Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Portland Community College
Facilities Plan - Phase 1
Monthly Report
December 23, 2016
Portland Community College Monthly Report-01
Facilities Plan – Phase 1 December 23, 2016
1
Summary The sections in this monthly report outline the status for each work group up through the current
month. This addresses the key activities, areas of focus, outstanding questions or information requests
and the next steps. The next month report notes would follow as shown on the first work group to track
progress from month to month. A work group summary may be followed directly with a team consultant
report update.
Overall Project Outstanding Items:
1. Team Access to the Google Drives will be critical for distributing project information and for
team communications.
Contents Space Utilization Work Group ....................................................................................................................... 2
Facilities Condition Work Group ................................................................................................................... 3
Capital Projects Work Group ........................................................................................................................ 5
Safety and Security ....................................................................................................................................... 6
Transportation and Parking Work Group ..................................................................................................... 7
Information Technology Work Group ........................................................................................................... 8
ADA Work Group........................................................................................................................................... 9
Sustainability Work Group .......................................................................................................................... 10
Draft Schedule for site visits (attached) ...................................................................................................... 11
Portland Community College Monthly Report-01
Facilities Plan – Phase 1 December 23, 2016
2
Space Utilization Work Group
12.23.16:
Summary of activities: See attached summary from Tom Hier of Biddison Hier.
Key Focus for month: See attached summary from Tom Hier of Biddison Hier.
Outstanding Items: See attached summary from Tom Hier of Biddison Hier.
Next Steps: See attached summary from Tom Hier of Biddison Hier.
01.27.17: (future notes to track progress from month to month)
Summary of activities:
Key Focus for month: PCC
Outstanding Items: PCC
Next Steps: PCC
Chair Members Consultant Team
Kurt Simonds
Dean of Instruction
Cascade Campus
Laura Massey
Tonya Booker
Tricia Brand
Ken Dodge
Karen Sanders
Tatyana Batazhan
Nita Posada (SRG)
Robert Lochner (SRG)
Tom Hier (Biddison Hier)
BIDDISON HIER, LTD. Consultants to Higher Education 1515 Fifteenth Street, NW Ste 613 Washington, DC 20011 202.882.8700 202.726.2251 fax www.biddhier.com
15 December 2016
Memorandum To: Kurt Simonds From: Tom Hier RE: Space Utilization Analyses – Additional Thoughts and Next Steps This memo is a follow-up to our 29 November teleconference, where we reviewed scope of the space utilization assessment and data issues. During our teleconference, there were essentially two significant areas of discussion regarding the scope of space utilization analyses, as follows: The range of space types (e.g., academic, administrative, instructional) to include in our space
utilization assessments as well as the nature of the analyses to undertake.
For instructional spaces, how to organize data for reporting (e.g., by physical campus location; campus budgetary authority).
For your review and comment, I have summarized below what I believe we concluded, identified areas where further information is necessary, and set out some next steps.
2
1 Range o f Spa ce Type s t o I n c l u de i n Spa ce Ut i l i z a t i on As s e s smen t s
While the initial focus of our work was to assess space utilization for regularly-scheduled instructional space – and this remains the primary focus – we also discussed the utility of having better information on the amount and type of space available in other space categories on each campus. The chart below outlines these different space types and the associated analyses that may be useful for each.
To summarize:
General and Academic Administrative Space: Analyze square footage allocations (e.g., per person, per department) for the primary types of administrative space – offices, conference rooms and support spaces.
Regularly‐scheduled Instructional Space: Evaluate room and seat utilization and other standard performance metrics for regularly-scheduled instructional space.
Event Space: Catalog the various event spaces across PCC and, where possible, provide qualitative insights into their use. By their nature, activities that occur in event spaces are generally not regularly-scheduled, vary widely from week to week, can have widely variable attendance, and lack complete data on each event. So it is not possible to quantify utilization in any meaningful way. Nonetheless, there was consensus that having more complete knowledge of what event spaces exist across the institution would be helpful.
Student Support Space: As is the case with event space, catalog the various student support spaces across PCC and, where possible, provide qualitative insights into their use.
Please confirm that this is your understanding of the approach that we should adopt. We are currently trying to discover what space data are available, and obviously the ability to create the analyses noted here will be dependent on the nature and completeness of PCC space datasets.
6
Proposed Scope Revisions Based on October Steering Committee Meeting
General
Administrative
Space
Offices
Conference rooms
Support spaces
Academic
Administrative
Space
Offices
Conference rooms
Support spaces
Regularly‐
Scheduled
Instructional
SpaceClassrooms
Teaching Labs
Event
Space
Meeting rooms
Assembly spaces
Student
Support Space
Community space
Student service space
Tutoring space
Advising offices
Space Types Included
Nature of Analyses
Analysis of current utilization
Develop Instructional Space Master Plan
Record space data
Gather qualitative information on use
Record space data
Gather qualitative information on use
Square footage allocation analyses, e.g.:
Per person
Per department
Per Campus
Square footage allocation analyses, e.g.:
Per person
Per department
Per Campus
3
2 Organ i z i ng Da ta f o r Repo r t i n g on Regu l a r l y ‐Schedu l ed I n s t r u c t i on a l Spa ce s Regularly-scheduled instructional activities are held at a variety of locations across the city – some directly at the campuses, some at major centers, and others at satellite locations. Regardless of physical location, all courses are also generally associated with one of the following campuses or areas (called “Campus (or Area) of Record” for simplicity) – which we believe to be related in some fashion to budgeting considerations: Cascade
Rock Creek
Sylvania
Southeast
Workforce & Community Education
Educational Services.
A chart in the 29 November presentation, reproduced below, shows the relationship between Campus Physical Locations of Buildings in which courses are held and the Campus or Area of Record above.
Since space utilization analyses are physical in nature, it makes most sense to evaluate space use by Campus Physical Location, and in our discussions on 29 November, the group concurred with this approach. There may also be situations, however, where it is helpful to look at utilization by Campus or Area of Record.
4
Accordingly, the following steps are required to prepare for analyses. Step 1. Simplify the number of physical locations and determine which – if any – to exclude from analyses.
In the chart above, there are 25 distinct categories of physical location, some with very few courses identified. The table below offers an initial attempt at collapsing these 25 categories into 14 categories. Detailed lists of courses included in each category are provided in an attached Excel spreadsheet. (Each aggregated physical location is a separate tab in the Excel file.) Please review the aggregation and confirm or suggest updates, as required. Further, it seems obvious that the first 11 major categories would be included in analyses. There is a question about how to handle categories 12 (Distance Learning), 13 (Off-Campus) and 14 (Null or Other – TBD). Please review courses in the Excel spreadsheet associated with these categories and advise as to how they should be treated for space utilization analyses.
Physical Locations
Physical Location Aggregated Physical Location
1 Cascade Cascade
Cascade (off campus)
2 Rock Creek Rock Creek
Rock Creek (off campus)
3 Southeast Southeast
Southeast (off campus)
4 Sylvania Sylvania
Sylvania (Distance Learning)
Sylvania (off campus)
5 CLIMB Climb Center
6 Downtown Center Downtown Center
7 Hillboro Center Hillsboro Center
8 Metro Center Metro Center (Portland Metropolitian Workforce Training Center)
9 Newberg Center Newberg Center
10 Swan Island Trades Center Swan Island Trades Center
11 Willow Creek Willow Creek Center
12 Distance Learning Distance Learning (Community Education)
Distance Learning (for Newberg Center)
Distance Learning (PCC District)
13 Off‐Campus Off Campus
Off Campus (PCC District Wide)
14 Null or Other ‐‐ TBD Columbia Center
Null ‐ location to be determined
Open Campus (PCC District Wide)
TBD
5
Step 2. Analyzing by Physical Location vs. Campus of Record.
Beyond analyzing space utilization by physical location, are there analyses that should be done by Campus or Area of Record? For example, there are a substantial number of courses associated with the Workforce and Community Education area, which are spread among various campuses and centers (e.g., CLIMB, Southeast, Sylvania, Willow Creek). Please consider what types of analyses might be desirable and informative, and advise how to proceed. 3 Nex t S t ep s In preparation for our next meeting sometime in mid-January, it would be helpful to address the issues raised in this memo, and to obtain guidance on and resolution of as many open questions as possible. To that end, would it be possible to schedule time for a short phone call before the holiday to review this memo with you, address any questions you have, and figure out how best to get these issues resolved? Thank you. Attachment
Excel file include course lists by major campus physical location CC:
Bryan Higgins, SRG Nita Posada, SRG
Portland Community College Monthly Report-01
Facilities Plan – Phase 1 December 23, 2016
3
Facilities Condition Assessment Work Group
12.23.16:
Summary of activities: The Facilities Work Group has met every 2 weeks since 10/31/16.
Key Focus for month: Reviewing existing material and organizing site visits. See attached schedule for
draft dates from each consultant. The schedule indicates which consultants will need to access buildings
and which consultants will focus on site only visits and may not need as much assistance.
Outstanding Items: All Consultants are currently reviewing the existing materials sent that consists of
existing plans and specifications. After review we will develop a list of outstanding items.
Site Visits:
1. PCC will be providing key cards for consultants that need to access buildings during site visits.
2. Coordination will be needed for any needed assistance during site visits.
3. Parking passes will be needed for each consultant group.
PAE: The following is a draft of PAE’s site visit process for each campus.
1. One week ahead of our meeting with PCC FMS staff responsible for maintenance of MEP system
on the particular campus, PAE will send a list with the building names on that campus and the
general questions about MEP systems. If time permits and FMS staff can return responses to
those questions ahead of our on-site meeting that would be great. If not, we can use the list as
an agenda item in our meeting.
2. We would like to ask that PCC assign FMS contact person for each campus and for each
discipline, so we can coordinate equipment testing and contact him or her during assessment
with questions that may come out from our site observations.
3. We propose to start our assessment at Southeast Campus and meet with FMS early in the week,
preferred Monday, January 9th. The person(s) with the most historical knowledge available for
that campus and each discipline should be at the kick-off meeting. We would like our team to
walk the campus with assigned FMS contacts after the meeting so that all PAE team members
are familiar with buildings and the access to rooms and equipment that need to be assessed.
The same day we would like to go through any required orientation, meet with security, get
badges or identifications and be informed of any limitations we may have during the assessment
(any events that may take place on the campus, midterms, areas that are off the limits, etc.). We
do not anticipate that any additional meetings will be required, but we need to be able to follow
up with either email or phone call to FMS contacts and will need our questions answered while
Chair Members Consultant Team
Tony Ichsan
Director
Facilities Support Services
John MacLean
Joe Gamble
Donna Bezio
Mark Erickson
Zahava Jones
Heidi VanBrocklin
Gary Danielson (SRG)
Bryan Higgins (SRG)
Nedzib Biberic (PAE)
Jared Lewis (Catena)
Tom Jaleski (Code Unlimited)
Brady Berry (WH Pacific)
Alex Simpson (WH Pacific)
Melinda Graham (2.ink)
Portland Community College Monthly Report-01
Facilities Plan – Phase 1 December 23, 2016
4
we are still working on that campus. It will take us three weeks to finish the work at Southeast
Campus.
4. We would than follow up with the same approach on Rock Creek, Cascade and Sylvania
campuses. We propose to meet with FMS on the following dates:
a. Rock Creek: Friday, January 27th.
b. Cascade: Friday, February 24th.
c. Sylvania: Friday, March 17th.
5. We anticipate that we will be able to assess two PCC centers per week. Please see attached
schedule for proposed times that we would be at each center. Similar what we are proposing for
campuses, we will provide questions to FMS staff on centers (at least a week prior to our site
visit).
PAE will need the following from PCC:
• FMS contacts for mechanical, electrical and plumbing systems on each individual
campus.
• Contacts for outside firms maintaining MEP equipment and permission to contact
them regarding equipment they maintain.
• Contacts for Fire Alarm Vendors and permission to contact them.
• One year of utility bills for all buildings (water, electricity, gas or propane).
• Existing facility assessment reports.
• Existing commissioning reports.
• We received one energy audit report for Sylvania campus. If energy audit reports are
available for other campuses and sites, we would need those as well.
• Balancing reports completed within last 12 months.
• Hydrant flow test completed within last 12 months.
Next Steps: PCC
Portland Community College Monthly Report-01
Facilities Plan – Phase 1 December 23, 2016
5
Capital Projects Work Group
12.23.16:
Summary of activities: The SRG Planning Team has sent pricing packages for the Tier I and select Tier II
bond projects to RLB for pricing as follows:
Tier I
01 Health Professions / IPT Building – Combined with 04 IT Location
02 Metro Center
03 OMIC Columbia County Center – Awaiting on PCC to provide original estimate, this will be a
verification from an existing report. We will send as soon as we receive from PCC sometime next week.
04 IT Location – Combined with 01 Health Professions / IPT Building
05 Cascade Public Safety Building
06 Sylvania Site Improvements
07 Student Housing Feasibility Study – Removed from scope
08 Rock Creek Events Center Parking Lot- Verification from existing estimate
09 Sylvania Health Technologies Building – This was previously a verification item, the scope has been
slightly modified since previous estimate was completed
Tier II
01 Sylvania Makerspace – Removed from Scope
02 Rock Creek CTE Building
03 Rock Creek Makerspace – Removed from scope
04 Hillsboro Center
05 Downtown Center
Key Focus for month: RLB will be pricing the bond projects package over the next 2-1/2 weeks and SRG
will field any questions.
Outstanding Items: NA
Next Steps: A meeting is scheduled with PCC to review the pricing on 1/6/17 prior to the January board
meeting.
Chair Members Consultant Team
Linda Degman
Director
Bond Program
Zahava Jones
Debra Jarcho
Rebecca Ocken
Gary Sutton
Tony Ichsan
Nita Posada (SRG)
Jason Karam (SRG)
Susan Gust (SRG)
Portland Community College Monthly Report-01
Facilities Plan – Phase 1 December 23, 2016
6
Safety and Security Work Group
12.23.16:
Summary of activities: A proposal from Layne Consultants was sent out for comment 11/16/16. The
work group reviewed the proposal in a conference call on 12/20/16. Everyone agreed that the proposal
addressed the scope of work expected by PCC. However, PCC would like to look at an additional scope of
work for standards development. Layne will send this to the team as a separate item for review.
Key Focus for month: Layne Consultants are currently reviewing the existing materials sent that consists
of existing plans and specifications.
Outstanding Items: Layne Consultants are currently reviewing the existing materials sent that consists
of existing plans and specifications. After review we will develop a list of outstanding items.
1. Stantec’s Basis of Design document for review
Next Steps: During the last conference call we are looking at the schedule for the first site visit.
Site Visit #1: January 10th – 13th. This would include campus site visits followed by a meeting with Derrick
Foxworth and team for review.
Chair Members Consultant Team
Derrick Foxworth
Director
Public Safety
Debra Jarcho
Alan Bral
Mike Sturgill
Kevin Crowley
Tony Ichsan
Neal Naigus
Ryan Aiello
Gary Danielson (SRG)
Bryan Higgins (SRG)
Rob Layne (Layne)
Mark Peterson (Layne)
Portland Community College Monthly Report-01
Facilities Plan – Phase 1 December 23, 2016
7
Transportation and Parking Work Group
12.23.16:
Summary of activities: The Transportation and Parking Work Group has met every 2 weeks since
10/31/16. During this time the scope has been refined and included in the overall project proposal for
review.
Key Focus for month: The meetings for this month have focused on completing the key strategies and
developing a cost benefit matrix. See attached draft strategies table under development.
Outstanding Items: All Consultants are currently reviewing the existing materials sent that consists of
existing plans and specifications. After review we will develop a list of outstanding items.
Next Steps: Through investigating the existing materials develop clear site plans of each campus to base
site visits and findings on.
Chair Members Consultant Team
Kathleen McMullen
Manager
Transportation and Parking
Karissa Nickerson
Wendy Palmer
Jennifer deLaix
Mark Gorman
Michael Kuehn
Narce Rodriguez
Dean Halley
Bryan Higgins (SRG)
Gary Danielson (SRG)
Todd Mobley (Lancaster)
Miranda Wells (Lancaster)
Phil Worth (Kittelson)
Portland Community College
Master Plan
Lancaster Engineering
DRAFT December 2016
Portland Community College Master Plan
Transportation and Parking
Portland Community College Master Plan – Transportation and Parking 1
Strategies There are many policy changes that are not easy to evaluate with a cost estimate or a broad benefit analysis as the solutions that were identified
in the previous section. These are broader strategies to reach the goals The advisory team reviewed the 2012 TDM and identified the most
relevant stratgies to prioritize based on the updated existing conditions and staff availability and capabilities. The recommended strategies are
outlined in Table X
Strategy Implementation Recommendations Maintenance and Expansion Considerations
Add additional
resources to the PCC
transportation and
parking team
• Hire one full-time (1 FTE) staff member to be an ambassador
• Hire one full-time (1 FTE) staff member to be an active
transportation lead
• Two additional FTE for maintenance for evenings for shuttle
services
• Additional drivers to support additional higher shuttle frequency
and longer hours
• Additional office support staff for transportation and parking
department
• Additional enforcement staff (2 FTE) for transportation and
parking
• New grant for ambassador and active
transportation lead covers the first two
years, but funding needs to be extended
forever and ever
• These staff needs are without any
additional strategies applied, additional
strategies applied may require additional
staff.
Improve the method at
which to incorporate
transportation
solutions into other
projects
• Integrate campus and center needed improvement into local
agency projects where possible:
-Powell/Division
-SW Corridor
-Springville
-Planning and Policy Plans (i.e., transportation safety action plans,
transportation system plans)
• New campus and centers input from transportation and parking
department at early stages
• Ensure staff dedicated to this…
Long-term evaluation
of impact to changing
parking fees and
structure
• Conduct a detailed study to evaluate costs and impacts for
parking fee increases.
• Identify methods that allow flexibility in parking fees by campuses
and centers.
• Negotiate language in union contract to allow for more flexibility
for staff parking fees.
• Set-up so that changes can be on-going…
Integrate
transportation specific
guidelines for new PCC
buildings, campuses,
and centers and have
transportation input
sooner for new
infrastructure
• All new infrastructure should include bicycle lanes, sidewalks, and
safe crossings.
• All new infrastructure should include safe bicycle storage areas
and showers if size is large enough.
• All new infrastructure should exceed ADA guidelines. – paths from
parking to building (meet owner standards and needs of the
population)
• Throw in power and communication as you go – create plan
Integrate new
technology solutions
for parking (i.e., pay by
space, license plate
reader)
• Learn from the work OHSU?? And PSU?? LPR System is currently
doing to integrate these technologies into their parking.
• Build the capital cost for these solutions into longer term plans
(i.e., PCC Master Plan).
• Require new or expanding campuses and centers to build systems
in as they are constructing new infrastructure.
Shift locations for
programs (i.e., nursing
from Sylvania to off-
site facility)
• Evaluate high attendance programs and minimize the overlap of
these programs at the same locations and times.
Create a district wide
communications plan
for transportation
options
• Hire an ambassador who’s primary job is getting communication
out about transportation options – been funded… but needs to
carry on
• Reintegrate discussion of transportation options into welcome
day, new employee orientation,
• Transportation solutions in permit renewal email and other mass
email options
• Create a transportation communications plan
• Partnering with other district services
Make alternative
modes to single
occupancy vehicles
more attractive for
employees
• Integrate a wellness incentive program in for employees.
• Highly subsidize transit passes.
• Increase frequency of shuttle services to better serve staff
schedules.
• Add shuttle stops at centers.
• Integrate a guaranteed ride home program.
Improve facilities to
support alternative
modes for students
and employees
• More showers at campuses and centers.
• More bike storage at campuses and centers.
•
Redo the Shuttle
Program
• Create hubs at each campus.
• Develop a program that allows the shuttle service to operate as a
typical transit program:
o Keep maintenance in house
o Hire dipatch service
o Integrate additional technology into shuttles
Housing next to
campus
• Use land that PCC owns next to Sylvania to build housing
• Evaluate purchases of land near other campuses for building
housing
• Guidelines for new campuses to buy additional land for building
housing near the campus
Add additional electric
vehicle stations
• Build infrastructure as you go
Improve pedestrian,
bicycle, and ADA
infrastructure to
buildings
• Path from all the way back to the buildings for all modes
• Make sure new projects coming in integrate improvements (i.e.,
SW corridor improving ADA and implementing ped, and bike
improvements from transit stops to buildings)
• Add additional ADA spots
Portland Community College Monthly Report-01
Facilities Plan – Phase 1 December 23, 2016
8
Information Technology Work Group
12.23.16:
Summary of activities: A third revision to the Vantage Consultants proposal was reviewed by the work
group on 12/5/16 and was generally approved, just needed one final review.
Key Focus for month: Once Vantage has access to the existing information from Google Drive they can
start to review and provide comments on other outstanding information needed for review.
Outstanding Items:
Vantage: At least 3 weeks prior to the initial site visit vantage will need the following information:
1. IT specific info which was being provided by the stakeholders on the Google Drive
2. A list of TRs and other spaces for each building
a. A list has been sent by PCC, attached is a pass at locating these to buildings
b. 88 IDF’s identified
c. There are (10) UPS locations which had names not matching named buildings in the
building list
d. 21 buildings currently are listed with no IDFs
3. The rest of the items we requested in our proposal’s Methodology section
4. Schedule of the unavailable dates for district’s facilities staff and other essential team members,
as well as the Districts’ preferred site visit schedule.
Next Steps: PCC will provide Vantage with additional comments to the proposal. Vantage will start
looking at scheduling their first site visits based on getting the information mentioned above.
Chair Members Consultant Team
Michael Northover,
Chief Information Officer
Information Technology
Val Moreno
Debra Jarcho
James Reece
Ed Hawkins
Payam Damghani
Andy Freed
Kevin Edwards
Charmagne Ehrenhaus
Hank Schottland
Bryan Higgins (SRG)
Bjorn Clouten (SRG)
Richard Bussell (Vantage)
Ken Godachy (Vantage)
Jon Young (Vantage)
VANTAGE TECHNOLOGY CONSULTING GROUP
Campus TR Reconciliation list
Cells in YELLOW indicate buildings without currently identied Technology Rooms or IDFs
Please verify Qty or indicate as N/A
Campus Qty of TRs
Building
Abbrev Building Name
Building
AiM
Number
UPS LOCATIONS
(Unmatched) Actual Building name
SY Campus General Campus 1000GC
SY 1 AM Automotive Metals 1010 CA EP BDF
SY ASB Automotice Storage Building 1015 CA PG BDF
SY 1 BK Bookstore 1020 CP MDF
SY 5 CC College Center 1030 SE AA BDF
SY 2 CSB College Services Building 1040 SE AS BDF
SY 2 CT Communication Technology 1050 SE AS IDF1
SY 1 HP Heat Plant 1060 SE LC BDF
SY 3 HT Health Technology 1070 SE LC IDF1
SY Gate House SE NP BDF
SY 2 LRC Library 1080 SE WP BDF
SY 1 PAC Performing Arts Center 1090
SY 1 SCB South Classroom Building 1100
SY 2 SS Social Science 1110
SY 2 ST Science Technology 1120
SY 4 TCB Technology Classroom Building 1130
CA Campus General Campus 2000GC
CA 3 CH Cascade Hall 2005
CA 2 JH Jackson Hall 2010
CA 2 MAHB Moriarty Arts and Humanities Building 2020
CA 1 PEB Physical Education Building 2030
CA 1 PSEB Public Service Education Building 2040
CA 1 PS Public Safety 2050
CA SC Student Center & Library 2060
CA 2 SSB Student Services Building 2070
CA 3 SU Student Union 2075
CA 3 TEB Technology Education Building 2080
CA 2 TH Terrell Hall 2090
CA KB Kanjaya Building 2100
CA 1 PB Paragon Club 2110
CA UGP Underground Parking 2120
RC Campus General Campus 3000GC
RC 1 B1 Building 1 3010
RC 3 B2 Building 2 3020
RC 4 B3 Building 3 3030
RC 1 B4 Building 4 3040
RC 3 B5 Building 5 3050
RC 1 B6 Building 6 3060
RC 4 B7 Building 7 3070
RC 4 B9 Building 9 3090
RC KEN Kennel 3110
UPS LOCATIONS in BLUE indicate locations named differently than Building Abbrev. Please provide correct Building name.
RC Care Takers Dwelling None
RC Farm Storage Building None
RC Farm Shop Building None
RC Farm Shop Building None
RC Barn None
RC New Shop Building None
RC Cattle Builidng None
RC Toilet Building None
RC Pole Building None
RC Green House None
RC Greenhouse (Hoops) None
SE Campus General Campus 4000GC
SE CHA Community Hall Annex 4003
SE LIBR Learning Commons 4005
SE 1 MSH Mount Scott Hall 4010
SE 4 MTH Mount Tabor Hall 4020
SE SAB Southeast Administration Building 4030
SE 3 SCOM Student Commons 4040
CLIMB Campus General Campus 5100GC
CLIMB CLIMB
Continuous Learning for Individuals,
Management and Business 5100
DC Campus General Campus 5200GC
DC 2 DC Downtown Center 5200
HTC Campus General Campus 5300GC
HTC ECB Education Center Building 5300
NB Campus General Campus 5400GC
NB 1 NB Newberg Center 5400
PMWTC Campus General Campus 5500GC
PMWTC 1 B1 Portland Metro Building 1 5500
PMWTC 1 B2 Portland Metro Building 2 5510
WC Campus General Campus 5600GC
WC 4 WC Willow Creek 5600
STC Campus General Campus 5700GC
STC 1 STC Swan Island 5700
CDSB Campus General Campus 6000GC
CDSB 1 CDSB Central Distribution Services Building 6010
TOTAL 88 District-wide Technology spaces
Portland Community College Monthly Report-01
Facilities Plan – Phase 1 December 23, 2016
9
ADA Work Group
12.23.16:
Summary of activities:
After meetings on 11/15/16 & 11/29/16 it was determined the ADA scope is the following:
Transportation (Lancaster and Kittelson Engineering): Review existing reports and confirm existing ADA
parking and required ADA parking and locations at all campuses and centers.
Site (SRG & WH Pacific Engineering): Provide an ADA assessment of the existing path of travel from ADA
parking and transit stops to the main entry at each building at all campuses and centers.
Building (SRG & Code Unlimited): Provide a list of applicable codes for accessibility for each of the
buildings. Review drawings of all of the buildings in the inventory for accessibility compliance issues.
Key Focus for month: All Consultants are currently reviewing the existing materials sent that consists of
existing plans and specifications.
Outstanding Items: All Consultants are currently reviewing the existing materials sent that consists of
existing plans and specifications. After review we will develop a list of outstanding items.
Next Steps: Meet with PCC and all consultants involved to review the schedule, scope of work and
outstanding items needed.
Chair Members Consultant Team
Jennifer Gossett
Accessibility Specialist
Disability Services
Wendy Palmer
Donna Bezio
Jody Giffen
Maria Mendez
Kathy McMullen
Alex Baldino
Jason Karam (SRG)
Gary Danielson (SRG)
Brady Berry (WH Pacific)
Alex Simpson (WH Pacific)
Tom Jaleski (Code Unlimited)
Portland Community College Monthly Report-01
Facilities Plan – Phase 1 December 23, 2016
10
Sustainability Work Group
12.23.16:
Summary of activities: The sustainability Work Group has met several times now and have developed a
scope of work vision as follows:
Version 3. We will develop a Sustainability Plan to include an assessment evaluating current college
systems and guidelines for college practices emphasizing sustainability in seven key areas:
● Energy & Emissions
● College Operations
● Construction & Renovation
● Grounds & Natural Systems
● Health & Well-being
● Education & Culture
● Resiliency
Key Focus for month:
Outstanding Items:
Next Steps: Inventory of existing resources and data gaps. Identify where we’re at and goals for the
future.
Chair Members Consultant Team
Briar Schoon
Manager
Sustainability
Laura Ward
Julie Mast
Alyson Lighthart
Elaine Cole
Jack Lussier
Lisa Peterson (SRG)
PCC SITE VISIT SCHEDULE WORK SHEET
TASK DURATION/DATE 0 1 3 14 15 16 17 18 19 20 21 22 24 25 26 27 28
5-11 12-18 19-25 26-1 2-8 9-15 16-22 23-29 30-6 7-13 21-27 28-3 4-10 11-17 18-24 25-1
CAMPUSSYLVANIA (14 Bldgs: 886,286sf)
SRG
PAE
Catena
WH Pacific
Vantage
Lancaster
Kittelson
Layne 1/10-1/13
Code Unlimited
2.ink
ROCKCREEK (20 Bldgs: 595,026sf)
SRG
PAE
Catena
WH Pacific
Vantage
Lancaster
Kittelson
Layne (2/6-2/8)
Code Unlimited
2.ink
SOUTHEAST (6 Bldgs: 228,455sf)
SRG
PAE
Catena
WH Pacific
Vantage
Lancaster
Kittelson
Layne (2/6-2/8)
Code Unlimited
2.ink
CASCADE (14 Bldgs: 517,148sf)
SRG
PAE
Catena
WH Pacific
Vantage
Lancaster
Kittelson
Layne (3/13-3/15)
Code Unlimited
2.ink
MAR
1-7 8-14 15-21 22-28 29-4 5-11 12-18 19-25 26-4
JAN FEBDEC
13 23
2017
11
2016
8 9 10 122 4 5 6 7
November 28, 2016
2017
APR MAY JUN
14-20
3 weeks
4 weeks
3 weeks
4 weeks
PCC MASTER PLAN PROJECT SCHEDULE SRG PARTNERSHIP, INC.
PCC SITE VISIT SCHEDULE WORK SHEET
TASK DURATION/DATE 0 1 3 14 15 16 17 18 19 20 21 22 24 25 26 27 28
5-11 12-18 19-25 26-1 2-8 9-15 16-22 23-29 30-6 7-13 21-27 28-3 4-10 11-17 18-24 25-1
CENTERCLIMB (35,646sf)
SRG
PAE
Catena
WH Pacific
Vantage
Lancaster
Kittelson
Layne (2/6)
Code Unlimited
2.ink
DOWNTOWN (43,595sf)
SRG
PAE
Catena
WH Pacific
Vantage
Lancaster
Kittelson
Layne (3/14)
Code Unlimited
2.ink
NEWBERG (12,880sf)
SRG
PAE
Catena
WH Pacific
Vantage
Lancaster
Kittelson
Layne (1/10)
Code Unlimited
2.ink
SWAN ISLAND (22,517sf)
SRG
PAE
Catena
WH Pacific
Vantage
Lancaster
Kittelson
Layne (2/6)
Code Unlimited
2.ink
23
2016 2017 2017
2 4 5 6 7 8 9 10
DEC JAN FEB MAR APR
14-20
November 28, 2016
JUN
1-7 8-14 15-21 22-28 29-4 5-11 12-18 19-25 26-4
MAY
11 12 13
PCC SITE VISIT SCHEDULE WORK SHEET
TASK DURATION/DATE 0 1 3 14 15 16 17 18 19 20 21 22 24 25 26 27 28
5-11 12-18 19-25 26-1 2-8 9-15 16-22 23-29 30-6 7-13 21-27 28-3 4-10 11-17 18-24 25-1
CENTERHILLSBORO (9,522sf)
SRG
PAE
Catena
WH Pacific
Vantage
Lancaster
Kittelson
Layne
Code Unlimited
2.ink
METRO (32,570sf)
SRG
PAE
Catena
WH Pacific
Vantage
Lancaster
Kittelson
Layne (2/6)
Code Unlimited
2.ink
WILLOW CREEK (95,308sf)
SRG
PAE
Catena
WH Pacific
Vantage
Lancaster
Kittelson
Layne (3/14)
Code Unlimited
2.ink
November 28, 2016
2 4 5 6 7 8 9 10 11 12 13 23
2016 2017 2017
DEC JAN FEB MAR APR
14-20
JUN
1-7 8-14 15-21 22-28 29-4 5-11 12-18 19-25 26-4
MAY