___________________________________________________________________________ 16/01040/AOP Comments from HFAG 8 Jan 2020 Page 1 of 33 Dear Buckinghamshire Council, PLANNING APPLICATION 16/01040/AOP WOODLANDS COMMENTS FROM HAMPDEN FIELDS ACTION GROUP HFAG HFAG strongly OBJECT to this application. We have scrutinised a wide range of aspects including taking independent professional advice and believe that the application in its current form cannot be granted permission to proceed. Set out below are our detailed comments under the following headings: 1. Prematurity 2. Alignment of Eastern Road (South) 3. Flood risk 4. Phasing 5. Financial viability 6. Water services infrastructure 7. Transport We will be happy to clarify or provide further information on any of these points. Please contact me at [email protected] or by phone to 07584 249440. Dr G P White, Secretary, HFAG By email 8 January 2021 Attachments: Jones-Parry Associates email to AVDC 17 October 2017 Transport Planning Practice report into Local Model Validation Report, April 2020 Transport Planning Practice report into SEALR Transport Assessment, June 2020

PLANNING APPLICATION 16/01040/AOP WOODLANDS ......2021/01/16  · 16/01040/AOP Comments from HFAG 8 Jan 2020 Page 5 of 33 15) In order to avoid applying the higher H++ standard to

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 1 of 33

    Dear Buckinghamshire Council,

    PLANNING APPLICATION 16/01040/AOP WOODLANDS

    COMMENTS FROM HAMPDEN FIELDS ACTION GROUP HFAG

    HFAG strongly OBJECT to this application. We have scrutinised a wide range of aspects

    including taking independent professional advice and believe that the application in its

    current form cannot be granted permission to proceed. Set out below are our detailed

    comments under the following headings:

    1. Prematurity

    2. Alignment of Eastern Road (South)

    3. Flood risk

    4. Phasing

    5. Financial viability

    6. Water services infrastructure

    7. Transport

    We will be happy to clarify or provide further information on any of these points. Please

    contact me at [email protected] or by phone to 07584 249440.

    Dr G P White, Secretary, HFAG By email

    8 January 2021

    Attachments:

    • Jones-Parry Associates email to AVDC 17 October 2017

    • Transport Planning Practice report into Local Model Validation Report, April 2020

    • Transport Planning Practice report into SEALR Transport Assessment, June 2020

    mailto:[email protected]

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 2 of 33

    Prematurity:

    1) The application is premature to the Vale of Aylesbury Local Plan. Whilst the bar is rightly

    set very high on refusing an application on the basis of prematurity, there is no doubt that

    in this case it is reached.

    2) The 2019 NPPF states:

    Local planning authorities may give weight to relevant policies in emerging plans

    according to:

    a) the stage of preparation of the emerging plan (the more advanced its

    preparation, the greater the weight that may be given);

    b) the extent to which there are unresolved objections to relevant policies (the less

    significant the unresolved objections, the greater the weight that may be given);

    and

    c) the degree of consistency of the relevant policies in the emerging plan to this

    Framework (the closer the policies in the emerging plan to the policies in the

    Framework, the greater the weight that may be given)22.

    (N.B bullet 22 refers the reader to the 2012 NPPF for Local Plans

    already submitted before 2019. This does apply to VALP, but the

    identical paragraph can be found at para 216 of the 2012 NPPF)

    3) Accordingly, bullet point 2 is of particular relevance here. If the council were to rely on any

    part of the Transport element of the VALP when considering this application, it would

    prejudice its own Plan. We would draw your attention to the following

    a) the level of objection received to the initial consultation,

    b) the controversial road alignment and its impact on Floodzone 3a

    c) the Inspector Interim comments on Transport published August 2018

    d) further main modifications to policies T3, T4 and T4 and publication of significant

    amounts of new information (including a new model run)

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 3 of 33

    e) a further public consultation period considered

    f) the Inspector’s letter outlining his plans to hold further hearing sessions on the VALP.

    4) In these circumstances any reasonable conclusion would be that there are significant

    unresolved issues which prevent any weight being given the VALP when determining this

    application, the main benefit of which is to provide part of the VALP infrastructure.

    5) The definition of the ‘high bar’ is detailed in the following paragraph:

    However, in the context of the Framework – and in particular the presumption in favour

    of sustainable development – arguments that an application is premature are unlikely

    to justify a refusal of planning permission other than in the limited circumstances where

    both:

    a) the development proposed is so substantial, or its cumulative effect would be

    so significant, that to grant permission would undermine the plan-making

    process by predetermining decisions about the scale, location or phasing of

    new development that are central to an emerging plan; and

    b) the emerging plan is at an advanced stage but is not yet formally part of the

    development plan for the area.

    6) In this case both parameters are clearly met. The application is premature and the

    council would be at risk of challenge if they were to prejudice it in such an obvious and

    unjustified manner.

    Alignment of Eastern Link Road (South)

    7) The claims over sequential and exception testing for flood risk in the FRA Addendum are flawed.

    The greatest level of risk applies to the route of the ELR(S). A full and detailed critique of the

    testing claims for this was provided to the Strategic Development Management Committee

    ahead of their meeting in October 2017, and the recent whole-site sequential test does not

    invalidate that critique (see attached).

    8) The three options for the ELR(S) route that are now stated to have been considered in the

    Design and Access stage of the application are basically the same route with very minor

    variations, all across Flood Zone 3. This strongly suggests they were not created to provide a

    genuine assessment of reasonable, valid alternatives. Nor were options referenced in the Officer

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 4 of 33

    Report to the Strategic Development Management Committee in October 2017. At least one

    valid alternative route across Flood Zone 1 was ignored even though it was identified in the

    VALP and shown by this Action Group to the SDMC.

    9) On this point, the VALP Examination Inspector commented (Interim Findings August 2018 para

    52): “In whatever way the Council chooses to represent this proposal [D-AGT3 ELR route] within

    VALP it needs to be clear that it has complied with the relevant regulations and explicit as to its

    reasons.” In their response, the Council accept that ‘the highest test of least effect on the

    floodplain will need to be undertaken to satisfaction of both the Environment Agency and lead

    local flood authority.” The EA have not yet commented on the Woodlands application, and the

    question remains open.

    10) In the light of these factors, the application cannot be approved.

    Flood risk

    11) We note that the updated FRA Addendum has been produced by the same consultancy who

    wrote the previous versions in 2016 and 2017 (FRA Addendum para 1.1.1). Much of the text is

    identical. This raises questions over the true level of objectivity in the current document.

    12) Even at this late stage and after four years of applicant work, a significant gap has been

    identified by the Lead Local Flood Authority. It is concerning to read that the surface water

    drainage calculations, needed by the LLFA to be able to assess the proposals, are missing (letter

    from BC Sustainable Drainage dated 15 Dec 2020). This lack of due diligence on the part of the

    applicant raises serious questions about the quality of work done to support this application,

    and the degree of confidence that can be placed on it.

    13) Comparing the Flood Zones maps from 2020 and 2018, it is difficult to accept the claimed

    reduction in flood risk for the site. Especially as the attenuation facility has been reduced. We

    share the Weston Turville Parish Council’s concern about this crucial factor.

    14) Maps in the FRA Addendum (Appendix C Figures 32113/34001/M1402 and M1404 attached)

    show that the 2020 ELR(S) Flood Mitigation Scheme will only shift the flood risk between

    different parts of the site. To the areas showing ‘Detriment’ and ‘Was Dry Now Wet’ must be

    added the substantial areas to the north east and the west where there is forecast to be

    ‘Negligible Impact’ on Flood Zones 3 and 2. At best, the mitigation only creates a residential

    location at the cost of surrounding it with flood-prone areas.

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 5 of 33

    15) In order to avoid applying the higher H++ standard to the flood risk assessment, Woodlands is

    “not considered to be a large-scale urban extension” (FRA Addendum para 2.1.5). This is a staggering

    assertion. The development was clearly described as ‘an urban extension to Aylesbury’ and

    ‘sizeable’ in the Officer report to the SDMC (para 9.8). It covers no less than 200 hectares and

    includes not only 1,000 houses but also substantial other commercial, employment, leisure and

    other facilities running to many tens of thousands of square metres. Part of the longstanding

    case for D-AGT3 is that it is large enough to contribute substantially to the overall plan for

    Aylesbury. This cannot be disowned now. Woodlands is a large-scale urban extension and the

    H++ standard must be applied here. The assessment cannot be relied upon unless this is done.

    16) A careful analysis has revealed that almost a quarter of the Woodlands site (22%) lies in national

    flood zone 3. Not all of this is covered by the ELR(S) route and so those areas cannot be

    accounted as ‘essential infrastructure’. For this reason, the site as a whole must be judged as

    failing the exception test.

    17) In a single short period (2016 to 2018), assessments of the site’s flood risk at Drayton Mead

    Ditch changed so much that new flood management measures are now required. As the current

    problems in Bedford have graphically demonstrated, it is sadly possible to underestimate the

    risk of flooding in the lifetime of a settlement, let alone two to three years. This reinforces the

    arguments against developing in a location that is widely agreed to be subject to significant

    threat of flooding (Flood Zones 3 and 2). There is also a question over whether homes and other

    properties on Woodlands will be able to obtain flood insurance, or if they are, at what cost,

    which may affect take-up on the site.

    18) The proposed sports facilities “will be at risk of flooding” (5.1.72), with “flood response and

    evacuation procedures prepared for the sports facilities prior to them becoming operational.” It

    is very difficult to see how any organisation could be attracted to pay to build and run these

    facilities in such a location. Flood risk thus translates directly into a threat to the financial

    viability of the Woodlands site (see also point 5 below).

    Phasing:

    19) The FRA Addendum now states that the Phase 1 (commercial) construction may progress in

    advance of the construction of the ELR(S) (para 5.1.63). But this is an important change from

    the Environment Agency comment reported to the SDMC (officer report para 7.1) which stated

    that “In terms of flood risk the eastern link road and the flood compensation will need to

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 6 of 33

    implemented first on site in order to prevent flooding in the commercial use area or indeed the

    ‘Later subsequent phases’.” This is an unjustified change of approach, not known by the SDMC

    when they considered this application. Furthermore, it goes against the infrastructure-led

    intention of the VALP.

    20) In their statement to the VALP public hearing on D-AGT3 (July 2018), the Woodlands applicant,

    Buckinghamshire Advantage, said that detailed discussions between them and the two councils

    were “now nearing completion” and they hoped that planning permission could be granted “in

    the next few weeks” (Statement on Matter 15c, policy AGT3 for Bucks Advantage). Yet we are

    not “a few weeks” but 2½ years beyond that. What have been the difficulties causing such a long

    delay? The statement indicates a level of unjustified, inaccurate optimism that is highly

    concerning when it was made by a major, well-resourced applicant in possession of all the

    relevant information to a government-appointed Inspector charged by law with objectively

    assessing the soundness of this major component in the local plan. It follows that other

    statements in the current application cannot be depended upon.

    21) The phasing of this development directly affects the assumptions and calculations on which the

    Standalone transport case is based. This crucial point is developed under Transport below, paras

    29 – 37.

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 7 of 33

    Financial viability.

    22) BC Affordable Housing confirms that the proposal cannot meet the requirement for affordable

    housing. “Schemes of 25 dwellings or over (or 1ha or more) are currently required to have 30%

    affordable housing, unless a Neighbourhood Plan indicates a greater percentage, or that level of

    provision is unviable. The applicant has advised that 30% affordable housing is unviable.”

    (17.12.20 letter to LPA). This challenges the financial viability of this scheme.

    23) It also sets a precedent for other components of the Aylesbury Garden Town plan: if the Council

    as the major stakeholder in Bucks Advantage can allow that applicant to evade Council

    standards, how can it hold other developers of even larger sites to that standard? Which will

    reduce the benefit to the local community across the whole of the town.

    Water services infrastructure

    24. It has been alarming to read the statement from Thames Water dated 11 December

    2020 saying that they cannot accommodate this development without network upgrades to

    water, foul water and sewage treatment that will also add further costs. Even though this

    problem can doubtless be fixed, how is it possible that such a major development in preparation

    for more than four years could still run into this basic problem?

    25. It goes without saying that the issues covered in Thames Water’s letter must be fully addressed

    and resolved before any planning permission could be granted.

    Transport

    The 2020 Aylesbury Transport Model with 2017 Base Year

    24. In developing the revised Transport Addendum Stantec (previously Peter Brett

    Associates) have been asked to use the updated Aylesbury Transport Model (“ATM”)

    with a base year of 2017.

    25. We are pleased that after nearly ten years of trying to convince Bucks Council to improve

    their modelling they have finally agreed with us.

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 8 of 33

    24. Whilst the new ATM is an improvement on the previous model there are still some

    serious reservations which cast doubt on the effectiveness of the model to be used in

    determining planning applications. Accordingly, we ask that this submission is read in

    conjunction with the Transport Planning Practice (“TPP”) report into the Local Model

    Validation Report (April 2020 - attached) and the TPP report in the SEALR Transport

    Assessment (June 2020 - attached) that were sent to the Council at the time.

    25. It should be noted that we have not received any correspondence at all regarding these

    reports and in particular to our request for more information, critical to the assessment of

    the Aylesbury Transport Model. We repeat those requests which can be found on page

    19 (paragraphs 81-83) of the SEALR report.

    26. Whilst we ask the reports to be considered as a whole particular concerns regarding the

    modelling are briefly highlighted below:

    a) The lack of specific detail on the performance of the ATM model in representing

    flows at the Walton Street gyratory is a serious omission from the LMVR. This

    junction is critically important. But the gyratory observed flows are not validated in the

    ATM LMVR or the TA. Therefore, there cannot be any confidence in the assertion

    that future year problems at the gyratory have been solved.

    b) TPP recommend that BC’s consultants provide some details of the demand and

    actual flows, particularly at the Walton Street gyratory. Without this information, the

    interpretation of the ATM model results can be difficult. This is particularly the case

    for the 2036 model runs, where a substantial increase in traffic (over 40% above the

    Base Year volumes) at an already congested location is being modelled.

    c) The ATM model base year has changed the model peak time periods. The modelled

    morning peak is now 07.00 to 08.00, not 08.00 to 09.00. Despite seeking clarification,

    no explanation has been given for this potentially very significant change. Especially

    when considering that the Walton Street Gyratory has the highest concentration of

    secondary students heading for the three schools in close proximity to it, all of which

    start at 08.45. The model needs to be representative of the busiest weekday hours

    and as such an explanation is again required if this is not to be judged incorrect.

    d) Jacobs have compared modelled junction turning movements with observed data at

    two locations – A41/Aylesbury Road and A41/Bedgrove/Broughton Lane. Whilst

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 9 of 33

    these junctions are important to the assessment of the Woodlands and Hampden

    Fields junctions, it is very surprising that no comparison was carried out for the

    Walton Street Gyratory and the A413/Camborne Avenue roundabout, both of which

    will be affected by the changes proposed.

    e) Regarding the ATM’s “Fitness for purpose” Jacobs comment as follows:

    “As evidenced by the overall calibration/validation statistics, it is considered that the

    model provides a good overall representation of current travel conditions for those

    areas included within the modelled network and is therefore appropriate for the

    purposes of assessing smaller scale schemes and developments. For larger scale

    schemes, (i.e., those of a similar size to SEALR and the other orbital link road

    schemes) an initial assessment of the extent of the scheme’s impact in terms of

    reassignment (potentially through the use of the existing Countywide model) and a

    detailed assessment of the model’s validation in the vicinity of the scheme should be

    undertaken before the model can be said to be fit for purpose for use as an evidence

    base for a major scheme appraisal of the given scheme.”

    24) To our knowledge, no such assessment of the wider impact and validation has been

    performed for a scenario that includes ELR(S), SLR, SEALR,SMRR and SWALR and the

    associated land use developments. Therefore it has not been demonstrated that the

    current version of the ATM Model is fit for purpose for examining the cumulative impact

    scenarios reported in the TAA. We want to make this overarching reservation clear,

    even though we have had to work with the modelled data in order to make our scrutiny

    comments that now follow.

    The Standalone Case for Woodlands

    25) The choice of 2022 as the forecast year for the Standalone case is unreasonable. NPPG

    requires that Transport Assessments are based on scenarios that will reasonably come to

    light. It is simply not possible that the Woodlands development will be completed by 2022

    and as such the Standalone assessment cannot be given any merit.

    26) Even the developer acknowledges that this will not happen. Paragraph 2.2.7 of the

    Transport Addendum, states that “construction of the ELR(S) and its associated flood

    mitigation works are now due to commence in 2022, with completion expected by the end

    of 2024. The remainder of Phase 1 of Woodlands (consisting primarily of employment

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 10 of 33

    land) will commence in 2023 with completion scheduled for the end of 2024.”

    27) It is important to note the developer is only talking about phase 1 being completed by

    2024 and not the full standalone scheme that should be considered in any recognisable

    Transport Assessment.

    28) The phasing and lack of trip generation in the standalone year is utterly misleading with

    none of the housing or any of the leisure facilities included in the standalone scenario. The

    authors of the TAA and the Highways Authority are fully aware that residential, hotel and

    school developments will generate significant traffic which has been erroneously excluded

    from the standalone assessment.

    29) The Local Planning Authority will be aware that 2022 is the same forecast year used in

    the March 2016 initial Transport Assessment. This year was just about acceptable then

    as it was six years away, but not now when there is only a matter of months before 2022.

    30) What was never acceptable, and never will be, is the exclusion of such significant trip

    generating parts of the development.

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 11 of 33

    31) The table below shows exactly how the level of development being considered in Phase

    1 is a very limited proportion of the whole scheme and how it excludes the largest traffic

    generators (the office and residential development):

    2022 Standalone Full 2036 Scheme

    Residential

    1,100 dwellings

    60 Residential Care home

    Employment B1 office 3,070 sqm

    B2 light Industry 39,850

    sqm

    B8 warehousing 32,800

    sqm

    B1 office 25,600 sqm

    B2 light industrial 44,400

    sqm

    B8 warehousing 32,800

    sqm

    Local centre

    Mixed use 4,000 sqm

    Leisure facilities - 5,000 sqm hotel

    3,500 sqm leisure centre

    16 ha sports

    village/pitches and

    athletes’ accommodation

    Schools - 2 primary schools

    Other - Eastern Link Road

    (South)

    32) The standalone case must reflect the full Woodlands development and currently does

    not. It is therefore completely invalidated and must be changed to accurately reflect a

    more reasonable and realistic scenario before the Highways Authority could possibly

    consider it.

    33) The ‘explanation’ at paragraph 1.2.4 was, and still is, unconvincing. The Council is well

    aware that the whole development is unviable if the ELR(S) and employment areas are

    built on their own. They cannot simply design a scenario where selective planning

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 12 of 33

    permission can be given ‘until the SLR is completed’. A standalone assessment must

    reasonably reflect the scheme that is before the Council to determine.

    34) The current Standalone assessment would only be valid if the application before the

    council for determination was for the ELR(S) and the Employment areas alone. It is not.

    35) The Hampden Fields s106 suggests that the Southern Link Road does not need to be

    delivered until “5 years after development” has begun. For Hampden Fields development

    to commence it still has to go through outline planning, get an agreed s106, face legal

    challenge, go through detailed planning, face another potential legal challenge, and then

    begin. Even in the unlikely event of this all going in favour of development it is very

    unlikely that development would begin before 2023/24. This would mean that the SLR

    may not be in place until 2028/9. Again, this significantly brings into question the 2022

    standalone year as anything like a reasonable scenario. It seems extremely strange that

    the Council are accepting a 2022 forecast year for a Standalone Assessment which even

    the developer admits is not realistic.

    36) A further cause for confusion is that some individual junction assessments in the TAA do

    have a 2036 do minimum (i.e. junction 22) but not a 2036 standalone. Any reasonable

    member of the public would find it incredibly difficult to follow this “mix and match”,

    “apples and pears”, approach. A standalone 2036 scenario is essential before any

    objective assessment can begin.

    37) Finally, the standalone scenario does not include the presence of the Stoke Mandeville

    Relief Road yet this is regarded by the council in all other scenarios and applications as

    a committed scheme. This error needs to be corrected.

    38) Overall the standalone 2022 scenario is significantly erroneous. It appears, from the

    developer TAA that the Council accept this. The council’s agreement to an unrealistic

    scenario is an unfortunate reflection that it has lost objectivity and is open to challenge if

    not corrected.

    Standalone Junction Assessments

    39) Notwithstanding the clear and obvious flaws in the standalone case, there are a number

    of critical junctions that have not been assessed in the standalone scenarios at all

    including:

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 13 of 33

    • Junction 22 Bedgrove/Broughton Crossing

    • Junction 98 New Road/A41

    • Junction 116 Marroway/Main Street/Brook End, Weston Turville

    40) Given the very close proximity to the development site, this omission needs correcting. It

    is very likely that flows through Weston Turville, for example, will increase with

    development even given the flawed standalone scenario.

    Cumulative Assessments

    41) It would have been helpful to have had the same comparator year as the VALP (2033) to

    allow meaningful comparisons.

    42) The addition of an extra 3 years of background growth traffic (to 2036) of course has the

    effect of increasing background traffic which is helpful to the scenarios presented by the

    developer. It is very disappointing that some base year comparisons are not given to

    allow decision makers to see the overall effect of the traffic growth around Aylesbury

    between 2017 and 2036. This would show the full impact of the growth and demonstrate

    that in virtually all cumulative situations, the traffic in, around and at key junctions in

    Aylesbury will be demonstrably worse than it is today, or in the base year.

    43) Given that the cumulative scenarios are based on 3 years after VALP it is strange that

    full analysis has not been carried out for the key junctions based on the full VALP case.

    Only two existing junctions have been modelled and this does not reflect a realistic

    scenario. Critically, given the significance of the gyratory system (Junction 99), it is a

    substantial omission not to have included this in the full VALP Sensitivity analysis. This

    must be done before any final assessment can be objectively delivered.

    44) It also only requires one of these developments such as the SLR or SEALR not to come

    forward for the cumulative scenarios to become unfit for purpose. We accept it would be

    unreasonable to have countless scenarios. However, several of the developments

    included in the Cumulative scenarios cannot be delivered by the Woodlands developers

    (SLR, SEALR and SWALR). These schemes require various levels of public funding and

    are subject to their own planning processes. They are not committed schemes.

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 14 of 33

    45) But, given the uncertainty and controversy of some of these proposals, especially with

    regards to Hampden Fields, a scenario without some of these major developments is

    highly desirable.

    46) The development has never been modelled without Hampden Fields (except in the 2022

    ‘standalone’). It is essential that this is done, or it will require the Council to accept that

    16/01040/AOP cannot proceed at all.

    47) Finally, all the 2036 scenarios include the Stoke Mandeville Relief Road, which is now

    considered a committed scheme. To reiterate the point above if it is a committed scheme

    it should also have been included in a realistic standalone scenario in the Transport

    Assessment.

    Annual Average Daily Traffic (AADT) forecasts

    48) AADT’s have been published in the Environmental Assessment Addendum within the Air

    Quality Assessment with the raw numbers and at Table 5.7 a percentage change table

    has been included.

    49) Although there are some % change figures published in Table 5.7 of the ES Addendum,

    for many links the forecast AADT flows are not published and many key junctions are

    missing. For example, the Walton Street Gyratory (Link 2.4) and Camborne Avenue (Link

    5.6). It should also be noted that the Cumulative 1 forecasts appear not to have been

    published. Such significant omissions make it extremely difficult to properly examine the

    material and accordingly prejudice the public. This should be corrected and the full AADT

    forecasts published so as to be available for public scrutiny.

    50) All junctions appear to be contained in Table 5.7: Link Analysis but only as percentage

    changes and not actual data flows. This is most unhelpful.

    51) There is no specific analysis of the AADT’s in the Transport Addendum other than very

    few passing comments without any specific data. This is despite very significant issues

    which can be identified by doing so.

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 15 of 33

    52) We have combined these two data sources to allow the public to better understand and

    scrutinise the impact of the proposed Transport Case. The full analysis is contained in

    Appendix A, with urgent and major concerns highlighted in Red and summarised below:

    53) Link 10.4 : A41 Westbound Off slip -- “Crow’s Nest Roundabout/Tring Hill”

    There is a significant increase in forecast flows at in Link 10.4. An increase of 5,000 vehicles

    per day.

    In turn this leads to significant increases in flows at Link 10.4, Crows Nest, Tring Hill exit.

    Vehicle. An increase of 5,000 vehicles per day.

    Where does all the traffic exiting this junction go? Given that flows are forecast to

    significantly fall by 3,000 vehicles (12%) on Link 8.1, (further down Tring Hill) and only

    slightly increase at link 8.3 (Icknield Rd), there appears to be is a likelihood that this will re-

    route through Halton and Wendover. The concern is the use of the ATM which is not

    adequately validated to cover the Wendover / Halton area (see section on Wendover/Halton

    below). An explanation is essential before the TAA can be objectively assessed. Mitigation

    may be required to prevent rat running and the overloading of the Halton Lane / Aylesbury

    road junction in Wendover.

    54) Links 1.4, 1.5, 1.6: A41 Aston Clinton Road (see also Link 1.7 Tring Road at para 54)

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 16 of 33

    The rationale for building a series of link roads around the town is to reduce traffic along the

    congested radial routes into the town. However, along this key route, traffic increases so that

    the A41 West of the Aston Clinton roundabout (Link 1.5) increases to 43,500 vehicles a day

    in the fully built out 2036 scenario. This is counter to the objective as this is still, despite

    recent widening in some places, a single carriageway road. There is a serious concern

    about the capacity of this road to carry even even more traffic. Its susceptibility to breakdown

    would increase still further and this is very unlikely to be acceptable to the Highways

    Authority or the public.

    Furthermore, link 1.6 shows a decline in volume by 40% from 44,700 vehicles to 26,800

    vehicles. Link 1.5 and 1.6 are a matter of few hundred yards apart. There are only two

    possibilities for traffic to turn off from this road between these two points. One is New Road

    and one will be the not yet constructed junctions of the MDA. The MDA flows do not appear

    to be modelled at all.

    Analysis of the potential turn off junctions show a small increase along New Road of 300

    vehicles (Link 7.6) leaving over 16,000 vehicles unaccounted for.

    The other possibility is that some may re-route through Bedgrove (Link 5.5) but this again

    shows a reduction of 48.9% in traffic (or c. 6,600 vehicles) using the same like for like

    comparison. The final possibility of diverting through Broughton encounters significant

    problems.

    Where do 16,700 vehicles “disappear” to between link 1.5 and 1.6? This must be explained.

    55) Link 5.3 Broughton Lane

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 17 of 33

    There is a claimed reduction in Broughton Lane traffic from 4,700 to 4,200 vehicles but this

    needs significant explanation. The background traffic using the road is forecast to drop from

    5,637 vehicles to 4,715 vehicles a day between 2022 and 2036. The 2036 do minimum

    includes significant new developments close to the area and we can find no other links

    where the background traffic reduces over the 2022-2036 period. It seems extremely odd

    that such a notorious rat running location would reduce in traffic without the Eastern Link

    Road in place.

    This needs an explanation and/or correction.

    Further, as it might be hoped, the introduction of the ELR(S) then leads to substantial

    reductions in the forecast flows of 46.4% in the standalone case and 10.6% in cumulative

    two scenario.

    Yet, the developer, and for that matter the Hampden Fields developer, have committed to a

    review of Broughton Lane traffic one year after the opening of the ELR(S) and the SLR. This

    is in both draft s106 documents.

    It is envisaged that there could still be ‘rat running’ along Broughton Lane even after millions

    of pounds have been invested to build these two ‘strategic link roads’. The result as set out

    in the draft S106s could be further expensive and disruptive mitigation on Broughton Lane

    itself, paid for principally by Woodlands, i.e. basically taxpayer-funded.

    One explanation could of course be that the AADT scenario in the ES appears to be based

    on the full Cumulative Two scenario, which won’t come to fruition until 2036. There appears

    to be no analysis of AADT’s in the Cumulative One scenario with Hampden Fields and

    Woodlands.

    It is surprising to note how little confidence the applicant has that its major road scheme will

    solve the local traffic problems, and indeed might even contribute to them. The seeming

    error in the background traffic using Broughton Lane is even more worrying in this context.

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 18 of 33

    The developer is clearly unsure about the effect their development will have on Broughton

    Lane. As well as being extremely concerning to local residents it shows that the Transport

    Assessment is incomplete.

    Broughton Lane needs closer examination before permission can be granted and mitigation

    must be identified upfront along with associated costs appropriately attributed to developers

    and included in the S106 agreement(s).

    56) Link 1.7 Tring Road (see also Link 1.4 etc Aston Clinton Rd at para 54 above)

    As can be seen, Tring Road increases vehicular traffic from 29,900 in the 2036 Without

    Woodlands scenario to 32,100. The stated aim of reducing traffic on this key arterial route is

    clearly missed.

    As you will see from the section below analysing the Bedgrove/Broughton crossing junction

    it appears that closure of the Richmond Road and diversion of Akeman Road only

    encourages more traffic to use the Tring Road. This is completely counter to policy and must

    be extremely concerning to promoters of this scheme and the Highways Authority.

    The Highways Authority should not consider granting a scheme that creates increased use

    of the Tring Road. This will lead to an increase from 23,600 vehicles to 32,100 vehicles in

    the full development scenario, a dramatic increase on one of Aylesbury’s PPTCs adjacent to

    an air quality management areas. Highly undesirable and needs to be reconsidered.

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 19 of 33

    57) Stocklake/Cambridge Street Corridor/Area

    There are significant increases in the standalone case scenario. Mitigation is required at

    Cambridge Street/New Road junction in any case. It appears the ELR will merely shift traffic

    around the ring so they come in along another radial route. This might be acceptable if it

    were not for the increases on the Tring Road corridor as well.

    58) New Southern Link Road

    Of significant concern are the flows along the new Southern Link Road. These are

    unacceptably high for a road that serves as an access road to a major development area. As

    can be seen from the table below the volume of traffic will exceed any other road in the

    Aylesbury area and is comparable to a major trunk road, not a link road through a residential

    development area.

    There will be 48,802 vehicles per day (to quote precisely from the developer document)

    using the Southern Link Road by the time the developments of Hampden Fields and

    Woodlands have been built out. It will be far the busiest road in the Aylesbury area. It is

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 20 of 33

    counter to policy and unacceptable given the location and use of this road with many

    pedestrian crossing points.

    59) Although we have previously covered the point about using the VALP as the policy

    platform in this case, we note the VALP Vision for Aylesbury Garden Town states that:

    "The impacts of climate change will have been minimised, especially by building

    exemplar new developments and increasingly sustainable travel choices. As a

    result, local carbon emissions will be low relative to UK averages.”

    60) Aylesbury’s CO2 emissions are already below the UK average (6.2 tonnes per person

    compared with 7.1) We note that no analysis of CO2 emissions have been included as

    part of the Environmental Addendum Assessment.

    61) It is unlikely that constructing a new road through a residential area which is forecast to

    carry in excess of 48,000 vehicles could be classified as in line with any reasonable

    assessment against the Garden Town’s policy or stated objectives.

    Junction Assessments

    62) Given the very limited time available and the amount of data published the Hampden

    Fields Action Group has been unable to resource expert analysis of the technical

    junction data. Many scenarios have not been published in a format that a member of the

    public could reasonably scrutinise, others have been missed completely. This has

    prejudiced the public and HFAG.

    63) Junction 9 A41 Woodlands Roundabout

    Standalone Scenarios

    It is common ground this is currently an overloaded junction. The do minimum scenario at

    table 3.11.2 of the TTA page 39 demonstrates this, with delays so large that they simply lack

    credibility.

    A queue of 1444 vehicles and a delay of 5073 seconds is equal to 1 hour 24 minutes.

    Firstly, it is longer than the model period of an hour and secondly is highly unlikely that this

    traffic would not re-route. This is clearly a significant error.

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 21 of 33

    In the 2022 Do Something, the effect of building the ELR(S) and the employment area is to

    significantly reduce congestion at this junction. For example the A41 East Arm (coming from

    the Tring direction) is reduced from a queue of 1444 vehicles in the Do Minimum in the pm

    peak to 12 in the Do Something (i.e., the partial development of Woodlands and the full

    signalisation of the Woodlands roundabout).

    As explained above, this is not a true standalone scenario and in this case it is even less

    plausible as it includes mitigation being brought forward as a result of a cumulative

    development with Hampden Fields. As the developer and the Highways Authority know it is

    impossible to include mitigation being brought forward as part of cumulative development in

    a fair standalone scenario. Unless the Woodlands application on its own is to pay for the

    signalisation of this junction on its own, in which case the Woodlands developer should

    have this total contribution clearly as part of the S106 and the signalisation in place before

    the ELR(S) is completed, it cannot be included in the standalone It is not.

    It is critical that decision makers see how this junction would operate in a true standalone

    scenario.

    Cumulative Scenarios

    In all cumulative scenarios delays on critical approaches are higher than they are in the

    2022 Do Something Standalone. This means the addition of Hampden Fields (in Cumulative

    1) and the SEALR + SWALR (Cumulative 2) make the situation worse than the standalone

    and the congestion at critical junctions is increased.

    PM Peak Junction Capacity

    (In this table, the do minimum scenarios are assessed differently because in the do minimum

    these are roundabouts not signalised junctions. Therefore, capacity is expressed as a decimal

    Ratio to Flow Capacity (above 0.85 RFC being problematic) in the Do Minimum scenarios and as

    a percentage Degree of Saturation (above 85% being problematic) in the Do Something and

    Cumulative scenarios).

    2022 Do-

    Minimum

    2036 Do

    Minimum

    Standalone

    2022 Do

    Something

    Cumulative

    One

    Cumulative

    Two

    Cumulative

    Three

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 22 of 33

    A41

    East

    Not

    publish –

    PLEASE

    PUBLISH

    2.44 RFC 83% 98% 104% 101%

    ELR(N) Not

    publish –

    PLEASE

    PUBLISH

    Not in

    existence

    26% 87% 99% 100%

    SLR (S) Not

    publish –

    PLEASE

    PUBLISH

    Not in

    existence

    Not

    Given/Not in

    existence.

    90% 83% 88%

    The developer’s explanation at paragraph 3.11.11 does not make sense. They argue “these

    results should be compared to the forecast 2036 Do Minimum results as a standard

    roundabout.” Table 3.11.2 makes no sense and is wrongly labelled at best, with one label

    suggesting this is a 2022 Do Minimum and one suggesting 2036 Do Minimum. If indeed they

    are trying to compare the published do minimum of 2022 with a cumulative scenario of 2036

    this is a meaningless comparison using “apples and pears”. If they are trying to compare the

    2036 do minimum with the cumulative scenarios we also need to be able to compare the

    2036 Do Something standalone.

    Overall Practical Reserve Capacity for the junction would also be a useful comparator in all

    scenarios and has been done for other key link junctions. You would have imagined that for

    one of the most important junctions for the whole of the Aylesbury network that basic

    modelling would have been presented, free of error, to give the public at least a reasonable

    attempt to scrutinise it. This section is so poor that the public is severely prejudiced with no

    hope of realistic input being possible.

    Considerable work needs to be done to produce a realistic 2036 Standalone and this needs

    to be published for scrutiny before the Highways Authority can assess this application.

    64) Junction 22 Bedgrove / Broughton Crossing

    Standalone Scenarios for Junction 22 Bedgrove/Broughton Crossing

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 23 of 33

    There are no junction assessments accessible for public scrutiny published. Please publish

    and allow the public sufficient time to scrutinise the standalone scenarios for this junction. It

    is our strong recommendation that this is done in line with a “fully built out” scenario as is

    required under NPPG guidance.

    There is no 2036 Do Something (i.e. Woodlands standalone). Only a 2036 Do minimum so

    no comparison can be made versus the Do something? Quite possibly this junction could be

    made worse between Do Minimum and Do Something.

    Without this it is not possible to comment on the standalone case so the Highway Authority

    has no evidence from which to take a decision.

    Cumulative Scenarios

    All cumulative scenarios show a significant deterioration in the overall Practical Reserve

    Capacity of the junction in the PM peak.

    AM Peak PM Peak

    2036 Do Minimum -57.9% -3.3%

    2036 Cumulative One -44.2% -26.5%

    2036 Cumulative Two -37.6% -24.8%

    This would not be acceptable so the developer is proposing a mitigation scheme, the closure

    of the Richmond Road arm and re-direction of Akeman Road (the practicality and legality of

    this is extensively covered below).

    Just considering the mitigation itself, along with changes in the cycle time, it appears to have

    significant benefits to the operation of the junction. Looking at this from the other side it is

    clear that without this mitigation granting of planning permission for Woodlands (and indeed

    Hampden Fields) would be highly unlikely.

    Overall RFC at Junction 22 Bedgrove/Broughton Crossing

    AM Peak PM Peak

    2036 Do Minimum -57.9% -3.3%

    2036 Cumulative One -44.2% -26.5%

    2036 Cumulative Two -37.6% -24.8%

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 24 of 33

    2036 Cumulative One plus

    Richmond Road Closure

    +24.7 +41.7

    2036 Cumulative Two plus

    Richmond Road closure

    +25.5 +42.3

    This increase in performance is significant. It should be noted mitigation has allowed the

    cycle time in the AM peak to change significantly, thus flows through the junction would be

    dramatically increased. It would also have the effect of “encouraging” more traffic to use the

    A41 Tring Road corridor, which as previously stated, is against policy.

    Analysis of the AADT data (above) show an increase of 2,200 vehicles a day using the Tring

    road in the 2036 comparison and an increase of 8,500 vehicles a day from 2022 to 2036.

    This is not acceptable to local residents and it cannot be reasonably acceptable to the

    highways authority.

    Given the impact of the proposed mitigation schemes in reducing delays, the Highways

    Authority should insist the full mitigation be run through the ATM model again to assess

    whether the flows at this junction, and other junctions, will increase. This could have wide-

    ranging impacts elsewhere in the network.

    Clearly, as the flows will be increased this traffic has to go somewhere. It will have the effect

    of more traffic meeting the King Edward Avenue/Oakfield Road junction, Woodlands, New

    Road junctions during peak am and pm periods. It appears that none of the surrounding

    junctions have been modelled taking into account the impact of the Richmond Road

    mitigation scheme.

    65) Tring Road Traffic Flows and impact on Air Quality

    Average Annual Traffic Data (AADT’s) published in the Air Quality Appendices of the 2020

    Environmental Statement show dramatic increases in traffic flows along the Tring Road.

    It is unclear as to which AADT scenarios (analysed above) have been compiled using the

    mitigated Richmond Road closure. Can this please be urgently clarified.

    2022 AADT’s suggest flows of 23,617 vehicles without the development. The underlying

    traffic growth pushes the overall flows to 29,880 without the scheme. However, with the

    scheme the growth is even higher at 32,148.

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 25 of 33

    Such increases in traffic volumes along the A41 corridor is counter the strategy of the “ring

    road” and is very likely to be met with strong disapproval by local residents.

    66) Impact on junction modelling

    It appears none of the surrounding junctions have been modelled with the Broughton

    Crossing mitigation (Richmond Road closure) in place. They appear to have all been

    modelled using the non-mitigated road layout, despite the developer [wrongly] stating this is

    a committed scheme.

    Could the Highways Authority please urgently confirm if the published junction assessments

    have been completed using the Richmond Road closure as well as other mitigation.

    This urgently needs to be addressed, if the current scenarios do not include the Richmond

    Road closures/mitigation the scenarios must be done for key junctions with the mitigation for

    the Broughton Crossing junction included, both standalone and cumulative, and the public

    must be given sufficient time to scrutinise these.

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 26 of 33

    As a minimum we suggest the following junctions require further assessment:

    Junction Number

    9 Woodlands Roundabout

    23 Bellingham Way / A4157 Stocklake

    26 Park Street Roundabout

    28 A418 Park Street

    30 Broughton Avenue Priority Junction

    31 A418 Cambridge Street

    36 A41 King Edward Avenue

    Without adequate junction assessments in all scenarios, with adequate mitigation being fully

    considered, the Highways Authority could not grant planning permission for application

    16/01040/APP.

    67) Richmond Road Diversion - Proposed Mitigation – Implications for Decision Makers

    68) To overcome the very clear problems that exist with the junction it is clear that mitigation

    is required in published scenarios. Once again we need to stress that a standalone

    scenario has not been published. As it has been well documented by others the Council

    will be aware of the land ownership dispute that exists regarding the Richmond Road

    green area. However, land ownership does not directly have any influence on the

    planning merits of the case.

    69) What does, however, is a planning decision being made that would be subject to a

    “different consenting regime” in relation to Highways changes, which the decision maker

    was unable to guarantee. The diversion of Richmond Road requires a number of legal

    procedures which are outside the control of decision makers in this planning application.

    Namely the publication and approval of a Traffic Regulation Order changing the layout of

    the Richmond Road area and the closure of Akeman Road. Such changes will no doubt

    be very heavily contested by local residents and are very uncertain to get approval even

    if land ownership issues can be overcome.

    70) It is an error of fact and very misleading indeed to suggest, as the developer does at

    3.21.5, that “This junction was the subject of a committed scheme of improvement which

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 27 of 33

    was agreed with Buckinghamshire Council as part of the 2017 technical work for

    Aylesbury Woodlands and Hampden Fields”. [Emphasis added]

    This statement is so erroneous, it merits an immediate correction of its own.

    71) If this were a committed scheme, then all transport assessments would have to be done

    with it included. It is not a committed scheme and what makes it worse is that it is being

    brought forward as joint mitigation for both Hampden Fields and Woodlands. Despite

    what it says at 3.21.8 of the TAA there still appears to be some confusion between the

    TAA’s / draft s106 agreements for Woodlands and Hampden Fields as to who will deliver

    or contribute to it.

    72) Regarding the granting of planning permission for a scheme that requires mitigation

    under a “different consenting regime” there is a notable precedent for Bucks Council.

    Having agreed with the Hampden Fields developer in 2013 that they would not object to

    their proposals an independent planning inspector and the Secretary of State disagreed

    and refused planning permission.

    73) Paragraph 27 of the Secretary of State’s decision letter 25th January 2015 repays

    reading in full:

    27.Like the Inspector, the Secretary of State has taken account of the fact that a scheme of

    mitigation has evolved for the Walton Street gyratory, but that its final form leaves a number of

    matters uncertain and any such scheme could only be implemented, and any prior planning

    permission for the Appeal B scheme realised, consequent on the confirmation of a Traffic

    Regulation Order which would be subject to its own consent regime. The Secretary of State

    agrees with the Inspector at IR9.586 that the benefits of such a scheme would be substantial.

    However, he also agrees (IR9.645) that it would not make sound planning sense to approve a

    major urban extension with known highway deficiencies, an incomplete solution and

    uncertainties about deliverability until it can be demonstrated that the full effects of the appeal

    scheme can be mitigated, managed and implemented. [Emphasis added]

    When read in full it is clear the Secretary of State is referring to:

    • A planning decision where it was common ground that mitigation was required,

    • That the mitigation would be subject to its own consent regime,

    • The mitigation related to off site works

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 28 of 33

    • The mitigation requires changes to established road layout*

    • It relates to a “major urban extension”,

    • It has known highways deficiencies and

    • Planning should not be granted until it can be “demonstrated that the full effects

    of the scheme can be mitigated, managed and implemented”

    *N.B The mitigation the SoS was referring to in his decision was the proposed closure of the

    “Aristocrat link” arm at the Walton Street gyratory.

    74) There needs to be certainty about how and when the mitigation will be achieved. Failure

    to provide certainty will leave the Council open to challenge to from the public.

    75) Junction 99 – The Walton Street Gyratory

    The lack of validation using observed flows at the gyratory system is a major omission which

    undermines the model and consequently the TAA. It cannot have escaped the HA at the

    most senior level that this junction is both the busiest and most controversial in the whole of

    the Aylesbury network.

    In addition, it forms part of an AQMA and a previous Highways Authority decision to allow

    planning permission for the original HF development was overturned by the SoS because of

    concerns about this junction. In this context, it is inconceivable that this junction has not

    been properly considered when developing this model.

    All comments regarding the gyratory should be taken in consideration with the inadequacies

    of the Aylesbury Transport Model validation in relation to the gyratory system as outlined

    above and contained within the TPP reports on the LMVR and the SEALR modelling.

    We also request again, as a matter of urgency, an explanation as to why the modelling time

    period in the AM peak has been changed to 07.00 to 08.00 from 08.00 to 09.00. This is

    wholly unrepresentative of the busiest period at this junction. Given the significance of this

    junction to the whole Aylesbury Road network a credible explanation needs to be given.

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 29 of 33

    It is also not possible for us to conduct a full assessment of the merits of this scheme as a

    full development 2036 standalone scenario has not been produced. This point of course

    applies to all other junction assessments.

    The developer does not appear to mention the Secretary of State’s 2015 decision relating to

    Hampden Fields and the gyratory. It has conveniently been airbrushed from the analysis yet

    it provides significant insight into this crucial junction. It merits consideration and

    considerable weight must be placed upon it by the decision makers.

    At the time of Secretary of State’s decision the Practical Reserve Capacity at the gyratory in

    2031 was as follows

    AM Peak PM Peak

    2031 Do Minimum -29.7 -3.3%

    2031 Do Something (with

    Hampden Fields)

    -31.8 -2.7%

    *from Inspector’s Report para 9.501 – 9.503

    The practical reserve capacity (PRC) of a traffic signal junction is a commonly used measure

    of its available space capacity. The PRC is related to the degree of saturation of a traffic

    signal junction. A positive PRC indicates that a junction has spare capacity and may be able

    to accept more traffic. A negative PRC indicates that the junction is over capacity and is

    suffering from traffic congestion. As can be seen there was a small decrease in PRC in the

    am peak, when congestion was shown to be particularly severe, and an actual increase in

    PRC in the pm peak, yet the inspector concluded

    9.504 Although the increased percentage total flow within the junction would be less

    than 5% in the morning peak and less than 1% in the afternoon peak, the

    significance of such seemingly minor increases would be heightened by the

    sensitivity of the junction in its already congested operation and its enhanced

    susceptibility to breakdown

    Even given the wholly inadequate 2022 scenarios several arms and entry points on the

    gyratory suffer from a worsening:

    In the AM peak:

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 30 of 33

    Stoke Road Lane Entry left Degree of Saturation (DoS) increased from 134.3% to

    134.5%,

    Walton Road entry DoS increased from 79,6% to 82.1%,

    Stoke Road entry left the queue increases from 201 vehicles to 207 vehicles.

    Overall the junction worsens marginally, but it does worsen.

    In the PM peak:

    Stoke Road 12/3 worsens from a DoS of 105.6% to 106.1%.

    Several junction approaches remain significantly over capacity:

    Walton Street Entry at 102.4%

    Stoke Road entry 106.8%

    Walton Street Stopline 104.5%

    There is an overall minor worsening of the junction performance in the AM peak and an

    overall minor improvement in the PM peak (-21% to -19%) but significantly the junction

    continues to operate way over capacity.

    Whilst the developer will no doubt argue that these minor movements are not significant it

    would be completely at odds with the conclusions of the Secretary of State who regarded

    “the significance of such seemingly minor increases would be heightened by the

    sensitivity of the junction in its already congested operation and its enhanced

    susceptibility to breakdown”.

    Accordingly, the standalone case, even given the inadequate 2022 scenarios, is not made.

    Cumulative Scenarios

    The cumulative scenarios are as follows:

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 31 of 33

    Practical Reserve Capacity 2036 at the gyratory system

    AM Peak PM Peak

    Inspector 2015 with

    Hampden Fields

    -31.8% -2.7%

    2036 Cumulative One -31.2% -19.3%

    2036 Cumulative Two -26.9% -17.0%

    It is clear that the gyratory is operating significantly worse in the PM peak than the scenarios

    the inspector rejected in 2015. Whatever is claimed by developers, we will have a

    dramatically worsening situation at the gyratory in the coming years in the PM peak.

    Developers of Hampden Fields, Woodlands and SEALR will claim that it is not their

    development that is making the gyratory system worsen and therefore they cannot be

    required to provide mitigation for it. However, the Highways Authority have a duty to reduce

    congestion and especially at this Air Quality Management Area. Overall from 2015 to 2036

    the performance of this junction significantly worsens so the overall strategy, which the full

    cumulative 2/3 should be addressing but demonstrably fails.

    It is also worth noting that when the Inspector made his comments the junction was ‘only’

    forecast to be operating at -31.8% (am peak) and -2.7% (pm peak) in the 2036 Cumulative 2

    scenario. Now it is operating in the very best case at -17% in the PM peak in the Cumulative

    Two scenario. The gyratory issues highlighted by the Secretary of State have not been

    answered either in the standalone or the cumulative scenarios.

    76) Wendover & Halton

    Analysis of AADT’s show a significant increase in the A41 Westbound exit slip on the A41

    from 8,165 in the 2036 Do minimum to 13,180 in the fully built out 2036 Cumulative Two.

    Although no forecast flows are published for Halton or W Road it appears probable that this

    will result in increased traffic rat running through Halton, Wendover and ending up at the

    Halton Lane/Aylesbury Road junction.

    We know from the VALP Countywide model run 1a (published December 2020) this junction

    becomes problematic and overloaded in 2033.

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 32 of 33

    It is a known weakness that the Aylesbury Transport Model is not validated to cover

    Wendover and Halton sufficiently well (if at all). Regardless of this, no attempt at modelling

    the effects of major network changes have been made. The effects on Wendover and Halton

    could be dramatic and it is very likely mitigation would be required at the Halton Lane /

    Aylesbury Road junction and other areas.

    At the very least the Highway Authority has to ensure that appropriate analysis of this area is

    made before any objectively based decision could be made.

    Transport Summary

    77) Our requests and concerns over the Aylesbury Transport Model have gone unanswered

    – they have been repeated here. Significant issues remain over the change in peak

    hours and the lack of validation at the Walton Street Gyratory system.

    78) Given the fact that the cumulative impact case includes four major road schemes and

    associated developments, Jacobs’ own recommendation is that it should be run back

    through the Countywide Model. Key Garden Town Principles are not achieved. These

    proposals encourage the use of cars and in key locations create by far the busiest roads

    in the town, encouraging yet greater use of vehicular transport. Key modal shift initiatives

    as part of the Cumulative Assessment, like the Park and Ride scheme along the A41

    corridor are now to be reviewed rather than brought forward.

    79) New roads, particularly the Southern Link Road operate at volumes 250% higher than

    the average Urban A road would, based on Department for Transport data.

    80) There appear to have been no greenhouse gases (GHG) or CO2 calculations made as

    part of the Environmental Assessment. For a cumulative impact road scheme of this

    size, the Planning Authority should want to know what the impact of increased traffic will

    be on GHGs and CO2.

    81) The Transport Assessment Addendum contains significant omissions in data which

    prejudice the public; forecast traffic flows have not been published on key links.

    82) Mitigation is proposed but these proposals have not been remodelled at key junctions.

    The complete model needs to be rerun and republished with the full mitigation schemes

    in place.

    83) The standalone using 2022 as the base year is unrealistic even by the developer’s own

    admission. It is so far outside of NPPG that it is almost certain open to challenge.

    84) A 2036 Standalone assessment is essential.

  • ___________________________________________________________________________16/01040/AOP Comments from HFAG 8 Jan 2020 Page 33 of 33

    85) Broughton Lane mitigation, required in all scenarios, is subject to a separate consenting

    regime over which the Council and developer cannot guarantee success.

    86) The Richmond Road closure / mitigation scheme attracts more traffic to the Tring Road

    corridor when the stated aim of the scheme is to reduce use of the Tring Road. This will

    be a major concern for residents.

    87) The Walton Street gyratory remains considerably overloaded in all scenarios. Even in the

    best case cumulative scenarios it is considerably worse than the scenario rejected by

    the Secretary of State in 2015.

    88) The claimed improvements in the gyratory performance are only achieved by adopting a

    wholly unrealistic earlier peak AM time of 07.00 to 08.00 when very few

    schoolchildren/parents/school buses will be present.

    89) These points taken together need much closer scrutiny with more analysis as required.

    The Highways Authority will be well aware they cannot allow a scheme to be approved

    with incomplete information, unrealistic and unreasonable scenarios demonstrating

    beyond any doubt that there significant highways deficiencies associated with amended

    Transport Assessment.

    Overall Submission Summary and Conclusion It is clear that many, significant issues must be addressed not only in the realm of transport

    but also in many other areas of this proposal. We therefore believe we are entirely justified

    in OBJECTING to application 16/01040/AOP and invite the Planning Authority to REJECT

    the application.