PT SMS
PT SMSMobilisasi & Fasilitas TemporarySurvey dan PengukuranPematokan dan BouwplankPekerjaan PersiapanPenyiapan Jalan AccessInvestigasi LapanganDetail DesignShop DrawingPelaksanaan KonstruksiPELAKSANAAN KONSTRUKSI WATER INTAKE KUPANG CITYPra KonstruksiStart1Peralatan : Excavator PC 400= 2 Unit Breaker= 2 Unit Bulldozer= 1 Unit Clamshell= 1 Unit Vibro Hummer= 1 Unit Jika dibutuhkan ( kondisi lapangan )Auger / Bored= 1 Unit Dump Truck= Disesuaikan kebutuhan Concrete Mixer= Disesuaikan kebutuhan Concrete/Activity Water Pump = isesuaikan kebutuhan Genset= 1 Unit Alat Bantu= Lump Sum PT SMS2
ExcavatorBreakerVibro HummerClamshellBulldozer
Dump TruckAuger Concrete Mixer Water PumpGenset3EXCAVATION
4Sea Water
SHEET PILING STEELSHEET PILE STEELT.120The main Steel BarSea Water
BARING
Sea WaterBekisting &CONCRETE