Point PlacePoint PlaceSewer Sewer
ImprovementsImprovements
Neighborhood Advisory Committee
February 8, 2006
Today’s MeetingToday’s Meeting
• Program update
• Point Place update
• Questions/Comments
Program UpdateProgram Update
• Bay View Wastewater Treatment Plant• Equalization Basin• Ballasted Flocculation• Grit Facility
• All on schedule
• Work on water tower has begun
BVWWTPBVWWTP
Program UpdateProgram Update
• River Road
• Long Term Control Plan• Submitted to EPA in December• Waiting to hear from EPA• Plan assumes only a 25 million gallon EQ basin
Phase 2CPhase 2C
• A few weeks behind schedule
• Equipment/technical problems
• Now making good time
Phase 2CPhase 2C
Phase 2CPhase 2C
Phase 2CPhase 2C
Phase 2CPhase 2C
Phase 2CPhase 2C
• Detour has just begun• Understand there are some problems with people not
following one way• Addressing with additional signage
DetourDetour
• Northbound traffic routed on three-phase detour
• Southbound traffic routed on Edgewater – one lane maintained• Flaggers needed on some sections
• No on-street parking on detour route
DetourDetour
Questions/CommentsQuestions/Comments
• Questions/Comments
• Next meeting