59
Section 2 Procedures and Tests -Plant- Job Guide – Concrete Paving Plant Monitor Contact Report – Paving Contractor Mix Designs JMF Concrete Aggregate Worksheet JMF Moving Average Summary JMF Adjustment Worksheet Well Graded Aggregate Incentive -#200 Wash Coarse Aggregate Quality Incentives Worksheets WC Ratio Calculation Worksheet WC Ratio Incentive Concrete Ingredient Summary Sample Cards -Field- Job Guide – Concrete Paving Inspector Air Content Worksheet Concrete Test Beam Data Probing, Coring, Texture Report and MIT-SCAN T2 Troubleshooting (IMCP Manual) Operation of MIT SCAN T2 Device

Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

Section 2

Procedures and Tests

-Plant- Job Guide – Concrete Paving Plant Monitor

Contact Report – Paving Contractor Mix Designs

JMF Concrete Aggregate Worksheet JMF Moving Average Summary

JMF Adjustment Worksheet Well Graded Aggregate Incentive

-#200 Wash Coarse Aggregate Quality Incentives Worksheets

WC Ratio Calculation Worksheet WC Ratio Incentive

Concrete Ingredient Summary Sample Cards

-Field-

Job Guide – Concrete Paving Inspector Air Content Worksheet

Concrete Test Beam Data Probing, Coring, Texture Report and MIT-SCAN T2

Troubleshooting (IMCP Manual) Operation of MIT SCAN T2 Device

Page 2: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

2

Page 3: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

JOB GUIDE CONCRETE PAVING PLANT MONITOR 1. Review the Contract and Plans:

• Become familiar with applicable specifications based upon the size of the project and delivery method of concrete.

• Review incentives and disincentives available. • Check Schedule of Materials Control for testing rates and sample sizes. • Attend the pre-construction meeting if possible. • Attend the pre-paving meeting.

2. Preliminary Testing and Mix Design Requirements:

• Verify the Contractor’s aggregate sources and make sure preliminary testing if required has been done well in advance of the project start date.

• Make sure the Contractor submits mix designs to the Concrete Engineering Unit for review and approval a minimum of 21 days prior to initial placement of mix design.

3. Become familiar with concrete batching and mixing equipment and the duties of the Contractor. • Obtain the Contractor’s organizational chart listing names, phone numbers and emails of

individuals responsible for mix design, process control administration and inspection. • Inspect batch trucks for compliance with specifications

4. Complete a Concrete Paving Contact Report (Form 2164): • Review the Contractor’s concrete paving combination plant-lab office for compliance. • Verify whether the Contractor has an electronic means of communication (email) • Check that scales and water meter are calibrated • Obtain pre-production coarse aggregate samples for quality testing in accordance with

the Schedule of Materials Control. Fill out Aggregate Sample I.D. cards completely and include with lab samples.

• Verify cement, fly ash, and admixtures are on the Certified/Approved Products list. • Obtain cement, fly ash, and admixtures samples from the Contractor per the Schedule of

Materials Control. Provide sampling containers and witness sampling when possible. • Include cementitious invoices when submitting samples to the laboratory for testing. • Fill out lab sample I.D. cards completely and enclose them with cement, fly ash, and

admixture samples. 5. During Concrete Production:

• Monitor stockpiling and loading of delivered aggregates. • Observe scale operation and loading of trucks at a minimum of 2 hour intervals

throughout the day. • Check field hoppers for contamination. If contaminated, have Contractor empty storage

and weigh hoppers and re-charge. • Review mix designs and ensure the Contractor is using correct mix design weights. • Check multiple times daily that batch weights are adjusted in accordance with current

moisture tests, the correct mix design weights are being used and the w/c ratio is not

Page 4: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

exceeding the specification requirements. • Ensure compliance with minimum and maximum mixing times.

6. Alkali Silica Reactivity (ASR) Sampling: • Obtain samples of cement, supplementary cementitious materials (fly ash or slag) and

sand in accordance with the Schedule of Materials Control. • Fill out the Sample I.D. card completely and enclose with lab samples. Identify ASR

sample with “Project Specific ASR Testing” on ID card.

7. Perform Moisture Tests and Water Content Verification Testing (Microwave Oven): • Verify contractor performs start-up moisture tests. • Take additional moistures whenever moisture appearance of delivered aggregate seems

to vary or batch water deviates greatly from previous loads. • Use Concrete W/C Ratio Calculation Worksheet to determine moisture contents, batch

ticket, w/c ratios, unit weight, microwave oven w/c ratios, charting and w/c ratio incentive/disincentives.

• Review water/cementitious ratio results for compliance with project specifications and verify with microwave oven testing.

8. Aggregate Gradation Testing:

• If testing aggregate gradations in the field, use JMF Concrete Aggregate Workbook to calculate gradations, otherwise submit to the lab.

• Verify Contractor is using JMF Concrete Aggregate Workbook for gradation testing, determining JMF moving average, charting and well-graded incentives.

• Review Contractor’s test results for compliance and compare to the Agency test results (split samples).

• Record Agency gradation test results (split samples) in the JMF Moving Average Summary within the Contractor’s JMF Concrete Aggregate Workbook.

• If submitting gradation samples to the lab, fill out Aggregate Sample I.D. cards completely including the JMF number found on the Contractor mix design and the QC Gradation results. Identify “QA Gradation” on ID card.

• Determine if Contractor is eligible for well-graded aggregate incentives. Review the Contractor’s JMF Aggregate Summary Workbook.

9. % Passing 75 µm (#200) Sieve:

• Perform all percent passing the #200 (75 µm) sieve at the Contractor’s plant site. • Verify Contractor washed all fine aggregate gradations to determine the percent passing

the #200 (75 µm) sieve. • Use JMF Concrete Aggregate Workbook to calculate the percent passing the #200 (75

µm) sieve in the field. • Review the Contractor’s percent passing the #200 (75 µm) sieve for the coarse

aggregate results to determine compliance or if additional testing is required and compare to Agency results.

• Record Agency test results in the Additional Remarks/Comments within the Contractor’s Concrete Aggregate Workbook.

10. Aggregate Quality Sampling:

• Determine when Aggregate Quality samples will be taken in accordance with the Schedule of Materials Control.

Page 5: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

• Fill out Aggregate Sample I.D. cards completely and record the Contractor and Agency -#200 (75 µm) test results.

• Identify Quality samples with a “Q” including the specification reference (Spec 3126 for sand and 3137.2D3 for coarse aggregate) on ID card.

• Identify the Quality Companion samples with a “Q”. 11. Coarse Aggregate Quality Incentive/Disincentive Sampling:

• Determine when random Coarse Aggregate Quality Incentive/Disincentive samples (Class B or Class C aggregates only) will be taken in accordance with the Schedule of Materials Control using the Coarse Aggregate Quality Incentive/Disincentive Workbook.

• Fill out Aggregate Sample I.D. cards completely and enclose with lab samples. Identify Incentive samples with “I/D” on ID card.

12. Complete Concrete Ingredient Summary Daily: • Collect a production summary in an electronic format of the daily total concrete produced

and daily total ingredient quantities (aggregate, cementitious and water) including the percent overrun/underrun.

• Collect final project total quantities for concrete produced and ingredients in an electronic format including the percent overrun/underrun.

• Verify daily and final quantities are within tolerances as required by the Specifications.

13. Contractor Records and Charts: • Obtain the Contractor’s on-site QC records and charts on a daily basis or otherwise

directed by the Engineer. • Review the Contractor’s on-site QC records and charts daily for accuracy and

completeness. • Obtain batch tickets on a daily basis or otherwise directed by the Engineer.

14. Maintain a daily diary:

• Includes hours of production, equipment, weather, concrete air content test results conducted at the plant, air temperatures, concrete yardage totals, and problems or unique circumstances encountered.

15. Submit the following to the MnDOT Concrete Engineering Unit: • Contact Report • W/C Ratio Incentive Calculation Worksheets • Well-graded Aggregate Incentive Worksheets • Quality Incentive/Disincentive Worksheets

References: MnDOT Specification 2301, 2461, 3126, 3137, Special Provisions, Schedule of Materials Control and MnDOT Concrete Manual.

Page 6: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

1

TP-2164 (1/1/2018)

Minnesota Department of Transportation

Contact Report - PavingOwner's Name:

Plant/Unit #:

Set Up Location:

Plant Superintendent:

Lab Equpment Calibrations - Date of seive calibration:

Scale and/or Meter Calibrations - Date of scale/meter calibration:

Batch Ticket - A computerized ticket that includes all MnDOT Specifications and supporting information.

Technicians -

Cert#:

Cert#:

Cert#:

Cert#:

Agency Representative:

x Approved for concrete paving production on SP/SAP #:

Date:

Not approved for the following reason(s):

Re-inspected and approved on by

Certified by:

Prior to the production of Agency concrete for a paving project, a Department Representative shall perform a thorough on-site inspection of the portable concrete plant with a MnDOT Certified Plant Level 1 or Level 2 Technician representing the Producer.

TUV Paving

651-343-6453

5/1/18

Whitey Walker 99663 Phone#:

Email Contact Report and Certificate of Compliance to the Concrete Office at [email protected].

Phone#:

8901-23

Agency:

Cell #:

MnDOT

5/1/18

612-987-6543

Date:

Phone:

Email:

651-345-5645

5/1/18

Age

ncy

Insp

ectio

n

5/1/18

After completing the Concrete Plant Contact Report, any procedural changes that cause non-compliance with this program may result in de-certification of the plant and cessation of further production of Department concrete as determined by the Concrete Engineer in accordance with 2461.3.F.4.h, "Decertification."

Phone#:

Sandy Beaches 99118 Phone#:

651-563-7634

Bill BatcherPlant Representative

2018

W123

St. Cloud

MnDOT Certified Plant 2 Technician:

A MnDOT Certified Concrete Plant Level 1 or 2 Technician, representing the Producer, signs the report certifying compliance with the Certified Ready Mix requirements and continual maintenance of the plant to assure that the plant can produce concrete meeting MnDOT Specifications.

Bill Batcher

Leo Sands

[email protected]

MnDOT Certified Plant 1 Technician:

MnDOT Certified Plant 1 Technician:

MnDOT Certified Plant 1 Technician:

Page 7: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

2

W123 2018

Mixer:

Type of Paving Plant: Make:Condition:

x

Max. mixer batch size: 10 yd3

Batching Equipment: Make:

All Dump Trucks are equipped with vibrators (y/n): y

Batch Ticket:

Note: All the following items are required on the computerized batch ticket

x Plant/Unit # x Pit Numberx Date x Target weight of materialsx State project number (SP) or (SAP) x Actual batched weights of materialsx MnDOT Mix Designation x Temper waterx Batch Time x Total water, lbsx Load Quantityx Running total of each type of concrete, each day for each projectx Cementitious Abbreviationx Admixture Abbreviation

Scale and Meter Information:

Plant Lab - Office (2301.3.B.3.a):

x Located within 100 yd from the batch plantx Plant lab and plant office separated and isolated by a wallx Plant lab floor area at least 144 sq.ftx Plant office floor area at least 80 sq.ftx One sturdily built workbench or countertop at least 30 in x 144 inx Shelf space of at least 8 ft x 8 inx Electronic scales of sufficient size to weigh the sample for all required materials testingx A four burner 30" standard stove top or stove and at least two additional electric burnersx Metal bowls of sufficient size to perform all required material testingx Water supply connected to the sink faucetx Two desksx At least four chairsx Telephone capable of providing emailx Printer with scanning and copying capabilitiesx Drinking water container or cooler with adequate supply of potable waterx Heating and cooling system capable of maintaining a uniform temperature between 72o and 85o Fx Adequate sample storage area to prevent contamination of the samplesx Detached portable toilet conveniently located

20 lb

10000 lb

10000 lb

1ASeltic

GoodModel:Rex

Plant and Lab

Digital

300 gal

Material

Dual Drum:

S

TypeDate of Scale and Meter CalibrationMake Capacity

Single Drum:

5 lb

5/1/18

Graduation

Model:

5 lb

10000 lb

Cement 5/1/18

10000 lb

Seltic

Seltic

5/1/18

5/1/18

Seltic

Seltic

Fly Ash

Slag

Water Scale

Seltic

Digital

Digital

Digital

Digital

Aggregate

20 lb

1 gal 5/1/18Water Meter

Page 8: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

3

W123 2018

Cementitious Materials:

W123 2018Automatic Cement Recorded (y/n):

Admixtures:

Does AEA bulk storage tank hold at least 300 gallons (y/n): yAdmixtures sampled: Dispensing Tubes (y/n): y

Aggregates:

Plant is feed by: y 3Number of working bins: 3Are stockpiles separated (y/n): yHow many belts feed plant working bins: 3Is turn head used (y/n): nAggregate sampled at: y

Water:

Source: Proportioned by:x City Water x Meter

Well Water ScaleOther-

Can water be heated with a boiler (y/n): n

Temperature gauge location:

WRXX

MnDOT AbbreviationProduct Name

Ajax

Sand

Asher

Specifications 3126/3137

Fly Ash

AEA Adcon

Material

Cement 240

MaterialsCapacity (tons)# of Silos

MnDOT AbbriviationCement Mill/Power Plant

Supplier

1

Slag

Graymatter

Type

In Plant Storage (tons)

A Adcon

Material Supplier

18888

Field Hoppers (y/n):

Belt:

What?

How many?

Pit Location Pit Number

St. Cloud

St. Cloud

Deliver By

Freeport 19999

18888

Salinger

Rock IslandC

Rock IslandC

75

3/4+

3/4-

Coarse Aggregate

Class

1

Page 9: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

4

W123 2018

Equipment:

Mechanical Shakers, Screens and Sieves

Box Screens: Must have all screens listed below Calibrated on

x 2" (50mm) x 3/4" (19mm) x #4 (4.75mm)

x 1 1/2" (37.5mm) x 5/8" (16mm)* x Bottom Pan

x 1 1/4" (31.5mm)* x 1/2" (12.5mm) x Mechanical Shaker

x 1" (25mm) x 3/8" (9.5mm)

*Sieves Not RequiredNote: Additional fill-in sieves may be needed to be added to prevent overloading.

Brass Sieves: Must have all screens listed below Calibrated on

x 3/8" (9.5mm) x #30 (600um) x Bottom Pan

x #4 (4.75mm) x #50 (300um) x Mechanical Shaker

x #8 (2.36mm) x #100 (150um)

x #16 (1.18mm) x 2 - #200 (75um)

Are replacement sieves available within 24 hours if needed (y/n): y

Scales, Microwave Oven Equipment and Miscellaneous

Scales:

Minimum 30 lb Capacity(minimum 0.1 lb graduated interval)

Minimum 6000 g Capacity(minimum 0.1 g graduated interval)

Microwave Oven and Ancillary Equipment:

x Microwave Oven with turntable or wave deflection fan (900 Watt)

x Heat resistant glass pan ( approx. 9" x 9" x 2")

x Plain weave fiberglass cloth (10 oz/yd2 and 14 mils thick)

x Metal scraper and grinding pestle

Miscellaneous:

x 2" (50mm) Sample Splitter with 3 Pans

x 6 Electric Burners (minimum)

Is the latest revised JMF Concrete Aggregate Workbook being used by the Contractor (y/n)? y

See the Concrete Pavement website: http://www.dot.state.mn.us/materials/concretepavement.htmlThe latest revision date is indicated next to the JMF Concrete Aggregate Workbook link on the website. This date should match the date indicated in the top right corner of each worksheet contain in the workbook.

Workbook

x

Calibrated on

Calibrated on5/1/18

5/1/18Electronic Scale

Electronic Scale

x

Note: Two #200 (75um) sieves are needed, one is for shaking the gradation and the second is for washing the sample during the final steps of the gradation process.

Equipment

Page 10: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

Minnesota Department of Transportation

Project Specific Mix Design (JMF)SP Number

Use for: Requested ByJob Specific Concrete using a JMF Company

Cement I/II 3.15 Paving Projects 3,500 CY or greater PhoneFly Ash F 2.50 High Performance Bridge EmailSlag AgencyContactOther CM Pit # Class SP.G. ABS. Agency PhoneAdmx#1 AEA 0.5-3 FA#1 19999 2.63 0.009 Agency EmailAdmx#2 A 0-5 FA#2 Plant NameAdmx#3 CA#1 18888 C 2.75 0.009 ContractorAdmx#4 CA#2 18888 C 2.69 0.013Fiber CA#3FiberColor

40 20 40

3A21-1 7.0 215 400 170 30 570 0.38 1217 636 1245 27.0 143.8 1/2-3"3A41-2 7.0 230 400 170 30 570 0.40 1201 628 1229 27.0 142.9 2-5"

Submit to: [email protected] Page 1

Name/Mill/PlantMnDOT

AbbreviationType/Class

ASCAMNGRSPMNGraymatter

Asher

Joe ContractorTUV Paving

[email protected]

8901-23

Adcon

3/4

WRXX

Volu

me

FA#1

FA#2

Mix

#

% A

ir

Slum

p Ra

nge

MnDOT Approval

Uni

t Wt.

Fly

Ash

Oth

er

CM

Comments:

% F

ly

Ash

% S

lag

% O

ther

CM CA

#1

W/C

Ra

tio

CA#2

CA#3

Slag

(3/22/18)

Sand

The Concrete Engineer reviews the Contractor's concrete mix design submittal and approves the materials and mix design based on compliance with the contract. Final approval for payment is based on satisfactory field placement and performance.

Wat

er

Cem

ent

SP.G / Dosage

%

Tern

ary

T.SandersSize

1 1/2

% Aggregate Proportion by Volume

JMF Number 18-004

[email protected]

TUV Batch PlantTUV Paving

Adcon

Ajax

Tota

l CM

Page 11: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

Minnesota Department of Transportation (3/22/18)

Contractor Mix Design - Specialty Concrete (JMF)JMF

FA #1 FA #2 CA #1 CA #2 CA #3 TOTAL % WORKING TOTAL %Agg. Size Sand 1 1/2 3/4 PASSING RANGE RETAINED SPProp. % 40 20 40 100% LIMITS

2" 100.0 100.0 100.0 100 ± 5 95 100 01 1/2" 100.0 97.2 100.0 99 ± 5 94 100 1

1" 100.0 43.7 100.0 89 ± 5 84 94 103/4" 100.0 5.6 96.2 80 ± 5 75 85 91/2" 100.0 0.9 65.1 66 ± 5 61 71 143/8" 100.0 0.6 41.6 57 ± 5 52 62 9#4 100.0 0.4 4.6 42 ± 5 37 47 15#8 92.0 0.1 1.0 37 ± 4 33 41 5#16 75.0 0.1 1.0 30 ± 4 26 34 7#30 50.0 0.1 1.0 20 ± 4 16 24 10#50 20.0 0.1 1.0 8 ± 3 5 11 12#100 4.0 0.1 1.0 2 ± 2 0 4 6#200 0.8 0.1 0.4 0.5 < 1.6 0.0 1.6 2

Page 2

JMFWORKING

RANGE

18-004

8901-23

workability of the mix.

% Retained(#30 through #200)

30

22Greater than 15%,

Coarse Sand

Fine Sand

generally enhances

generally enhancescohesion of the mix.

Mix #

% Retained(#8 through #30)

Between 24-34%,

3A21-13A41-2

0

2

4

6

8

10

12

14

16

18

20

22

24

#200 #100 #50 #30 #16 #8 #4 3/8" 1/2" 3/4" 1" 1 1/2" 2"

% R

ETA

INED

SIEVE SIZE

Well-Graded Aggregate Optional Incentive - % Retained Gradation Band

Page 12: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

(2/9/2018)Minnesota Department of Transportation

S.P. Plant: Date: FA #1: 19999 FA #2:Engineer: Tester: Time: CA #1: 18888 CA #2: 18888 CA #3:Lot #: Test #: JMF #:

Sieve Analysis of Coarse AggregateSample Wt. Sample Wt. Sample Wt.

Aggregate CA #1 CA #2 CA #3Fraction Mix Prop. Mix Prop. Mix Prop.Sieve SizesPass - Ret. Ind. Cum. Ind. Cum. Ind. Cum.2" - 1 1/2" 0.0 26.4 100 0.0 12.6 1001 1/2" - 1 1/4" 3.0 26.4 100 0.0 12.6 1001 1/4" - 1" 11.0 23.4 89 0.0 12.6 1001" - 3/4" 9.4 12.4 47 0.8 12.6 1003/4" - 5/8" 0.0 3.0 11 0.0 11.8 945/8" - 1/2" 2.5 3.0 11 5.3 11.8 941/2" - 3/8" 0.2 0.5 2 2.8 6.5 523/8" - #4 0.2 0.3 1 3.3 3.7 29#4 - Btm 0.1 0.1 0 0.4 0.4 3Check Total 26.4 12.6

Sieve Analysis of Fine Aggregate Percent Passing #200 Sieve TestSample Wt. Sample Wt. CA #1 CA #2 CA #3

Aggregate FA #1 FA #2 (A) Dry weight of original sample 5027.2 2540.5Fraction Mix Prop. Mix Prop. (B) Dry weight of washed sample 5004.0 2523.5Sieve Sizes (C) Loss by washing (A-B) 23.2 17.0Pass - Ret. Ind. Cum. Ind. Cum. (D) % Passing #200 (C/A)*100 0.5 0.71/2" - 3/8" 0.0 533.7 1003/8" - #4 0.0 533.7 100 FA #1 FA #2#4 - #6 6.8 533.7 100 (A) Dry weight of original sample 534.1*#6 - #8 29.6 526.9 99 (B) Dry weight of washed sample 530.8#8 - #16 85.9 497.3 93 (C) Loss by washing (A-B) 3.3#16 - #30 130.0 411.4 77 (D) % Passing #200 (C/A)*100 0.6#30 - #50 202.4 281.4 53#50 - #100 68.6 79.0 15 Additional Remarks or Comments#100 - #200 6.5 10.4 2*#200 - Btm 0.6 3.9 0.7Loss by Washing 3.3Check Total 533.7

Composite Gradation for Job Mix FormulaAggregate CA #1 CA #2 CA #3 FA #1 FA #2Fraction 1 1/2"- 3/4"- SANDMix Prop. 20% 40% 40% Coarse Sand % Retained

2" 20 40 40 100 100 ± 5 95 100 0 (#8 through #30)1 1/2" 20 40 40 100 99 ± 5 94 100 0 20

1" 9 40 40 89 89 ± 5 84 94 113/4" 2 37 40 80 80 ± 5 75 85 91/2" 0 21 40 61 66 ± 5 61 71 19 Fine Sand % Retained3/8" 0 12 40 52 57 ± 5 52 62 9 (#30 through #200)#4 0 1 40 41 42 ± 5 37 47 11 30#8 37 37 37 ± 4 33 41 4

#16 31 31 30 ± 4 26 34 6#30 21 21 20 ± 4 16 24 10#50 6 6 8 ± 3 5 11 15#100 1 1 2 ± 2 0 4 5#200 0.1 0.3 0.3 0.7 0.5 ± 1.6% max 0.0 1.6 0.3

± 0.3% of Sample Wt ± 0.3% of Sample Wt

Weights (g) Weights (g)

± 0.2 lb of Sample Wt ± 0.2 lb of Sample Wt

Agency % passing #200 CA #1 = 0.6; CA #2 = 0.6

% Pass % Pass

Weights (lb)

40%SAND

± 0.2 lb of Sample Wt

Weights (lb) Weights (lb)% Pass % Pass

1 1/2"-20% 40%

3/4"-

534.1

Agency only - QC Test Number corresponding to this test:

JMF Concrete Aggregate WorksheetAggregate Sources (Pit #):

T.Sanders

Total % Passing

Total % Retained

Comp. Grad. Req.

JMF JMF Working RangeWorking Range

Coarse Aggregate

Fine Aggregate

% Pass

1

TUV PavingL.Bean

1 18-004

5/5/20188:30 AM

26.5 12.8

8901-23

Page 13: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

1

Minnesota Department of Transportation

JMF Moving Average SummaryPlant: SP:

Test #:

JMF #:

2" 100 100 100 95 100 100 100 100 95 100 100 100 100 95 100 100 100 100 100 95 100

1 1/2" 100 100 99 94 100 100 100 99 94 100 100 100 99 94 100 100 100 100 99 94 100

1" 89 88 89 84 94 90 91 89 84 94 89 90 89 84 94 89 89 89 89 84 94

3/4" 80 81 80 75 85 80 80 80 75 85 80 81 80 75 85 80 81 80 80 75 85

1/2" 61 62 66 61 71 62 62 66 61 71 60 65 66 61 71 61 62 61 66 61 71

3/8" 52 53 57 52 62 53 55 57 52 62 52 54 57 52 62 53 54 53 57 52 62

#4 41 41 42 37 47 41 43 42 37 47 41 40 42 37 47 41 42 41 42 37 47

#8 37 36 37 33 41 37 37 37 33 41 37 37 37 33 41 37 37 37 37 33 41

#16 31 30 30 26 34 30 32 30 26 34 31 32 30 26 34 31 31 31 30 26 34

#30 21 21 20 16 24 17 18 20 16 24 18 18 20 16 24 17 19 18 20 16 24

#50 6 6 8 5 11 4 5 8 5 11 6 7 8 5 11 5 5 5 8 5 11

#100 1 1 2 0 4 1 1 2 0 4 1 1 2 0 4 1 1 1 2 0 4

#200 0.7 0.6 1 0.0 1.6 0.4 0.5 1 0.0 1.6 0.7 0.5 1 0.0 1.6 1.0 0.7 0.7 1 0.0 1.6

Remarks or Comments

TUV Paving 8901-23

(2/9/2018)

1 2 3 4

18-004 18-004 18-004 18-004

Siev

e

Cont

ract

or

Resu

lts

Agen

cy

Verif

icat

ion

Resu

lts

Mov

ing

Aver

age

Tota

l %

Pass

ing

Cont

ract

or

Resu

lts

Agen

cy

Verif

icat

ion

Resu

lts

Mov

ing

Aver

age

Tota

l %

Pass

ing

JMF

Wor

king

Ra

nge

Cont

ract

or

Resu

lts

JMF

Wor

king

Ra

nge

Cont

ract

or

Resu

lts

Agen

cy

Verif

icat

ion

Resu

lts

Mov

ing

Aver

age

Tota

l %

Pass

ing

JMF

Wor

king

Ra

nge

Agen

cy

Verif

icat

ion

Resu

lts

Mov

ing

Aver

age

Tota

l %

Pass

ing

JMF

Wor

king

Ra

nge

Page 14: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

1

Minnesota Department of Transportation

0 ≤ 5 ≤ 16 ≤ 20 4 - 20 4 - 20 4 - 20 ≤ 12 ≤ 12 4 - 20 4 - 20 ≤ 10 ≤ 2 > 15 24-34

1 5/5/18 0 0 11 9 19 9 11 4 6 10 15 5 0 20 30

2 5/5/18 0 0 10 10 18 9 12 4 7 13 13 3 1 24 30

3 5/5/18 0 0 11 9 20 8 11 4 6 13 12 5 0 23 30

4 5/5/18 0 0 11 9 19 8 12 4 6 14 12 4 0 24 30

Lot 1 Average 0 0 11 9 19 8 12 4 6 12 13 4 0 23 30 $2.00 5,371 5363 $10,726.00

5 5/7/18 0 0 11 9 19 9 11 4 6 11 14 5 1 21 31

6 5/7/18 0 0 10 10 19 9 11 4 6 13 14 3 0 23 30

7 5/7/18 0 0 11 9 19 9 11 4 6 14 13 3 1 24 31

Lot 2 Average 0 0 11 9 19 9 11 4 6 13 14 4 1 23 31 $2.00 4,321 4321 $8,642.00

8 5/8/18 0 0 11 9 18 9 12 4 7 13 13 3 0 24 29

9 5/8/18 0 0 10 11 17 9 12 4 6 13 13 4 0 23 30

10 5/8/18 0 0 11 9 19 8 11 5 6 14 12 4 1 25 31

Lot 3 Average 0 0 11 10 18 9 12 4 6 13 13 4 0 24 30 $2.00 4,395 4387 $8,774.00

Lot Average

< --

- Yar

dage

per

Lot

pro

duce

d at

the

plan

t.

Ince

ntiv

e

Tota

l CY

P

rodu

ced

for

Lot

Pay

Fac

tor

< --

- Yar

dage

per

Lot

pla

ced

in th

e fie

ld

dete

rmin

ed b

y th

e A

genc

y fie

ld p

erso

nal.

Th

e in

cent

ive

is d

eter

min

ed fr

om th

is

quan

tity.

Specification

3/4"1" #50

#100

#200

Lot #

Test

#

Dat

e Te

sted

2"

1 1/

2"

#30

1/2" #4 #8 #16

Tota

l CY

M

easu

red

for

Lot

% R

etai

ned

(#8

to #

30)

% R

etai

ned

(#30

to #

200)

3/8"

1

2

3

8901-23T.Sanders

14071$28,142.00Well Graded Aggregate Incentives TOTAL INCENTIVE ($):

TOTAL YD3:ENGINEER:

SP #:

Page 15: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

Minnesota Department of Transportation

JMF Adjustment Worksheet

S.P. Number: Date:

Sp. Gravity:

Current Mix Design Information % Aggregate Proportion by Volume

40 20 40

2" 100.0 100.0 100.0 100 03A21-1 7.0 215 400 170 1217 636 1245 1 1/2" 100.0 97.2 100.0 99 13A41-2 7.0 230 400 170 1201 628 1229 1" 100.0 43.7 100.0 89 10

3/4" 100.0 5.6 96.2 80 91/2" 100.0 0.9 65.1 66 143/8" 100.0 0.6 41.6 57 9#4 100.0 0.4 4.6 42 15#8 92.0 0.1 1.0 37 5

#16 75.0 0.1 1.0 30 7#30 50.0 0.1 1.0 20 10

Current JMF Number: #50 20.0 0.1 1.0 8 12#100 4.0 0.1 1.0 2 6#200 0.8 0.1 0.4 0.5 2

Aggregate Proportion Adjustment % Aggregate Proportion by Volume40 24 38

2" 100.0 100.0 100.0 102 03A21-1R 7.0 215 400 170 1217 764 1183 1 1/2" 100.0 97.2 100.0 101 13A41-2R 7.0 230 400 170 1201 754 1167 1" 100.0 43.7 100.0 88 13

3/4" 100.0 5.6 96.2 78 101/2" 100.0 0.9 65.1 65 133/8" 100.0 0.6 41.6 56 9#4 100.0 0.4 4.6 42 14#8 92.0 0.1 1.0 37 5

#16 75.0 0.1 1.0 30 7#30 50.0 0.1 1.0 20 10

New JMF Number: #50 20.0 0.1 1.0 8 12#100 4.0 0.1 1.0 2 6#200 0.8 0.1 0.4 0.5 2

Page 1Submit to MnDOT Concrete Office for New JMF Number: [email protected]

Slag

FA#1

FA#2

CA#1

CA#2

FA#1

FA#2

CA#1

CA#2

FA#2

CA#1

CA#2

Contractor Representative Agency Representative

18-004

18-015

Seiv

e Si

zes

Seiv

e Si

zes

Aggregate Gradation Adjustment

Slag

Oth

er

CM FA#1

FA#2

CA#1

CA#2

CA#3

Mix

#

% A

ir

Wat

er

Cem

ent

Fly

Ash

Mix

#

% A

ir

Wat

er

Cem

ent

Fly

Ash

8901-23 5/6/18

CA#3FA#2 CA#1 CA#23.15 2.50 2.63 2.75

Cement

CA#3

Fly Ash Slag Other CM FA#12.69

Oth

er

CM FA#1

(1/1/18)

Tota

l %

Pass

ing

Tota

l %

Reta

ine

d

Tota

l %

Pass

ing

Tota

l %

Reta

ined

For use only when immediate JMF adjustments to the mix are needed.

CA#3

CA#3

Page 16: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

Minnesota Department of Transportation (1/1/18)

JMF Adjustment Worksheet100

Make JMF adjustments in accordance with 2301.2.L.3.b, "JMF Adjustments."

Page 2

% Retained(#30 through #200)

30Between 24-34%,

workability of the mix.generally enhances

Coarse Sand

No. 100 [150 um] +/- 2

Sieve Size Allowable Adjustment, %> No. 4 [4.75 mm] +/- 5

No. 8 [2.36 mm] - No. 30 [600um] +/- 4

% Retained(#8 through #30)

22Greater than 15%,generally enhancescohesion of the mix.

Fine Sand

No. 50 [300 um] +/- 3

Allowable JMF Adjustment per 2301.2.L.3.b

0

2

4

6

8

10

12

14

16

18

20

22

24

#200 #100 #50 #30 #16 #8 #4 3/8" 1/2" 3/4" 1" 1 1/2" 2"

% R

ETA

INED

SIEVE SIZE

Adjusted Well-Graded Aggregate Optional Incentive - % Retained Gradation Band

Page 17: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 18: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 19: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

(1/1/2018)Minnesota Department of Transportation

Coarse Aggregate Quality Incentive/Disincentive

Lot

Quality Cubic Yards

Testing Location (Cubic

Yards)

1 0.71 1,034 1,034

2 0.53 772 2,228

3 0.58 844 3,756

4 0.29 422 4,790

5 0.30 437 6,261

6 0.77 1,121 8,401

7 0.01 15 8,751

8 0.76 1,107 11,299

9 0.81 1,179 12,827

10 0.71 1,034 14,138

SP Number: Engineer: T.Sanders8901-23

10

Total Project Cubic Yards

Cubic Yards Per Lot

14560

1456

NOTE: Click "Generate Random Numbers" to establish the testing location.

The macros must be enabled for the random numbers generator to work.

Number of Lots (n)

3

5

10

3,500 - 7,500

Plan (cubic yards) of Concrete

7,501 - 10,000

25,001 - 50,000

50,001 + 20

15

Samples Per Fraction (n)

10,001 - 25,000

Page 20: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

3/22/2018

(1/1/2018)Minnesota Department of TransportationClass C - Coarse Aggregate Quality Incentive/Disincentive

S.P. Number: 8901-23 Engineer: T.Sanders

Pit # 18888 Pit # 18888Aggregate Fraction 1 1/2" Aggregate Fraction 3/4"Number of Samples (n) 10 Number of Samples (n) 10Number of Cubic Yards 14560 Number of Cubic Yards 14560

Lot # Lot #1 4.00 1 16.202 5.20 2 16.403 2.30 3 17.204 3.50 4 15.905 4.60 5 16.806 4.20 6 14.507 3.90 7 13.908 5.20 8 16.109 6.30 9 15.50

10 4.30 10 21.8011 1112 1213 1314 1415 1516 1617 1718 1819 1920 20

X = mean 4.35 X = mean 16.43s = standard deviation 1.08 s = standard deviation 2.13QI = quality index 5.72 QI = quality index 19.12I/D per Cubic Yard $1.00 I/D per Cubic Yard $0.50

I/D per Fraction $14,560.00 I/D per Fraction $7,280.00

% Carbonate % Carbonate

Total Incentive/Disincentive: $21,840.00

Page 21: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

(1/1/2018)

Minnesota Department of Transportation

Concrete W/C Ratio Calculation Worksheet

MIX DESIGN BATCH SIZE, (cy) 8 (A)

= 570 (B)

BATCH REPORT

FRACTIONWT OF SAMPLE + PAN (WET), (g)WT OF SAMPLE + PAN (DRY), (g)WT OF PAN, (g)TOTAL MOISTURE FACTORABSORPTION FACTORFREE MOISTURE FACTOR

TOTALDESIGN WT (OVEN DRY), (lb/cy)TOTAL MOISTURE, (lb/cy) = 88 (C)FREE MOISTURE, (lb/cy) = 56 (D)

= 32.14 (E)

WATER/CEMENT CALCULATION

TICKET # BATCH TEMPER FLY ASH/SLAG 155.9 (F)WATER WATER(GAL) (GAL) 162.3 (G)

28 152 629 155 3 166.0 (H)30 155 231 157 0 218.3 (I)32 157 133 157 0 0.38 (J)34 152 235 152 0 250.4 (K)36 152 437 152 0

AVE. 154.1 1.8AVE. CM

UNIT WEIGHT TEST % PASSING #4 SIEVE

VOLUME OF UNIT WEIGHT BUCKET, VOL ft3 MASS OF SAMPLE RETAINED #4 SIEVE, WR4 736.3 gMASS OF UNIT WT. BUCKET, BWT lb MASS. OF SAMPLE PASSING #4 SIEVE, WP4 860.9 gMASS OF UNIT WT. BUCKET & CONCRETE, CBWT lb (WD - WR4) - WS

% PASSING #4, P4 53.9 %MASS OF CONCRETE, (CBWT - BWT), CWT lb WP4 / (WD-WS)

UNIT WT. OF CONCRETE, CWT / VOL, UW lb/cf % PASSING #4 FROM JMF, P4JMF 42.0 %

% PASSING #4 FROM TOTAL MIX, P4TM 51.2 %MICROWAVE OVEN TEST

MASS OF TRAY & CLOTH, WS gMASS OF TRAY, CLOTH & WET CONCRETE, WF g CORRECTION FACTOR, CF 0.94MASS OF PAN, CLOTH & DRY CONCRETE, WD g (100 - P4 / 100 - P4TM)

TOTAL MEASURED WATER CONTENT, WTM lb/cy ADJUSTED TOTAL WATER CONTENT, AWTM 241.6 lb/cy(WF - WD / WF - WS) x 27 x UW WTM X CF COMPARE TO (K)

ESTIMATED ABSORBED WATER CONTENT, WTA lb/cy ADJUSTED MIXING WATER CONTENT, AMW 209.5 lb/cySum of Absorbed Moistures (E) AWTM - WTA

ESTIMATED MIXING WATER CONTENT, MW lb/cy ADJUSTED W/C RATIO 0.37WTM - WTA ((AMW) / (AVE CM / A)) COMPARE TO (J)

FA #1 FA #2 CA #1 CA #2

3A21-1

TOTAL CEMENTITIOUS, (lb/cy)

93

5.60

3/4"2972.62902.5281.20.0270.0130.014

12183317

15.83

CA #3

2893.2249.70.0140.0090.005

622

Sand758.9737.2175

0.0390.0090.030

11904636

10.71

0.25

43.197.63

400215

170

1 1/2"2929.7

32

1

T.SandersW.Sayment

CEMENT, (lb/cy)FLY ASH, (lb/cy)SLAG, (lb/cy)

TOTAL AVERAGE BATCH WATER, (GAL)

257.0

35.56

( D + G )

( E + I )

( AVE. BATCH WATER + AVE. TEMPER WATER )ACTUAL BATCH WATER USED, (lb/cy)

2921

1323.83035.6

13603240 1355

S.P.

DATETIME

TICKET #LOT #

32453185

ENGINEER

CONTENT

DESIGN W/C

(lbs)

0.38

ABSORBED MOISTURE, (lb/cy)

CEMENTCONTENT

(lbs)

32251345

3220

8901-235/5/20188:15am

TEST #1

TESTER

WATER, (lb/cy)

3221 13554576

320032503225

W/C RATIO

(( F x 8.33 ) / A )

(((AVE. CM * 0.40) - D)*A) / 8.33))

TOTAL MIX WATER USED, (lb/cy)

MAXIMUM BATCH WATER AVAILABLE, (GAL)

31903230 1355

13501350

13601365

13501360 ( I / AVE. CM )

TOTAL WATER IN CONCRETE, (lb/cy)

142.2

x100[((∑ Agg. Design WT.) x (P4JMF/100))+ (AVE CM / A)][(∑ Agg. Design WT.) + (AVE CM / A)]

224.9

32.14

Page 22: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

Page 1

(1/1/2018)Minnesota Department of Transportation

W/C Ratio Incentive Calculation

1 5/5/18 3A21-1 0.38

2 5/5/18 3A21-1 0.36

3 5/5/18 3A21-1 0.38

4 5/5/18 3A21-1 0.37

Lot # 1 Average: 0.37 5371 $3.00 5363 $16,089.00

5 5/7/18 3A21-1 0.36

6 5/7/18 3A21-1 0.39

7 5/7/18 3A21-1 0.36

Lot # 2 Average: 0.37 4321 $3.00 4321 $12,963.00

8 5/8/18 3A21-1 0.37

9 5/8/18 3A21-1 0.37

10 5/8/18 3A21-1 0.37

Lot # 3 Average: 0.37 4395 $3.00 4387 $13,161.00

Lot # Average:

2

3

LOT # TEST #DATE

TESTEDMIX

NUMBERW/C

RATIO (J)

TOTAL CY PRODUCED BY

LOT PAY FACTOR

TOTAL CY MEASURED

FOR LOTINCENTIVE/

DISINCENTIVE

1

< --

- Yar

dage

per

Lot

pro

duce

d at

the

plan

t.

< --

- Yar

dage

per

Lot

pla

ced

in th

e fie

ld

dete

rmin

ed b

y th

e Ag

ency

fiel

d pe

rson

al.

The

ince

ntiv

e/di

sinc

entiv

e is

det

erm

ined

fro

m th

is q

uant

ity.

0.3714,071

$42,213.00

SP NUMBER:ENGINEER:

AVERAGE W/C RATIO:TOTAL CUBIC YARDS:

TOTAL INCENTIVE/DISINCENTIVE:

8901-23T.Sanders

REMARKS

Page 23: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

Page 1 3/22/2018

(1/2018)Minnesota Department of Transportation

Concrete Ingredient SummaryS.P.: 8901-23 Engineer: T.Sanders 8,792

Plant: TUV Batch Plant Inspector: L.Bean -0.42

Date Product Type Batched Quantity (lb) Required Quantity (lb) Daily Overrun/Underrrun (%)

Cummulative Overrun/Underrrun (%) Mix Type Batched Quantity (cubic

yards)

Cement 1,650,000.00 1,657,600.00 -0.46 -0.46 3A21-1 3983

Fly Ash/Slag 666,840.00 664,960.00 0.28 0.28

Water

FA#1 6,117,800.00 6,137,260.00 -0.32 -0.32

FA#2

FA#3

CA#1 3,677,040.00 3,709,800.00 -0.88 -0.88

CA#2 3,504,100.00 3,521,580.00 -0.50 -0.50

CA#3CA#4 Waste

Cement 672,380.00 675,200.00 -0.42 -0.45 3A21-1 1799

Fly Ash/Slag 270,900.00 270,080.00 0.30 0.29

Water

FA#1 2,462,000.00 2,470,400.00 -0.34 -0.32

FA#2

FA#3

CA#1 1,503,380.00 1,518,240.00 -0.98 -0.91

CA#2 1,448,480.00 1,456,120.00 -0.52 -0.50

CA#3CA#4 Waste

Cement 710,000.00 712,400.00 -0.34 -0.42 3A21-1 3010

Fly Ash/Slag 285,480.00 284,960.00 0.18 0.26

Water

FA#1 2,649,700.00 2,657,560.00 -0.30 -0.32

FA#2

FA#3

CA#1 1,640,940.00 1,657,180.00 -0.98 -0.93

CA#2 1,412,880.00 1,419,200.00 -0.45 -0.49

CA#3CA#4 Waste

Cement

Fly Ash/Slag

Water

FA#1

FA#2

FA#3

CA#1

CA#2

CA#3CA#4 Waste

Total Batched Quantity (cubic yards)Final Cement Overrun/Underrun (%)

5/5/18

5/5/18

5/7/18

Page 24: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 25: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 26: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

JOB GUIDE CONCRETE PAVING INSPECTION 1. Review Contract and Plans:

• Obtain plans and special provisions and study them in detail. • Attend the pre-construction meeting. • Attend the pre-paving meeting.

2. Determine Random Numbers:

• Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report.

3. Become familiar with concrete paving equipment and paving operations.

• Check paving equipment for proper adjustment and compliance with specifications. • Understand the function of each piece of equipment. • Become familiar with paving sequence and review field controls for line and grade. • Verify string line is set sufficiently in advance to avoid delays. • Check vibration equipment and verify vibration monitors are operating correctly. • Verify that utility work and conduits are complete. Pre-locate utility fixtures to be

incorporated into the pavement.

4. Placement on Grade: • Check that the grade is in a moist condition ahead of the concrete placement. • Trucks hauling concrete are not allowed on the finished grade unless authorized by the

Engineer.

5. Placement on Asphalt: • Clean the milled surface by sweeping and patching, or as directed by the Engineer. • Maintain the asphalt surface in a moist condition and at a surface temperature not

greater than 120 °F [50 °C] before or during concrete placement. • Ensure the Contractor trucks don’t tear up the asphalt during turning movements.

6. Placement on Geotextile: • Clean the surface of the concrete prior to placing the geotextile fabric by power

sweeping and air blasting. • Ensure fabric is tight without excess wrinkles or folds. • Maintain the surface in a slightly damp, not saturated, condition before placing the

concrete. • Ensure the Contractor trucks don’t tear up the geotextile during turning movements.

7. Reinforcing Steel and Keyway Placement:

• Check size, spacing, and placement of reinforcing steel, and any other special reinforced panels.

• Verify proper reinforcement size, grade, lap ties, depth and spacing. • Check size and length of centerline steel and keyway tie steel. • Check if the required mechanical placer is placing it at the proper depth. • Assure location at proper elevation. • Make sure bars are the right size and length, and properly spaced.

Page 27: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

• Make sure keyway tie steel is not placed at a doweled joint.

8. Dowel Basket Assemblies: • Check proper size and type of dowel bar assembly. • Review Quality Control Plan for Anchoring Dowel Basket Assemblies. • Observe for approval the Contractor’s fastening method for dowel bar assemblies before

the beginning of concrete placement and each day prior to beginning paving. • Check dowel bar assemblies for proper placement to assure that they are parallel with

the base and centerline of road, properly supported and staked. • Make sure dowel baskets are securely anchored on the bottom rail using the correct

number of anchors. Refer to the Standard Plates for details. • If a bond breaker layer is used, make sure dowel baskets are securely fastened through

the bond breaker layer into the concrete below. • Check the placement of dowel assemblies at catch basins and manholes; keep joint at

least 3 ft (1 m) from structure. • Make sure an approved form release agent has been applied to dowel bars. • Confirm joint sawing locations are marked at the same location as the dowel baskets. • Mutually use the MIT-SCAN T2 device for locating dowel basket assemblies in the

plastic concrete.

9. When using forms: • Inspect pavement forms, as necessary, to ensure cleanliness and compliance with form

requirements. • Verify the forms are set to the alignment and grade shown on the plans for a distance

equal to at least 3 hours ahead of concrete placement. • If rain or cold weather occurs, ensure forms are removed and reset as necessary to

allow drainage.

10. Verify the Contractor’s prepared for inclement weather (rain or cold weather conditions). • Review the Contractor’s written cold weather protection plan.

11. During Concrete Placement: • Make sure concrete is placed within the time specification. • Check that no concrete is lost on the haul road or sticks in the truck after it dumps. • Stencil the stationing into the edge of the pavement every 500 ft (200 m) as directed by

the Engineer. • When placing concrete adjacent to in-place concrete pavement, protect the existing

transverse joints and the edges of the pavement. • Set manhole and catch basin frames or rings to the elevation shown on the plans during

the paving operations. 12. Monitor paving operation for continuous placement and consolidation of concrete.

• Make sure concrete is spread uniformly and ensure there is uniform strike-off. • Check to see that paver is not over or under loaded, and that concrete is “rolling” not

“sliding” in front of the screed. • Check if vibrating tubes are operating • Spot check vibration equipment daily and verify vibration monitors are operating

correctly.

Page 28: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

• Computerized vibration monitors are required on slipform pavers. Obtain an electronic copy of all vibration monitor data from the Contractor at the end of the project.

13. Concrete Appearance:

• Check that the concrete is maintained at a uniform consistency. • Monitor the surface and edge slump. • Make sure the tamping bar is properly adjusted so large aggregate is tucked below the

surface and not dragged.

14. Verify pavement dimensions: • Measure pavement width, thickness, crown, superelevation, edge slump, and joints

match to ensure it meets plan requirements. • Observe the Contractor’s probing operations.

15. Air Content and Slump Testing in accordance with the Schedule of Materials Control:

• Observe Contractor perform air content testing for slipform placement before and after consolidation.

• Observe Contractor perform air content and slump testing for fixed form placement. • Contractor test results should be recorded on the MnDOT Air Content Chart. • Perform correlation air content testing for slipform placement before and after. • Verify the air content and slump test results are within Specifications. • Record all test results on the Contractor’s Air Content Chart and compare.

16. Flexural Strength Testing (Opening Pavement to Traffic):

• Observe Contractor make beams as required in the Schedule of Materials Control. • Contractor removes beams from boxes, cleans boxes, and reassembles boxes. • Agency cures and breaks beams. • Record beam break results on Concrete Test Beam Data (MnDOT Form 2162). • Verify minimum strength requirements for opening pavements to construction and to

general traffic. • Cylinders may be substituted for beams at the discretion of the Engineer.

17. Finishing:

• Do not allow the Contractor to add water to the surface of the concrete to aid in finishing without the approval of the Engineer.

• Check surface using a 10 ft (3 m) straightedge to check for tolerance.

18. Texturing: • Ensure texturing is properly performed at the appropriate time • Check texture marks for uniformity. • Provide random sand patch test locations to the Contractor. • Verify texture by observing Contractor sand patch testing. • Contractor test results should be recorded on the Probing, Coring, Texture and MIT-

SCAN T2 Report. • Review the Contractor’s Concrete Texture results for compliance.

19. Headers:

• Construct construction headers, temporary headers, and permanent headers as shown on the plans and Standard Plates.

Page 29: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

• Do not allow incorporating any concrete accumulated in the grout box of the paver into the pavement. Construct all headers such that the concrete contained in the grout box is removed from the project.

• Use internal vibration to consolidate the concrete along header joints before final finishing.

20. Curing:

• Verify an approved curing compound lot/batch is used by checking the Approved/Qualified Products list.

• Check application rate of curing compound for uniformity, yield, and timely placement. • Ensure compliance with cold weather protection requirements.

21. Sawing Joints:

• Check joint sawing operation. Check joint location adjustments at side streets, inlets, manholes, etc.

• Check appearance, depth, and width of sawed joints on a daily basis. No raveling and no random cracking should occur at the time of initial sawing.

22. Sealing Joints:

• Verify joints are clean and dry before approving. • Do not allow traffic on the slab until the joints are sealed.

23. MIT-SCAN T2 Dowel Bar and Tie Bar Testing in Plastic Concrete:

• Use the Probing, Coring, Texture and MIT-SCAN T2 Report to provide random testing locations to the Contractor

• Observe the Contractor scan the tie bar steel and dowel bar anchoring. • Contractor test results should be recorded on the Probing, Coring, Texture and MIT-

SCAN T2 Report. 24. Thickness (Cores) Verification:

• Observe the Contractor’s coring operation to verify authenticity. • Field measure concrete cores, record the results on the Field Coring Report and submit

cores to the MnDOT Laboratory for official measurement and testing.

25. Pavement Surface Smoothness: • Make sure the Inertial Profiler (IP) is certified and displaying the certification sticker on

the vehicle. Make sure IP operator is certified. See MnDOT Smoothness website for a list of the certified IP’s, required settings for individual certified IP’s, and certified operators.

• Observe all Contractor profiling, unless approved by the Engineer. • Review the Contractor’s printouts containing the IP’s settings, each segment’s left and

right IRI values, the signature of the operator and electronic ERD files submitted on the same day of the profiling.

• Review the Smoothness Assurance analysis for contract compliance. • Determine if grinding is needed or required. • Check the final Concrete Profile Summary reports for contract compliance.

26. Maintain Agency Daily Diary:

Page 30: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

• Includes hours of production, equipment, concrete temperatures, air content, slump reading, cylinder and beam data, stations paved, width, depth, yield, weather, air temperatures, and problems or unique circumstances encountered.

27. Submit the following to the MnDOT Concrete Engineering Unit:

• Weekly Concrete Reports – Form 2448 • Concrete Test Beam Data – Form 2162 • Field Coring Reports • Field Probing Reports • Concrete Texture Reports • Concrete Profile Summary Worksheets • Change orders and Supplemental Agreements

Page 31: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

AIR CONTENT WORKSHEET/CHART (1/2018)

1

5/5/18 5/5/18 5/5/18 5/5/18 5/5/18 5/5/18 5/7/18 5/7/18 5/7/18 5/7/18 5/7/18 5/7/18

Time 7:46am 8:30am 9:55am 12:50pm 2:05pm 3:44pm 7:55am 9:05am 10:16am 12:13pm 2:11pm 3:21pm

Station 322+50 322+15 319+05 309+00 300+01 287+20 276+32 267+85 257+12 239+23 222+21 210+10

Concrete Temperature 67 67 68 68 68 67 66 67 67 67 68 67

% Air Content [a] 7.2 7.5 7.1 6.9 7.0 7.5 6.9 6.8 6.7 6.9 6.8 6.5Agency Correlation % Air Content 6.8 6.5

SAM Number** 0.15 0.18 0.23 0.21

Time 8:40am 2:15pm 9:15am 2:19pm

Concrete Temperature 67 68 67 68

% Air Content [b] 7.1 6.5 6.1 5.9Air Loss Correction Factor [a-b] 0.4 0.4 0.4 0.5 0.5 0.5 0.7 0.7 0.7 0.9 0.9% Air Content or Adjusted % Air Content 7.1 6.7 6.5 6.5 7.0 6.4 6.1 6.0 6.2 5.9 5.6Agency Correlation % Air Content 6.8 6.3

SAM Number** 0.17 0.22

8901-23 Engineer: T.Sanders Contractor: TUV Paving

Befo

re C

onso

lidat

ion

Additional Information or Comments

Additional Information or Comments

Afte

r Con

solid

atio

n

Date

Project Number:

7.27.5

7.16.9 7.0

7.5

6.9 6.8 6.76.9 6.8

6.5

7.16.7

6.5 6.5

7.0

6.46.1 6.0

6.25.9

5.6

2.0

3.0

4.0

5.0

6.0

7.0

8.0

AIR

CON

TEN

T (%

)

% Air Before % Air After

Page 32: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

1

Minnesota Department of Transportation

Mix Age Ave. Mix MixProject No.: No. No. No.Date: 3A21 3 535Project Engineer: 3A41HE 3 465Inspector: 3A21 28 762Contractor: 3A41HE 28 660

1A 508+00 5/5/14 3A21 8/26/13 6.12 6.00 20 560 B 0.98 550 31B 508+00 5/5/14 3A21 9/20/13 6.10 6.00 20 815 B 0.98 800 281C 508+00 5/5/14 3A212A 548+30 5/6/14 3A21 8/27/13 6.10 6.00 20 415 B 0.98 410 32B 548+30 5/6/14 3A21 9/21/13 6.10 6.00 20 710 B 0.98 700 282C 548+30 5/6/14 3A213A 569+00 5/7/14 3A41HE 8/28/13 6.10 6.05 20 480 B 0.97 465 33B 569+00 5/7/14 3A41HE 9/22/13 6.10 6.00 20 670 B 0.98 660 283C 569+00 5/7/14 3A41HE4A 589+20 5/8/14 3A21 8/29/13 6.10 6.00 20 653 B 0.98 645 34B 589+20 5/8/14 3A21 9/23/13 6.10 5.90 20 770 B 1.02 785 284C 589+20 5/8/14 3A21

8901.236/25/14

T.SandersL.Bean

TUV Paving

Ave. Strength

Age (days)

NotesIdentication No. StationDate Made

Ave. Strength

Modulus of Rupture

(psi)

Age (days)

Age (days)

Total Test Load (psi)

Spiral

Concrete Test Beam DataTP 2162-06 (1/2017)

Mix No.Date

Tested

Ave. Width "B"

(in)

Ave. Depth "D"

(in)

Span Length (in)

Area Correction

Factor

Page 33: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

1

Last Revised (1/2017)Minnesota Department of Transportation

Data Entry Enter the Entire project prior to start!

S.P.: Engineer: Inspector:

Starting Core #: 1 Is this an overlay where the slope/crown correction is with concrete? No

EBEBEBEBWBWBWB

Joe Inspector

TH 10 1 Lane Left of Centerline 65+00 130+00 12 8.0

60+00 12 8.0

TH 10 Off Ramp 0+00 12+00 18 7.0TH 10 1 Lane Right of Centerline 65+00 130+00 12 8.0

TH 10 1 Lane Left of Centerline 60+00 65+00 12 10.0TH 10 1 Lane Left of Centerline 0+10 60+00 12 8.0

Paving Contractor:

Roadway Direction LaneBegin Station

(ft)End Station

(ft)

TUV PavingT.Sanders8901-23

TH 10 1 Lane Right of Centerline 60+00 65+00 12 10.0

Lane Width(ft)

Design Thickness Requirement (in)

TH 10 1 Lane Right of Centerline 10+00

Page 34: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

2

Last Revised (1/2017)

Minnesota Department of Transportation

Field Probing ReportS.P.:

Corrected

Probe # Offset

P29 4.7

P30 1.4

P31 1.6

P32 14.3

P17 6.7

P5 5.3

P18 7.3

P6 10.6

P19 9.6

P20 8.9

P7 5.0

P21 6.4

P8 7.7

P9 5.7

P22 5.7

P1 2.7

P3 8.0

P2 1.8

P4 7.7

P10 6.3

TUV Paving8901-23 Engineer: T.Sanders Contractor:

5/5/14

5/7/14

5/7/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

TH 10, WB, 1 Lane Left of Centerline

15+11

14+02

8.1

7.1

8.4

Probed

Date

5/7/14

5/5/14

5/5/14

5/5/14

5/7/14

8.3

8.1

8.2

7.0

7.0

7.0

7.0

8.0

8.0

8.0

ThicknessRequirement

(in)

7.2

7.1Height

8.0

8.0

8.0

8.0

4+46

Station

TH 10, EB, Off Ramp

TH 10, EB, Off Ramp 4+44

Name

1+81Station

29+14

TH 10, EB, 1 Lane Right of Centerline

TH 10, EB, Off Ramp

25+09

TH 10, EB, Off Ramp

TH 10, EB, 1 Lane Right of Centerline

Offset from

pavement edge

25+05

19+35

9+05

TH 10, WB, 1 Lane Left of Centerline

Corrected

TH 10, WB, 1 Lane Left of Centerline

TH 10, WB, 1 Lane Left of Centerline 38+50

39+89

46+45

7+45

TH 10, EB, 1 Lane Right of Centerline

TH 10, WB, 1 Lane Left of Centerline

TH 10, EB, 1 Lane Right of Centerline 8.274+49

51+94

TH 10, EB, 1 Lane Right of Centerline

TH 10, WB, 1 Lane Left of Centerline 60+75

TH 10, EB, 1 Lane Right of Centerline 60+55

45+28

TH 10, WB, 1 Lane Left of Centerline 55+63

TH 10, EB, 1 Lane Right of Centerline 62+92 62+98

TH 10, WB, 1 Lane Left of Centerline 63+69

TH 10, EB, 1 Lane Right of Centerline

8.0

10.0

10.0

10.0

10.0

8.5

8.5

6.8

7.9

8.1

8.2

8.2

5/5/14

5/5/14

5/5/14

5/5/14

10.1

8.5

10.5

10.3

38+55

8.0

8.0

8.0

8.0

Page 35: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

3

Last Revised (1/2017)

Minnesota Department of Transportation

Field Coring ReportS.P.:

Core # Offset Offset

C15 4.7 PVC P29 7 7 7.0

C16 9.6 QAC 7.2 7.0

C9 7.3 PVC P18 8 8.2 8.0

C10 6.4 QAC 5.3 8 8.0

C4 2.3 QAC 8.1 8.0

C3 7.7 PVC P8 8.1 8.1 8.0

C12 3.9 QAC 8.2 8.0

C1 2.7 PVC P1 9.7 8.3 10.0

C2 4.6 QAC 10.1 10.0

C5 6.3 PVC P10 8.2 8.2 8.0

C11 5.3 PVC P24 8.1 8.2 8.0

C6 4.2 QAC 7.9 8.0

C7 3.5 PVC P14 8 8.1 8.0

C13 7.5 PVC P27 8.1 8.1 8.0

C8 3.0 QAC 5.5 8.2 8.0

C14 5.5 QAC 8.3 8.0127+36

74+49

84+28

86+38

106+60

112+17

120+26

1+81

7+75

19+35

25+37

38+42

46+45

58+30

60+55

62+65

TH 10, EB, 1 Lane Right of Centerline

TH 10, WB, 1 Lane Left of Centerline

TH 10, EB, 1 Lane Right of Centerline

TH 10, WB, 1 Lane Left of Centerline

TH 10, WB, 1 Lane Left of Centerline

TH 10, EB, 1 Lane Right of Centerline

TH 10, EB, 1 Lane Right of Centerline

TH 10, EB, 1 Lane Right of Centerline

TH 10, WB, 1 Lane Left of Centerline

TH 10, EB, 1 Lane Right of Centerline

TH 10, EB, Off Ramp

TH 10, EB, Off Ramp

TH 10, WB, 1 Lane Left of Centerline

TH 10, WB, 1 Lane Left of Centerline

TH 10, EB, 1 Lane Right of Centerline

TH 10, EB, 1 Lane Right of Centerline

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/29/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/5/14

5/7/14

5/7/14

5/5/14

5/5/14

5/5/14

5/5/14

Date CoredStation

8901-23

QCP Probe Height

Field Height

Core Type

Corrected

StationName

Engineer: T.Sanders Contractor: TUV Paving Joe InspectorInspector:

Date Poured

((REQUIRED))

7+71

84+23

ThickReq.(in.)Probe #

Page 36: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

4

Last Revised (1/2017)

Minnesota Department of Transportation

Concrete Texture ReportS.P.: 67,963

13 X

14 X

15 X

1 X

16 X

2 X

3 X

17 X

18 X

4 X

19 X

5 X

20 X

6 X

7 X

21 X

22 X

8 X

23 X

9 X

8901-23 Engineer: T.Sanders Contractor: TUV Paving

Dia. 1 (mm) Dia. 2 (mm) Dia. 3 (mm)

CarpetVolume of Spheres

(mm3):Texture Type:

Dia. 4 (mm)

285TH 10, EB, Off Ramp 285 287

285

285

287

TH 10, EB, 1 Lane Right of Centerline 18+07 245

289TH 10, WB, 1 Lane Left of Centerline 278 278

248

278

245TH 10, WB, 1 Lane Left of

Centerline 19+02 285 285TH 10, EB, 1 Lane Right of

Centerline 25+83

278

285TH 10, EB, 1 Lane Right of Centerline 33+01 285 285 285

TH 10, WB, 1 Lane Left of Centerline 36+06 278

278

285TH 10, WB, 1 Lane Left of Centerline 38+35 285 285 285

TH 10, EB, 1 Lane Right of Centerline

278

285TH 10, WB, 1 Lane Left of Centerline 55+65 285 285 285

TH 10, EB, 1 Lane Right of Centerline 57+91 278

278

285TH 10, WB, 1 Lane Left of Centerline 58+12 285 285 285

TH 10, EB, 1 Lane Right of Centerline

278

285TH 10, EB, 1 Lane Right of Centerline 71+21 285 285 285

TH 10, WB, 1 Lane Left of Centerline 76+97 278

279

274TH 10, WB, 1 Lane Left of Centerline 83+53 274 274 274

TH 10, EB, 1 Lane Right of Centerline

285

278TH 10, WB, 1 Lane Left of Centerline 88+86 278 278 278

TH 10, EB, 1 Lane Right of Centerline 99+10 285

Ave. Macrotexture Depth (mm)Test # Station

Outside Wheel Path

(OWP)

6+19

10+02

10+43

Name

TH 10, EB, Off Ramp

245

285

285

278 278 278 278

285

285

278 278

46+99 278 278 278

278 278

68+47 278 278 278

278 278

86+57 279 279 279

285 285

1.06

1.06

1.10

1.43

1.07

1.12

1.07

1.12

1.07

1.12

1.07

1.12

1.07

1.12

1.07

1.12

1.15

1.11

1.12

1.07

Page 37: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

5

Last Revised (1/2017)

Minnesota Department of Transportation

MIT-SCAN T2 ReportS.P.:

Scan #

14.2

13.1

13.2

14.3

13.3

14.4

14.5

13.4

14.6

14.7

13.5

13.6

15.1

13.7

15.2

1.1

14.1

15.3

1.2

1.3

5/5/14

5/7/14

TH 10, WB, 1 Lane Left of Centerline

TH 10, EB, Off Ramp

TH 10, EB, Off Ramp

Station

0+33

0+56

2+20

8901-23 Engineer: T.Sanders Contractor: TUV Paving

Name Corrected Station

YTH 10, WB, 1 Lane Left of

Centerline 11+94 11+85 5/5/14 Y

YTH 10, EB, 1 Lane Right of

Centerline 10+66 5/5/14 Y

Y

TH 10, EB, Off Ramp 9+64 5/5/14 Y

Y

TH 10, EB, Off Ramp 8+15 5/5/14 Y

YTH 10, WB, 1 Lane Left of

Centerline 6+70 6+79 5/5/14 n - Basket was adjusted

Y

TH 10, EB, Off Ramp 5+43 5/5/14 Y

TH 10, WB, 1 Lane Left of Centerline 9+94 5/5/14

TH 10, EB, Off Ramp 11+01 5/5/14

TH 10, EB, Off Ramp

Comments

5/7/14

TH 10, EB, Off Ramp 3+51 3+64 5/5/14

TH 10, WB, 1 Lane Left of Centerline 4+03 5/5/14

TH 10, WB, 1 Lane Left of Centerline 5+61 5/5/14

YTH 10, WB, 1 Lane Left of

Centerline 3+63 5/5/14 Y

Y

Y

YTH 10, WB, 1 Lane Left of

Centerline 2+38 5/5/14 Y

Date Scanned

7+05 5/5/14

TH 10, WB, 1 Lane Left of Centerline 8+54 5/5/14

TH 10, EB, 1 Lane Right of Centerline 12+63 5/5/14

5/5/14 Y

YTH 10, EB, 1 Lane Right of

Centerline 12+90

Page 38: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 39: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 40: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 41: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 42: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 43: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 44: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 45: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 46: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 47: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 48: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 49: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 50: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 51: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 52: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 53: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch
Page 54: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

1

Operation of MIT SCAN T2 Device –

Locating Reinforcement Bars and Dowel Bar Baskets 1. Assemble the device by connecting the two parts together. Do not force the connection. Be

sure the device is fully charged.

Page 55: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

2

2. To turn on the device, press both the top and bottom buttons on the handle and release.

3. The Main Menu will appear on the LCD panel. Main menu consists of:

A - Search/Measurement B - Location Settings C - System D - Data Management E - Off F - Device Settings

Page 56: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

3

4. To locate reinforcement bars or dowel bar baskets, select A – Search/Measurement.

5. Press and hold the bottom button on the handle while moving the device over the targeted area.

Page 57: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

4

6. To locate the reinforcement bars or dowel bar basket immediately after the paver or when the concrete is in plastic form, hover the device over the concrete. The wheels of the device do not need to touch the concrete for this function to work.

7. To locate the reinforcement bars or dowel bar basket when the concrete is in hardened form, either hover or roll the device over the concrete.

Page 58: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

5

8. If the sensor head approaches reinforcement bar or dowel bar basket from the side, one bar will appear higher than the rest. The four bars shown on the LCD panel represent four sensors evenly spaced on the bottom of the device (sensor head).

Note the location of rebar in relation to sensor.

Page 59: Plant - dot.state.mn.us€¦ · Plant Superintendent: Lab Equpment Calibrations - Date of seive calibration: Scale and/or Meter Calibrations - Date of scale/meter calibration: Batch

6

9. If the sensor head approaches the reinforcement bar or dowel bar basket straight on, all four bars will appear highest and equal.

10. For questions or further information, please contact: Robert Golish Assistant Concrete Engineer MnDOT Office of Materials and Road Research 1400 Gervais Avenue Maplewood, MN 55109 Office: 651-366-5576 Cell: 651-216-0516 Email: [email protected]