Upload
balan
View
63
Download
3
Embed Size (px)
DESCRIPTION
Piling workshop
Citation preview
Pile Driveability Workshop
Saipem Singapore Ltd.
01 September 2007 Singapore, Presented by: C. Parisi (Saipem S.p.A.)
5People, Ideas, Energy
EniEniEniEniTABLE OF CONTENT
Foundation Piles Overview General Definitions Driveability Analysis Overview Soil Resistance to Driving (SRD) Pile Stick-up Analysis GRLWEAP Software Overview Pile Installation Overview Hammer Overview Hammers Refusal Criteria Pile Handling Piling Engineering Pile Complex Project Case : TTPP Project (PTT Thailand) Pile Stick-up Analysis Hand Calculation (Example) References
Foundation
5
Structures and components that carrying out
the full weight of an offshore structure
against all external actions and anchor the
platform to the sea floor
People, Ideas, Energy
EniEniEniEni
Topside Facility(Upper structure/Deck)
Piles / Foundation
Jacket (Sub structure)
Sea Bed
Sea Level
People, Ideas, Energy
EniEniEniEni
TYPES OF FOUNDATIONSTYPES OF FOUNDATIONSPeople, Ideas, Energy
EniEniEniEni
Main PileFoundation pile (multiple sections) which are driven into the seabed through the jacket legs of the platform
TYPES OF FOUNDATIONSTYPES OF FOUNDATIONS
Skirt Pile Foundation pile (one section) that are installed inside the sleeves welded around the jacket legs
People, Ideas, Energy
EniEniEniEni
TYPES OF FOUNDATIONSTYPES OF FOUNDATIONS
Suction PileLarge diameter of pile with a relatively short penetration (one or two times pile diameter) mostly used to mooring anchors in a deep sea. It offers several advantages e.g. installation that relies on pumps rather than underwater hammer. Installation involves penetration by deadweight and the reduction of pressure under the caisson cap creating a downward differential pressure. It is used where the soil at the pile base has desirable permeability.
People, Ideas, Energy
EniEniEniEni
Caisson Cap
TYPES OF FOUNDATIONSTYPES OF FOUNDATIONSPeople, Ideas, Energy
EniEniEniEni
Pin PileA large diameter of foundation pile (7296) that driven to seabed through a template guide
TYPES OF FOUNDATIONSTYPES OF FOUNDATIONSPeople, Ideas, Energy
EniEniEniEni
Pin Pile Installation Sequence
1 Driving pin piles through the template guide
2 After driven (template guide has been removed)
3 Placing the jacket to the pin piles
4 Driving skirt piles through the jacket sleeves
5 After driven
TYPES OF FOUNDATIONSTYPES OF FOUNDATIONS
Anchor PileFoundation pile (one section) for FPSO, CALM buoy or PLEM with small design penetration (e.g. 1425m)
People, Ideas, Energy
EniEniEniEni
HydroHammer
+
Follower
AnchorPile +
Padeye
PLEM
HydroHammer
+
Follower
PLEM Pile
Conductor Pile (not a foundation pile)The scope of conductor pile is only to be a template-guide to the drill string that will reach the well of the gas or oil field. It has typical outside diameter (20 or 30) with an uniform wall thickness (1). Installed in vertical position.
People, Ideas, Energy
EniEniEniEni
SOME DEFINITIONSSOME DEFINITIONS
HammerA machine that able to drive the pile into the soil up to desired penetration. Depend on its use, hammer consist of 3 types: Main Hammer / Spread Hammer
Hammer that able to drive up to the target penetration in anycondition (continuous and restart).
Back-up HammerHammer that able to replace main hammer with the same energy or more powerful.
Contingency HammerPowerful hammer to be used in case of the following contingencycircumstances: High soil resistance encountered Unexpected main hammer refusal In case main/backup hammer damage
People, Ideas, Energy
EniEniEniEni
SOME DEFINITIONSSOME DEFINITIONS
continuation......
Underwater BallastAn additional device needed for hydraulic hammer tocompensate the weight loss when it is used for under water driving.
Striking EnergyEnergy produced by hammers machinery.
Hammer EfficiencyRatio between the striking energy produced by hammer(considering internal mechanical losses) and hammernominal striking energy.
RamPart of hammer that moves up and down to generate the striking energy.
E = Mass of Ram x Stroke HeightE = Nominal of striking energy (kNm)
People, Ideas, Energy
EniEniEniEni
Ram
Anvil
SOME DEFINITIONSSOME DEFINITIONS
continuation......
Helmet (the cap)All components located underneath the hammers ram and above the pile.
Hammers Cushion BlockA relatively lightweight and flexible material (e.g.: bongossi wood, alumunium micarta, etc.). Its function is primarily to protect pile againsthigh stresses.
Anvil (the striker plate)Part of hammer that contacts with the top of pile.
Hammer Sleeve / Hammer CageThe bottom part of hammer that will fit on the top of pile to align hammerand pile.
Blow CountNumber of hammer blows per linier unit of pile penetration (bl/25cm or bl/m).
People, Ideas, Energy
EniEniEniEni
SOME DEFINITIONSSOME DEFINITIONS
continuation......
Pile RefusalThe point where the pile driving with a proposed hammer has to be stopped and other methods instituted (e.g. drilling system or using a powerful hammer).
Cantilever SectionLast restrain that holds the pile after being placed on the jacket leg (e.g. jacket top horizontal frame, jacket sleeve for skirt pile).
Resulting Free Standing LengthActual length of a pile calculated from last restrain (i.e. cantilever section).
Allowable Free Standing LengthMaximum allowed length of pile that can withstand static loads (axial and bending) without overstress.
People, Ideas, Energy
EniEniEniEni
SOME DEFINITIONSSOME DEFINITIONS
continuation......
Static StressStresses on the pile (bending and axial compressive stress) due to its weightand hammer weight.
Dynamic StressCompressive stress on pile sections that occur during driving due to hammerimpact.
People, Ideas, Energy
EniEniEniEni
SCOPE OF DRIVEABILITY ANALYSIS
Driveability analysis is performed to verify if the selected hammer is able to drive the pile up to the target penetration in any conditions (continuous or restart mode).Pile driveability is performed through steps:
1. Estimation of soil resistance to driving (SRD) in accordance with International Engineering Standards and Guidelines (e. g. API RP 2A-WSD, OTC 3969 Semple article, OTC 4205 Stevens article, OTC 6237 Puech article and other technicalarticles).
2. Static and dynamic pile stick-up analysis.3. Pile driveability evaluation by using GRLWEAP software.
People, Ideas, Energy
EniEniEniEni
SRD Estimation
Stick-up Analysis
Wave Equation Analysis (GRLWEAPTM)
Blow Count Estimation
Blow Count >Pile Refusal
Blow Count < Pile Refusal
Dynamic Stress Evaluation
Comp. Stress < 8090% SMYS
Dyn. + Static Stress > SMYS
Dyn. + Static Stress SMYS
FINISH
START
Higher StrikingEnergy
Lower StrikingEnergy
Comp. Stress > 8090% SMYS
-Soil Investigation Report-Pile Configuration
More powerful Hammer
Static Stress at Cantilever or Critical Section
Unity Check 1.0 Unity Check > 1.0Pile Make-up Modification
Lighter Hammer
Remedial Action
People, Ideas, Energy
EniEniEniEni FLOW CHARTFLOW CHART
SOIL RESISTANCE TO DRIVING (SRD)SOIL RESISTANCE TO DRIVING (SRD)
Def : Resistance of soil encountered by pile during driving.
Generally, there are 4 SRD conditions to be considered :Lower Bound Plugged and Unplugged (Core), Upper Bound Plugged and Unplugged (Core)
Lower Bound and Upper BoundEstimation of soil resistance that might be occur during driving, rangefrom minimum to maximum value.
Plugged Pile ConditionA condition where the soil inside the pile moves downward together withthe pile during driving. Soil resistance due to external friction and end bearing.
Unplugged Pile ConditionA condition where the soil inside the pile remains stationary duringdriving. Soil resistance due to internal and external pile friction, annulusend bearing.
People, Ideas, Energy
EniEniEniEni
Ultimate Pile CapacityCapacity of the pile to withstand axial load in static condition. Usually, foundation pile gain its ultimate capacity at certain period of time after driving ( Qult = Qf + Qp ). Qf = skin friction resistanceQp = total end bearing
RestartResumption of driving after interrupted for welding add-ons, hammerchange, etc. For long delay, ultimate capacity might be encountered(depends on type of soil , i.e. clay).
Pile Self Weight Penetration (SWP)Pile penetration estimation based on equilibrium between the initialassembled pile weight (with or without hammer) and the soil resistance.
People, Ideas, Energy
EniEniEniEni SOIL RESISTANCE TO DRIVING (SRD)SOIL RESISTANCE TO DRIVING (SRD)
People, Ideas, Energy
EniEniEniEni SOIL RESISTANCE TO DRIVING (SRD)SOIL RESISTANCE TO DRIVING (SRD)
People, Ideas, Energy
EniEniEniEni SOIL RESISTANCE TO DRIVING (SRD)SOIL RESISTANCE TO DRIVING (SRD)
Soil TypeSoil Type DescriptionDescription Design Design ParametersParameters CategoriesCategories
CLAY CLAY (Cohesive Soil)(Cohesive Soil)
SiltySilty CLAYSCLAYS(Cohesive Soil)(Cohesive Soil)
Cu Cu ((UndrainedUndrained
Shear Shear Strength),Strength),
(Submerged (Submerged unit weight)unit weight)
SANDSAND((CohesionlessCohesionlessSoil / Granular)Soil / Granular)
SiltySilty SANDSSANDS((CohesionlessCohesionless
Soil)Soil)
Composed of individual soil Composed of individual soil particles that slide when it is particles that slide when it is loaded. Can only be held loaded. Can only be held together by confining together by confining pressure. pressure.
(internal (internal
Friction Angle), Friction Angle),
(Submerged (Submerged unit weight)unit weight)
Very LooseVery LooseLooseLooseMedium DenseMedium DenseDenseDenseVery DenseVery Dense
ROCKROCKComposed of material that Composed of material that bond each others, e.g. bond each others, e.g. sandstone, limestone, sandstone, limestone, conglomerate, etc. conglomerate, etc.
UCSUCS(Unconfined (Unconfined Compressive Compressive
Strength)Strength)
Very WeakVery WeakWeakWeakModerately StrongModerately StrongStrongStrongVery StrongVery Strong
Composed of fines soil Composed of fines soil particles (
People, Ideas, Energy
EniEniEniEni SOIL RESISTANCE TO DRIVING (SRD)SOIL RESISTANCE TO DRIVING (SRD)
Calcareous Silica SILT
Calcareous Silica SAND
CLAY HARD CLAY
ROCKSAND
PILE STICKPILE STICK--UP OVERVIEWUP OVERVIEW
EachEach foundationfoundation or conductor pile on or conductor pile on whichwhich a a hammerhammer willwillbebe placedplaced shallshall bebe checkedchecked forfor loadsloads causedcaused byby itselfitself weightweightand and installationinstallation equipmentequipment (e.g. (e.g. stabbingstabbing guide, guide, internalinternalclampclamp, , etcetc.)..).
TheseThese loadsloads maymay bebe limitinglimiting factorsfactors in in establishingestablishing the the maximummaximum lengthlength of the of the addadd--onsons or the or the suitablesuitable spreadspreadhammerhammer forfor the the skirtskirt pilespiles in in orderorder notnot toto damagedamage the pile.the pile.
ToTo avoidavoid failurefailure of the pile of the pile installationinstallation due due toto the the aboveabovementionedmentioned loadsloads, the , the pilespiles and and hammerhammer equipmentequipment shouldshouldbebe designeddesigned toto satisfysatisfy bothboth strengthstrength and and stabilitystability criteriacriteria..
People, Ideas, Energy
EniEniEniEni
PILE STICK-UP ANALYSIS
Scope of the stick-up analysis are :1. Evaluate the allowable free-standing length (Lfs) for a given pile make-up / hammer configuration or ;
2. Verify the Rfs (Resulting free-standing length) is lesser than Lfs for a given pile section in order not to damage the pile sections during placement of the hammer spread and during the pile driving up to the target penetration.
People, Ideas, Energy
EniEniEniEni
PILE STICK-UP ANALYSIS
Calculation of pile stick-up is performed according to API RP 2A WSD, 2002 edition (American Petroleum Institute Recommended Practice for Planning, Designing and Constructing Fixed Offshore Platforms -Working Stress Design).
The following conditions are verified : Static pile stick-up - Each column pile section must resist axial loads
and static bending that are generated during initial hammer placement.fs = fa+fb
Dynamic pile stick-up - Each free-standing pile section must resistdynamic stresses that occur during driving.
a) f dyn 8090 of SMYS b) fs +f dyn 100% SMYS
People, Ideas, Energy
EniEniEniEni
Where : fs = Static Stress, MPafa = Actual Compressive Stress, MPa
= Axial Load / Apile on cantilever sectionSMYS = Specified Minimum Yield Strength of the pile, MPa
fb = Actual Bending Stress, MPa= Bending Moment / Section Modulus
F dyn = Dynamic Stresses, MPa
where:mh = weight of the hammer, cap, and
leads (kN); mL = weight of the pile (kN);Rfs = free standing length of the pile (m); C.o.G.= distance of mh barycentre from pile
head (m); = inclination of the pile/ true batter
(degrees).
People, Ideas, Energy
EniEniEniEni
The bending moment and axial load acting in the critical section have been evaluated as:M = mh x (Rfs + C.o.G.) x sin (alpha) + mL(Rfs / 2) x sin ()N = (mh + mL) x cos ()
API Minimum Bending Moment API Minimum Bending Moment (Section 6.10.4) :(Section 6.10.4) :0.02 x hammer weight x resulting free standing length
PILE STICK-UP ANALYSIS
Cantilever section
PILE STICK-UP ANALYSIS
a) Cantilever section at top jacket frame (Main pile, Conductor pile)
b) Cantilever section at pile sleeve(Skirt pile)
c) Le = K x RfsK = 2.1 (required by API-RP2A WSD)Rfs = Free standing length from
cantilever section.
People, Ideas, Energy
EniEniEniEni
60tD
,
c
cc
c CrKlfor
CrKl
CrKl
FyCrKl
Fa Fafa
0.1
'1
.
+
FbFefafbCm
Fafa
0.16.0
+Fbfb
Fyfa
( )22
/2312'
rklEFe =
15.0Fafa
0.1+Fbfb
Fafa
0.1Fafa1. 2. For
a.
b.
3. For
Cm = Minimum reduction factor (Sec.6.10.4) = 1.0K = Effective length factor (Sec.6.10.4) = 2.1fa = Actual compressive stressfb = Actual bending stress
People, Ideas, Energy
EniEniEniEni
Combined Stress (API RP2A-WSD 2002)
Where :
People, Ideas, Energy
EniEniEniEni
There is SMYS reduction related with pile wall thickness (steel plate).Ex : EN 10025
1
Self Weight Penetration
Rfs
For conductor pile, 1 degree inclination (include tolerance) should be considered. For main pile, pile true batter should be applied.
Free standing length for lead section should considering the pile self weight penetration
People, Ideas, Energy
EniEniEniEni
People, Ideas, Energy
EniEniEniEni
Under Water Ballast
For skirt pile, submerged weight of the pile should be considered since some part of the pile are under water (buoyancy effect).
For hydraulic hammer, hammer weight should consider hammer configuration (with or without under water ballast).
People, Ideas, Energy
EniEniEniEni PILE FAILURE MODE (BUCKLING)PILE FAILURE MODE (BUCKLING)
GRLWEAP : Globe Rausche Likins WaveEquation Analysis of Pile Driving
Corporate software used for pile driveabilityanalysis.
Pile driving program which simulates motionand forces in a foundation pile when drivenby an impact hammer or a vibratory hammer. The program computes the following:
1. The blow count of a pile under one or more assumed ultimate resistancevalues and other dynamic soilresistance parameters, given a hammerand driving system (helmet, cushion, etc.)
2. The axial stresses in a pile3. The energy transferred by the hammer
to the pile for each capacity analyzed Mathematical model of the soil, hammer and
pile. Soil is modeled by a series of springs and
dashpots.
Schematic Model
Soil -Pile
HammerHammer Cushion
Pile Cushion Pile
Spring
Hammer Frame
GRLWEAP OVERVIEWPeople, Ideas, EnergyEniEniEniEni
Hammer and pile is modeled by a series lumped mass connected by springs.
MAIN INPUT DATA FOR GRLWEAP TMPeople, Ideas, EnergyEniEniEniEni
Main Screen
Pile InformationPeople, Ideas, Energy
EniEniEniEni MAIN INPUT DATA FOR GRLWEAP TM
Soil DataPeople, Ideas, Energy
EniEniEniEni MAIN INPUT DATA FOR GRLWEAP TM
MAIN INPUT DATA FOR GRLWEAP MAIN INPUT DATA FOR GRLWEAP TMTM
Hammer Data (hammer type, striking energy, efficiency, helmet weight)
Hammer Cushion Data (area, elastic modulus, thickness, coefficient of restitution). Hammer cushion e.g. Bongossi, Conbest, Micarta, Alluminium, Monocast, Steel wire.
Pile Information (pile section length, outside diameter, wallthickness, yield strength, restart and target penetration)
Soil Data (quake and damping parameters, unit shaftresistance, toe resistance, ultimate capacity)
People, Ideas, Energy
EniEniEniEni
MAIN PRACTICAL OUTPUT DATAMAIN PRACTICAL OUTPUT DATA
Blow count vs penetration depth Dynamic stress (i.e. max. compressive stress) along the pile sections
during driving ENTHRU energy (transferred energy by hammer to the pile for each
ultimate soil resistance analyzed). Global efficiency (ENTHRU energy divided by hammer nominal
striking energy)
Based on these results, the following can be indirectly evaluated: Driving pile in lower bound (low soil resistance) Driving pile in upper bound (high soil resistance) Driving pile in full set up (ultimate static capacity) or restart
People, Ideas, Energy
EniEniEniEni
MAIN PRACTICAL OUTPUT DATAPeople, Ideas, Energy
EniEniEniEni
MAIN PRACTICAL OUTPUT DATAPeople, Ideas, Energy
EniEniEniEni
DRIVING RECORD
During pile driving, it is very important to record the following parameters :
Number of blow count per meter or 25 cm.
Hammer striking energy Pile self weight penetration
with or without hammer Any additional information
during pile driving process (e.g. pile refusal, hammer stops, etc)
Manual Driving Record
People, Ideas, Energy
EniEniEniEni
People, Ideas, Energy
EniEniEniEni
Hydraulic Hammer (Menck) Driving Record
DRIVING RECORD
BACK ANALYSIS
Comparison between the estimated number of blow count obtained from driveability analysis with the actual blow count occurs in field.
Back analysis is useful for better estimation of soil resistance when driving the future pile in the nearby area.
Blow Count vs. Penetration
0
10
20
30
40
50
60
0 50 100 150 200 250 300Blow, bl/m
P
e
n
e
t
r
a
t
i
o
n
,
m
In Field IKA C1
In Field IKA C2
In Field IKA C3
In Field IKA C4
Estimated_Lower Plug
Estimated_LowerUnpluggedEstimated_Upper Plug
Estimated_UpperUnplugged
People, Ideas, Energy
EniEniEniEni
GENERAL CORRELATION GENERAL CORRELATION STICKSTICK--UP & HAMMER ENERGYUP & HAMMER ENERGY
People, Ideas, Energy
EniEniEniEni
Longer Pile StickLonger Pile Stick--up up Length + Heavier Length + Heavier HammerHammer
Less residual dynamic stressLess residual dynamic stress
STICKSTICK--UPUPShorter Pile StickShorter Pile Stick--up up Length + Lighter Length + Lighter HammerHammer
More residual dynamic stressMore residual dynamic stress
HIGHER ENERGYHIGHER ENERGYLow number of blow count ;Low number of blow count ;High dynamic stresses ;High dynamic stresses ;Hammer striking energy might be limitedHammer striking energy might be limitedHAMMER HAMMER
ENERGYENERGYLOWER ENERGYLOWER ENERGY
High number of blow count ;High number of blow count ;Low dynamic stresses ;Low dynamic stresses ;Pile refusal might be encounteredPile refusal might be encountered
PILE INSTALLATION
General description of a Foundation Pile installation:1. Moving piles from cargo barge to installation vessel.2. Upending Lead section by means ILT (Internal Lifting Tool),
crawler crane or upending clamp.3. Stabbing Lead section inside the jacket leg.4. Install bear cage on top lead section.5. Lifting and stabbing 1st add-on and weld.6. Welding is done either in manual mode (SMAW) or semi-
automatic mode (FCAW) or a mix of both system. The weld integrity is checked by Ultrasonic Testing (UT).
People, Ideas, Energy
EniEniEniEni
PILE INSTALLATIONcontinuation..
7. Remove the bear cage from the piles .8. Install the hammer on pile top.9. Drive pile up to the foreseen penetration.10. Perform cut-off of damaged part due to hammers impact.11. The same installation procedure will be repeated for each add-on
up to reach the design penetration or refusal.12. Jacket leveling13. Upon completion of the pile driving and leveling, the piles are
welded to the jacket on top of legs (shims or collars).
People, Ideas, Energy
EniEniEniEni
People, Ideas, Energy
EniEniEniEni
People, Ideas, Energy
EniEniEniEni
People, Ideas, Energy
EniEniEniEni
People, Ideas, Energy
EniEniEniEni
JACKETS DISASTER VIDEO
People, Ideas, Energy
EniEniEniEni
PILE FREE RUNNING
Pile suddenly starts to fall rapidly after receiving hammer impact.
Several possible reasons for this occurrence :- The presence of weak soil layer below hard soil layer, e.g. clay layer
below rock. High hammers striking energy is required to break through rock layer , but the energy is excessive for driving in clay.
- Gas deposit encountered.- Etc.
A conical reduction or a follower can be used when:
The outside diameter of the pile is not suitable for the hammers anvil/sleeve
It is necessary to drive the pile above water (diesel or steam hammer)
There is interference between hammer sleeve and the jacket leg sleeves top
FOLLOWERFOLLOWERPeople, Ideas, Energy
EniEniEniEni
PAD EYE VS HAMMER SLEEVE CLASH
If pad eye is presence on top of pile, a clash check should be conducted between hammer sleeve and the pad eye.
Clashes
People, Ideas, Energy
EniEniEniEni
HAMMER SLEEVE VS TOP OF JACKET LEG CLEARANCE
Remaining length of the pile from top of jacket leg (clearance +hammer sleeve) should be appropriate with bear cage height (height of bear cage welding area).
Clearance
People, Ideas, Energy
EniEniEniEni
RemainingLength
RemainingLength
BEAR CAGE (EXTERNAL PILE CLAMP)BEAR CAGE (EXTERNAL PILE CLAMP)
Bear cage holds the two section of the pile (e.g. lead section plus 1st add-on) during the offshore welding operations.
People, Ideas, Energy
EniEniEniEni
INTERFERENCE OF PILE TOPINTERFERENCE OF PILE TOP
IfIf the the inclinationinclination of the of the jacketjacket legslegs isis tootoo high, high, therethere isis possibilitypossibility of of interferenceinterference of pile top. of pile top. ThereforeTherefore, the , the sequencesequence of pile of pile installationinstallationshouldshould bebe concernedconcerned..
People, Ideas, Energy
EniEniEniEni
People, Ideas, Energy
EniEniEniEniINSTALLATION CHECK LISTINSTALLATION CHECK LIST
Hammers anvil / sleeve vs. piles outside diameter Pile stick-up vs. spread hammer Hammers sleeve height vs. jacket leg / template top sleeve clearance Hammers sleeve overall outside diameter vs. jacket leg clearance Bear cage overall O.D. vs. conductor piles O.D. interference Hammers sleeve overall O.D. vs. conductor piles O.D. clearance Conductor pile O.D. vs. conductor piles O.D. clearance Bear cage weld window elevation vs. spread hammer sleeve heights Minimum self piles penetration vs. spread hammer Piles elevation vs. final piles cut-off length Foundation piles height vs. after intermediate cut-off I.D. hammer sleeve vs. O.D. skirt pile with weld beads (total gap min. 1)
TYPES OF HAMMERSTYPES OF HAMMERS
Depending on the source of energy : Diesel hammers Steam hammers Hydraulic hammersThese hammers are categorized as impact hammers.
Other type of hammer (non-impact hammer) are vibration hammers.
People, Ideas, Energy
EniEniEniEni
People, Ideas, Energy
EniEniEniEni
Hydraulic Hammer Steam Hammer
Anvil
Cushion Block
Pile Sleeve
Ram
Piston Rod
Steam Inlet
Shock Absorber
Suppressor
Clamp Gear Case
Ram
Fuel Injection Device
Anvil
Cushion
Diesel Hammer
People, Ideas, Energy
Vibratory Hammer
EniEniEniEni
MAIN DIESEL HAMMERS IN SAIPEM ASSETSMAIN DIESEL HAMMERS IN SAIPEM ASSETS
LOW RANGE : D30 (102 kN-m) D46 (165 kN-m) D55 (170kN-m) MEDIUM RANGE : D62 (223 kN-m) - D80 (288 kN-m) HIGH RANGE : D100 (360 kN-m) - D200 (666 kN-m)
HAMMER EFFICIENCY = Range from 60% to 70%
EASY TO USE ( TALL and LIGHT) BUT LOW CAPABILITIES FOR LARGE DIAMETER PILES
CAN BE UTILIZED ONLY ABOVE WATER
MAX. BATTER = 45 (by using cylinder length extension)
THE STRIKING ENERGY CAN BE SET ONLY TO FOUR VALUEe.g. D100-13 : 60%, 77.2%, 89.7%, 100% of nominal value
PROVIDED WITH CUSHION TO AVOID DAMAGING THE ANVIL e.g.: Aluminium, Micarta, Monocast, Combest, Steel wire, etc.
HAMMER SLEEVE / ANVIL MUST BE SUITABLE WITH PILES DIAMETER
People, Ideas, Energy
EniEniEniEni
MAIN DIESEL HAMMERS IN SAIPEM ASSETSMAIN DIESEL HAMMERS IN SAIPEM ASSETS
Diesel Hammer Settings Energy (by Delmag Manufacturer):
People, Ideas, Energy
EniEniEniEni
Energy Energy SettingsSettings
DelmagDelmagD55D55
DelmagDelmagD62D62--1212
DelmagDelmagD80D80--1212
DelmagDelmagD80D80--2323
DelmagDelmagD100D100--1313
Setting 1Setting 1 100 %100 % 100 %100 % 100 %100 % 100 %100 % 100 %100 %
Setting 2Setting 2 ~ 83 %~ 83 % ~ 83 %~ 83 % ~ 83 %~ 83 % ~ 89.7 %~ 89.7 % ~ 89.7 %~ 89.7 %
Setting 3Setting 3 ~ 66 %~ 66 % ~ 66 %~ 66 % ~ 66 %~ 66 % ~ 73.6 %~ 73.6 % ~ 77.2 %~ 77.2 %
Setting 4Setting 4 ~ 50 %~ 50 % ~ 50 %~ 50 % ~ 68 %~ 68 % ~ 60 %~ 60 % ~ 65 %~ 65 %
People, Ideas, Energy
EniEniEniEni
Example of Monocast MC-901 cushion block that is inserted between ram and anvil. It may last from approximately 5000 to 15000 blows (depends on soil type and hammer use)
People, Ideas, Energy
EniEniEniEni
MAIN STEAM HAMMERS IN SAIPEM ASSETSMAIN STEAM HAMMERS IN SAIPEM ASSETS
LOW RANGE : MRBS1800 (257 kN-m) MRBS3000 (441 kN-m) MEDIUM RANGE : MRBS4600 (676 kN-m) HIGH RANGE : MRBS5000S (735 kN-m)
HAMMER EFFICIENCY = Range from 60% to 85% normally
STEAM HAMMERS REQUIRES LARGE BOILERS MORE DIFFICULT TO HANDLE (TALL and HEAVY)
CAN BE UTILIZED ONLY ABOVE WATER WITH 10 MAX. BATTER
PROVIDED WITH CUSHION TO AVOID DAMAGING THE ANVILBongossi wood (hard wood)
HAMMER SLEEVE / ANVIL MUST BE SUITABLE WITH PILES DIAMETER
People, Ideas, Energy
EniEniEniEni
People, Ideas, Energy
EniEniEniEni
Example of Bongossi Wood cushion that is inserted inside the anvil. It may last from approximately 3000 to 5000 blows.
Example of Anvil.Due to hammers anvil shape (steps) for each suitable pile OD, there are minimum and maximum allowable pile wall thickness that can be driven.
People, Ideas, Energy
EniEniEniEni
MAIN HYDRAULIC HAMMERS IN SAIPEM ASSETSMAIN HYDRAULIC HAMMERS IN SAIPEM ASSETS
LOW RANGE : MHU 195 (191 kN-m) MHU220 (215 kN-m) MEDIUM RANGE : MHU 600I (588 kN-m) MHU 600T (659 kN-m) HIGH RANGE : MHU 1000 (1000 kN-m) MHU 3000 (2945 kN-m)
HAMMER EFFICIENCY = Range from 85% to 95%
CAN BE UTILIZED ABOVE AND UNDER WATER WITH 14 MAX. BATTERAbove water, efficiency can be in excess of 100%
For under water driving, under water ballast is used to compensate weight loss
AVAILABLE ALSO FOR VERY LARGE WATER DEPTH
ABLE FOR AUTOMATIC RECORD DRIVING PARAMETERS(Blow count, striking energy, penetration depth, etc)
HAMMER SLEEVE / ANVIL MUST BE SUITABLE WITH PILES DIAMETER
People, Ideas, Energy
EniEniEniEni
Under Water Ballast
People, Ideas, Energy
EniEniEniEni
VIBRATION HAMMERSVIBRATION HAMMERS
Typically for onshore applications. Efficient for shorter penetrations (piles for sub sea templates
and manifolds). Effective and quick installation. Vibratory driving occurs relatively easily in non-displacement
piles such as open-end pile or caissons. Vibratory hammer can also be adapted to work underwater
with an additional underwater kit (e.g. ICE brand).
HAMMER FREQUENCY = 4001400 VPM
People, Ideas, Energy
EniEniEniEni
Consists of two major components : Gear case and suppressor.
The gear case contains eccentric weights, which rotate in a vertical plane to create vertical vibration.
The suppressor contains rubber elastomers, which dampen the vibration reaching the crane by 90% or more.
A hydraulic clamp, bolted to the bottom of the gear case, transmits vibration to the pile attached.
People, Ideas, Energy
EniEniEniEni
People, Ideas, Energy
EniEniEniEni
People, Ideas, Energy
EniEniEniEniTypes of Hammer
DescriptionHydraulic Steam Diesel Vibratory
Efficiency 85%-95% 60%-85% 60%-70% Up to 100%
Both
-
0100%
-(Vibration
per minute)
Above/Under Water Driving
Both(equipped with under
water ballast for driving
below water)
Above water only
Above water only
Hammer Cushion - Bongossi
Allumunium, Micarta,
Monocast, Combest, Steel Wire,
etc.Energy Setting 0100% 0100%
4 settings only
Blow Count Record Automatic Manual Manual
CRITERIA FOR PILE REFUSALCRITERIA FOR PILE REFUSAL
From API RP 2A-WSD 2000 Section 12.5.6 (to be used only if the event that no other provisions are included in the installation contract):Pile driving refusal with a properly operating hammer is defined as the point where pile driving resistance exceeds either 300 blows per foot (0.3 m) for five consecutive feet (1.5 m) or 800 blows per foot (0.3 m) of penetration.If there has been a delay in pile driving operations for one hour or longer, the refusal criteria stated above shall not apply until the pile has been advanced at least one foot (0.3 m) following the resumption of pile driving. However, in no case shall the blow count exceed 800 blows for six inches (152 mm) of penetration.
People, Ideas, Energy
EniEniEniEni
CRITERIA FOR PILE REFUSALCRITERIA FOR PILE REFUSAL From hammer manufacturer (Menck):
People, Ideas, Energy
EniEniEniEni
CRITERIA FOR PILE REFUSALCRITERIA FOR PILE REFUSAL
From hammer manufacturer (Delmag):Delmags official policy is that driving should be terminated at a penetration rate of less than 20 mm per 10 impacts (152 blows per foot). Delmags policy is that warranty conditions are voided at penetration rates less than (i.e. blow counts greater than) 240 blows per foot.Driving with every Delmag Diesel Hammer at blow count above this is possible intermittently, but prolonged operation at these higher counts only damages the pile, hammer, and related equipments. A larger hammer should be used.
People, Ideas, Energy
EniEniEniEni
CRITERIA FOR PILE REFUSALCRITERIA FOR PILE REFUSAL Saipem Mediterranean Services Criteria for Refusal
(Doc. CR-SMS-INST-305-E) :Hydraulic Hammer Continuous Driving
250 blows per 0.25 m of penetration over maximum distance 1.50 m in one stretch.
After Successful Restart or When Experiencing Higher Soil Resistance350 blows per 0.25 m of penetration over maximum distance 0.75 m in one stretch.
End of Driving600 blows per 0.25 m of penetration over a short distance (0.25 m).
Accidental Refusal (Only When Experiencing Hard Layers or Rocks)25 blows per 0.025 m of penetration.
Re-startBlow count shall not exceed either 240 blows per 0.15 m of penetration or 600 blows per 0.25 m of penetration.
People, Ideas, Energy
EniEniEniEni
CRITERIA FOR PILE REFUSALCRITERIA FOR PILE REFUSAL Saipem Mediterranean Services Criteria for Refusal
(Doc. CR-SMS-INST-305-E) :Steam Hammer Continuous Driving
200 blows per 0.25 m of penetration over maximum distance 1.50 m in one stretch.
After Successful Restart or When Experiencing Higher Soil Resistance250 blows per 0.25 m of penetration over maximum distance 0.75 m in one stretch.
End of Driving350 blows per 0.25 m of penetration over a short distance (0.25 m).
Accidental Refusal (Only When Experiencing Hard Layers or Rocks)25 blows per 0.025 m of penetration.
RestartBlow count shall not exceed either 240 blows per 0.15 m of penetration or 350 blows per 0.25 m per 0.25 m penetration.
People, Ideas, Energy
EniEniEniEni
CRITERIA FOR PILE REFUSALCRITERIA FOR PILE REFUSAL Saipem Mediterranean Services Criteria for Refusal
(Doc. CR-SMS-INST-305-E) :Diesel Hammer
20 blows per 0.025 m of penetration (20 mm per 10 blows) 200 blows per 0.025 m of penetration 240 blows per 0.30 m of penetration.
These criteria are applied independently from continuous driving or restart, interrupted previously for at least one hour.
People, Ideas, Energy
EniEniEniEni
PILE HANDLINGPILE HANDLING
Upending by main cranes (S7000) and lifting clamps Upending by main vessel crane and crawler crane Upending by upending clamp Launching longitudinally (utilised only in the past) Launching transversally (utilised in the past)
TO BE VERIFIED: GLOBAL AND LOCAL PILE STRESSES
People, Ideas, Energy
EniEniEniEni
PILE HANDLING (S3000 AND CASTORO 8)PILE HANDLING (S3000 AND CASTORO 8)
SKIRT PILES On board: 6065m (S3000) or 7075m (Castoro 8) Longer lifted length (upending clamp): 130m, 50m overhanging
MAIN PILES Longer lead section length: 7075m (due to hook height) Longer add-on section: 3840m (due to practicality) Use bear cages or turnbuckles according to main on board practice
TO BE VERIFIED: GLOBAL AND LOCAL PILE STRESSES
People, Ideas, Energy
EniEniEniEni
INSTALLATION AIDS FOR PILE INSERTIONINSTALLATION AIDS FOR PILE INSERTION
Skirt pile lateral guide Main docking pile guide Bear cages to help main pile welding operation and access Turnbuckles to help main pile welding operation and access
TO BE VERIFED: LOCAL IMPACT STRESSES ONTO AIDS
People, Ideas, Energy
EniEniEniEni
CONNECTION PILE TO PLATFORMCONNECTION PILE TO PLATFORM
Grouting Crown plates Pins for small manifolds and shorter piles
TO BE VERIFED: LOCAL IMPACT STRESSES ONTO AIDS
People, Ideas, Energy
EniEniEniEni
CONNECTION PILE TO PLATFORMCONNECTION PILE TO PLATFORMPeople, Ideas, EnergyEniEniEniEni
GROUTING
CROWN SHIM
CONNECTION PILE TO PLATFORMCONNECTION PILE TO PLATFORMPeople, Ideas, EnergyEniEniEniEni
EPIC PILING ENGINEERING (SKIRT PILE)EPIC PILING ENGINEERING (SKIRT PILE)
Establish previous comparable cases Evaluation of stick up and driveability of some diameters Consideration of platform variation vs pile diameter Consideration of soil strata features vs penetration Avoid to reach very hard soil strata If unavoidable, start driving before the hard soil Reduced penetration means easier installation but also reduced
capability to carry foundation loads Increased penetration means harder driving but increase of capability
to carry foundation loads Book on time hammer spread and handling spread Establish contingency cases (drilling and jetting)
BALANCE TO BE PERFORMED FOLLOWING EXPERIENCE AND GOOD SENSE
People, Ideas, Energy
EniEniEniEni
EPIC PILING ENGINEERING (MAIN PILE)EPIC PILING ENGINEERING (MAIN PILE)
Establish previous comparable cases Evaluation of stick up and driveability of some diameters Consideration of platform variation vs pile diameter Consideration of soil strata features vs penetration Avoid to reach very hard soil strata If unavoidable, start driving before the hard soil with final hammer Reduced penetration means easier installation but also reduced
capability to carry foundation loads Increased penetration means harder driving but increase of capability
to carry foundation loads Book on time hammer spread, handling spread Establish contingency cases (drilling and jetting)
BALANCE TO BE PERFORMED FOLLOWING EXPERIENCE AND GOOD SENSE
People, Ideas, Energy
EniEniEniEni
T&I PILING ENGINEERINGT&I PILING ENGINEERING
Pile diameter established by others Establish previous comparable cases Evaluation of stick up and driveability Consideration of soil strata features vs penetration Avoid to reach very hard soil strata If unavoidable, start driving before the hard soil Book on time hammer spread, handling spread Establish contingency cases (drilling and jetting)
BALANCE TO BE PERFORMED FOLLOWING EXPERIENCE AND GOOD SENSE
People, Ideas, Energy
EniEniEniEni
VERIFICATION TO BE PERFORMEDVERIFICATION TO BE PERFORMED
Free standing length vs reaction on bear cages Verify the vessel practical capabilities not only theoretical Establish a plan to maximise number of contemporary piles on which
installation shall occur Book relevant bear cages or turnbuckle spread (if requested) Bear cage weld window elevation vs spread hammer sleeve height In case of multiple driving verify if top of pile do not interfere (due to free
standing length vs batter) For skirt piles verify clearances between overall diameter of hammer bell
with jacket leg For main pile verify the clearances between preinstalled piles including
pile deformation due to self weight Hammer sleeve height vs top of jacket leg/template clearance If self weight penetration of initial assembled pile can reach the 1st
intermediate penetration, pile is not necessary to be driven.
People, Ideas, Energy
EniEniEniEni
A TYPICAL PILE COMPLEX PROJECTA TYPICAL PILE COMPLEX PROJECTPTT ThailandPTT Thailand
People, Ideas, Energy
EniEniEniEni
People, Ideas, Energy
EniEniEniEni PROJECT OVERVIEW PROJECT OVERVIEW PROJECT :PTT RISER Platform (PRP) Third Transmission Pipeline Project (TTPP), Erawan Field, Gulf of Thailand.
CLIENT :PTT Public Company Limited
CONSULTANT :Bechtel International Inc.
CONTRACTOR :SAIPEM Asia Sdn.Bhd. / SOME Pte.Ltd.Consortium
PRP COMPLEX CONSISTS OF :PRP Jacket (8 Legged) Flare Tripod Pedestrian Tripod
WATER DEPTH :63 m depth
INSTALLATION VESSEL :Castoro 8
People, Ideas, Energy
EniEniEniEni LOCATION MAPLOCATION MAP
PRP Complex
Platform Location
1,003,550
1,003,600
1,003,650
1,003,700
1,003,750
752,500 752,550 752,600 752,650 752,700 752,750 752,800
Easting (m)
N
o
r
t
h
i
n
g
(
m
)
Pedestrian Tripod
Flare Tripod
PRP Jacket
People, Ideas, Energy
EniEniEniEniPRP JACKET DRAWINGPRP JACKET DRAWING
Elevation Row 1 Elevation Row A
Jacket Framing Plan
People, Ideas, Energy
EniEniEniEni PRP JACKETPRP JACKETFOUNDATION PILES INFORMATIONFOUNDATION PILES INFORMATION
Legend :Available Spread Hammer
Proposed Hammer
Analyzed Hammer
Platform OD, WTOD, WTSMYSSMYS[MPa][MPa]
ConfigConfig..TotalTotal
LengthLength
345345414414
Org :Org :196.7m196.7m
Vertical Vertical TargetTargetPent.Pent.
SpreadSpreadHammersHammers
126m126m(127m)(127m)
D100D100--13, 13, MHU 600B,MHU 600B,MHU 800S,MHU 800S,MHU 1000, MHU 1000, MHU 1700MHU 1700
PRP JacketPRP Jacket(8 No. Piles)(8 No. Piles)
LegLeg A1A1--4 & B14 & B1--44Batter = 8.05Batter = 8.05
48,48,1.53.251.53.25
Lead Lead SectionSection
++4 Add 4 Add --
onsons
10
0
50
100
130
z (m)
20
30
40
60
70
80
90
110
120
SRD (kN)10,000 50,000
SRD Lower Bound
SRD Upper Bound
R ultimate API 2000-Fugro
R ultimate Static Capacity API 2000
People, Ideas, Energy
EniEniEniEni PRP JACKETPRP JACKETESTIMATED SOIL RESISTANCE TO DRIVINGESTIMATED SOIL RESISTANCE TO DRIVING
z (m)SRD Estimated
SRD In Field (Re-Created from Driving Record)
People, Ideas, Energy
EniEniEniEniPRP JACKETPRP JACKET
BACK ANALYSISBACK ANALYSIS
0
100
140
20
40
60
80
120
SRD (kN)10,000 20,000 30,000 40,000 50,000
People, Ideas, Energy
EniEniEniEni PRP JACKETPRP JACKETPile MakePile Make--up Modification Considerationup Modification Consideration
Considering original pile make upDriving resumption at 99.0 m depth after welding last add-on (P5) using MHU 600B was foreseen too risky due to high estimated Soil resistance expected (>40MN @ 100% Rult) after set-up effect (high dynamic stresses and number of blow count close with the limit, 1000 bl/m).Reducing hammer striking energy would cause hammer unable to overcome soil resistance at this depth. More powerful hammer (MHU 1000, MHU 1700) was not feasible to be used due to stick up problem. MHU800S was proposed as back-up of MHU600B to drive the last two add-ons (No stick-up problem) and to increase slightly the probability to resume driving at 99m.Based on Pile monitoring (Driving records) of existing Platforms of the Field, a Soil set-up analyses were conducted by Geotechnical specialists to estimated a more accurate SRD in continuous driving and after a long delay (24 h set-up).Final decision was to reduce the risk to have refusal and a new pile make up was advised.Considering new pile make up This configuration moved up last intermediate penetration from 99.0 m to 94.0 m. It was certain that MHU 600B able to resume and complete the driving of last add-on (P5) without any problem. However, this would reduce total length assembled pile and some pile would not reach target penetration.
PRP JACKETPRP JACKETMain Pile Configuration Main Pile Configuration -- ORIGINALORIGINALPeople, Ideas, Energy
EniEniEniEni
Original Lead Section Length
Make-upLength
[m]Cut-off
[m]
Lead Section 69.05 -1
1
1
6.212
1st Add-on 39.40
2nd Add-on 34.50
3rd Add-on 32.20
4th Add-on 31.10
People, Ideas, Energy
EniEniEniEni PRP JACKETPRP JACKETMain Pile Configuration Main Pile Configuration -- MODIFIEDMODIFIED
Modified Lead Section Length
Make-upLength
[m]Cut-off
[m]
Lead Section 63.81 -1
1
1
5.242
1st Add-on 39.40
2nd Add-on 34.50
3rd Add-on 32.20
4th Add-on 31.10
People, Ideas, Energy
EniEniEniEni FLARE TRIPODFLARE TRIPODFOUNDATION PILES INFORMATIONFOUNDATION PILES INFORMATION
Platform OD, WTOD, WTSMYSSMYS[MPa][MPa]
Conf.Conf.TotalTotal
LengthLength
345345 153.6m153.6m
Vertical Vertical TargetTargetPent.Pent.
SpreadSpreadHammersHammers
84 m84 m(84.7m)(84.7m)
D62-22, D80-23,D100-13, IHCS280, MHU 270T
Flare TripodFlare Tripod(3 No. Piles)(3 No. Piles)
True Batter = True Batter = 7.817.81
30,30,0.751.50.751.5
Lead Lead SectionSection
++5 Add 5 Add --onsons
Legend :Available Spread HammerProposed and Adopted HammerAnalyzed Hammer
FLARE TRIPODFLARE TRIPODPile Configuration Pile Configuration -- ORIGINALORIGINALPeople, Ideas, Energy
EniEniEniEni
Make-upLength
[m]Cut-off
[m]
Lead Section 69.50 -
1
1
1
1
5th Add-on 16.50 3.292
1st Add-on 22.00
2nd Add-on 17.65
3rd Add-on 17.654th Add-on 17.65
Original Length
People, Ideas, Energy
EniEniEniEni FLARE TRIPODFLARE TRIPODPile Configuration Pile Configuration -- MODIFIEDMODIFIED
Modified Length
Make-upLength
[m]Cut-off
[m]
Lead Section 69.50 -
1
1
1
1
5th Add-on 16.50 3.292
1st Add-on 22.00
2nd Add-on 17.65
3rd Add-on 23.654th Add-on 11.65
SRD Lower BoundSRD Upper BoundSRD Ultimate Static Capacity API 2000
People, Ideas, Energy
EniEniEniEni FLARE TRIPODFLARE TRIPODESTIMATED SOIL RESISTANCE TO DRIVINGESTIMATED SOIL RESISTANCE TO DRIVING
SRD (kN)
6
0
30
64
88
z (m)
12
18
24
36
42
48
56
72
80
5,000 10,000 15,000 20,000 25,000
SRD Ultimate Static Capacity API 1986SRD Lower BoundSRD Upper Bound
FLARE TRIPODFLARE TRIPODPile MakePile Make--up Modification Considerationup Modification Consideration
Considering original pile make upDriving resumption at 52m depth after welding of P5 section using D100 was foreseen too risky (premature refusal) due to high estimated Soil resistance expected (>10MN @ 100% Rult) after full set-up effect. A dense sand layer ( 3454m) was present in site. Also the driving resumption at 68m depth after welding of last section (P6) using D100 was foreseen too risky (premature refusal) due to high estimated Soil resistance expected (>12MN @ 100% Rult) after full set-up effect.Using diesel hammer with the max. striking energy was foreseen unable to overcome soil resistance at these depth. More powerful and light hammer such as IHC S280 was proposed and used as back-up of Delmag D100 to drive the last two add-ons (No stick-up problem) and to reach the target penetration.Final decision was to reduce the risk to have refusal and a new pile make up was advised plus the renting of IHC hammer.Considering new pile make up This configuration moved down intermediate penetration from 52m to 58m beyond the critical sand layer. In this way the D100 increased the probability to be able to resume P5 section driving. Whilst, using the powerful hydraulic hammer IHC S280 as back-up of D100 for resume driving of last add-on (P6) reduced the risk to have a premature refusal and guarantied the target penetration (83m) achievement.
People, Ideas, Energy
EniEniEniEni
People, Ideas, Energy
EniEniEniEni PEDESTRIAN TRIPODPEDESTRIAN TRIPODFOUNDATION PILES INFORMATIONFOUNDATION PILES INFORMATION
Platform OD, WTOD, WTSMYSSMYS[MPa][MPa]
Conf.Conf.TotalTotal
LengthLength
345345 149.9m149.9m
Vertical Vertical TargetTargetPent.Pent.
SpreadSpreadHammersHammers
79.5 m79.5 m(80.2m)(80.2m)
D62-22,D80-23D100-13,IHCS 280
Pedestrian Pedestrian TripodTripod(3 No. Piles)(3 No. Piles)
True Batter = True Batter = 7.817.81
30,30,0.751.50.751.5
Lead Lead SectionSection
++5 Add 5 Add --onsons
Legend :Available Spread Hammer
Proposed and Adopted Hammer
People, Ideas, Energy
EniEniEniEni PEDESTRIAN TRIPODPEDESTRIAN TRIPODPile Configuration Pile Configuration
Make-upLength
[m]Cut-off
[m]
Lead Section 69.50 -
1
1
1
1
5th Add-on 16.50 3.092
1st Add-on 20.00
2nd Add-on 17.00
3rd Add-on 17.00
4th Add-on 17.00
People, Ideas, Energy
EniEniEniEni PEDESTRIAN TRIPODPEDESTRIAN TRIPODESTIMATED SOIL RESISTANCE TO DRIVINGESTIMATED SOIL RESISTANCE TO DRIVING
SRD Ultimate Static Capacity API 1986SRD Ultimate Static Capacity API 2000SRD Lower BoundSRD Upper Bound60% SRD Ultimate Static Capacity API 2000
PEDESTRIAN TRIPODPEDESTRIAN TRIPODOriginal Pile MakeOriginal Pile Make--up Considerationup Consideration
Considering original pile make upDriving resumption at 64m depth after welding of last section (P6) using D100 was foreseen too risky (premature refusal) due to high estimated Soil resistance expected (>7MN @ 100% Rult) after full set-up effect. Only clay layers were present in site. Using the diesel hammer with the max. striking energy would cause hammer unable to overcome soil resistance at this depth. More powerful and light hammer such as IHC S280 was proposed and used as back-up of Delmag D100 to drive the last add-on (No stick-up problem) and to reach the target penetration (80m).Final decision was to reduce the risk to have refusal and using the original pile make up the renting of IHC hammer was advised.
People, Ideas, Energy
EniEniEniEni
People, Ideas, Energy
EniEniEniEni PRP JACKET PRP JACKET -- PILES DRIVINGPILES DRIVING
People, Ideas, Energy
EniEniEniEni FLARE TRIPOD FLARE TRIPOD -- PILES DRIVINGPILES DRIVING
WHAT TO DO IN CASE OF REFUSAL?WHAT TO DO IN CASE OF REFUSAL?
Change with the powerful hammer (if any) If refusal occurs far away from final penetration, jetting or drilling
shall be performed (if available) Close to final penetration, drilling could be counter productive, since
it removes the tip resistance In this case drilling and grouting shall apply Drilling involves a costly preparation of equipment Drilling implies full commercial coverage, since a few days could be
lost on each pile, all on critical path Drilling feasible on all main piles but complex on skirt pile ?
People, Ideas, Energy
EniEniEniEni
EXAMPLE : PILE STICKEXAMPLE : PILE STICK--UP CALCULATIONUP CALCULATION
People, Ideas, Energy
EniEniEniEni
People, Ideas, Energy
EniEniEniEni
DATA
Conductor PileO.D. = 30 = 762 mmW.T. = 1 = 25.4 mm (uniform WT)
Pile Length = 60 mFy = 345 MPa (EN 10025 S355JO)True Batter = Vertical (1 include tolerance)
Hammer Data :Type = MHU 270T (above water,
without under water ballast)Weight,mh = 444.4 kNC.o.G = 2.5 m
Resulting Free Standing Length :Rfs = 60 (5 +20 + 5)
= 30 m
Resulting Free Standing Length (Rfs)
Cantilever Section
(+)5.0 m
(-)20.0 m
Penetration = 5 m
HammerSleeve
C.o.G
People, Ideas, Energy
EniEniEniEni
LOADS CALCULATIONBending MomentM = mh x (Rfs + C.o.G.) x sin 1 + mL x (Rfs / 2) x sin 1
Where : mL = weight of pile (kN)= 0.25 (OD2 ID2) x Rfs x 7850 kg/m3= 0.25 (0.7622 0.71122) x 30 x 7850= 13842.23 kg
mL = 135.792 kN
M = 444.4 x (30+2.5) x sin1 + 135.792 x (30/2) x sin1M = 287.387 kN-m
Minimum bending moment based on API requirement:M = 2% x mh x Rfs
= 2% x 444.4 x 30M = 266.64 kNm
Therefore, adopt M = 287.387 kNm
Axial (Compressive) LoadN = (mh + mL) x cos 1
= (444.4 + 135.792) x cos 1N = 580.104 kN
1
C.o.G
mh
mL
mh.cos
mh.sin
mh
mL.cos
mL.sin
mL
ACTUAL STRESSES CALCULATION
SMfb =
( )44 IDODOD
321 =S
( )44 7112.0762.00.762
321 =S
2b kN/m 27,3700.0105
287.387f ==
MPa 27.370fb =
Actual Bending Stress
Where ;
3m 0.0105S =
Actual Compressive Stress
( ) 222a kN/m 98690.71120.7620.25 580.104ANf ===MPa 9.869fa =
People, Ideas, Energy
EniEniEniEni
ALLOWABLE STRESSES CALCULATION
y
y
y F20,680
tD
Fy10,340
59.94F
20,680
29.97F
10,340
301
30tD
===
==
( ) MPa 18.067242.30723206,00012
Kl/r23E12F 2
2
2
2
a ===
Allowable Compressive Stress
I = 0.00399 m4A = 0.25 (0.7622 0.71122) A = 0.0588 m2
( )44 0.71120.762641 =I
Where :
People, Ideas, Energy
EniEniEniEni
COMBINED STRESSES CALCULATION
1.0 0.54518.0679.869
Ff
a
a ==
b'e
a
bm
a
a
FFf
1
fCFf
+ ( ) 22
2
2'e 242.30723
206,00012Kl/r23
E12F =
=
MPa 18.067F'e =
1.0 0.778259.639
18.0679.8691
27.370118.0679.869 =
+
1.0 0.154259.63927.370
3450.69.869
Ff
0.6Ff
b
b
y
a =+=+
1.0 0.652259.63927.370
18.0679.869
Ff
Ff
b
b
a
a =+=+d )
Where :
a )
b )
c )
People, Ideas, Energy
EniEniEniEni
RESIDUAL DYNAMIC STRESS CALCULATION
Total Static Stress:fs = fa + fb
= 9.869 + 27.370 = 37.239 MPa
Residual Dynamic Stress:Rf dyn = Fy fs
= 345 37.239 = 307.761 MPa
Percentage of Residual Dynamic Stress,% Rf dyn = (307.761 / 345) x 100%
= 89.21 %
People, Ideas, Energy
EniEniEniEni
The above calculation calculates static stress (fs) only. The next steps are :Final Check , If fs + f dyn SMYS (OK) and
f dyn 80% 90% SMYS (OK)Where f dyn is the compressive stress at cantilever section, taken from driveability analysis (GRLWEAP output).
People, Ideas, Energy
EniEniEniEni REFERENCESREFERENCES
American Petroleum Institute API RP 2A-WSD Recommended Practice for Planning, Designing and Constructing Fixed Offshore Platforms -Working Stress Design.
American Institute of Steel Construction (AISC), Manual of Steel Construction.
Brochure Diesel Hammer by Delmag. Brochure Hydraulic Hammer by Menck. Brochure Steam Hammer by Menck. Brochure Vibratory Hammer by ICE. European Norm (EN10025-95): Technical Specifications of Coils and Strips,
Sheet and Heavy Plates. GRLWEAP Handbook, 2005 Version. Pile Driveability Course, PT. Saipem Indonesia, Jakarta 2005 (Parisi, Saipem
S.p.A.). SMS Work Instructions, Doc.CR-SMS-INST-305-E, Criteria for Refusal of
Offshore Installation Platforms Pile Driving, 2006 (Parisi, Saipem S.p.A.) Stevens, R.S., E.A. Wiltsie and T.H. Turton Evaluating Pile Driveability for
Hard Clay, Very Dense Sand, and Rock XIV OTC, Houston, 1982