Affordable Care Act Patient Center Medical Home – Facility Improvements (PCMH-FI) Grant Program HRSA-14-073. Post-Award Technical Assistance. Objectives. Describe the outcome of the Patient Centered Medical Home – Facility Improvement (PCMH-FI) Program funding opportunity - PowerPoint PPT Presentation

Citation preview

Page 1: Post-Award Technical Assistance

Affordable Care ActPatient Center Medical Home – Facility Improvements (PCMH-FI)Grant ProgramHRSA-14-073

Post-AwardTechnical Assistance

Page 2: Post-Award Technical Assistance

Describe the outcome of the Patient Centered Medical Home – Facility Improvement (PCMH-FI) Program funding opportunity

Discuss project management and critical compliance requirements

Review the terms and conditions of the PCMH-FI Notices of Award (NoA)

Explain the process for PCMH-FI post-award submission and review

Objectives

2

Page 3: Post-Award Technical Assistance

HRSA awarded $35.7 million in PCMH-FI awards to 147 health centers

Grants awarded with a 2-year project period The awards will fund one distinct, site-specific, stand-alone

facility project for either:– Alteration/Renovation (A/R) for an existing facility, or – Construction for a new site or expansion of existing site

Awards

3

Page 4: Post-Award Technical Assistance

4

HRSA Activity Code: C8C Separate PMS sub-account code located in Box 17 of the

NoA Funds must be accounted for and reported separately from

section 330 funds and from other Affordable Care Act (ACA) funds– If other sources of funding exist to support the PCMH-FI

project, PCMH-FI funds should be drawn down proportionately to approved total (Federal and non-Federal) costs

Administrative Notes

Page 5: Post-Award Technical Assistance

5

Ineligible costs include, but are not limited to: All costs incurred before 90 days prior to the award date All physical construction costs incurred prior to the award date Costs that do not meet federal procurement guidelines as listed

in 45 CFR 74.40 – 74.48 or Part 92 Land and building purchases or lease payments Operating costs (e.g., funding direct health care services, clinical

full-time equivalents, rent, mortgage payments) Permanent relocation costs Expenditures for personnel unrelated to the project Mobile vans EHR ongoing operations and maintenance Abatement of site and building hazardous material Disposable office, medical, or educational supplies

Ineligible Costs

Page 6: Post-Award Technical Assistance

6

Review all terms and conditions in the Notice of Award (NoA)

Do not begin construction or draw down funds for demolition, site preparation, or construction activities until all grant conditions have been approved and are lifted in a revised NoA

Grantees may only incur costs or draw down funds to pay for related non-construction activities:– Preparation/preliminary work (site plans, architectural

and engineering schematics, environmental and historic preservation requirements)

– Administrative planning costs directly related to the project

Before Starting Construction

Page 7: Post-Award Technical Assistance

7

A folder for the C8C grant has been created for your organization's EHB portfolio

The Authorized Official needs to ensure he/she has added the PCMH-FI grant to the portfolio and that the correct staff are assigned to roles and functions in the C8C grant folder

The following EHB Help Resource can guide you through these processes:– https://grants.hrsa.gov/webexternal/help/hlpPage.asp?hF

=grants_management#HowToAdd

Electronic Handbook (EHB)

Page 8: Post-Award Technical Assistance

8

Provides guidance on overall programmatic objectives Reviews and processes revised budgets, schematics,

concept/site plans, and construction timelines Reviews and processes prior approval requests (i.e.,

changes to project scope, project period extensions) Provides ongoing program/project monitoring and technical

assistance Closeout

Roles - Project Officer

Page 9: Post-Award Technical Assistance

9

Provides ongoing financial and grants management monitoring and technical assistance

Reviews federal interest, lease documentation, revised budgets

Reviews annual Federal Financial Reports (FFR) Processes prior approval requests (e.g., Project Director

changes) Closeout

Roles - Grants Management Specialist

Page 10: Post-Award Technical Assistance

10

The PO listed in your C8C grant folder is responsible for managing and monitoring the award. It is imperative to work with your C8C PO. PO’s for other grants, including your H80 PO are not responsible for this award and cannot authorize actions for it.

Ann Piesen is identified as the HRSA Project Officer for all PCMH-FI grants. HRSA will assign another Project Officer to each C8C/PCMH-FI grant. The assigned Project Officer has or will be contacting you shortly with their contact information.

Roles – Administrative Notes

Page 11: Post-Award Technical Assistance

How do I find out who my current PO and GMS are?1) Click on the Grants Tab in EHB

2) Find your C8C grant and click on the Grant Folder in EHB.

3) Within the C8C grant folder, select HRSA Contacts.

4) Under the HRSA Contacts section, the PO and GMS contact information will be viewable.

Roles – Administrative Notes

11

Page 12: Post-Award Technical Assistance

12

Grantees are required to submit all documentation identified as a condition of award or reporting requirement on the NoA into HRSA’s Electronic Handbook (EHB)– By default, the grantee’s Project Director as shown on

the NoA will have access to all EHB submissions– All other users must be given privileges to view, edit, or

submit by the Project Director or other user with the ability to Administer User Privileges in the Grant Handbook

HRSA Program or Grants Office Personnel may also request other information through the EHB by either requests for information or additional conditions

Electronic Document Submissions in EHB

Page 13: Post-Award Technical Assistance

13

If an extension to a submission deadline is needed:– Please discuss with your assigned C8C Project Officer

and/or Grants Management Specialist. – You must include a justification for your extension

request and describe the impact of the extension on the overall construction timeline.

– Submit extension requests through the EHB within each submission in the “request an extension” function.

Conditions with Award Issue Date deadlines: Please be aware that the deadline for demonstrating that these conditions have been met is based on the date the awards are released to Award Recipients, which may be later than the Award Issue Date in Box 1 of the NoA.

Condition Deliverables and Due Dates

Page 14: Post-Award Technical Assistance

14

The federal government always retains interest in property constructed, acquired, or improved with federal funds:– All construction projects, regardless of cost, must file a

Notice of Federal Interest (NFI) – A/R projects with total (federal and non-federal) costs

more than $500,000 (excluding moveable equipment) must file a Notice of Federal Interest (NFI)

– Applicants not required to file an NFI (A/R projects with total federal and non-federal costs less than $500,000)• Federal Interest still exists• Maintain documentation regarding protection of all

Federal Interest Additional resources are available at found at

http://bphc.hrsa.gov/policiesregulations/capital/nfifilingguide.pdf

Federal Interest Conditions

Page 15: Post-Award Technical Assistance

15

Funds may not be used to pay lease costs Funds for a leased property cannot address needs that are part of the terms

of the lease (i.e., the responsibility of the lessor) If funds address improvements that would impact terms of the lease (e.g.,

double paned windows) applicants must have written evidence of negotiated offset in the rent

The Landlord Letter of Consent/Statement of Agreement from the facility owner must address the following:– Approval of the scope of the project– Agreement to provide the applicant health center reasonable control of

the project site for required number of years– Agreement to file a Notice of Federal Interest (NFI) in the land records of

the local jurisdiction before the project begins (if applicable) HRSA will determine if the term of the lease is sufficient for the full value of

the grant-supported improvements to benefit the grant activity. HRSA will take into account the purpose and duration of the grant, the expected life of the facility, and the use of the facility for grant-supported purposes.

The lease agreement must provide the applicant reasonable control

Leasehold Improvement Conditions

Page 16: Post-Award Technical Assistance

16

Most projects will include several conditions for environmental and/or historic preservation reviews and compliance with federal laws– DO NOT begin construction or draw down funds for

demolition, site preparation, or construction activities until these conditions have been approved and are lifted

– PLEASE PLAN ACCORDINGLY in project schedules; consultation under Section 106, takes a minimum of a month to prepare, while an environmental assessment may take several additional months to prepare, review, and distribute for public comment

– Grant recipients should work closely with their C8C Project Officer and environmental reviewer

Technical assistance for environmental and historic preservation requirements is available at http://bphc.hrsa.gov/policiesregulations/capital/environmentandhistoric/capitaldevelopment.html/

Environmental and Historic Preservation Conditions

Page 17: Post-Award Technical Assistance

17

Grantees must comply with applicable procurement regulations: – All contracts for goods and services equal or greater

than $100,000 must be competitively bid– Technical assistance on this topic is available at

http://bphc.hrsa.gov/policiesregulations/capital/postaward/faqprocurment.pdf

The simplified acquisition threshold applies to work < $100,000– Recipients should keep in mind that they still need to get

more than one quote (not bids) for the work to determine that the costs are reasonable, and the threshold shall not be broken down into several purchases or artificially reduced to smaller quantities to permit negotiations under simplified acquisition procedures

Procurement Rules

Page 18: Post-Award Technical Assistance

18

Projects must be also compliant with the following: – Uniform Relocation Assistance, 45 CFR Part 15– ADA Accessibility Guidelines for Building and Facilities

(28 CFR Part 36), and the 2010 Standards for Accessible Design)

– Real Property insurance, maintenance, disposition, and federal interest, 45 CFR Part 74.31-.37, and 92.31 and DHHS Grants Policy Statement

Other Policy Requirements

Page 19: Post-Award Technical Assistance

19

Grantees are encouraged to consider the following: NFPA 101 Life Safety Code (2015 edition) AIA Guidelines for Design and Construction of Hospital and

Health Care Facilities (2009 edition) Sustainable design practices for both renovation and

construction– Green Guide for Health Care http://www.gghc.org/ – Leadership in Energy and Environmental Design

principles (LEED) http://www.usgbc.org/ Sustainable Equipment Purchases

– Electronic Product Environmental Assessment Tool (EPEAT) Silver Rated products http://www.epeat.net

– Energy Star Products http://www.energystar.gov

Design Considerations

Page 20: Post-Award Technical Assistance

20

Quarterly Progress Reports (starting January 1, 2015) – Includes information on the progress of the planning and

implementation of the project.– Additional information on the Quarterly Progress Report

(QPR) requirement can be found at http://bphc.hrsa.gov/policiesregulations/capital/• QPR Manual• QPR Quick Guide• QPR Presentation – walkthrough of the submission

process– A separate Technical Assistance Call will be scheduled in

December 2014 in preparation for the first QPR reporting period for the C8C grant

Routine Reporting

Page 21: Post-Award Technical Assistance

21

Federal Financial Report (FFR) – Reviewed by Grants Management Specialist– Includes:

• Financial Status Report (submitted annually) • Federal Cash Transaction Report (PMS) (submitted

quarterly)– Additional information is available at:

• http://www.hrsa.gov/grants/manage/technicalassistance/federalfinancialreport/ffrquickguide.pdf

• http://www.dpm.psc.gov/grant_recipient/ffr_info/ffr_info.aspx?explorer.event=true

Routine Reporting

Page 22: Post-Award Technical Assistance

22

Federal Funding and Transparency Act Reporting (FFATA)– For each Federal sub-award of $25,000 grantees must

report information about the recipient and the project being funded.

– FAQs and additional reporting requirement information are available at: http://www.hrsa.gov/grants/ffata.html

Routine Reporting

Page 23: Post-Award Technical Assistance

23

The following documentation must be submitted during the course of the project:– Project Implementation Certification – Certification of Final Design – Bonding Coverage Certification– Construction Contract Information

• Copy of the selected contract• Letter of contract certification by the hired architect • Copy of the formal recommendation(s) of award or award letter(s) • Statement of determination that the selected contractor is not on

the US General Services Administration Lists of Parties Excluded from Federal Procurement or Non-Procurement Programs (debarred list) found at http://sam.gov

• If the contract is awarded to any qualified bidder other than the lowest bidder, provide proper documentation for your decision

Templates are available at http://bphc.hrsa.gov/policiesregulations/capital/

Monitoring—Required

Page 24: Post-Award Technical Assistance

24

HRSA may request additional documentation to verify the status of the project, such as:– Milestone chart/construction schedule– Field observation reports– Application and certificate for payment (AIA G702)– Specific documentation (such as permits and invoices)

as necessary

Monitoring (as necessary)

Page 25: Post-Award Technical Assistance

25

Grantees may be required to request prior approval from HRSA for changes that occur during the grant period. These changes includes, but are not limited to:– Significant changes in the approved project budget,

including a significant increase or decrease to the total project cost, as well as significant changes to each budget line item

– Changes to the approved physical project scope (i.e., change in the square footage affected, change in the orientation of the modified physical space)

– Changes to the Project Director– Extensions to the project period

HRSA approval of a prior request will be provided in a NoA

Prior Approval Requests

Page 26: Post-Award Technical Assistance

26

Closeout documentation is required within 90 days of the completion of the PCMH-FI project

The closeout documentation consists of the following items:– Project Completion Certification

• A certificate of occupancy or evidence of acceptance by the permitting authority

• A certificate of substantial completion• Property insurance statement

– Final budget information / Final equipment list– Photos of the completed project as well as before photos

Tangible Personal Property Report (SF-428)

Closeout and Property Reports

Page 27: Post-Award Technical Assistance

Resource Purpose

HRSA Electronic Handbook (EHB)

https://grants.hrsa.gov/webexternal/home.asp

To access information about you C8C grant, identify your project officer, request prior approvals, submit responses to conditions of grant award

HRSA Call Center

877-Go4-HRSA/877-464-4772 or

301-998-7373(9:00 AM to 5:30 PM ET M-F)

Email: [email protected]

For assistance accessing EHB or with user name or and password issues

BPHC Help Line

1-877-974-BPHC

(8:30 AM to 5:30 PM ET M-F)

Email: [email protected]

For program specific help and system issues

EHB Resources

27

Page 28: Post-Award Technical Assistance

28

TA call presentation and transcripts will be available at http://www.hrsa.gov/grants/apply/assistance/PFI/

All other TA materials will be posted at http://bphc.hrsa.gov/policiesregulations/capital/– Submission templates – Program FAQs– Environmental review forms and compliance FAQs– Historic Preservation FAQs sheets– Procurement FAQs– Federal Interest FAQs