Point PlacePoint PlaceSewer Sewer
ImprovementsImprovements
Neighborhood Advisory
Committee
July 19, 2005
Today’s MeetingToday’s Meeting
• Purpose – review Phase 2C of sewer improvement project
• Gather input on:• Construction issues• Traffic issues
Program UpdateProgram Update
• Bay View Expansion
• River Road
• EPA
Phase 2C – SchedulePhase 2C – Schedule
• Advertise for Construction Bids – July 30th
• Award of Contract – Fall 2005
• Construction Begins – November 2005
• Street Restoration – Spring 2005
Phase 2C – OverviewPhase 2C – Overview
• 24-inch gravity relief sewer from 135th north on Edgewater to 149th
• Will bid two ways• Open trench• Boring
Option #1 – Option #1 – One-Way BypassOne-Way Bypass• Northbound traffic routed on three-phase detour
• Southbound traffic routed on Edgewater – one lane maintained• Flaggers needed on some sections
• No on-street parking on detour route
Option #1 – Option #1 – One-Way BypassOne-Way Bypass• Phase 1
• 136th east to Lakeside northeast to 317th north to 141st west
• 138th bypass - 136th east to 313th north to 138th west
• Phase 2• One-lane maintained with flaggers between 141st
and 145th
• Phase 3• 145th east to 321st north to 146th east to 324th north to
149th west to Edgewater south
Detour RouteDetour Route
Option #2 – Option #2 – One Lane With FlaggersOne Lane With Flaggers• No detour
• Like last phase of Edgewater work
• One lane maintained around construction with flaggers
RecommendationsRecommendations
• City recommends one-way bypass detour
• Approved by TARTA and Fire Department
Access for Safety ServicesAccess for Safety Services
• Police and Fire will have direct communication with construction crews
Work Hour – OptionsWork Hour – Options
• Standard 8-hour shifts• Less disruption for residents
• Work 24 hours• Shortens construction period• More disruptive to neighbors
Public Notification/Public Notification/CommunicationsCommunications• Meetings with businesses and Police/Fire
• Point Shoreland Journal – advertising with map showing construction schedule and detours
• Run 2 times before start of construction
• Signage placed on Edgewater warning of coming detours (2 weeks prior)
Public Notification/Public Notification/CommunicationsCommunications• Notification of residents – mailers or door
hangers?
• Other recommendations from Committee
• Another public meeting prior to start of construction
Next MeetingNext Meeting
• Date