Upload
trandieu
View
217
Download
1
Embed Size (px)
Citation preview
PhilippinesNuclear Power Program
Dir. Jesus T. TamangEnergy Policy Planning BureauDepartment of Energy
Technical Meeting on Building a National Position on a New Nuclear Power Program
IAEA Headquarters, Vienna, Austria
24-26 June 2014
Basic steps we have taken in developing the first Nuclear Program in the Philippines
a. Saw the need and evaluated its feasibility
b. Required legislations were set in place including membership to IAEA
c. Identified potential sites, technology and fuel providers and other key players i.e. regulator, implementor and operator of the Nuclear Power Plant (NPP)
d. Official announcement of the program
e. Launch the construction of the NPP
Initial Development Program
1950 Meralco commissioned Gilbert Associates to do a preliminary study on the feasibility of a nuclear power plant. Study concluded that it was not yet timely to undertake the project
1958 Passage of RA 2067 creating the Philippine Atomic Energy Commission
1959 Philippines became a member of IAEA1963 Second pre-investment feasibility study was conducted by
IAEA. Recommended Philippines to seriously consider use of nuclear power and enact legislation for regulation of nuclear power
1965 IAEA Siting Mission identified potential sites for a nuclear power plant
1968 RA 5207 or the Philippine Atomic Regulatory and Liability Act was enacted on June 1968
Initial Development Program
1968 Philippines and United States agreed on July 1968 on the construction of two nuclear power plants and on the long-term supply of enriched uranium
1971 RA 6395 was enacted authorizing National Power Corporation to establish and operate nuclear power plants.
1972 IAEA completed a follow up feasibility study with findings that a. 600 MWe nuclear power plant in Luzon is technically feasible; b. that suitable sites were identified and available (per IAEA Site
Selection Sub-Committee). These sites are (1) Bagac, Bataan (2) San Juan, Batangas (3) Ternate, Cavite (4) Padre Burgos, Quezon and (5) Limay, Bataan.
Initial Development Program
1973 Marcos government announced on July 1973 its decision to build a nuclear power plant to be constructed by Westinghouse
1977 Construction of a 620 MWe Bataan Nuclear Power Plant at was started at Napot Point in Morong, Bataan.
Initial Development Program
Three-Mile Island Accident (1979) Construction was stopped. IAEA
recommended incorporation of additional safety devices
Chernobyl Accident (1986) Newly installed government
decided to mothball BNPP Cabinet Committee was formed
to study options and alternatives Philippine Atomic Energy
Commission reorganized into Philippine Nuclear Research Institute
Shifts in Nuclear Power Program
Pre-Fukushima (2010) Pangasinan Provincial Board
passed resolution inviting government to explore feasibility of locating nuclear power facility within their boundaries
Regional Development Council of Mindnao passed resolution enjoining DOE and DOST to study feasibility of establishing NPP in Mindanao
Inter-agency Survey in 10 cities showed 60 percent of respondents willing to support a nuclear power program
Shifts in Nuclear Power Program
Post-Fukushima
Household Energy
Consumption Survey in 2011
One in three (33%) willing to
support nuclear for power
47 % were undecided about
harnessing nuclear energy
20% were reluctant to support
nuclear for power
Shifts in Nuclear Power Program
Come up with Policy Statement on Nuclear consistent with the Energy Reform Agenda including: Fuel Mix Self Sufficiency Energy Efficiency GHG
Continue Capacity Development
Conduct more IEC
Current Directions
Decide on offers for Bataan
Nuclear Power Plant
Rehabilitate in two years
Convert to Non-Nuclear New
Power Plant i.e. Coal and
Natural Gas
Green Conversion plus
Training Center on Power
Generation and Environment
Current Directions
PhilippinesNuclear Power Program
Dir. Jesus T. TamangEnergy Policy Planning BureauDepartment of Energy
Technical Meeting on Building a National Position on a New Nuclear Power Program
IAEA Headquarters, Vienna, Austria
24-26 June 2014
Primary Energy Mixin MTOE
77,525
2012 2030
Total Energy (MTOE) 42.90 77.53
Self-sufficiency (%) 56.32 52.70
Shares (%)
Renewable Energy (RE) 40.2 37.8
Green Energy (RE + Natural Gas) 48.2 52.8
Fuel Input for Power Generationin MTOE
77,525
2012 2030
Total Energy (MTOE) 21.87 44.58
Self-sufficiency (%) 56.3 72.2
Shares (%)
Renewable Energy (RE) 52.6 54.9
Green Energy (RE + Natural Gas) 67.6 72.9
Fuel for Power wrt Primary Energy Mix 52.4 57.5
2012 Power Generation Fuel Mix
Source GWh % share
Oil 4,254.0 5.83
Hydro 10,252.13 14.06
Geothermal 10,249.99 14.06
Coal 28,264.87 38.76
Natural Gas 19,641.53 26.93
Solar/Wind 76.66 0.11
Biomass 182.82 0.25
Total Generation 72,922.01 100.00
Self Sufficiency % 58.78
Renewable Energy 20,761.60 28.47
Green Energy (RE + Natgas) 40,403.13 55.41
EBT as of July 29, 2013
Source kTOE % share
Coal 6,300.49 29.02
Natural Gas 2,993.47 13.79
Oil-Based 971.25 4.47
Hydro 2,552.64 11.76
Geothermal 8,814.99 40.60
Other RE* 78.21 0.36
Total Input 21,711.06 100.00
Renewable Energy 11,445.85 52.72
Green Energy (RE + Natgas) 14,439.32 66.51
*biomass, solar, wind, etc
EBT as of July 29, 2013
2012 Power Generation Mix