of depreciation would be on a diminishing balance method at the rate of
7/26/2019 Prefabricated Construction Blocks
23/31
Pre-Feasibility Report Prefabricated Construction Blocks
will be used. The cost of the utilities including electricity, diesel/fuel, telephone, andwater is estimated to be around Rs. 2 million per annum. Approximate cost of utilities has
been given below:
Utility Total Monthly
Cost (Rs.)
Total Annual
Cost (Rs.)
Annual %age
Increase
1. Electricity 58,000 696,000 5%
2. Furnace Oil, Lubricants etc. 5,000 60,000 3%
3. Diesel for Vehicles and Machinery 28,500 342,000 5%
4. Water 70,200 842,400 5%
5. Telephone 5,000 60,000 5%
Total 166,700 2,000,400
77..66 WWOORRKKIINNGGCCAAPPIITTAALLRREEQQUUIIRREEMMEENNTTSS
It is estimated that an additional amount of one million rupees (approximately) will be
required as cash in hand to meet the working capital requirements. These provisions havebeen estimated based on the following assumptions for the proposed business.
Utilities - (Office & Factory) 87,140
1. Electricity - 01 Month 58,240
2. Oil, Lubricants & Other consumables - 01 Month 5,000
3. Water - 07 days 18,900
4. Telephone - 01 Month 5,000
Salaries - Three Months (Production Staff) 213,000
Raw Material Inventories (Cement & Sand/Crushed Stone) 238,380
Cement 01 Month 325,000
7/26/2019 Prefabricated Construction Blocks
24/31
Pre-Feasibility Report Prefabricated Construction Blocks
77..88 VVEEHHIICCLLEEFFOORRSSUUPPPPOORRTTAANNDDMMAAIINNTTEENNAANNCCEESSEERRVVIICCEESS
An additional light loading vehicle would be required for providing services for themaintenance, communication of machinery spare parts, labor etc. For this purpose, atransportation vehicle has been proposed and an amount of Rs. 400,000 is assumed to berequired to purchase the vehicle.
77..99 PPRREELLIIMMIINNAARRYYEEXXPPEENNSSEESSAANNDDCCOONNTTIINNGGEENNCCYYPPRROOVVIISSIIOONN
A lump sum provision of Rs. 300,000 is assumed to cover all preliminary expenses whichwill be amortized over the 5 year period.
77..1100 SSEELLLLIINNGG&&DDIISSTTRRIIBBUUTTIIOONNEEXXPPEENNSSEESS((OORRDDEERRBBOOOOKKIINNGGAAGGEENNTTSS))
For the purpose of this pre-feasibility, it has been assumed that the block maker would
work in association with building material suppliers and will appoint 5 to 6 suppliers asbooking agents. These arrangements would raise the selling costs for the business for
which an amount equivalent to 2% of the annual sales has been assumed which alsocovers the distribution cost of bulk supplies, entertained directly by the owner.
77..1111 MMIISSCCEELLLLAANNEEOOUUSSEEXXPPEENNSSEESS
Miscellaneous expenses of running the business are assumed to be Rs. 5,000 per month.
These expenses include various items like office stationery, daily consumables, travelingallowances etc. and are assumed to increase at a nominal rate of 10% per annum.
7/26/2019 Prefabricated Construction Blocks
25/31
Pre-Feasibility Report Prefabricated Construction Blocks
77..1133 RREEVVEENNUUEEPPRROOJJEECCTTIIOONNSS
For the revenue projections, prefab construction blocks are assumed to be produced asfollows:
S.No.
Block Type Size/
Dimension Standard
Production (as % of
Total)Color
SellingPrice/ unit
1 Masonry Block
Solid Block 4x8x12 600-800 psi 10% Natural Grey 15
Solid Block 5x8x12 600-800 psi 20% Natural Grey 16 Solid Block 6x8x12 600-800 psi 10% Natural Grey 17
Hollow Block 5x8x16 600-800 psi 10% Natural Grey 23
Fair Face Blocks
Solid Block 90x190x390 mm 600-800 psi 15% Natural Grey 28
2 Pavers 300x300x40mm 4000 psi 5% Natural Grey 40
3 Kerb Stone/Block 6x12x12 5000 psi 30% Natural Grey 90
Working with the proposed plant and machinery, the project will be capable of producing
4,000 sq.ft. of concrete blocks at 100% capacity utilization with single shift of 8 hours aday. It has been assumed that it will take some time for the business to reach the optimal
capacity utilization point for the projected period. Therefore, the first year production ofprefab construction blocks has been estimated with 70% capacity utilization. Annual
increase of 3% in capacity utilization is assumed over the projection period. Allprojections are based on 8 working hrs a day with 26 days a month.
Based on our discussions with the industry experts and entrepreneurs it is assumed that
the sales price will increase with a nominal rate of 5% on all product categories during
the projected period.
7/26/2019 Prefabricated Construction Blocks
26/31
Pre-Feasibility Report Prefabricated Construction Blocks
77..1166 FFIINNAANNCCIIAALLCCHHAARRGGEESS
It is assumed that long-term financing for 5 years will be obtained in order to finance theproject investment cost. This leasing facility would be required at a rate of 15%(including 1% insurance premium) per annum with 60 monthly installments over a period
of five years.
77..1177 TTAAXXAATTIIOONN
The business is assumed to be run as a sole proprietorship; therefore, tax rates applicableon the income of an individual tax payer are used for income tax calculation of the
business.
77..1188 CCOOSSTTOOFFCCAAPPIITTAALL
The cost of capital is explained in the following table:
Particulars Rate
Required return on equity 20%Cost of finance 15%
Weighted Average Cost of Capital 17.5%
The weighted average cost of capital is based on the debt/equity ratio of 50:50.
77..1199 OOWWNNEERRSSWWIITTHHDDRRAAWWAALL
It is assumed that the owner will draw funds from the business once the desiredprofitability is reached from the start of operations. The amount would depend onbusiness sustainability and availability of funds for future growth.
7/26/2019 Prefabricated Construction Blocks
27/31
Pre-Feasibility Report Prefabricated Construction Blocks
(in Pak. Rs.)
Sr.
No.PARTICULARS TOTAL COST/DETAILS
Land 2,000,000
Plant & machinery 35,300,000
Concrete Blocks Making Plant (Imported) 30,000,000
Transportation Machinery/Vehicles 5,200,000
Plant & machinery Installation & trial run expenses 100,000
Vehicle for support and maintenance services - One light vehicle 400,000
Site/Office Renovation & Contruction 4,070,000
Factory / Office Furniture 60,000
Preliminary Expenses 300,000
Total Fixed Capital 42,130,000
Utilities - (Office & Factory) 87,140
1. Electricity - 01 Month 58,240
2. Oil, Lubricants & Other consumables - 01 Month 5,000
4. Water - 07 days 18,900
Water Requirement (Quantity) 66,000
5. Telephone - 01 Month 5,000
Salaries - Three Months (Production Staff) 213,000
Raw Material Inventories (Cement & Sand/Crushed Stone) - 07 Days 238,380
Cement - 26 Days 325,000
Sand and Crushed Stone - 07 Days 31,500
Misc. Expenses - Three months (@ 5000 /month) 15,000
Total Working Capital 910,020
TOTAL PROJECT COST 43,040,020
Loan Finance 21,520,010
Equity Financing 21,520,010
Debt:Equity Ratio (50:50) 50.00%
IRR 26%
NPV 14,127,743
Payback Period (Years) 4 Years
Debt Equity Ratio 50:50'
Required return on equity20%
Cost of finance15%
Weighted Average Cost of c apital17.50%
1 Depreciation 10%
Summary of Key Assumptions
Fixed Capital
Working Capital
PROJECT RETURNS AND OTHER FINANCIAL
OTHER ASSUMPTIONS
7/26/2019 Prefabricated Construction Blocks
28/31
Pre-Feasibility Report Prefabricated Construction Blocks
1. REVENUE CALCULATION
ProductionRated capacity of the Block Making Plant 500 sq.ft. of concrete / hr.
No. of Operating Hours - Single Shift Basis 8 Hrs / Day
Estimated Optimal Production 4,000 sq.ft. of concrete / day
Expected Capacity Utilization (At the beginning of the project) 50%
Annual Capacity Utilization Growth Rate 5%
Expected Concrete Production at the beginning of the project 2,000 sq.ft. of concrete / day
Expected Blocks Production at the beginning of the project Blocks/day
Sales prices of differe categories of construction blocks
No. of Blocks Produced (Approximately)
Size Masonry Block
4x8x12 Solid Block 450 15 Rs.5x8x12 Solid Block 840 16 Rs.
6x8x12
Solid Block 300 17 Rs.5x8x16 Hollow Block 225 23 Rs.
Fair Face Blocks
90x190x390 mm Solid Block 305 28 Rs.300x300x40mm Pavers 144 40 Rs.
6x12x12 Kerb Stone/Block 600 90 Rs.
Total Blocks Produced 2,864
Construction Block Category Production Assumptions
Masonry Block
Solid Block 15%
Solid Block 28%
Solid Block 10%
Hollow Block 10%
Fair Face Blocks
Solid Block 2%
Pavers 5%Kerb Stone/Block 30%
100%
C onst ruct ion Bl ock Category B locks Produced / D ayProduction in
RupeesMasonry Block
Solid Block 450 6,750 Rs.
Solid Block 840 13,440 Rs.
Solid Block 300 5,100 Rs. Hollow Block 225 5,175 Rs.Fair Face Blocks
Solid Block 305 8,533 Rs.Pavers 144 5,760 Rs.Kerb Stone/Block 600 54,000 Rs.
Total Value of Blocks Produced per Day 2864 98,758 Rs.
Total Value of Blocks Produced per Month 2,567,717 Rs.
Gross Annual Sales 30,812,600 Rs.
Provision for Finished Goods Inventory 7 Days
Estimated Finished Goods Inventory at the end of the Year 396,695 Rs
PREFABRICATED CONSTRUCTION BLOCKS MANUFACTURING
COST AND REVENUE SHEET
7/26/2019 Prefabricated Construction Blocks
29/31
Pre-Feasibility Report Prefabricated Construction Blocks
PREF-X/Dec, 2006/Rev1
Projected Income Statement (Rs.) Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
Net (Adjusted Sales) 30,233,409 33,930,278 37,408,136 41,242,476 45,469,835 50,130,499 55,268,883 60,933,951 67,179,689 74,065,617
Cost of Sales 17,801,280 19,617,481 21,619,315 23,825,772 26,257,785 28,938,432 31,893,150 35,149,982 38,739,840 42,696,800
Fue l & El ec tri cit y Consumed Duri ng Product ion 16, 829, 280 18,554,281 20,456,095 22,552,845 24,864,511 27,413,124 30,222,969 33,320,823 36,736,208 40,501,669
Labor (Production Staff) 852,000 937,200 1,030,920 1,134,012 1,247,413 1,372,155 1,509,370 1,660,307 1,826,338 2,008,971
Other Utilities 120,000 126,000 132,300 138,915 145,861 153,154 160,811 168,852 177,295 186,159
Gross Profit 12,432,129 14,312,797 15,788,821 17,416,704 19,212,050 21,192,067 23,375,732 25,783,969 28,439,849 31,368,817
Gross Profit Margin 41% 42% 42% 42% 42% 42% 42% 42% 42% 42%
General Administrative & Selling Expenses
Salaries 180,000 198,000 217,800 239,580 263,538 289,892 318,881 350,769 385,846 424,431
L ease Charges of Land - Quarry / Excavation 31,500 32,445 33,418 34,421 35,454 36,517 37,613 38,741 39,903 41,100
Factory/Office Miscellaneous Expenses 60,000 66,000 72,600 79,860 87,846 96,631 106,294 116,923 128,615 141,477Amortization of Preliminary Expenses 60,000 60,000 60,000 60,000 60,000 - - - - -
Depreciation Expense 3,983,000 3,584,700 3,226,230 2,903,607 2,613,246 2,372,272 2,135,045 1,921,540 1,729,386 1,556,447
Maintenance Expense 1,059,000 1,059,000 1,059,000 1,059,000 1,059,000 1,059,000 1,059,000 1,059,000 1,059,000 1,059,000
Selling & Distribution 604,668 678,606 748,163 824,850 909,397 1,002,610 1,105,378 1,218,679 1,343,594 1,481,312
Subtotal 5,978,168 5,678,751 5,417,211 5,201,317 5,028,481 4,856,921 4,762,209 4,705,652 4,686,344 4,703,768
Operating Income 6,453,961 8,634,046 10,371,610 12,215,386 14,183,569 16,335,146 18,613,523 21,078,316 23,753,505 26,665,049
Financial Charges (15% Per Annum) 3,018,969 2,516,684 1,933,654 1,256,900 471,355 - - - - -
Earnings Before Taxes 3,434,992 6,117,363 8,437,956 10,958,486 13,712,214 16,335,146 18,613,523 21,078,316 23,753,505 26,665,049
Tax 858,748 1,529,341 2,109,489 2,739,622 3,428,054 4,083,787 4,653,381 5,269,579 5,938,376 9,205,267
Net Profit 2,576,244 4,588,022 6,328,467 8,218,865 10,284,161 12,251,360 13,960,142 15,808,737 17,815,129 17,459,782
Monthly Profit After Tax 214,687 382,335 527,372 684,905 857,013 1,020,947 1,163,345 1,317,395 1,484,594 1,454,982
PREFABRICATED CONSTRUCTION BLOCKS MANUFACTURING
7/26/2019 Prefabricated Construction Blocks
30/31
Pre-Feasibility Report Prefabricated Construction Blocks
PREF-X/Dec, 2006/Rev1
Projected Balance Sheet (Rs.) Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
Ass ets
Current Assets
Cash & Bank Balance 2,671,640 3,286,008 6,603,692 9,710,622 12,678,042 14,897,694 22,622,121 30,777,191 38,022,249 45,031,816 49,254,776
Fuel Inventoriy (Diesel) 238,380 701,220 773,095 852,337 939,702 1,036,021 1,142,213 1,259,290 1,388,368 1,530,675 1,687,570
Finished Goods Inventory 0 396,695 437,309 482,080 531,436 585,844 645,824 711,944 784,833 865,185 953,764
Accounts Receivable 0 1,520,795 1,696,514 1,870,407 2,062,124 2,273,492 2,506,525 2,763,444 3,046,698 3,358,984 3,703,281
Total Current Assets 2,910,020 5,904,719 9,510,610 12,915,447 16,211,304 18,793,052 26,916,683 35,511,870 43,242,147 50,786,662 55,599,391
Fixed Assets
Plant Machinery & Facility 35,300,000 31,770,000 28,593,000 25,733,700 23,160,330 20,844,297 18,759,867 16,883,881 15,195,493 13,675,943 12,308,349
Factory Construction 4,070,000 3,663,000 3,296,700 2,967,030 2,670,327 2,606,794 2,346,115 2,111,503 1,900,353 1,710,318 1,742,786
Furniture & Fixtures 60,000 54,000 48,600 43,740 39,366 35,429 31,886 28,698 25,828 23,245 20,921
Vehicle 400,000 360,000 324,000 291,600 262,440 236,196 212,576 191,319 172,187 154,968 139,471Total Fixed Assets 39,830,000 35,847,000 32,262,300 29,036,070 26,132,463 23,722,717 21,350,445 19,215,401 17,293,860 15,564,474 14,211,527
Intangible Assets
Preliminary Expenses 300,000 240,000 180,000 120,000 60,000 - - - - - -
Total Assets 43,040,020 41,991,719 41,952,910 42,071,517 42,403,767 42,515,768 48,267,128 54,727,270 60,536,007 66,351,136 69,810,918
Owner's Equity 21,520,010 23,596,254 27,184,276 31,512,743 36,731,608 42,515,768 48,267,128 54,727,270 60,536,007 66,351,136 69,810,918
Long Term Liability 21,520,010 18,395,464 14,768,634 10,558,773 5,672,159 0 0 0 0 0 0
Total Equity & Liabilities 43,040,020 41,991,719 41,952,910 42,071,517 42,403,767 42,515,768 48,267,128 54,727,270 60,536,007 66,351,136 69,810,918
PREFABRICATED CONSTRUCTION BLOCKS MANUFACTURING
7/26/2019 Prefabricated Construction Blocks
31/31
Pre-Feasibility Report Prefabricated Construction Blocks
PREF-X/Dec, 2006/Rev1
Projected Statement of Cash Flows (Rs.) Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
Cash Flow From Operating Activities
Net Profit 0 2,576,244 4,588,022 6,328,467 8,218,865 10,284,161 12,251,360 13,960,142 15,808,737 17,815,129 17,459,782
Add: Depreciation Expense 0 3,983,000 3,584,700 3,226,230 2,903,607 2,613,246 2,372,272 2,135,045 1,921,540 1,729,386 1,556,447
Amortization Expense 0 60,000 60,000 60,000 60,000 60,000 - - - - -
(Increase) / decrease in Receivables - (1,520,795) (175,719) (173,893) (191,717) (211,368) (233,033) (256,919) (283,253) (312,287) (344,296)
(Increase) / decrease in RM - (462,840) (71,875) (79,242) (87,365) (96,319) (106,192) (117,077) (129,077) (142,308) (156,894)
(Increase) / decrease in FG Inventory (396,695) (40,613) (44,772) (49,355) (54,409) (59,979) (66,120) (72,890) (80,352) (88,579)
Net Cash Flow From Operations 0 4,238,914 7,944,515 9,316,790 10,854,035 12,595,311 14,224,427 15,655,071 17,245,057 19,009,568 18,426,460
Cash Flow From Financing Activities
Receipt of Long Term Debt 21,520,010
Repayment of Long Term Debt (3,124,546) (3,626,831) (4,209,860) (4,886,614) (5,672,159) - - - - -
Owner's Equity 21,520,010 (500,000) (1,000,000) (2,000,000) (3,000,000) (4,500,000) (6,500,000) (7,500,000) (10,000,000) (12,000,000) (14,000,000)
Net Cash F lo w Fr om Fin an ci ng Ac ti vi ti es 43,040,020 (3,624,546) (4,626,831) (6,209,860) (7,886,614) (10,172,159) (6,500,000) (7,500,000) (10,000,000) (12,000,000) (14,000,000)
Cash Flow From Investing Activities
Capital Expenditure (39,770,000) (203,500) (203,500)
Factory/Office Furniture (60,000)
Preliminary Operating Expenses (300,000)
Raw Material Inventory (15 Days) (238,380)
Net Cash Flow From Investing Activities (40,368,380) 0 0 0 0 (203,500) 0 0 0 0 (203,500)
NET CASH FLOW 2,671,640 614,368 3,317,684 3,106,930 2,967,420 2,219,652 7,724,427 8,155,071 7,245,057 7,009,568 4,222,960
Cash at the Beginning of the Period 0 2,671,640 3,286,008 6,603,692 9,710,622 12,678,042 14,897,694 22,622,121 30,777,191 38,022,249 45,031,816Cash at the End of the Period 2,671,640 3,286,008 6,603,692 9,710,622 12,678,042 14,897,694 22,622,121 30,777,191 38,022,249 45,031,816 49,254,776
PREFABRICATED CONSTRUCTION BLOCKS MANUFACTURING