Pink Elephant Showcase - 7.12.2015 1

Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Embed Size (px)

DESCRIPTION

Deliverables Project Plan Rev 1.5, 1.6 M7.2 (39 issues – 10% done), M7.3 (57 issues – 46% done) Discussion, Note and Messaging Software Product Manual o Done Project Demo based on New Scenario o On Live 3

Citation preview

Page 1: Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Pink ElephantShowcase - 7.12.2015

1

Page 2: Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Brief• What have we done last week?

o Deliverableso Estimations

• What are we going to do this week?o Deliverables of the Next Week

• Project Demo

2

Page 3: Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Deliverables• Project Plan Rev 1.5, 1.6

• M7.2 (39 issues – 10% done), M7.3 (57 issues – 46% done)Discussion, Note and Messaging

• Software Product Manual - 1.0o Done

• Project Demo based on New Scenarioo On Live

3

Page 4: Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Project Plan

4

• Trello Project Management Tool

Page 5: Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Project Plan

5

• Ganttify Extension

Page 6: Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Semantic Search

6

• Brief information gathered• Initial semantic search

implementationo getrecommendedGroups method

Page 7: Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Estimations• Barış Özcanlı

7

Issue Estimation ActualCoding 3,5 hours 3,5 hours

Testing + Communication

1 hour 1 hour

Total 4,5 hours 4,5 hours

Page 8: Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Estimations• Hayri Can Akyel

8

Issue Estimation Actual

Project Plan Rev 1.5 1 hour 1 hour

Semantic Search Analysis 2 hours 2 hours

Mobile - Create Discussion 2 hours 2 hours

Mobile - Create Discussion Revision

1 hour 1 hour

Transfer Project Plan to Trello

2 hours 5 hours

Project Plan Rev 1.6, Showcase Presentation Week 11, SPM Rev 1.0

3 hours 3 hours

GitHub Issue Tracking 1 hour 1 hour

Communication 2 hours 2 hours

Total 14 hours 17 hours

Page 9: Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Estimations• Mehmet Çelikel

9

Issue Estimation Actual#206 Logout Service 0,5 hours 0,5 hours

#201, #178 Initial Semantic Search Implementation for Recommended Groups

4 hours 3 hours

#148 Messaging 4 hours 4 hours

#146 Search User 0,5 hours 0,5 hours

#204, #203, #200, #187, #186, #180 Refactoring

2 hours 4 hours

#202, #183 Bugfixing 2 hours 2 hours

Communication 2 hours 2 hours

Total 13 hours 14 hours

Page 10: Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Estimations• Orkun Koçyiğit

10

Issue Estimation ActualImplementing Join Group, Leave Group, List Popular Groups

4 hours 3 hours

Developing Data Model 1 hour 1.5 hours

Communication 0.5 hours 1 hour

Code Refactoring 2 hours 2.5 hours

Bug Fixing 1 hour 0.5 hour

Total 8,5 hours 8,5 hours

Page 11: Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Estimations• Recep Günay

11

Issue Estimation ActualCoding 8 hours 8 hours

Communication 1 hour 1 hour

Total 9 hours 9 hours

Page 12: Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Estimations• Sinan Can Sürücü

12

Issue Estimation ActualBugfixes 2 hours 2 hours

Discussion Functions Development

4 hours 5 hours

Discussion Functions Testing 0,5 hours 0,5 hours

Note Functions Development 2 hours 2 hours

Note Functions Testing 0,5 hours 0,5 hours

Github issue tracking 1 hour 1 hour

Communication 2 hours 2 hours

Total 12 hours 13 hours

Page 13: Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Estimations

13

Estimation ActualAnalysis & Coding 46,5 hours 48,5 hours

Documentation & Issue Tracking

8 hours 11 hours

Communication 8,5 hours 9 hours

Total 63 hours 68,5 hours

Page 14: Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Deliverables of Next Week

• Project Plan Rev 1.7, 1.8• Software Product Manual Rev 1.1• M8.2 - Search and Bugfixes• M8.3 - Search and Bugfixes• Project Demo

14

Page 15: Pink Elephant Showcase - 7.12.2015 1. Brief What have we done last week? o Deliverables o Estimations What are we going to do this week? o Deliverables

Thank you!

15

• We will continue to the showcase with the project demo.