Upload
others
View
10
Download
0
Embed Size (px)
Citation preview
AA-1AREA OF WORK(SECOND FLOOR)
ABAAM
AP-1AE
AE
AA-1
AA-2
AA-3
AT
AS
AP-2
AK
Campus Drive East
Cam
pus Drive East
Cam
pus Drive East
Cam
pus Drive W
est
Filmore Avenue
Dawes Avenue Dawes Avenue
Dawes Avenue
Terra
ce Dri
ve
Branch Avenue
BEAUR
EGARD
STREE
T
LEESBURG PIKESR-7
SR-613
PROJECTLOCATION
N
Structural Frame*
Bearing Walls - Exterior*
Bearing Walls - Interior
Nonbearing Walls &Partitions - Exterior
Nonbearing Walls &Partitions - Interior*
Floor Construction(Including SupportingBeams & Joists)
Roof Construction(Including SupportingBeams & Joists)
BUILDING ELEMENT FIRE-RESISTANCE RATINGREQUIREMENTS (IN HRS.)
0*
0*
0*
0*
0*
0*
0 (X>30')*
*See VUSBC Table 601 for further specification
ASBESTOS & LEAD PAINT ANALYSES HAVE BEEN COMPLETED BY THE OWNER. THE REPORT, DATED DEC. 27, 2012,IS AVAILABLE FOR REFERENCE FROM THE OWNER’S REPRESENTATIVE.THE OWNER WILL ABATE ASBESTOS & LEAD CONTAINING MATERIALS FROM THE AREA OF WORK UNDER A SEPARATECONTRACT. THIS WORK WILL BE COMPLETED PRIOR TO THE START OF CONSTRUCTION FOR THIS CONTRACT.IF THE CONTRACTOR DISCOVERS OR INADVERTENTLY DISTURBS ANY MATERIAL THAT MAY CONTAIN ASBESTOS ORLEAD THAT HAS NOT BEEN PREVIOUSLY IDENTIFIED, THAT WAS OVERLOOKED DURING THE REMOVAL, OR WHICH WASDEEMED NOT TO BE FRIABLE OR WHICH WAS ENCAPSULATED, THE CONTRACTOR SHALL STOP WORK IN THE AREACONTAINING THE ASBESTOS, SECURE THE AREA, AND NOTIFY THE OWNER IMMEDIATELY BY TELEPHONE OR INPERSON WITH WRITTEN NOTICE FOLLOWING AS SOON AS POSSIBLE. THE OWNER SHALL HAVE THE SUSPECTMATERIAL SAMPLED. IF THE SAMPLE IS POSITIVE AND MUST BE DISTURBED IN THE COURSE OF THE WORK, THEOWNER WILL HAVE THE MATERIAL REPAIRED OR REMOVED AND WILL PAY FOR THE BULK SAMPLE ANALYSIS. IF THEMATERIAL DISTURBED IS NOT WITHIN THE CONTRACTOR’S AUTHORIZED WORK AND/OR WORK AREA OR UNDER THISCONTRACT, THE CONTRACTOR WILL PAY FOR ALL ASSOCIATED SAMPLING & ABATEMENT COSTS.NO ASBESTOS-CONTAINING MATERIALS SHALL BE USED ON THE PROJECT
ASBESTOS & LEAD-BASED PAINT ABATEMENT
GeneralG0.01 Cover Sheet
ArchitecturalAD1.01 Demolition Plan & Demolition RCPA1.01 New Work Plan & New Work RCPA4.01 Interior Elevations & Details
MechanicalM0.00 Cover Sheet - MechanicalM1.00 Demolition / New Work Plans - MechanicalM2.00 Ventilation Tables - Mechanical
PlumbingP0.00 Cover Sheet - PlumbingP1.00 Floor Plan, Risers - Plumbing
ElectricalE0.00 Cover Sheet - ElectricalE1.00 Demolition Floor Plans - ElectricalE2.00 New Work Floor Plans - ElectricalE3.00 Panel Schedules - ElectricalE4.00 Lighting Schedule, F.A. & Power Riser - Electrical
SHEET INDEX
Police Station UpgradesBisdorf I (AA1) BuildingNorthern Virginia Community CollegeAlexandria Campus3001 North Beauregard StreetAlexandria, VA 22311-5097
Consultants
703.684.5994
333 North Fairfax StreetAlexandria, Virginia 22314
Seal
Key Plan
Drawing
Revisions
Date
Project No.
Sheet No.
BCOM SUBMISSION 01/21/15
Submission Set Date
PC No. 260-A2260-140
coleanddenny.com
Copyright © 2014 - Cole & Denny Incorporated. No part of this document or design may be reproduced or distributed in any way without the expressed written permission of the Architect.
21 January 2015
11004.26A2
3001 North Beauregard StreetAlexandria, VA 22311-5097
G0.01
Cover Sheet
Police Station Upgrades
1. THE PROJECT CONSISTS OF THE RENOVATION & EXPANSION OF THE EXISTING POLICE OFFICE IN THEBISDORF BUILDING AND ADDITION OF A SINGLE OCCUPANCY TOILET / SHOWER ROOM AND BREAK ROOM.
2. THE OCCUPANCY WILL REMAIN UNCHANGED.3. THE ROOMS TO BE RENOVATED, 239, 239A, 239B, 239C, 239D, 240, 240A, 240B, & 241 WILL RECEIVE NEW
FLOOR, WALL, & CEILING FINISHES, INCLUDING ANTI-BALLISTIC WALL ARMOR ON THE CORRIDOR PARTITION.4. DEMOLITION TO INCLUDE NON-LOAD BEARING PARTITIONS, DOORS, ALL FLOORING IN RENOVATED
SPACES, AND ALL CEILING IN RENOVATED SPACES.5. EXISTING MECHANICAL & ELECTRICAL EQUIPMENT & SYSTEMS WILL BE MODIFIED AS NECESSARY.6. NEW LIGHTING AND DIFFUSERS TO BE INSTALLED.7. NEW PLUMBING WILL BE PROVIDED FOR THE TOILET / SHOWER ROOM AND BREAK ROOM.
DESCRIPTION OF WORK
CODE SUMMARYAPPLICABLE CODES:
USE GROUP:
BUILDING PURPOSE:
CONSTRUCTION TYPE:
SPRINKLERED:
STORIES ABOVE GRADE:
PROJECT AREA:
VIRGINIA UNIFORM STATEWIDE BUILDINGCODE (VUSBC) 2012 EDITIONVIRGINIA STATE FIRE PREVENTION CODE2012 EDITION2010 ADA STANDARDS FOR ACCESSIBLEDESIGN - SEPT 15, 2010
BUSINESS (GROUP B)
CLASSROOMS & OFFICES
IIB
NO
3
SECOND FLOOR: 1,273 SF (RENOVATED)
LOCATION MAP
SPECIFICATIONS (CONTINUED)4) Anti-Ballistic Wall Armor
a) Bullet Resistant Fiberglass Panels shall be USFA 3 Armor by US Bulletproofing, UL 752 Level 3, 1/2" thick, 5 lbsper sq. ft., or approved equal.
b) Bullet Resistant Fiberglass shall be of the "non-ricochet type". The design is intended to permit the capture andretention of an attacking projectile lessening the potential of a random injury or lateral penetration.
c) Install in accordance with the Manufacturer's printed recommendations.d) All joints shall be reinforced by a back-up layer of bullet resistant material. The bullet resistance of the joint, as
reinforced, shall be at least equal to that panel. Minimum width of reinforcing layer at joint shall be 4-inches (2" oneach panel or a 2" minimum overlap).
e) Install supporting members prior to bullet resistant material. Contractor shall verify that all supports have beeninstalled as required by the contract documents.
5) Suspended Ceilings:a) Metal Suspension Systems:
i) Armstrong 'Silhouette' 9/16" bolt slot 1/8" reveal grid system, to match existing building standards. Color: White.ii) Install ceiling in accordance with UL G031 floor assembly at corridor.iii) Install hangers plumb and free from contact with insulation or other objects within ceiling plenum that are not
part of supporting structure or of ceiling suspension system. Splay hangers only where required to missobstructions; offset resulting horizontal forces by bracing, countersplaying, or other equally effective means.
iv) Where width of ducts and other construction within ceiling plenum produces obstructions, install supplementalsuspension members and hangers in form of trapezes or equivalent devices.
v) Secure wire hangers directly to structures or to inserts, eye screws, or other devices that are secure andappropriate for substrate.
b) Acoustical Panels:i) Armstrong 'Georgian/Silhouette' Beveled Tegular Tile with HumiGuard Plus, #1753, 24"x 24"x 9/16",
to match existing building standards. Color: White.ii) Install acoustical panel ceilings to comply with ASTM C 636, per Manufacturer’s written instructions and
CISCA’s "Ceiling Systems Handbook."iii) Install acoustical panels with undamaged edges and fit accurately into suspension system runners and edge
moldings. Scribe and cut ceiling panels at borders and penetrations to provide a neat, precise fit.iv) Install panels with pattern running in one direction parallel to long axis of space.v) Install reveal-edged panels with bottom of reveal in firm contact with top surface of runner flanges.vi) Paint cut edges of panel remaining exposed after installation; match color of exposed panel surfaces using
coating recommended by Acoustical Panel Manufacturer.6) Carpet:
a) Carpet tile 1 (CPT-1): Shaw Contract Group, No Rules, Color 05500 Versatile, 59106 Linage, or approved equal.i) Adhesives: Install with mildew-resistant, nonstaining type adhesive to suit products and subfloor conditions,
that complies with flammability requirements for installed carpet, and is recommended or provided by CarpetManufacturer.
b) Preparation: Comply with CRI 104, Section 7.3, "Site Conditions; Floor Preparation," and with CarpetManufacturer’s written installation instructions for preparing substrates.i) Remove adhesives or other materials that may be bonded to the slab, in accordance with the Carpet
Manufacturer’s substrate preparation instructions.ii) Use trowelable leveling and patching compounds, according to Manufacturer’s written instructions, to fill
cracks, holes, depressions, and protrusions in substrates.iii) Remove coatings, old adhesives, and other substances that are incompatible with adhesives and that
contain soap, wax, oil, or silicone, without using solvents. Broom and vacuum clean substrates to becovered immediately before installing carpet.
c) Direct-Glue-Down Installation: Comply with Carpet Manufacturer's written installation instructions.i) Install tiles in quarter turn pattern. Cut and fit carpet to butt tightly to vertical surfaces and permanent
fixtures.ii) Extend carpet into toe spaces, door reveals, closets, open-bottomed obstructions, removable flanges,
alcoves, and similar openings.iii) Install to comply with Carpet Manufacturer’s written recommendations.
7) Resilient Base:a) Resilient Base at carpet: Armstrong Color-Integrated Wall Base, or approved equal. Rubber, no toe, 1/8" thick,
4 inches high, from continuous coil. Corners may be job formed. Color: 59 Charcoal Gray.b) Install wall base in lengths as long as practicable without gaps at seams and with tops of adjacent pieces aligned.
Tightly adhere wall base to substrate throughout length of each piece, with base in continuous contact withhorizontal and vertical substrates.
c) In carpeted areas, install the base before the carpet is installed.d) Attach to partitions using Manufacturer's approved adhesive and without wrinkling, gaps at seams or top,
bulging at corners, or adhesive overflow.8) Ceramic Tile:
a) Floor Tile (in Shower Room 240E)i) Daltile 'Natural Hues' or approved equal. Color: Pebble QH18. Size 8 x 8.ii) With Abrasive Content.iii) 1/8" grout joint. Grout color: Mapei Gray #9.iv) Install per Manufacturer's recommendations and Tile Council of North America Handbook.v) Use Self-Leveling Underlaymentvi) Install waterproofing membrane in accordance with ANSI A118.10.vii) Thinset: Portland cement ASTM C150, Type 1, Gray.viii) Grout: Standard unsanded grout. Use joint sealant.ix) Provide ADA compliant marble threshold uniform in color and finish. ASTM C503 and ASTM C241.
b) Wall Tile (in Shower Room 240E)i) Daltile 'Natural Hues' or approved equal. Color: Almond QH02. Size 4x 8. Stacked bond pattern.ii) Trim: Bullnose 2 3/4" x 5 3/4", Corner Bullnose 2 3/4" x 2 3/4", Cove Base: 5 1/2" x 7 3/4". Color: Almond QH02.iii) 1/8" grout joint. Grout color: Mapei Malt #16.iv) Install per Manufacturer's recommendations and Tile Council of North America Handbook. Use Joint Sealant.v) Grout: Standard unsanded grout. Use joint sealant.
9) Painting & finishing:a) Paint all partitions & other exposed areas, including but not limited to ceiling bulkheads, walls, doors and frames.b) Apply paint according to Manufacturer’s written instructions. Use applicators and techniques best suited for substrate
and type of material being used.c) Provide Manufacturer’s best quality paint material for the coatings specified.d) Examine substrates, areas, and conditions under which painting will be performed for compliance with paint
application requirements. Remove dirt, rust, scale, grease, moisture, scuffed surfaces, or conditions detrimental toformation of a durable paint film before painting the surface. Do not begin to apply paint until unsatisfactory conditionshave been corrected and surfaces receiving paint are thoroughly dry.
e) Provide finish coats that are compatible with primers used.f) Provide the number of coats and film thickness required regardless of the application method.g) Do not apply succeeding coats until the previous coat has cured for the full time period recommended by the
Manufacturer.h) Sand between applications if sanding is required to produce a smooth, even surface.i) Omit primer on items that have been shop primed. Touch up and re-prime areas that have been exposed (i.e.,
door undercuts, etc.) before applying final coats.j) Clean and prepare surfaces to be painted according to the Manufacturer’s written instructions for each particular
substrate condition.k) Clean galvanized surfaces with non-petroleum-based solvents so surface is free of oil and contaminants before painting.l) Protect work of other trades, whether being painted or not, against damage by painting. Correct damage by cleaning,
repairing, replacing, and/or repainting to the Tenant's satisfaction.m) Provide "wet paint" signs to protect newly painted finishes.n) Remove temporary protective wrappings, provided to protect work by others, after completing painting operations.o) Mask window mullions, hardware, hinges and other items that cannot be removed. Remove all masking before the
Architect's final inspection.p) Remove empty cans, rags, rubbish, and other discarded paint materials from the site at the end of each workday.q) Paint schedule: provide the number of coats necessary to cover but not less than one (1) prime coat and two (2)
finish coats on new and patched surfaces. Use specific paint recommended by Paint Manufacturer based uponsubstrate and finish specified below:i.) Interior gypsum wallboard (unless otherwise noted)
a) 1 coat, drywall primer, vinyl latex sealer: all gypsum wallboard surfaces.b) 2 coats, ultra-deluxe interior vinyl egg shell finish: Color to be selected by Architect.
ii) Painted wood doors (factory primed):a) 2 coats: deluxe latex satin finish. Color to be selected by Architect.
iii) Hollow metal door jambs & door closer covers at painted doorsa) 2 coats: deluxe latex semi-gloss finish. Color to be selected by Architect.
10) Architecturcal Woodworka) Provide shop drawings showing dimensions and details, including all joints and connections.b) Installation: install architedctural woodwork plumb, level, true, and straight with no distortions.
i.) Shim as required using concealed shims. Install to a tolerance of 1/16" in 8'-0" for plumb and level.ii.) Anchor woodwork to metal wall studs. Secure to grounds with countersunk concealed fasteners and blind nailing as
required for a complete installation.iii.) Scribe work to fit adjoining surfaces. Woodwork shall be accurately and neatly fitted together by skilled Finish
Carpenters. Neatly fit all hardware.c) Solid Surface Material - Counter & Backsplash: Silestone Quartz Surface, Color: Blanco City, or approved equal.d) Solid Surface Material - Integral Bowl: Whitee) Wood - Cabinets: Merillat Classic, Fusion style or approved equal. Color to be selected by Architect.
11) Counter Support Bracketsa) Rakks EH-1818-FM Flush Mount Brackets, or approved equal.b) Install per Manufacturer guidelines. Determine support spacing per Manufacturer guidelines.
12) Appliancesa) Provide and install appliances per Manufacturer's guidelines for Break Room 240G.
i.) Refrigerator - 20 cubic feet, Side-By-Side; GE GSS20ESHSS or approved equal.ii.) Microwave - Sharp R-21LTF or approved equal.
13) Toilet Accessoriesa) Refer to Toilet Fixture Schedule and Shower Room Elevations.b) Provide blocking in the wall for mounting of all accessories.
14) Electrical switch plates & devices:a) The visible elements of all new devices (switch plates, switches, receptacles, etc.) shall be white plastic with
smooth finish. Replace remaining existing devices and plates so that elements match new devices.15) Mechanical:
a) See mechanical specifications and notes on Sheet M0.0.16) Electrical:
a) See electrical specifications and notes on Sheet E0.0.
GENERAL NOTESA. GOVERNING CODE
All work shall be performed in accordance with the requirements of the 2012 VUSBC, and localcodes, laws, regulations, and ordinances. The Building Code Authority is the Virginia Departmentof General Services (DGS), Bureau of Capital Outlay Management (BCOM), Division of Engineeringand Buildings (DEB).The General Contractor shall comply with the 2012 Virginia State Fire Prevention Code andNFPA 241-2004. The General Contractor shall maintain a copy of the above documents at thesite.
B. PRICINGThe General Contractor shall promplty notify the Architect and Owner for clarification of anyambiguity or inconsistency which he may discover upon examination of the ConstructionDocuments or the site and existing conditions prior to submitting his price. The GeneralContractor, by making his bid, represents that:
a. He has read and understands the documents and his bid is made in accordance therewith.b. He has visited the site, has familiarized himself with the site and job conditions and
jurisdictional requirements under which the work is to be performed and has correlated hisobservations with the requirements of the Contract Documents.
c. His price is based upon the materials, systems, and equipment required by the BiddingDocuments without exception. The General Contractor shall contact the Owner'sRepresentative to make an appointment to visit the site. Failure to visit the site will notrelieve the General Contractor of the obligation to furnish all material and labor necessaryto carry out the provisions of the Contract Documents and to complete the work for theconsideration set forth in his bid.The Owner's Representative is Pat Didonato and her phone number is 703-323-3714.
C. OWNER OCCUPANCYThe building and site will be occupied during construction. The Contractor shall obtain the Owner'sapproval and coordinate and schedule in advance with the Owner all work that may affect theOwner's operations. Such work includes deliveries, storage of materials, staging operations,interior work including removal and replacement interior finishes and work above the ceilings,interruptions in power, air conditioning and heating, and similar work. If necessary toaccommodate the Owner's schedule, some outages may need to be scheduled after hours or onweekends. See specifications for additional information.
D. MEASUREMENTS & EXISTING CONDITIONSDimensions are from finished face of construction to finish face of construction unless notedotherwise.Information contained in these documents is based on existing documents and field measurements.The Contractor shall field verify existing conditions and all measurements at the building and shallbe responsible for correctness of same. Where conflicts occur between the documents and theexisting conditions, the Contractor shall notify the Architect for resolution of discrepanciesbefore proceeding with the work.The hazardous material survey report is available for informational purposes only. The scopes ofwork as described in the report are not part of this contract for construction or for this buildingpermit submission. The Owner will have all hazardous material removal performed under a separatecontract with a Qualified Contractor, under a separate building permit as submitted and approvedby BCOM Officials. Scope of work pertaining to the removal of hazardous materials will beperformed prior to the commencement of any work associated with this project permit.
E. DEMOLITIONDemolition includes controlled destruction of existing construction and the removal and disposalof demolished materials as shown on the drawings and/or included in these notes.Demolition shall be performed in sections small enough so as not to endanger any adjacentmaterials or facilities to remain in place. Provide adequate shoring, bracing, and protection toprevent movement, settlement, collapse, or damage to existing materials or facilities which are toremain. Contractor shall submit to the Architect for review and acceptance, prior to beginning thework, complete details of shoring procedures signed by a registered Professional Engineer.Promptly repair all damages caused by the demolition to adjacent facilities or materials at no costto the Owner.
F. CUTTING & PATCHING OF THE WORKThe Contractor shall be responsible for all cutting, fitting, and patching that may be required tocomplete the work and make its several parts fit together to achieve the professional quality ofnew work. Where existing construction is disturbed, the affected area shall be replaced andrepaired with matching materials and finishes and blended with existing work. Where paint cannotbe touched up to match, repaint entire surface.
G. TEMPORARY FACILITIESThe Owner will provide utilities available from the existing building for use by the Contractor. TheContractor shall provide temporary toilet facilities for the workmen and shall make additionalprovisions if required to accomplish the work. At the completion of construction and beforerequest for final payment, all existing facilities used by the Contractor shall be cleaned andrestored to original condition to the Owner's satisfaction.
H. TEMPORARY CONSTRUCTION BARRIERSThe Contractor will comply with the Owner's and local jurisdiction's requirements for erection ofnon-combustible safety barricades for protection of people and property at and around all workareas. Paint with appropriate colors, graphics, and warning signs to inform personnel and thepublic of the hazard being protected against. The Contractor must maintain access to all exits andmaintain required egress passage widths throughout the demolition and construction period. Theegress passage may not be used as a pathway to transport materials to and from the area ofwork while the building is occupied.
I. FIELD COORDINATIONContractor shall coordinate building access neccessary to perform the work with the Owner'sRepresentative. Contractor shall protect the space and equipment that is outside of the specificarea of work from damage. Should any damage occur, Contractor shall repair to the Owner'ssatisfaction at no additional cost to the Owner.
J. WORK EXECUTIONAll materials and products are to be manufactured, assembled, and installed in accordance withManufacturer's recommendations, requirements, and shop drawings. Contractor shall post a firewatch complying with Chapter 26 of the Virginia Statewide Fire Prevention Code for any weldingand other hot work. The fire watch shall extend a minimum of two hours after the welding and/orhot work is complete.
K. CLEANINGThe work site must be kept clean of construction debris and discarded packaging material. TheContractor shall arrange for his own trash containers and their removal. Location of the containersmust be coordinated with the Owner's Representative. Trash to be disposed of in a proper andlegal manner. All work shall be thoroughly cleaned and polished before final inspection. Cleaningmust be approved by the Owner prior to final acceptance.
L. SHOP DRAWINGS & SUBMITTALSSubmit shop drawings and product data to the Architect for the following items. Shop drawings,product data, warranties, operation and maintenance manuals, qualifications, and other requiredapplicable information for a single specification section shall be consolidated into one submittal oras few submittals as economically possible. Shop drawings shall be sufficient in scale and detail toindicate materials, methods of fabrication, joints, and general configuration. Work shall notcommence on each item until the Owner has approved the submittal. Submit samples only foritems below marked with an asterisk (*).
a. Doors, Frames, & Hardwareb. Carpet Tile*c. Resilient Base*d. Ceiling Panels & Grid Systemse. Light Fixturesf. Paint*g. Solid Surface Counters*h. Millwork & Cabinetry*i. Ceramic Tile*j. Counter Support Bracketsk. Plumbing Fixturesl. Appliancesm. Air Balance Reportn. Mechanical Equipmento. Electrical Equipment
SPECIFICATIONS1) Doors & Frames:
a) Stained wood doors shall be flush, solid-core with hardwood facing to match existing in species and finish.b) Install doors in accordance with Manufacturer’s instructions and conforming to AWI requirements for fit tolerances.
Doors shall swing freely, free from rattling when in latch position, and free from hinge binding.c) Pre-machine doors for finish hardware, complying with hardware templates furnished by hardware supplier.d) Hollow metal door frames shall be full weld type, 16-gauge, zinc-coated steel with mitered corners and corner
tabs to ensure alignment of the pieces.e) For door frames, provide 10-gauge reinforcing for mortised hinges, strike plate, and other specified hardware.
Provide jamb anchors appropriate for metal stud assemblies and accommodation for 3 silencers per leaf.2) Hardware:
Door Type Ai) 3'-0" x 6'-8" x 1 3/4" flush solid core, stain grade hardwood facing.ii) Sargent 10G24 cylinder office/entrance lock, 'P' lever with 'G' rose. Finish: 26D Satin Chrome ANSI 626.iii) 1 1/2 pair Hager hinges, BB1279 4.5x4.5, or approved equal. Finish: 611 US9 Bright Bronze.iv) 3 silencers, grayv) 1 surface mounted closer with cover, LCN Seried 1460, mounted on pull side, or approved equal. Finish: 611 US9
Bright Bronze.vi) 1 Ives WS402CVX wall bumper where indicated on plan, or approved equal. Finish: 611 US9 Bright Bronze.
3) Interior partitions:a) See partition types on sheet A2.b) Install plumb and level with deviation no more than 1/8" over any 8-foot dimension.c) Tape, fill and sand exposed joints, edges, openings, and fixings, to produce surface ready to receive surface finishes.
Feather coats onto adjoining surfaces so that camber is maximum 1/32".d) Provide fire-retardant, solid-wood blocking in partitions where required to support wall mounted items.e) Provide all accessories, fasteners and sealants necessary for proper installation.f) Install high strength corner trim (Gordon #901 SC 375) at outside corners.g) Install water-resistant and mold-resistant gypsum panels throughout in Shower Room (240E).
Mechanical, Electrical, & Plumbing Engineers:
Mega Consulting Engineers6350 Palmetto PlaceCentreville, Virginia 20121703-830-9777
No. Revision Date
AA-1AREA OF WORK(SECOND FLOOR)
POLICEADMIN239
POLICEADMIN239A
POLICESTORAGE
240A
SQUADROOM240B
SERGEANTOFFICE240C
POLICE240
CLASSROOM241
D-1D-2
D-2
D-5
D-3D-1
D-1
D-1 D-1
D-1
D-1
D-2
D-2
D-2
D-2 D-2
D-4
D-4
D-4
D-4
D-4
D-4
D-4
EXISTING PASS-THROUGH DRAWERFOR BULLETPROOF WINDOW
EXISTING FIRE ANNUNCIATORPANEL TO REMAIN & REMAINOPERATIONAL THROUGHOUTDEMOLITION & CONSTRUCTION
TEMPORARY, NON-COMBUSTIBLE FIXED BARRIER; MUSTREMAIN IN PLACE THROUGHOUT DEMOLITION &CONSTRUCTION PERIODS. RESTORE ANY SURFACESDAMAGED AS A RESULT OF THIS TEMPORARY BARRIER.
EXISTINGBASEBOARDHEATER TOREMAIN
EXISTINGBASEBOARDHEATER TOREMAIN
EXISTINGBASEBOARDHEATER TOREMAIN
D-2
3'-8
" MIN
.EG
RES
SPA
SSAG
E
EXISTING CORRIDOR PARTITION
D-6D-6
D-6
D-6
D-6
D-6
D-6
POLICEADMIN239
POLICEADMIN239A
POLICESTORAGE
240A
SQUADROOM240B
SERGEANTOFFICE240C
POLICE240
CLASSROOM241
#
#NAME ROOM NAME &
NUMBER
PARTITION TYPE
DOOR TYPE
KEYNOTE
#
##
SECTION REFERENCE
SECTION NUMBER
SHEET NUMBERWHERE SECTION ISREFERENCED FROM
SHEET NUMBER WHERESECTION IS LOCATED
INTERIOR ELEVATIONELEVATION NUMBER
SHEET NUMBER WHEREELEVATION IS LOCATED
#
#
##
WALL MOUNTED BUMPER
EXISTING TO BE DEMOLISHED
NEW CONSTRUCTION
CEILING HEIGHT
ACOUSTICAL PANEL CEILING
GYPSUM BOARD CEILING
ACOUSTICAL PANEL CEILING
GYPSUM BOARD CEILING
RECESSED FLUORESCENT LIGHT FIXTURE,SEE ELECTRICAL
DOWNLIGHT FIXTURE, SEE ELECTRICAL
SCONCE FIXTURE, SEE ELECTRICAL
8' - 6"
ACP
GWB
MECHANICAL FIXTURE, SEE MECHANICAL
A TOILET FIXTURE
# WORKSTATION NUMBER
EXISTING TO REMAIN
Consultants
703.684.5994
333 North Fairfax StreetAlexandria, Virginia 22314
Seal
Key Plan
Drawing
Revisions
Date
Project No.
Sheet No.
BCOM SUBMISSION 01/21/15
Submission Set Date
PC No. 260-A2260-140
coleanddenny.com
Copyright © 2014 - Cole & Denny Incorporated. No part of this document or design may be reproduced or distributed in any way without the expressed written permission of the Architect.
21 January 2015
11004.26A2
3001 North Beauregard StreetAlexandria, VA 22311-5097
AD1.01
Demolition Plan & Demolition RCP
Police Station Upgrades
0' 2' 4' 8'
SCALE: 1/4" = 1'-0"
GENERAL DEMOLITION NOTES1. ALL EXISTING DIMENSIONS AND CONDITIONS SHALL BE FIELD VERIFIED.2. REQUIRED DEMOLITION SHALL NOT BE LIMITED TO THAT PORTION ON THE PLANS, BUT SHALL
INCLUDE ALL NECESSARY WORK (OR INCIDENTAL THERE TO) TO COMPLETE THE WORK INACCORDANCE WITH THE CONTRACT DOCUMENTS.
3. REMOVE FLOOR, WALL, AND CEILING FINISHES AND CONSTRUCTION AS INDICATED.4. REPAIR EXISTING CONSTRUCTION TO REMAIN WHERE MECHANICAL, PLUMBING, FIRE PROTECTION,
AND ELECTRICAL WORK IS REMOVED TO MATCH EXISTING CONSTRUCTION. WHERE MASONRY ISEXPOSED, TOOTH-IN NEW WORK WITH FULL-SIZE MASONRY UNITS.
5. PREPARE REMAINING SPACE TO RECEIVE NEW CONSTRUCTION. PATCH ALL AREAS INCLUDING BUTNOT LIMITED TO ROOFS, WALLS, FLOORING, AND SLABS. ALL PATCH WORK TO MATCH EXISTING.
6. PATCH AS REQUIRED TO ACCOMMODATE NEW MECHANICAL, PLUMBING, AND ELECTRICAL WORK.REFER TO ENGINEERING DRAWINGS. ALL NEW WORK SHALL BE CONCEALED UNLESS NOTEDOTHERWISE.
D-1 REMOVE EXISTING DOOR & FRAMED-2 REMOVE PARTITIOND-3 REMOVE WINDOW AND FRAMED-4 REMOVE FLOORING THROUGHOUTD-5 PATCH GWB WHERE PARTITION WAS REMOVEDD-6 REMOVE CEILING PANELS, GRID, LIGHTING, AND MECHANICAL
DIFFUSERS AND GRILLES THROUGHOUT
KEYED DEMOLITION NOTES
1/4" = 1'-0"AD1.011 DEMOLITION FLOOR PLAN
1/4" = 1'-0"AD1.012 DEMOLITION RCP
N
N
LEGEND
No. Revision Date
AA-1AREA OF WORK(SECOND FLOOR)
9'-1"
REF.
EVID.CAB.
LATERALCAB.
EXISTINGTRANSACTIONWINDOW
EXISTING FIREANNUNCIATORPANEL
7'-6"
6'-2 3/4" 6'-8 3/8" 5'-0 1/2"
3'-0"
240A
LIEUTENANT'SOFFICE 240B
INTERVIEWROOM
240C
SERGEANT'SOFFICE
240E
SHOWERROOM
240F
LOCKERROOM
240D
LOCKERROOM
240
RECEPTION /OFFICE
240G
BREAKROOM
9'-2 3/4"13'-0 3/8"
LINE OF SOFFITABOVE
ALIGN ALIGN ALIGN ALIGN
11'-3
3/4
"
8'-1
0"
5'-7"
10'-0
"
5'-7 1/8"3'-1"
A4.01 1
2
3
4
A A A
AA
A
EX
2
2
222
2
2
1 1
2
2
2
2
2
2
2
1
9A4.01A1.01
10A4.01A1.01
3'-8
" MIN
.EG
RES
SPA
SSAG
E
1
4'-1
5/8
"
MAINTAIN EGRESS PASSAGEAT ALL TIMES
R-1R-1
1'-8
"
9'-6
1/2
"1'
-8"
6'-9
5/8
"
8A1.01 A4.01
TYP.
3
33
3
MARBLE THRESHOLDDTL. 7/A4.01
LINE OF SOFFITABOVE
EXISTING PARTITION WITH LEVEL 3ANTI-BALLISTIC WALL ARMOR
PAINT AND BASE TO MATCH EXISTINGCORRIDOR FINISHES (TYPICAL)
PAINT AND BASE TO MATCH EXISTINGCORRIDOR FINISHES (TYPICAL)
A4.01
5
8'-6"
5'-0
"
45°
1
2
3 4 5
6 7 8 9 10
11
3
11A4.01A1.01
COUNTERSUPPORTBRACKET
2'-10"
MICROWAVE
240A
LIEUTENANT'SOFFICE
240
RECEPTION /OFFICE
240B
INTERVIEWROOM
240C
SERGEANT'SOFFICE
240E
SHOWERROOM
240D
LOCKERROOM 240F
LOCKERROOM
240G
BREAKROOM
8' - 6"
8' - 6"8' - 6"
8' - 6"
7' - 6" 7' - 6"
8' - 6"
8' - 6"8' - 6"
8' - 6"
8' - 6"
9A4.01A1.01
ACP
GWB
ACPACP
ACP
ACP
ACP
ACP
ACP
GWBGWB
EQ EQ
EQ EQ
2'-0
"1'-9"
5'-0
3/4
"
2'-0
"
5'-1
7/8
"4'
-10
3/4"
2'-4" 2'-6" 1'-6"
#
#NAME ROOM NAME &
NUMBER
PARTITION TYPE
DOOR TYPE
KEYNOTE
#
##
SECTION REFERENCE
SECTION NUMBER
SHEET NUMBERWHERE SECTION ISREFERENCED FROM
SHEET NUMBER WHERESECTION IS LOCATED
INTERIOR ELEVATIONELEVATION NUMBER
SHEET NUMBER WHEREELEVATION IS LOCATED
#
#
##
WALL MOUNTED BUMPER
EXISTING TO BE DEMOLISHED
NEW CONSTRUCTION
CEILING HEIGHT
ACOUSTICAL PANEL CEILING
GYPSUM BOARD CEILING
ACOUSTICAL PANEL CEILING
GYPSUM BOARD CEILING
RECESSED FLUORESCENT LIGHT FIXTURE,SEE ELECTRICAL
DOWNLIGHT FIXTURE, SEE ELECTRICAL
SCONCE FIXTURE, SEE ELECTRICAL
8' - 6"
ACP
GWB
MECHANICAL FIXTURE, SEE MECHANICAL
A TOILET FIXTURE
# WORKSTATION NUMBER
EXISTING TO REMAIN
AREA OF WORK(SECOND FLOOR)
PAINT CORRIDOR WALL TO MATCH EXIST.
Consultants
703.684.5994
333 North Fairfax StreetAlexandria, Virginia 22314
Seal
Key Plan
Drawing
Revisions
Date
Project No.
Sheet No.
BCOM SUBMISSION 01/21/15
Submission Set Date
PC No. 260-A2260-140
coleanddenny.com
Copyright © 2014 - Cole & Denny Incorporated. No part of this document or design may be reproduced or distributed in any way without the expressed written permission of the Architect.
21 January 2015
11004.26A2
3001 North Beauregard StreetAlexandria, VA 22311-5097
A1.01
New Work Plan & New Work RCP
Police Station Upgrades
0' 2' 4' 8'
SCALE: 1/4" = 1'-0"
GENERAL NEW WORK NOTES1. DIMENSIONS ARE TO FINISH FACE OF CONSTRUCTION UNLESS OTHERWISE INDICATED.2. HINGE OF DOOR JAMBS TO BE 4" FROM WALL INTERSECTION UNLESS OTHERWISE
INDICATED.3. PROVIDE NON-COMBUSTIBLE OR FIRE RETARDANT TREATED WOOD BLOCKING IN
PARTITIONS WHERE REQUIRED TO SUPPORT WALL MOUNTED ITEMS.4. FURNITURE IS SHOWN FOR INFORMATION ONLY. FURNITURE SHALL BE PROVIDED BY
THE OWNER. GC SHALL COORDINATE WITH THE OWNER FOR WORK ASSOCIATED WITHTHE FURNITURE. IT IS THE OWNER'S RESPONSIBILITY THAT THE FURNITURE SHALLCOMPLY WITH THE ADA STANDARDS FOR ACCESSIBLE DESIGN (2010).
R-1 PATCH, REPAIR OR RELPACE, & PAINT DISRUPTED FINISHES IN CORRIDOR TO MATCH EXISTING
KEYED REPAIR NOTES
1/4" = 1'-0"A1.011 NEW WORK PLAN
1/4" = 1'-0"A1.012 NEW WORK RCP
GENERAL RCP NEW WORK NOTES1. EQUAL DIMENSIONS APPLY INDIVIDUALLY IN EACH ROOM & IN EACH DIRECTION ONLY.
N
N
LEGEND
1" = 20'-0"A1.013 NEW WORK PLAN - EXTENT OF CORRIDOR PAINT N
0' 10' 20' 30'
SCALE: 1" = 20'
No. Revision Date
AA-1AREA OF WORK(SECOND FLOOR)
D
CERAMIC TILEAT SHOWERSURROUND
CERAMIC TILEWAINSCOT
PAINT
3'-2
1/4
" TYP
.
I
1'-6
"
J
FCB
D
CERAMIC TILEWAINSCOT
PAINT
2'-1
1 1/
2"3'
-10"5'-7
5/8
"
4"
EQEQ
H1'-3 1/8"
AE
BC
F
CERAMIC TILEWAINSCOT
PAINT LIGHT FIXTUREG
E
APAINT
CERAMIC TILEWAINSCOT
LIGHTFIXTURE
G
1
6"
BRACE STUDS TOSTRUCTURE ABOVE@ 48" O.C. MAX.
ACP OR GWB CEILINGWHERE INDICATED
3 5/8" METAL STUDSAT 16" O.C.
5/8" GYSPUM WALL BOARDOR 5/8" WATER RESISTANTBOARD AT TILED WALLS
ACOUSTICAL SEALANT
FINISH FLOOR
BASE
EXISTING CEILING
UNDERSIDE OF 8" CAST-IN-PLACE CONCRETESLAB ABOVE
1 LAYER 1/2"LEVEL 3 ANTI-BALLISTICWALL ARMOR
ALIGN FACE W/ADJACENTEXISTINGCONSTRUCTION
CORRIDOR POLICE STATION
2
6"
BRACE STUDS TOSTRUCTURE ABOVE@ 48" O.C. MAX.
ACP OR GWB CEILINGWHERE INDICATED
3 5/8" METAL STUDSAT 16" O.C.
5/8" GYSPUM WALL BOARDOR 5/8" WATER RESISTANTBOARD AT TILED WALLS
ACOUSTICAL SEALANT
FINISH FLOOR
BASE
UNDERSIDE OF 8" CAST-IN-PLACE CONCRETESLAB ABOVE
3
ACP CEILING WHEREINDICATED
EXISTING CEILING(IN CLASSROOM)OR NEW ACPCEILING WHEREINDICATED (INPOLICE STATION)
EXISTING PARTITION
6"
BRACE STUDS TOSTRUCTURE ABOVE@ 48" O.C. MAX.
FINISH FLOOR
BASE
UNDERSIDE OF 8" CAST-IN-PLACE CONCRETESLAB ABOVE
GYPSUM WALLBOARD & METALSTUD EXTENSION
EXISTING BASE (INCLASSROOM) ORNEW BASE (INPOLICE STATION)
1'-0
"6"
ACOUSTICALCEILING PANEL
5/8" MOISTURE &MOLD RESISTANTGWB
5/8" GWB10"
LIMIT OF GWB ATADJACENT ROOMS
1'-8"
CERAMIC TILE
3 5/8" METAL STUDS
SHOWER PAN MEMBRANE
CRUSHED TILE OR STONE
SLOPED SETTING BED1/2" x 2" MARBLE SILL;ALIGN WITH WALL
5/8" CEMENTITIOUS BACKERBOARD
CERAMIC TILE
SHOWER PANMEMBRANE; TURN UPAT SILL AND WALLS
1/4" SLOPE TO DRAIN
1/4" / FT.
SLOPE TO DRAIN
1/4" / FT.
SLOPE PERPENDICULARTOWARD ROOM FLOORDRAIN AT 1/4" / FT MAX.SEE PLAN.
6" M
IN.
MARBLETHRESHOLD
TILEFLOORING
CARPET
DOOR
SPLICE PIECE -TYPICAL AT ALLWALL ARMORJOINTS
2" MIN. 2" MIN.
A
2" 3'-0" 2"
2"6'
-8"3'-6" 1'-0"
3'-0" 6"
2'-1
1 1/
2"
2'-1
1 1/
2"
3'-4
"3'
-0"
1'-6
"
2'-1
0"
2'-0" 1'-0"
A
F F
B CC B
3'-3
"
E
8"
3'-3
"
G
2"
SEE PARTITION TYPESSEE PARTITION TYPE
CONTINUOUS PERIMETERSEALANT EACH SIDE
H.M. FRAME
DOOR
A
MARK ITEM MODEL TYPE REMARKS
MIRROR BOBRICK B-165 2436 SURFACE
B SURFACE
C
TOILET PAPER DISPENSER
SURFACE
D SURFACE
E SURFACE
F SURFACEFURNISHED BY OWNER
GRAB BAR BOBRICK B-5806 X 42
GRAB BAR BOBRICK B-5806 X 36
SHOWER GRAB BAR BOBRICK B-6861
PAPER TOWEL DISPENSER FURNISHED BY OWNER
HAND SOAP DISPENSERG SURFACEFURNISHED BY OWNER
FURNISHED BY OWNER, INSTALLED BY GC
FURNISHED BY OWNER, INSTALLED BY GC
FURNISHED BY OWNER, INSTALLED BY GC
SHOWER SOAP DISPENSERH SURFACEFURNISHED BY OWNER FURNISHED BY OWNER, INSTALLED BY GC
FOLDING SHOWER SEATI SURFACEBOBRICK B-5181
SHOWER RODJ SURFACEBOBRICK B-207 X 36
2'-1
0"1'
-10"
2'-6
"
4"
BACKSPLASH
SOLID SURFACE COUNTER
MOVABLE SHELF, TYP.
3/4" SOLID SURFACECOUNTER
1/4" RAD
1/8 RAD
SEALANT
CERAMICTILE
RAKKSEH-1818-FM FLUSHMOUNTCOUNTERSUPPORTBRACKET ATOPEN SIDE
APRON ATOPEN SIDE
COVE
1'-6"
PROVIDE ANDINSTALL INSULATEDCOVERING OVEREXPOSED PIPINGAND FITTINGS
INTEGRAL BOWLLAVATORY
1'-10"
1 1/
2"
1/2"1"
BACKSPLASH BEYOND
BACKSPLASH
2 3/
4"
Consultants
703.684.5994
333 North Fairfax StreetAlexandria, Virginia 22314
Seal
Key Plan
Drawing
Revisions
Date
Project No.
Sheet No.
BCOM SUBMISSION 01/21/15
Submission Set Date
PC No. 260-A2260-140
coleanddenny.com
Copyright © 2014 - Cole & Denny Incorporated. No part of this document or design may be reproduced or distributed in any way without the expressed written permission of the Architect.
21 January 2015
11004.26A2
3001 North Beauregard StreetAlexandria, VA 22311-5097
A4.01
Interior Elevations & Details
Police Station Upgrades
0' 2' 4' 8'
SCALE: 1/4" = 1'-0"
1/4" = 1'-0"A1.01 A4.011 SHOWER ROOM ELEV.
1/4" = 1'-0"A1.01 A4.012 SHOWER ROOM ELEV.
1/4" = 1'-0"A1.01 A4.013 SHOWER ROOM ELEV.
1/4" = 1'-0"A1.01 A4.014 SHOWER ROOM ELEV.
1 1/2" = 1'-0"A1.01 A4.019 SOFFIT DETAIL
3" = 1'-0"A1.01 A4.0110 SHOWER DRAIN DETAIL
3" = 1'-0"A4.01 A4.017 THRESHOLD DETAIL
3" = 1'-0"A1.01 A4.018 WALL ARMOR DETAIL
1 1/2" = 1'-0"A4.01 A4.016 HEAD/JAMB DETAIL
TOILET FIXTURE SCHEDULE
FIXTURE MOUNTING HEIGHTS DOOR TYPES
PARTITION TYPES
1/4" = 1'-0"A1.01 A4.015 BREAK ROOM ELEV.
0' 6" 1'4"2"
SCALE: 3" = 1'-0"
0' 1' 2'6"
SCALE: 1 1/2" = 1'-0"
3" = 1'-0"A1.01 A4.0111 VANITY DETAIL
No. Revision Date
G0-01 - Cover SheetAD1-01 - Demolition Plan & Demolition RCPA1-01 - New Work Plan & New Work RCPA4-01 - Interior Elevations & DetailsM0.0-Layout1M1.0-Layout1M2.0-Layout1P0.0-LayoutP1.0-LayoutE0.0-Layout1E1.0-Layout1E2.0-Layout1E3.0-Layout1E4.0-Layout1