PNB 400 Final Report

Embed Size (px)

DESCRIPTION

A brief report on Underground Bord and Pillar Mining in South African Mines from the Mpumalanga Province.

Citation preview

  • 1

    Table of Contents List of Figures .......................................................................................................................................... 3

    List of Tables ........................................................................................................................................... 4

    1. Introduction ..................................................................................................................................... 5

    2. Khutala Coal ................................................................................................................................... 5

    Mine background and General Information .......................................................................... 5

    Mining Method .................................................................................................................................... 6

    Mining Activities ................................................................................................................................. 6

    Coal cutting ..................................................................................................................................... 6

    Roof Support .................................................................................................................................. 7

    Tramming ......................................................................................................................................... 7

    Pillar design and Support .............................................................................................................. 8

    Equipment Selection ....................................................................................................................... 8

    Production rates ............................................................................................................................. 10

    Personnel ........................................................................................................................................... 11

    3. Shanduka Coal ........................................................................................................................... 12

    Mine Background and general information ........................................................................ 12

    Mining Method and Mining Activities .................................................................................... 14

    Equipment Selection .................................................................................................................... 14

    Production rates and Unit costs .............................................................................................. 15

    Personnel ........................................................................................................................................... 15

    4. Penumbra Coal Mining ........................................................................................................... 16

    Background ....................................................................................................................................... 16

    Mining Method ................................................................................................................................. 17

    Equipment and Personnel ......................................................................................................... 17

    Pillar Design and Support .......................................................................................................... 18

    Ventilation .......................................................................................................................................... 18

    Production Rates and Unit Costs ........................................................................................... 18

    Challenges ........................................................................................................................................ 19

    5. New Denmark Colliery ............................................................................................................ 20

    Mine Background ........................................................................................................................... 20

    Mining Method & Activities ........................................................................................................ 20

    Pillar Design and Support .......................................................................................................... 22

  • 2

    Equipment Selection .................................................................................................................... 23

    Ventilation .......................................................................................................................................... 24

    Production Rates............................................................................................................................ 24

    Unit Costs .......................................................................................................................................... 24

    Personnel ........................................................................................................................................... 25

    6. Msobo Coal .................................................................................................................................. 26

    Location and background ........................................................................................................... 26

    Mining method and activities .................................................................................................... 28

    Equipment Selection .................................................................................................................... 29

    Ventilation .......................................................................................................................................... 30

    Unit Costs and Personnel .......................................................................................................... 30

    7. Sasol ............................................................................................................................................... 32

    Mine Background ........................................................................................................................... 32

    Brandspruit Colliery ...................................................................................................................... 32

    Mining Method ................................................................................................................................. 33

    Pillar Design and Support .......................................................................................................... 35

    Equipment Selection .................................................................................................................... 35

    Ventilation .......................................................................................................................................... 35

    Middelbult Colliery- Ithemba Lethu Shaft ................................................................................ 37

    Background ....................................................................................................................................... 37

    Mining Method ................................................................................................................................. 37

    Pillar Design and Support .......................................................................................................... 38

    Equipment Selection and Personnel .................................................................................... 39

    Ventilation .......................................................................................................................................... 39

    Production Rates and Unit Costs ........................................................................................... 39

    Challenges ........................................................................................................................................ 39

    8. References ................................................................................................................................... 40

  • 3

    List of Figures

    Figure 1 Location of Khutala Colliery (BHP Billiton, 2014) ................................................... 5 Figure 2: Typical cutting sequence (BHP Billiton, 2014) ........................................................ 7 Figure 3: Joy Continuous Miner (12HM31B) (BHP Billiton, 2014) ..................................... 8 Figure 4: Joy Shuttle Car (10SC32-56C) (BHP Billiton, 2014) ........................................ 9 Figure 5: FFE Feeder breaker. (BHP Billiton, 2014) .............................................................. 10 Figure 6 Location of Graspan Complex (Infomine, 2014) ............................................... 12 Figure 7: The location of Continental Coal Operations .................................................... 16 Figure 8: Twin decline shafts at Penumbra Coal. (Conti Coal Presentation, 2014)

    ..................................................................................................................................................................... 17 Figure 9: Map of wetland at Penumbra Coal. (Continental Coal Presentation,

    2014) ......................................................................................................................................................... 19 Figure 10 Longwall section layout. ............................................................................................. 21 Figure 11: Basic Chock support illustration .............................................................................. 23 Figure 12: Map Showing Msobo Coal Mine ........................................................................... 26 Figure 13: The stratigraphy of Msobo Coal Reserves ............................................... 27 Figure 14> Location of the shafts at Brandspruit ................................................................ 32 Figure 15: The cutting sequence using the Nevid Method ............................................. 33 Figure 16: The Nevid Method pillar extraction. .................................................................... 34 Figure 17: Basic air flow through a Nevid section. ............................................................. 36 Figure 18 Location of Middelbult Colliery ................................................................................ 37 Figure 19: The 4-seam layers. ..................................................................................................... 38

  • 4

    List of Tables

    Table 1: Equipment used at Shanduka Coal ......................................................................... 15 Table 2: The total number of people employed at Shanduka Coal. .................................. 15 Table 3: The pillar design and support specifications at Penumbra Coal. .............. 18 Table 4. Table showing equipment and details .................................................................... 23 Table 5: Underground equipment used at the mine .......................................................... 29 Table 6: Personnel specifications ............................................................................................... 30 Table 7: The type of equipment and the total number ...................................................... 35 Table 8 Pillar design and support specifics ............................................................................ 38

  • 5

    1. Introduction

    Between the period of the 28th of January and the 7th of February 2014, a total of

    six coal mines were visited. These mines are located in differing environments

    and therefore utilise specialised mining methods for that particular area.

    Moreover, there are varying challenges faced by each mines. Each of the six

    mines visited is described in terms of the mining methods, pillar design and

    support, equipment, personnel and other relevant factors.

    2. Khutala Coal

    Mine background and General Information

    Khutala colliery is located in Ogies as shown in figure 1 and is part of the

    Witbank coalfields. This coalfield is part of the Vryheid formation under the Karoo

    Super group.

    Figure 1 Location of Khutala Colliery (BHP Billiton, 2014)

    BHP Billiton owns the colliery. The mine has an open cast operation as well as

    an underground operation. The open cast operation mines the 2, 4 and 5 seams

  • 6

    while the underground operation only mines the 2 and 4 seams. Plans are in

    place to turn the underground operation into an open cast operation to be able to

    mine the high-grade coal in the 5 seam. The seams have the following features:

    No.2 Seam ranges from 0.5 to 20 meters in thickness but at the mine it

    is about 7.1m with a calorific value of 20.05MJ/kg. It is 108.61m from

    surface.

    No.4 Seam ranges from 0.5 to 6.5 meters in thickness but at the mine it

    is 6.2m (average) with a calorific value of 18.29MJ/kg. The distance from

    surface is 83.42m

    No. 5 Seam ranges from 0 to 2 meters in thickness but at the mine, the

    seam is 1.63m thick and has a calorific value of 28MJ/kg. It is 60.56m

    from surface.

    The mine supplies coal to the Kendal Power station and the tender was approved

    in September in 1986. The contract expires on 31 December 2033. The 4320

    MW base load power station was made in such a way to accommodate the

    quality of the coal in the reserve. It is the biggest power station in Africa. It is a

    dry-cooled operation since water is a constraint in the area and thus there is a

    need to recirculate the water. The coal has calorific value of MF 19.6Mj/kg (4680

    Kcal). The power station supplies 9-12% of South African electrical power

    demand. It has a maximum burn rate capacity of 17million tons per annum.

    Mining Method Mechanized bord and pillar is the mining method that is being used to mine the 4

    and the 2 seam. Conventional bord and pillar is used in areas where dykes are

    encountered. Mining is done from the right to the left for ventilation purposes.

    The mining height is about 4.5m while the mining width (bord) is 6.8m.

    Mining Activities

    Coal cutting A continuous miner (CM) is used to cut the coal, which it loads onto the shuttle

    cars that then take it to the feeder breaker. The CM sumps in 0.5m from the roof

  • 7

    into the face at a distance of 0.85m. It then shears down to fill one 20t shuttle car.

    The CM cuts 12m before support is installed. The development per shift is

    usually 50m. The cutting sequence as shown in figure 2, is in such a way that

    there is always through ventilation and the tramming on the CM is less as well as

    the cable handling. The effective cutting time on the CM is normally 160 minutes

    per shift, which simplifies to 12t per min. The CM also has 93% availability and

    40% utilization.

    Figure 2: Typical cutting sequence (BHP Billiton, 2014)

    Roof Support The roof support installed in a normal bord and pillar development end are 1.8m

    long roof bolts that are spaced 1.5m apart. It normally takes 20-25 minutes to

    install support with a Fletcher roofbolter for a 12m development end.

    Tramming The mine also has an incline shaft for the conveyor belts that transport the coal

    from the feeder-breaker to surface. The incline shaft is about 7m wide and it

    accommodates 2 belts. The configuration is such that there are surge bins that

    accommodate the ore from both seams and ensure that the conveyor belt is

    loaded properly. The conveyor belt speeds vary from 2m/s to 3m/s.

  • 8

    Pillar design and Support The pillars are designed in such a way that the total extraction of the mine is only

    40%. The safety factor with regard to the main development is 2 while for the

    secondary development it is 1.6. The mine also uses full cover mesh for back

    bye areas as well as Oslo straps for where sidewall nets are joined.

    Equipment Selection In the production sections the mine uses a number of different mining machines

    that are fit for different purposes. At the face, the mine uses continuous miners of

    which there are twelve 12HM 31 Remote Control JNA 2 Continuous Miners as

    shown in figure 3 and two 12HM21 Onboard Joy Continuous Miners.

    Figure 3: Joy Continuous Miner (12HM31B) (BHP Billiton, 2014)

    The number of continuous miners matches the number of sections, which makes

    it a continuous miner per section. The mine is working on phasing out the

    onboard continuous miners as a means of reducing the number of people

    exposed to the working face and thus reduce fatality caused by on board

    continuous miners. The aim is to have sections that are operated by remotely

    controlled continuous miners.

    Onboard continuous miners have an overall length of 12 m and a height of 5.5m.

    The maximum cutting width is normally 3.65m while the cutter head is 1.118m.

    The cutting speed is around 50 rpm. The continuous miners loading rate can go

    up to 20t/min. The spacing and lacing is around 0.0762. The machine itself

    weighs 103t.

  • 9

    The mine uses a total of nine roof bolters to install support. These consist of

    Fletcher twin boom roofbolters and five Rham twin boom Roofbolters. The

    Fletcher twin roof bolters have the capacity to do 200 roofbolts per shift and they

    utilise dry drilling as a means of drilling. The Rham twin roof bolters have the

    capacity of doing 20 bolts per hour with sidewall bolting capacity. These Rham

    roof bolters can only operate at heights ranging from 2.5m to 5.5m with the hole

    dimensions being from 23mm to 42mm. They have an overall length and width of

    6.2m and 3.2m respectively. They have an average weight of about 28tons.

    The mine has forty-two 10SC 22 20t C and D type Shuttle Cars and thus three

    per section. The shuttle cars carry the coal from the continuous miner to feeder

    breaker. The Joy 10 SC 32 56C shuttle cars, shown in figure 4 have an overall

    length and width of 9.24m and 2.72m respectively. These machines weigh 27t

    and have a loading capacity of 20t. The tramming speed ranges from 2.50m/s

    when empty to 2.2m/s when loaded.

    Figure 4: Joy Shuttle Car (10SC32-56C) (BHP Billiton, 2014)

    The other machines which form part of the underground fleet include bird

    machines, stone duster (Bateleur), Sandvik LHD (LS191) and a feeder breaker.

    The Stone dusters are used to spray stone dust frequently as a means of

    preventing coal dust explosions. Stone dust is usually a primary inerting agent

    such as calcium carbonate. The mine has fourteen FFE Feeder breakers, 1 per

  • 10

    section. The FFE Feeder breaker as shown in figure 5 has a capacity of 850t/hr

    and feeds the conveyor.

    Figure 5: FFE Feeder breaker. (BHP Billiton, 2014)

    Production rates The total production is around 11Mt with the underground operation producing

    9Mt while the Open cast operation produces the remaining 2Mt (Portion 16). The

    production from the underground sections comes mainly from the 2 Seam (4Mt)

    and the 4 seam (5Mt). Currently the mine has 14 sections in operation that run

    on a 3 shift system (Monday Morning Saturday Morning) in a 24-hour cycle that is as follows:

    Day shift: 06:20 16:00 (Bank to Bank)

    Afternoon shift: 14:20 00:10

    Night shift: 22h20 08:10

  • 11

    Personnel The mine has a total of 2801 employees of which 1697 are owned by the

    company while the remaining 1104, are contractors. The personnel required per

    section per shift are:

    2 Artisan

    1 Miner

    1 Supervisor

    2 Continuous Miner Operators

    1 LHD driver

    6 Multi-skilled operators.

  • 12

    3. Shanduka Coal

    Mine Background and general information Shanduka Coal produces thermal coal as well as anthracite coal to a lesser

    extent. It is operated in partnership with Glencore International and owns the

    Middelburg complex, Umcebo complex and the Springlake colliery. The

    Middelburg complex consists of the Graspan complex (as shown in figure) and

    the Middelburg Townlands sections as shown in figure 6. The Umcebo complex

    on the other hand contains the following sections: Middelkraal, Kleinfontein,

    Klippan and Wonderfontein. The Springlake colliery is suited in KwaZulu Natal,

    and it is where anthracite coal is mined.

    Figure 6 Location of Graspan Complex (Infomine, 2014)

    Both the Middelburg complex operations are open cast. The Run of mine

    Production of the Middleburg complex is 7.3Mtpa while the overburden is 22.1

    Mbcm per annum. The total number of operating pits is 7 of which 3 are on the

    Graspan section and the remaining four are on the Townlands sections. The 3

    pits at Graspan are: Block A, Northwest pit and South pit while for the Townlands

    sections they are: Block D, Block B, Steelcoal East and Steelcoal west. The pits

    each have different seams and challenges, which are as follows:

    Block A - Mining is being done in the 2 seam and the 1 seam, which is all

    export coal.

  • 13

    Northwest pit - Mining is being done in the 1 seam, 2 seam, portions of the

    3 seam and recently the 4 seam. The challenge is that the coal obtained

    is normally Eskom coal and export coal, therefore the mining should be

    such that it provides the quantity required for both export and commercial

    supply ( Eskom). The Eskom coal is only just crushed while the export one

    goes through the whole beneficiation process.

    South pit Similar geology as the north pit but the mining is much easier

    because the Eskom and export coal are in separate layers unlike in the

    north pit.

    Block D consist of the 2 seam, 3 seam and a bit of the 4 seam. A

    contractor known as JCI is doing the mining. The quality of the coal here is

    quite good.

    Block B consist of the 1 seam, 2 seam, 3 seam and the 4 seam but the

    quality of the coal is not that good and thus it sold to Eskom coal. Andru

    mining is the contractor responsible for mining the pit.

    Steelcoal East consist of the 1 seam, 2 seam and the 3 seam. Here

    there is both Eskom and export coal. Andru mining is also responsible for

    mining this pit.

    Steelcoal West consist of the 1 seam and the 2 seam. Sandton was

    responsible for mining this this pit but now Shanduka itself is going to take

    over.

    The plant capacity at Graspan is sub-divided into the Export main plant (180

    000t), secondary wash plant (90 000t) and Eskom crushing plant (150 000t). The

    discard from the main export plant becomes the feed material for the secondary

    wash plant, which gives out a different quality product. The plant capacity at

    Townlands per month is sub-divided into the Export plant (110 000t), inland plant

    2 (75 000t), Steelcoal plant (120 000t) and Eskom crushing plant (60 000t). The

    Eskom plant works on a 20 CV and it involves crushing and screening the coal.

    The Export plant works on a 26.2 CV and the inland plant as well as the

  • 14

    Steelcoal plant both work on a 23.5 CV. The mine doesnt discard their tailings

    and fines but rather blend them with other the Eskom low CV coal.

    Mining Method and Mining Activities Both the Graspan sections and Townlands sections are open cast operations.

    The Townlands section is a truck a shovel operation that is contractor operated

    with an overburden of 11.3 BCM. The Graspan operation is also a truck and

    shovel operation but in this case it is operated by Shanduka themselves; with an

    overburden of 10.8 BCM. The tramming distance at Graspan is usually 2.5km to

    the processing plant. The blocks of the pits are 600m with strips of 50 m at a

    width of 40m. The stripping ratio is normally 4:6.

    To deal with the water problem at the pit, the mine uses 160kpa pressure diesel

    pumps at every bench. The ramps are inclined at 30. The mine uses ANFO and

    electronic detonators in their blasts with an effective burden of 5.5m. The blast

    radius is around 600m. The blast design includes a pre-split that has a spacing of

    2m between the holes. The burden to spacing ratio on the bench is 5mx5m. The

    expected swell factor after the blast is normally 30cm. The timing between the

    holes is about 10ms while the timing between the rows is 15ms in a blast design

    timing sequence.

    The mine uses the roll over method of disposing its waste and this involves

    throwing the waste over parts that are planned for rehabilitation to form a base.

    The soil removal personnel are always two strips ahead of the bench being

    prepared for a blast. The mine uses a double loading method for the truck and

    shovel operation. It normally takes 5 minutes to and from the processing plant

    after the truck has been fully loaded.

    Equipment Selection One of the parameters that provide minimum cost for the targeted production in a

    mine is surely the suitability of the machines/equipment selected. Moreover,

    equipment selection directly affects the pit design and production planning. At

    Shanduka Coal equipment selection was made according to many factors related

    to the ore and mining conditions of this region. It was explained that the main

  • 15

    purpose of equipment selection is to choose the optimum and cost effective

    equipment. The following table shows the equipment used at Shanduka coal.

    Table 1: Equipment used at Shanduka Coal

    Type of Equipment

    Total Number of Equipment

    Excavators 47

    Dozers 41

    Trucks 198

    Front End Loader 56

    Production rates and Unit costs The life of mine of the reserve is 27Mtons and sellable production is 3.2MTpa,

    Townlands reserve is left with 7years of mining and the life of mine of Graspan

    reserve is also 7years. Townlands produces 3.33MT per annum. Graspan

    produces 4MTpa and export at R368/ton and sell to Eskom at R147/ton.

    (Mabogoane, M. 2014)

    Personnel Shanduka opencast runs on a three shifts per day system. The day shift runs

    from 6am to 4 pm, the afternoon shift runs from 4:30pm to 10pm and the night

    shift runs from 10:30pm to 2am. They is a 30minutes break during each shift.

    The following table shows the total number of people employed on this mine:

    Table 2: The total number of people employed at Shanduka Coal.

    Contractors 1800

    Own labour 833

    Total labour 2633

  • 16

    4. Penumbra Coal Mining

    Background Penumbra Coal is one of twelve coal operations currently under Continental Coal

    Limited in Ermelo as shown in figure 7 below.

    Figure 7: The location of Continental Coal Operations

    The New Order Mining Right was awarded in May 2010. Development then

    started in September 2011 and the first coal production was in November 2012.

    The total capital costs as in January 2012 amounted to R319 million. Penumbra

    has a forecasted 10 year life of mine with measured gross in-situ coal resources

    amounting to 13Mt.

    The mine is located 2km from the wash plant and rail siding. The plant is

    relatively small with a capacity of 300t/hour. The coal yield is between 48-51%.

    Total fines amount to 7% and these are blended with the export product. About

    6000 Kcal of coal is exported at R700/t.

  • 17

    Mining Method Access to the mine is by twin decline shaft of 360m length as shown in figure 8

    below.

    Figure 8: Twin decline shafts at Penumbra Coal. (Conti Coal Presentation, 2014)

    The decline dips at 5 and increases to 8 as the length increases due to the

    dolerite sill encountered underground. Mining is done at depths of between 50-

    115m. The C-lower seam with an average seam height of 1.8m is mined.

    The mine uses the Bord and Pillar mining, with 2 fully mechanized Continuous

    Miner production sections and 1 Drill and Blast section. The mine is located in an

    area with geological features such as dykes, faults and most frequently

    sandstone rolls. The Drill and Blast operation is therefore used when these

    features are encountered due to its flexibility.

    Equipment and Personnel Each CM section consists of

    2 x Continuous Miners

    4 x 10t Shuttle Cars

    1 Single-Boom Roof bolter

    A total of 12 people work 2 shifts/day, 5days a week for each CM section. The

    Drill and Blast section is operated by a contractor and has 28 people per section

    on a full production shift.

  • 18

    Pillar Design and Support The Continuous Miner section visited was at a 58.7m depth below surface. The

    pillar design and support specifications are shown in Table x below.

    Table 3: The pillar design and support specifications at Penumbra Coal.

    Bord width 6.5m

    Pillar centres 14m

    Pillar width 7.5m x 7.5m

    Width to Height Ratio 4

    Number of roads 7

    Roof Bolt length 1.5m

    Support dimensions 1.5m x 2m

    Safety Factor >1.6

    The pillar center dimensions are subject to change due to the constantly

    changing geological conditions.

    Ventilation The mine uses 11KW force fans and ventilation brattices for the underground

    workings. Two fans with capacity of between 60-80m3 are used. Velocity is

    maintained at 1.2m/s.

    Production Rates and Unit Costs The target production per mechanized panel is 1600t/shift at an advance of 50m.

    The entire mine achieves a production rate of 50 000t/month ROM. However,

    sandstone rolls cause a drastic drop in the production rate when encountered as

    they have to be mined out. Mining of the sandstone rolls in order to return to the

    seam comes at a cost of R100/ton. For one month in 2013, the mine lost R4

    million due to this.

    The Drill and Blast section achieves lower production rates and costs more than

    the CM sections. The CM sections cost 70 % of Drill and Blast. The operating

    costs for the mining operation are R220/ton. The plant operating costs are on the

    other hand are R40/ton.

  • 19

    Challenges The location of Penumbra near wetland is a serious challenge faced by the mine.

    Figure 9 below shows the surface view of the mine.

    Figure 9: Map of wetland at Penumbra Coal. (Continental Coal Presentation, 2014)

    Water flows into the mine resulting in the weathering of the roof and side walls of

    the shaft. On the 26th of December 2013, the mine experienced a roof collapse

    in the decline shaft as a result of subsidence. When water reaches the shaft

    bottom, it results in poor floor conditions that cause the Continuous Miner to get

    stuck. To counter the effects of water, the mine practices water interception

    cementitious material on the roof and side walls. The water that intercepted is

    directed down the shaft to a reservoir and then pumped out of the mine. The

    other major challenge faced by the mine is the intersection of unforeseen dykes,

    dolerite lenses and stone rolls. These reduce production rates and increase

    operating costs.

  • 20

    5. New Denmark Colliery

    Mine Background New Denmark Colliery (NDC) is wholly owned by Anglo American Thermal Coal

    and is the deepest Anglo coal mines in South Africa, approximately 210m. It is

    located 30 km from Standerton and 165 km from Johannesburg. It was

    commissioned in 1982 and mines Bituminous coal. NDC uses three production

    shafts namely Central, Okhozini and West Main shaft. The mine supplies

    Eskoms Thutuka Power Station with approximately 4.5 million tonnes of coal

    each year.

    NDC mines the No.4 seam which has an average thickness of 1.95m and varies

    from 1.5m to 2.5m. The roof in the mine consists of Sandstone and the floor of

    Siltstone. It has 1 Longwall (LW) section and 7 Continuous Miners (CM) sections.

    Mining Method & Activities The only Longwall mining section in South Africa is done at NDC in the Okhozini

    shaft. Longwall mining requires a constant seam thickness with a stable elevation

    that doesnt change over large areas. The reserve should be relatively large

    because of the extensive amount of time it takes to relocate the LW equipment.

    This mining method causes caving of overlying strata which can lead to a

    considerable amount of surface damage and groundwater disturbances. The

    subsidence at NDC is 0.5m and it takes 5 years for it to reach surface.

    Precautions must be taken to minimalise these disturbances like buying out the

    surface area to ensure no damage is done to the publics property.

    The development for a LW mining section is done with CMs in a Chain road

    style. This means that there is a three road development at each side of the LW

    section. The face of the LW section is 230m-243m wide and has a thickness of

    2.1m. The development done allows for an air intake and return which will

    ventilate the LW section. It also provides the space needed for the placement of

    the conveyor belt which will transport the coal out of the mine.

  • 21

    Figure 10 shows the layout of a LW section. The advancing direction of the face

    can be in reverse or in advance. Okhozini is advancing in reverse, thus they

    developed onto the end of the coal seam and now they are progressing back to

    the shaft with the LW. This gives the mine better knowledge about the geological

    features the might encounter.

    The double drum shearer produces 6200t/shift and extracts 93% of the coal. This

    is a huge improvement on the CMs 800t/shift and 40% extraction. The minimum

    width that the shearer can cut is 1.85m and its cutting depth is o.93cm with a 1m

    drum.

    The Armoured face conveyor (AFC) is a conveyor belt that is used to transport

    the coal from the LW face onto the transport conveyor belt via the stage loader at

    the side of the face. It is also used as an anchor for moving the support chocks. It

    is durable and flexible and has a self-cleaning action.

    The activities of a LW section start off with the Shearer that shears in a parallel

    direction to the face. The AFC discharges the coal from the face onto the

    transport conveyor belt. The hydraulic chocks moves forward whilst the shearer

    move down the face. Goafing commences once the hydraulic chocks are moved

    Figure 10 Longwall section layout.

  • 22

    into their new positions. The coal is transported out of the mine and further

    conveyed to Thutuka Power Station. Transport to and from the LW and CM

    sections can take 30-60 minutes.

    Pillar Design and Support The Multi-road sections are used for CM production and development areas. It

    consists of 8-10 roads. The center to center distances of these pillars are

    25m19m and the road width is 7.2m. It provides enough space for 2 returns,

    belt road, tractor road and 3 intakes.

    The Chain-road section is solely for LW development purposes. It consists of 3

    roads that provide sufficient space to place a return, tractor road and conveyor

    belt. The center to center distance is 30m19m.

    The sandstone roof is very competent at 80Mpa and the floor is 30Mpa. The

    support in the CM sections is done with a double boom Joy roofbolter. The

    roofbolts are 1.1m long and 22mm in diameter. The roofbolts are spaced

    1.8m1.8m apart. The holes are drilled and filled with a spin-to-stol resin that

    mixes and hardens when the roofbolt is inserted into the hole. 1.5m Roofbolts is

    sometimes used in the spilts when needed.

    Bigger pillars are left in between the CM and LW sections these pillars are

    30m25m and are called crush pillars. They are used as support together with

    the Chocks to prevent premature goafing. Once the LW advances the pressure

    of the overlying strata will be placed onto these pillars and they will eventually

    collapse/goaf.

    The LW uses 129 hydraulically powered chocks for support, ideally for 2.35m.

    These chocks are imported from the UK and they are ideal for thinner seams and

    softer floor conditions. They move forward one by one as the shearer passes.

    Controlled goafing commences once the chock are moves forward. It takes

    approximately 3 months to disassemble and relocate the LW section and this is a

    major drawback in LW mining.

  • 23

    Figure 11 shows a cross section of the chocks support system. It supports the

    roof while the shearer advances and stops the goafed material to enter the

    cutting face.

    Equipment Selection Table 4. Table showing equipment and details

    Equipment Detail

    Joy AAA CM 3,6m Drum, 1 cycle=11 tonnes(60-90sec), 200m Cable

    Roofbolter Double boom

    Battery Hauler 16 tonne capacity

    Feeder Breaker 75m from CM

    Battery Bay 1 battery bay per section,3 batteries per car, 80m from face

    Sandvik LHD 7 tonne capacity

    11Kw Transformer 1 per section

    Equipment Detail

    LW Shearer 695 tonnes per cut

    Armored Face Conveyor Coal transport

    Hydraulic Chocks 129 chocks

    Transport conveyor Coal transport

    Headpiece Support

    Tailpiece Support

    Stage Loader disposes coalfrom AFC to transport conveyor

    Figure 11: Basic Chock support illustration

  • 24

    Ventilation Air is supplied through the intake via 400kW surface fans that sucks the air

    through the workings. These fans are located on the return airways ventilation

    shaft. Brattices are installed to direct the fresh air along the intake onto the face.

    The volume of air on the face is 53-60 m3/sec. The speed of the air in the intake

    is 2.5m/sec. Once it enters the face 0.5m/sec of air will filter through the area that

    has goafed, located behind the support Chalks. The face speed will thus be

    2m/sec. Sensors placed 75m into the tailgate measure the ventilation speed and

    detect gasses. Airview is the brand of sensors used. The quality of the air is also

    measured before it enters the face.

    The ventilation in the CM sections require 30m3/sec at a speed of 1m/s. Force

    fans are used to supply air onto a face when the CM cut exceeds 12m in length.

    Production Rates The LW optimally produces 6200t/shift and a CM section produces 800t/shift.

    The combined monthly production rate target of the 7CM sections with the LW

    section is 318 000 tonnes/month, but the actual production is 160 000

    tonnes/month. This is significantly lower that the target. It may be because of the

    40% availability of the LW and the 2-3 hours of CM productivity per shift.

    Unit Costs The operating costs which include mining activities costs R35/tonne and the

    Engineering activities costs R65/tonne. Transport cost is R60/tonne. The total

    cost of producing one tonne of coal is R300 and this includes the operating and

    engineering costs. The final cost is R360/tonne which includes the total cost of

    production with the transport cost.

  • 25

    Personnel Personnel per shift in a CM section for production/development:

    1Miner

    1Electrician

    1Fitter

    2Operators

    2Supporters

    1Diesel Driver

    1Control Stick

    Maintenance crews consist of 6-11 people, usually 7 artisans and one foreman.

    The expertise and the number of personnel for the maintenance shift depends on

    what maintenance is required to be done for that specific shift.

  • 26

    6. Msobo Coal

    Location and background Msobo Coal mine is a new mine that started in 2011 with a business plan to

    acquire established coal mines near Ermelo in South Africa. Msobo successfully

    negotiated the purchase of the Highveld coal reserves which were previously

    owned by Xstrata before 2011. This makes the Msobo coal mine project a brown

    field project with a life of mine of 30years. Msobo coal mine is located in Breyten,

    Mpumalanga (figure 12).

    Figure 12: Map Showing Msobo Coal Mine

    The Msobo coal reserve is under the Ermelo coal fields and they mine the Below

    Seam (BL) which is seam A,B,C and D as shown (in figure 13) below. The

    geology of the Msobo reserve falls under the stratigraphy of the Karoo Super

    group, Ecca group in the Karoo Basin. The Ecca group is a group of sedimentary

    geological formations found in the Southern Africa.

  • 27

    It consists of mainly shale and sandstone as shown (in figure 13) below, laid

    down in the sandy shorelines of swamplands during the Permian Period. (Davies,

    P & Brant, J. 2010)

    Figure 13: The stratigraphy of Msobo Coal Reserves

    Xstrata also granted prospecting rights to Msobo coal in Chrissiesmeer,

    Mpumalanga. Chrissiesmeer is a large wetland area. It is home to various frog

    species, insects, birds, small game and their predators. This includes various

    endangered species such as cranes and allegedly some newly discovered

  • 28

    endemic species of fish and frogs. In 2010, even before Msobo coal came into

    scene, the landowners of the wetlands area started taking collective steps to

    declare the Chrissiesmeer wetlands a protected environment under the

    Mpumalanga Biodiversity Stewardship Programme. Now Msobo coal is faced

    with a tough decision to choose between coal and wetlands. It remains unclear

    whether Msobo coal will support the plans for the protected area. If they

    successfully oppose it, the past four years of hard work to declare the area

    protected will become redundant and the whole wetlands area will become

    vulnerable to exploitation in search of finite coal reserves. (Fuls,F. 2.013)

    Mining method and activities The most economical method of coal extraction from coal seams depends on the

    depth and quality of the seams, geology and environmental factors. Coal mining

    processes are differentiated by whether they operate on surface or underground.

    At Msobo coal they mine both on surface and underground and 60% of the coal

    is from surface and 40% is from underground. During our visit at the mine we

    visited their underground operation where they are mining 20m-120m below

    surface. Mineable coal reserves at Msobo coal are mainly mined through two

    mining methods. In underground operations board and pillar (12m by 18m

    centres) method is used. Continuous Miners (CM) are used to cut the coal and

    the CM loads the coal on a shuttle car which takes about 45seconds to fill this

    shuttle with average capacity of 20tons. The shuttle car takes the coal to the

    Buffalo feeder breaker. Each feeder breaker has a total power capacity of 50kW.

    The coal is then transported to surface stockpiles by 1200mm conveyors.

    (Marshall, T.2014)

    After every 12m advance the Fletcher twin boom roof bolter comes in to support.

    Lengths of the bolts used are 1.5m, 1.8m and 2.1m depending on the roof

    conditions. This type of support is called the suspension support system. Four

    roof bolts are installed in a row, 1.5m apart and 1.5m in advance. Drilling and

    blasting is undertaken where conditions do not allow the use of a CM. These

    conditions include geological discontinuities like faults and dykes but this is

  • 29

    sporadic at this reserve. They load and haul all waste material out of the pit to

    expose coal and stockpile for final void rehabilitation. The General Manager

    (Tammy Marshal) explained that they only load and haul topsoil material and

    mainly weathered waste material determined through geological limit of

    weathering which is in turn dumped back in the void as part of their continuous

    rehabilitation program. Semi carbonaceous materials are dozed over in the void.

    (Marshall, T.2014)

    Equipment Selection The mine is equipped with electrical, mechanical and other equipment that

    contribute to achieving conditions for safe operations and healthy environment.

    To make sure the mine complies with the DMR requirements, the maintenance

    team and the competent Artisans available to maintain the machines and

    equipment at regular intervals. Foremen, GES and the engineer do the follow up

    inspections on weekly and monthly basis to ensure compliance. The table below

    shows the equipment used per section to get the coal to surface. (Marshall,

    T.2014)

    Table 1: Showing equipment used underground

    Table 5: Underground equipment used at the mine

    Main equipment:

    Continuous Miner

    Roof Bolter

    Shuttle car (by 3)

    Feeder breaker

    Conveyor belt

    Additional equipment:

    Sandvik ED7 LHD

    JA Engineering Scoops

    Aim Tractors

    Toyota and Nissan LDVs

  • 30

    Material is transported from surface to work areas by flameproof tractors and

    telecom trailer systems. Men are transported to and from workplaces using

    flameproof tractors and man carrying trailers or man carrying non flameproof

    LDVs. (Marshall, T.2014)

    Ventilation All underground workings make use of a ventilation method. This is done by

    means of air crossings and ventilation stoppings so as to ensure that all

    production sections have an independent fresh air intake, and thereby, creating

    independent ventilation districts. At Msobo coal they is a ventilation fan on the up

    cast shaft which sucks up 150m3/s of air. Sufficient air quantity is supplied to

    each production section to maintain an average air velocity in the last through

    road (LTR) of 1.0m/s and not less than 0.60m/s at any point in the LTR. When

    cutting takes place with a CM the velocity on the intake side of the CM will not be

    less than 1.0m/s. (Davies, P & Brant, J. 2010)

    Unit Costs and Personnel At Msobo coal the unit cost for underground operations is R200/ton and most of

    the coal is exported and the remaining coal is sent to Eskom. The table below

    shows the underground personnel per CM section and drill and blast section. At

    this coal mine the average workforce has 18years work experience. The mine

    works on a two shift cycle per day. Day shift starts at 5:30am to 3:30pm and the

    Night shift starts at 2pm to 2am. (Marshall, T.2014).

    Table 6: Personnel specifications

    Production Sections

    No. of workers

    Dyke Development crew No. of workers

    Shift Overseer 1 Miner 1

    Miner 1 Jack Hammer operator 3

    CM Operator 2 Roof Bolter Operator/HDV Driver Whombat

    3

    Roof Bolter Operator

    4 Labourer General 1

  • 31

    Shuttle car operator

    3 Roof Bolter Assistant 1

    LHD Operator Scoop

    1 Total 9

    Multi Skilled Tractor Driver

    1

    Labourer Belts FB Att

    1

    Labourer General Pinch bar att

    1

    Total 15

  • 32

    7. Sasol

    Mine Background Sasol has five mining operations in Secunda which all mine the nr.4 seam, these

    are Brandspruit, Middelbult, Twistdraai, Bosjesspruit and Syferfontein. Two

    different mines were visited while at Sasol, Brandspruit Colliery and Middelbult

    (iThemba Lethu Shaft).

    Brandspruit Colliery Brandspruit is the oldest of these 5 collieries and commenced in June of 1977. It

    mines at a depth of 135m with a coal seam that is 3.7m in height on average.

    The mine uses 9 Continuous Miner (CM) sections to produce 7.2Mt of coal per

    annum. Brandspruit employs 1100 employees with approximately 450

    contractors.

    Figure 14 shows the Shafts and basic geography of Brandspruit. Originally the

    main shaft was the only one but the travelling distances increased and thus shaft

    2 and 3E was sunk. Main Shaft includes a man, ventilation and decline shaft.

    Figure 14> Location of the shafts at Brandspruit

  • 33

    The decline is for transporting the coal out of the mine. 2 and 3E shafts only have

    one shaft which is divided into a man and ventilation shaft. The coal from 2 and

    3E shafts are transported via conveyors to the main shaft where it connects with

    the decline for removing the coal. The decline conveyor transports coal all the

    way to Sasol Synfuels Secunda plant. 2 Shaft has a 5 year LOM left. Future

    operations include the Impumulelo Shaft which will be in operation from 2015

    Mining Method Stooping is done with the Nevid Pillar extraction method. This method is done

    from the limit of the Bord and Pillar excavation in a reverse direction, thus back to

    the shaft. It causes the stress on the pillars to be redistributed onto smaller pillars

    which will lead to disturbances in the surrounding walls and pillars and will

    eventually lead to the goafing of the roof. This method allows for the goafing to

    be done in a safe and controlled manner. Areas with unfavourable geological

    features and dams are not stooped.

    The pillar sizes differ between sections and thus the stooping pillar sizes differs

    too. Stopper pillars are left to prevent unexpected failures. They are spaced in

    every 3 rows and act as yield pillars. Figure 15 shows the cutting sequence of the

    Nevid method. The sizes used in the figure may vary. The CM cuts at a 45

    degree angle. This allows the CM operator to be a safe distance away and under

    supported roof.

    Figure 15: The cutting sequence using the Nevid Method

  • 34

    Figure 16 shows a Nevid pillar extraction section. The sequence of the CM cuts

    is indicated with the numbers. The Lone pillar in the goaf area is the Stopper

    pillar. Policemen, which are wood poles or sticks, are placed in the haulage

    areas in and around the stooping section. They are used as a warning that

    goafing has started. They tend to bend and crack once there is roof movement.

    Figure 16: The Nevid Method pillar extraction.

    60% of the pillars are extracted. The CM doesnt exceed 15m per cut when doing

    stooping. This allows for a double lift to be taken and also makes the cable

    handling easier. The three triangles left ensure that the goaf is kept away from

    the center rib and that the goaf happens at least two rows away from where the

    CM is cutting. The goaf is also less violent.

    It is crucial to plan the stooping beforehand and prepare the section by marking

    off the 45 degree angles with red paint to show the CM operator where his next

    cu should be. The cuts must be inspected by supervisors to improve their

    awareness and knowledge of the section.

  • 35

    Pillar Design and Support The Nevid Method allows for the strongest possible remaining pillar to be next to

    the CM. Mininmum pillar sizes from center to center is 28m28m. The sandstone

    roof varies from a laminated to a competent roof which has to be supported

    accordingly.

    Equipment Selection Table 7: The type of equipment and the total number

    Ventilation Figure 17 shows the basic ventilation of a Nevid Stooping section. The air from

    the intake is directed to where the CM is cutting and then straight to the return

    airway. The return airway is also known as the bleeder road. Methane is common

    in coal mines and special care is taken to measure and control the leaking

    methane.

    Production Equipment Amount

    Continuous Miner 9

    Shuttle Cars 30

    Aro Roof Bolter 1

    Fletcher Roof Bolter 13

    Other Roof Bolters 6

    Feeder & Crushers 11

  • 36

    Figure 17: Basic air flow through a Nevid section.

    The CM operator is placed in the intake to avoid dust and gasses. Auxiliary fans

    is not necessary when doing the Nevid method but they are needed in the normal

    CM sections where cuts can easily exceed 24m.

  • 37

    Middelbult Colliery- Ithemba Lethu Shaft

    Background Middelbult Colliery is located in Secunda in the Mpumalanga Province. It is

    owned by Sasol as part of the Sasol Complex in Secunda. The figure below

    shows its location.

    Figure 18 Location of Middelbult Colliery

    The iThemba Lethu The project is an extension of Middelbult Colliery and thus it

    is a brownfields project. Ithemba Lethu Shaft is located on the Zandfontein farm

    in Secunda. The shaft is a split person-and-materials and ventilation shaft. The

    shaft uses a 40MW substation built by Eskom. Approximately R140 million

    capital was required for this project. Coal is transported along the underground

    conveyor system and does not come to surface at the iThemba Lethu shaft.

    Mining Method Bord and Pillar mining is used to mine the 4 m seam using a Continuous Miner. A

    Drill and Blast section is used to mine through geological features like dykes.

    Middelbult Colliery

  • 38

    The 4-lower seam is mined at iThemba Lethu. The 4-upper seam is 0.5-1m thick

    and it is not mined due lots of methane releases. Figure 19 below shows both the

    4-seams and the sandstone roof.

    Figure 19: The 4-seam layers.

    Pillar Design and Support The mine uses a bord width of 7.2m with 25m pillar centres as shown in table 8

    below.

    Table 8 Pillar design and support specifics

    Bord width 7.2 m

    Pillar centers 25m

    Barrier Pillar 28.8m

    Width to Height Ratio 4

    Number of roads 7

    Roof Bolt length 1.8m

    Support dimensions 2m x 2m

    Roofbolts are used to support the sandstone roof and these are normally 1.8m.

    On rare occasions, 1.5m roofbolts are used per Rock Mechanics discretion. The

  • 39

    bolts are placed 2m x 2m apart. Supporting is done after every 15m advance by

    the continuous miner. Moreover, the support system used is such that the

    continuous miner stops if more than 2 faces are unsupported faces.

    Equipment Selection and Personnel The equipment used per mechanized section is as follows:

    3 x Shuttle Cars (20 tonne)

    1 x Fletcher Roof bolter

    1 x Continuous Miner

    Equipment is installed with a close-proximity system which brings to a halt a

    machine when it is near people. This ensures a safe working environment in the

    section. A total of 13 people work in one section.

    Ventilation Two 750 kW fans are used for ventilation. In the section, every road is installed

    with a Dura-fan. Each Dura-fan produces up to 8m3/s air capacity.

    Production Rates and Unit Costs A section has a target of 50 m advance per shift. However, this target is barely

    reached due to machine breakdown, bad ground floor conditions and

    inexperience of the employees. An advance as low as 15m per shift can be

    reached when the continuous miner breaks down. The amount of coal extracted

    amounts to an average of 1350 tonnes/shift.

    In-section costs amount to between R60 and R70 per tonne of coal. For the

    whole Middelbult Colliery, the total costs average R170 per tonne.

    Challenges The challenges faced at iThemba Lethu include faults, dykes and methane

    releases. The accumulation of water underground is also a major problem as it

    slows down machinery and thus reducing production.

  • 40

    8. References

    1. BHP billiton. (2014). Khutala Colliery (2 seam underground visit).

    2. Davies, P. & Brant, J.2010. Coal vs. Biodiversity Xstrata.Leerdersboek

    3. Fuls, F. 2013. Choosing between coal and wetlands in Chrissiesmeer.

    Mpumalanga:Lapa.

    4. Infomine. (2014, February 23). Retrieved February 23, 2014, from

    www.infomine.com/index/properties/Graspan.html

    5. Mabogoane, M. (2014). University of Pretoria ( Presentation).

    6. Marshall, T.2014. University of Pretoria presentation.

    7. New Denmark Colliery visit

    8. Penumbra Coal Mine Visit 2014

    9. PMY 320 Handbook, Chapter 6: Underground Coal Mining