PEOPLES ENERGY LIMITED KHIMTI-2 HYDROELECTRIC PROJECT (48.8 MW) PROGRESS REPORT July 2019

PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

PEOPLES ENERGY LIMITED KHIMTI-2 HYDROELECTRIC PROJECT

(48.8 MW)

PROGRESS REPORT

July 2019

Page 2: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | i July 2019

PEOPLES ENERGY LTD.

Shree Krishna Sadan – 6th Floor, New Baneshwor-10, Kathmandu, Nepal. Tel.: +977-1-4781891, 4786030 Email: [email protected], [email protected] Website: www.peoplesenergy.com.np

Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report

July 2019

Contact Details:

Head Office: Shree Krishna Sadan, New Baneshwor-10, Kathmandu Metropolitan City, Kathmandu, State No. 3, Nepal.

Tel.: 01-4781891, 4786030

Site Office: Bhimsenthan, Gokulganga Rural Municipality, Ramechhap, State No. 3, Nepal. Tel.: 9849150807, 9840231804

Page 3: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | ii July 2019

Table of Contents PEOPLES ENERGY LIMITED ............................................................................................................................................... i

LIST OF ABBREVIATIONS ................................................................................................................................................. iii

CHAPTER – 1 PREAMBLE ........................................................................................................................................... 4

1.1 Introduction ...................................................................................................................................................... 4

1.2 Objective of this report ................................................................................................................................. 4

1.3 Key Dates and Milestones ............................................................................................................................ 5

1.4 Bank Consortium ............................................................................................................................................. 6

1.5 The Employer .................................................................................................................................................... 6

1.6 Procurement and EPC-F Contract ............................................................................................................. 6

1.7 Local Contractors for Site Infrastructures ............................................................................................... 7

1.8 Access to the Site ............................................................................................................................................ 8

CHAPTER – 2 TECHNICAL FEATURES OF THE PROJECT .................................................................................. 9

2.1 Salient Features of the Project ................................................................................................................... 9

CHAPTER – 3 PROGRESS DETAILS ....................................................................................................................... 15

3.1 Progress Summary on Construction of Site Infrastructures ......................................................... 15

3.2 Administrative Works ................................................................................................................................. 17

3.3 Design and Physical Model Study .......................................................................................................... 18

3.4 Progress work in Detail/ Photographs .................................................................................................. 19

3.4.1 Access Road .......................................................................................................................................... 19

3.4.2 Bailey Bridge ......................................................................................................................................... 23

3.4.3 Camp Facilities .................................................................................................................................... 25

3.4.4 33Kv Transmission line for Construction Power ...................................................................... 26

3.4.5 Design & Engineering Works .......................................................................................................... 27

3.4.6 Administrative Works ........................................................................................................................ 29

CHAPTER – 4 RESOURCE DETAILS ....................................................................................................................... 30

4.1 Manpower Details ........................................................................................................................................ 30

4.2 Equipment Details ....................................................................................................................................... 30

4.3 Difficulties & issues being faced / envisaged at site ........................................................................ 31

Page 4: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | iii July 2019

LIST OF ABBREVIATIONS

PEL Peoples Energy Ltd.

PHCL Peoples Hydro Co-operative Ltd.

PPA Power Purchase Agreement

NEA Nepal Electricity Authority

K2HEP Khimti-2 Hydroelectric Project

HEP Hydroelectric Project

MW Mega Watts

RCOD Required Commercial Operation Date

HCE Hydro-Consult Engineering Limited

CWTW Chongqing Water Turbine Works Co. Ltd.

IEE Initial Environmental Examination

EPC-F Engineering Procurement Construction-Financing

TOR Term of Reference

LC Letter of Credit

FC Financial Closure

DFO District Forest Office

KV Kilo Volt

PH Power House

MoU Memorandum of Understanding

BDR Basic Design Report

Page 5: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 4 July 2019

CHAPTER – 1 PREAMBLE

1.1 Introduction Peoples Energy Limited is being developing Khimti-2 Hydroelectric Project (48.8 MW) located in the

border of Ramechhap and Dolakha districts of Janakpur zone. Khimti River is a tributary of

Tamakoshi a major branch of Saptakoshi river system of Nepal. The Khimti River originates at EL.

4500m and converges with the Tamakoshi River at EL. 600m. The total drainage area of the Khimti

River is 492.4km2, and the drainage area in front of the intake and powerhouse is 295.34km2 and

351.4km2respectively. The river section from the dam site to powerhouse is about 7km long. The

ridges on both banks are at EL. 2,300~3,000m; the riverbed at the dam is at EL. 1,627m; the riverbed

at the powerhouse tailrace is at EL. 1,278m. The run-of-river development scheme is selected.

The headworks site is located at Rasnalu/Gokulganga Rural Municipality of Ramechhap and Jiri

Municipality of Dolakha district whereas the powerhouse site is located at Simlep and

Hawa/Tamakoshi Rural Municipality of Dolakha District. The headwork is located about 150m

downstream the confluence of Jiri Khola and Khimti Khola with headrace alignment passing along

the right bank of Khimti Khola and powerhouse site also located on the right bank.

Geographical Coordinates of Khimti-2 Hydroelectric Project

Coordinates From To

Latitude 27°33'07"N 27°35'13"N

Longitude 86°09'26"E 86°14'18"E

1.2 Objective of this report

Objective of this report is;

To update the status of various development activities completed and being undertaken in

implementation of 48.8 MW Khimti-2 Hydroelectric Project.

To update the status of schedules and planning

To bring forward the difficulties & issues being faced / envisaged at site to the notice of

concern authorities and stakeholders

Page 6: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 5 July 2019

1.3 Key Dates and Milestones

S/N Activity Date Remarks

1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed

2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed

3. Updated Survey License Issuance (48.8 MW) 2070 Chaitra 7 Closed

4. IEE ToR Approval 2071 Bhadra 28 Closed

5. Grid Connection Agreement 2071 Kartik 13 Closed

6. IEE Report Approval 2072 Kartik 22 Closed

7. Power Purchase Agreement (PPA) with NEA 2072 Ashwin 14 Closed

8. Application for Generation License 2072 Kartik 11 Closed

9. Public Notice of Generation License 2073 Kartik 9-10 Closed

10. Generation License Issuance 2073 Paush 25 Closed

11. Generation License Transfer from PHCL to PEL 2073 Falgun 5 Closed

12. Land Ownership Transfer from PHCL to PEL 2074 Jestha 11 Closed

13. IEE Report Approval transfer from PHCL to PEL 2074 Ashoj 2 Closed

14. PPA Transfer from Peoples Hydro to Peoples Energy Limited 2074 Ashad 22 Closed

15. Financial Closure 2074 Ashoj 8 Closed

16. Memorandum of Understanding (MoU) Signing with CWTW in EPC-F modality

2074 Kartik 26 Closed

17. EPC-F Contract Agreement signed Between PEL and CWTW

14 March 2018 Closed

18. Shifting of Grid Connection for Power Evacuation (loop-in, loop-out with 132 kV line near PH site)

2073 Chaitra 17 Awaiting approval

19. Forest and Government Land Approval/Cabinet approval

2073 Falgun 22 Awaiting approval

20. Explosive License 2074 Shrawan Awaiting approval

21. Updated IEE Report 2075 Chaitra Report submitted to DoED

22. Required Commercial Operation Date (RCOD) 2021 July 16 (2078 Shrawan 1) Fixed Date

Page 7: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 6 July 2019

1.4 Bank Consortium Financial closure (FC) for the development of Khimti-2 HEP was concluded with the bank consortium of ten Class 'A' Commercial Banks of Nepal, with Sanima Bank as the lead bank, on September 24th, 2017.

List of Consortium Banks:

S/N Name of the Bank Role Remarks 1. Sanima Bank Lead Bank/ Participating Bank 2. Siddhartha Bank Participating Bank 3. Nabil Bank Participating Bank 4. Janata Bank Participating Bank 5. NIC Asia Bank Participating Bank 6. NMB Bank Participating Bank 7. Bank of Kathmandu Participating Bank 8. Civil Bank Participating Bank 9. Global IME Bank Participating Bank 10. NCC Bank Participating Bank

1.5 The Employer Peoples Energy Ltd. (PEL), previously Peoples Hydro Co-operative Ltd. (PHCL), is the developer of Khimti-2 Hydroelectric Project, situated at Dolakha and Ramechhap districts. PEL obtained the survey license for the project on 2012/10/31. After, feasibility level investigation was concluded and the Power Purchase Agreement (PPA) was signed with Nepal Electricity Authority (NEA) on 2015/10/01. Generation license was obtained for the project on 2017/01/06 by PHCL, and later transferred to PEL on 2017//02/16.

1.6 Procurement and EPC-F Contract The Employer has identified Chongqing Water Turbine Works (CWTW) as the EPC Contractor appropriate party to execute and implement Khimti-2 HEP in an EPC+F modality. PEL and CWTW have signed contract agreement on 14th March 2018.

EPC Contract Contract Details

Contractor: Chongqing Water Turbine Works Ltd. (Govt. Owned)

Contract Signing Date 2074 Falgun 30

Contractor’s Parent Company

CME (China Govt. Owned)

Page 8: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 7 July 2019

EPC Contract Price: US$88 million

EPC Cost Includes: Civil Cost, Hydro mechanical Cost, Electromechanical Cost, Transmission Line Cost, Access road and bridges, IDC, Detail Design

Developers Part: Pre-Operation Cost, Operation Cost, Land Cost, Client’s Camp, Project Supervision Cost, Environmental Cost, Documentation Cost etc.

Payment Model:

5% of Contract Price as advance payment: Within June 2018 against APG issued from Bank of China

5% of Contract Price as advance Payment: within December 2018 against APG issued from Bank of China

Rest 90% of Contract Price to be paid within 700 days from COD.

Design Company: Power China Guiyang Engineering

TAX & TDS: Included

Escalation: will not effective

Contractors Bank at China Bank of China

Insurance Sinosure

1.7 Local Contractors for Site Infrastructures PEL has engaged several local contractors for the construction of site infrastructures as pre-construction activities such as access track opening and slope protection works for Access Road, drainage and stone soling for improvement of Access Road, Project Camp, Boundary wall construction and construction of three motorable bailey bridges etc. To execute the mentioned works PEL has engaged some of the local contractors employed at site are: For Bridge Construction (three bridges over Khimti Khola)

S.K. Construction (for Dharapani Bridge at Dam Site)- Bridge I Likhu Nirman Sewa (for Hodampa Bridge for HRT adit site)- Bridge II Him Sagarmatha Construction (for Palate Bridge/PH site)-Bridge III

For Road Access and Gabion Works

Bhimeshwor Nirman Sewa Chandrama Nirman Sewa Dangdunge Nirman Sewa Dharmasthali Suppliers

Page 9: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 8 July 2019

Dipshree Construction Khani Nirman Sewa Kritim Nirman Sewa Likhu Nirman Sewa Moti Construction Pvt. Ltd. New Jagriti Nirman Sewa Prakriti Nirman Sewa Rambole Construction Pvt. Ltd. Serakali Construction Pvt. Ltd. Seti Bhumi Nirman Sewa Sunuwar Nirman Sewa

For Camp Construction Edgemark Consultancy Pvt. Ltd. Jyoti Shree Interior Pvt. Ltd.

For Road Access and Gabion Works

New Satakri Khimti Construction Pvt. Ltd.

1.8 Access to the Site The project site is accessible from Kathmandu by the following roads:

i. Kathmandu – Dhulikhel - Dolalghat – Lamosangu - Charikot - Jiri – Headworks site (198 km length)

ii. Kathmandu – Dhulikhel – Nepalthok – Khurkot – Manthali – Khimti – Betali – Bhimsenthan – Powerhouse site (145 km length)

Page 10: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 9 July 2019

CHAPTER – 2 TECHNICAL FEATURES OF THE PROJECT

2.1 Salient Features of the Project

Name of Project: Khimti -2 Hydroelectric Project Installed Capacity: 48.8 MW Type of Project: Run of River (ROR) Location: Jiri Municipality and Tamakoshi Rural Municipality of Dolkha District (Previous Jiri, Thulopatal and Hawa VDC) of Dolkha District) Gokulganga Rural Municipality of Ramechhap District (Previous Rasnalu & Betali VDC of Ramechhap District) Comparative Salient Features of the Project:

Project Features Features Details (As per Feasibility/IEE)

Features Details (As per final DPR)

Remarks

General

Project Boundary 27°33'07"N to 27°35'13"N 86°09'26"E to 86°14'28"E 27°33'07"N to 27°35'13"N 86°09'26"E to 86°14'28"E Gross Head 355m 351.5m Rated Head 345.66m 341.643m FSL 1633.00masl 1633.00 masl Normal TWL 1275.96 masl 1275.96 masl Minimum TWL 1275.00 masl 1275.00 masl Turbine Centre Line 1278.00 masl 1281.50 masl

Hydrology Catchment area at Intake site 317.94 km2 317.94 km2 Catchment area at Powerhouse 351.4 km2 351.4 km2 Average Flow 27.36 m3/sec 27.36 m3/sec Minimum Monthly flow 4.45m3/sec 4.45m3/sec Design Discharge(Q40) 16.11 m3/sec 16.11 m3/sec Design flood at intake site (Q100) 1165 m3/sec 1165 m3/sec Design flood at intake site (Q1000) 1657 m3/sec 1657 m3/sec Diversion Structure

Type of diversion structure Ogee weir with U/ S vertical face Ogee weir with U/ S vertical face and undersluice gates D/S Slope 1:1 1:0.7

Page 11: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 10 July 2019

Weir crest level 1633.00masl 1633.00masl Crest Length of Chute section 10m Crest length of Ogee section 16m 17.5 m Total Crest Length of Weir 26m 17.5 m Width of Weir 18.3m 12.10 m Riverbed Level 1628.00 masl 1627.00 masl Undersluice Crest length of undersluice 8.5m 10 m Width of undersluice 11.5m 14.35 m Dimension of undersluice (L x B) 2 Nos. 3.5m x 5.5m 2 Nos. 5m X 6m Undersluice crest level 1628.0 m 1627 masl Undersluice Gate Radial gate, 2nos 3.5m x 5.5m Radial gate, 2nos. 5m x 6m Stilling Basin Stilling Basin for Ogee Weir (L x B) 34.5 m x 16 m 26.35m X 21.08m Stilling basin for Undersluice (L x B) 41.2 m x 9,5 m

Floor level of stilling basin 1624.00 masl 1625.00 masl End level of stilling basin 1627.00 masl 1625.00 masl Intake Intake type Side intake Side Intake Coarse trashrack (B x H) 2 nos 2.6m x 4.0 m 8 nos. 4m X 2m Intake gate (B x H) 2nos 2.6 m x 2.6 m 2nos 2.6 m x 2.6 m Invert level of Intake gate 1630.00 masl 1631.00 masl

Gravel Flushing Culverts Forebay Flushing Tunnel

Size (B x H) before/after gate 0.6 m x 1.0 m /1.2 m x 1.2 m 1m X 1m, 3m X 3.5m Length after junction 19.86 m 65.2m Number of culverts/ tunnels 2 1 Flushing Gate One, 1.2 m x 1.2 m One, 1m X 1m Invert level of Opening 1628.8 masl 1627.00 masl Level at beginning of culvert/tunnel 1626.6 masl 1627.00 masl Level at Flushing end 1626.4 masl 1626.00 masl

Settling Basin Location Surface Underground ChangedType Dufour Dufour

Page 12: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 11 July 2019

Number of compartments 2 2Effective length 100m 55.27m, 67.31m Total width of basin 16m 25.24m Width of one compartment 8m 12.62 m Height in rectangular section 8m 16.00m Side slope of the compartment 1:1 1:1.7 Flushing system Intermittent Intermittent Longitudinal slope of flushing channel 1:50 1:50 Invert level at the beginning of flushing channel 1624.10 masl 1624.00 masl Invert level at the end of flushing channel 1622.10 masl 1622.65 masl Width of the flushing channel 0.6m 1 m Flushing Pipe NA 1 m dia. Invert level at the beginning of flushing pipe NA 1622.65 masl Invert level at the end of flushing pipe NA 1621.00 masl Flushing Culvert/Tunnel (L x H) 1 m x 1 m 2mX2m (Inverted-D) Invert level at the beginning of flushing culvert/ tunnel 1622.10 masl 1621 masl Invert level at the end of flushing culvert/ tunnel 1621.5 masl Not Applicable

Water Conveyance system (Headrace Tunnel)Type of flow Pressurized Pressurized Shape of Tunnel Horse shoe Inverted D type Length 6.6 km 6.7 km Diameter 3.6 m 4.0m (W)X 4.25m (H) Gradient of HRT 1:389 1:333 Tunnel Portal Level 1617 masl 1624.30 masl Surge shaft bottom 1600 masl 1602 masl No. of bends in HRT 5 5

Adit Tunnels No. of Adit Tunnels 3 6 ChangedTotal Length of Adit Tunnel 1029 m 2017 m

Page 13: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 12 July 2019

Diameter 4 m 4m(W) X 4.25m (H) Shape Inverted D type Inverted D type Adit -1 Length 412m 223.78 m Adit -1 HRT junction chainage 2+094 0+000 Adit -1 Portal level 1590 masl 1620 masl Adit -2 Length 440 m 315.80 m Adit -2 HRT junction chainage 3+944 3+302 Adit -2 Portal level 1590 masl 1590 masl Adit -3 Length 177m 342m Adit -3 HRT junction chainage 0+027(from surge tunnel outlet) 4+440 Adit -3 Portal level 1590 masl 1612 masl Adit -4 Length 386.50m Adit -4 HRT junction chainage 6+650 Adit -4 Portal level 1580 masl Adit -5 Length 207.7m Adit -5 HRT junction chainage 6+771 Adit -5 Portal level 1440 masl Adit -6 Length 453.33 m Adit -6 HRT junction chainage 6+902 Adit -6 Portal level 1320 masl

Surge Tunnel Diameter 4 m 4 m Shape Inverted D type Inverted D type Length 437 m 412m Surge Tunnel –HRT junction chainage 6+614 6+627 Invert level of inlet 1600.00 masl 1602 masl Invert level of outlet 1660.00 masl 1655.20 masl Pressure Shaft / Tunnel Diameter 2.3 m 2.3 mTotal Length 822 m Length upto Manifold 425.7 m 653 m Vertical section 323.8 m 353 m (Inclined Shaft)

Horizontal shaft section 101.9 m 300m

Page 14: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 13 July 2019

Manifold length 18.3 m Not Applicable Manifold diameter 1.9 m Not Applicable Pressure shaft after Manifold 2 x 24.13 m 169m in total Diameter of pressure after manifold 1.5 m 1.3 m Lining Steel lined embedded in concrete Shotcrete wire mesh and bolts lining

Powerhouse Type of Power house Underground Surface Changed Powerhouse cavern dimension (l x B x H) 46 m x 12m x 21m (from turbine CL) 45m x 16m x 32m Transformer cavern dimension (l x B x H) 37m x 10m x 18 m Not Applicable Surface structure Cavern Crown level 1299.00 masl Not Applicable Machine floor level 1286.00 masl 1293.80 masl Turbine Axis Level 1278.00 masl 1281.50 masl

Turbine Type of turbine Pelton Pelton Shaft configuration Vertical Vertical No.of turbine 2 3Turbine Output 24.4 MW 16.267 MW No of nozzle 5 6 Specific speed 500 rpm 500 rpm Optimal jet diameter 180mm 128 mm Generator Type Synchronous Synchronous Rated output capacity per unit 24.4 MW 16.267 MW Power Factor 0.85 0.85Voltage 11 KV 11kVFrequency 50 Hz 50 Hz No. of Units 2 3 Efficiency 98% greater than 97.5% Transformer No. of Transformer 7 Nos., single phase including 1 sphere 3 Nos., three-phase

Rated capacity 2 units of 3 x 10 MVA 3 units, 3 x 22 MVA Voltage ratio 11/132 kV 11/132 kV

Page 15: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 14 July 2019

Efficiency 99% 99%Transmission line Length 11.5 km 11.5 km Type 132 kV,Single circuit 132 kV,Single circuit Cable ASCR,Bear ASCR,Bear Tailrace Outlet Type Tunnel Box Culvert Type of flow Free flow Free flow Shape Inverted D type Rectangular Diameter 4m 3.5m X 3.5m Total length of tailrace tunnel 562 m 180m Invert level of outlet 1274.36 masl 1274.91 masl Energy Wet Energy 217.5 GWh 219.5 GWh Dry Energy 44 GWh 40.8 GWh Total Energy 261 GWh 260.3 GWh Firm Energy 113 GWh 107 GWh Financial Total Project cost NRs. 7.45 billion NRs. 7.45 billion Revenue NRs. 1.4 billion NRs. 1.4 billion B/C Ratio 1 .41 1 .41 IRR 16.01 % 16.01 % Cost per MW (USD) 1550 1550Access to the site Kathmandu- Charikot - Jiri 198 km (188 km blacktopped) 198 km (188 km blacktopped)

Jiri to Dam site 11 km Gravel Road 11 km Gravel Road Dam Site to Powerhouse site 16 km Gravel Road 16 km Gravel Road Birgung-Bardibas-Khurkot- Manthali-Kirnetar/Khimti 290 km 290 km Khimti to Powerhouse site 27 km Gravel Road 27 km Gravel Road

Page 16: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 15 July 2019

CHAPTER – 3 PROGRESS DETAILS

3.1 Progress Summary on Construction of Site Infrastructures

S/N Project Activity Total Length Status/Progress

ACCESS ROAD

1. Dharapani to Dam site (Ramechhap side)

1.0 km

1.0 km of Track opening works – Completed.

Gabion works/Slope protection – Completed.

2. Intake-Dharapani Road (Dolakha Side)

0.5 km 200 m of Track Opening – completed. Rock cutting till foundation level of right

abutment – Completed.

3. Burke – Hodampa/Phulping (Ramechhap side)

2.5 km

2.5 km track opening completed Gabion works and Maintenance of Burke-Bhage road- Ongoing.

4. Thulopatal – Hodampa/Phulping - Gaighat (Dolakha side)

2.0 km 2.0 km Track opening - Completed. Gabion works and widening the track is

remaining

5. Hanwa - Palate (Dolakha side)

5.5 km

3.0 km (out of 5.5 km) of Track opening – Completed.

Remaining works on 2.5 km – Pending due to forest clearance issue.

6.

Bhimsenthan – Palate/Powerhouse site new track (Ramechhap side)

0.5 km

0.5 km of Track opening – Completed. Slope protection completed. Gabion work to protect road section at

river side remaining.

7.

Bhimsenthan – Palate/Powerhouse site Old track to be upgraded (Ramechhap side)

3.0 km Stone soling works & side drainage for access road improvement – Completed.

PROJECT CAMP

8. Camp Boundary Wall – Civil/Masonry works

Wall and Permanent fencing

Masonry works for boundary wall completed.

Front entrance gate completed. Angle post erected and painting works for

angle post completed. Delivery of fencing material & erection

completed.

9. Building Construction works

Total 12 Buildings

All Civil works including truss works and roofing of all 12 buildings completed.

Complete finishing of 2 building completed.

Sanitary works of 5 building completed, and 7 building partially completed.

Electrical works of 11 building completed. False ceiling works of 11 buildings

completed.

Page 17: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 16 July 2019

Painting of 2 building completed, and 6 building partially completed.

Landscaping work remaining.

10. Water Supply System

Drinking water to Project Camp

Drinking water source identified. Design & estimation for works –

Completed. Water source registration Process-

Completed. Pipe laying Completed Intake tank completed. Works on storage Tank ongoing. Water supply pipeline inside camp

remaining Drinking

water to Locals

Reservoir tank- Location fixed Pipe Laying remaining Tap stand construction remaining.

33KV TRANSMISSION LINE FOR CONSTRUCTION POWER

11. 33 kV Transmission Line for Construction power

9 km 33 kV sub-transmission line

Contract award to New Satakri Khimti Construction

Pole erection from Dam site to PH site completed.

Cable installation competed in Ramechhap side.

Accessories installation in poles remaining Pole erection and cable installation in

dolakha side remaining Application for connection with Bojini

Switchyard for charging – Submitted. BAILEY BRIDGE

12. Dharapani Bridge (Bridge I)

42.672m Civil works Completed. Erection work Completed.

13. Hodampa Bridge (Bridge II)

33.528m Civil works Completed. Erection work Completed.

14. Hawa-Palate Bridge (Bridge III)

51.816m Civil works Completed. Erection work Completed.

OTHER ACTIVITIES

15. Hydrology and Sediment Study

Hydrology and Sediment Study

Sediment collection & Analysis by HydroLab-Completed.

Discharge Measurement & Hydrological Analysis by Recham Consult -completed.

Page 18: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 17 July 2019

3.2 Administrative Works

16. ADMINISTRATIVE WORKS

Various

administrative issues

Shifting grid

Connection for Power Evacuation

Explosive

License Updated IEE

Report

Forest clearance approval – File forwarding to Ministry of Forest

Land acquisition: about 95% completed Survey License for Transmission Line

(Power Evacuation): Submitted to DoED Explosives License: Received approval for

Nepali Explosive. Application for use of construction power

from Bojini Switchyard – Process initiated.

Preliminary discussion held on loop-in, loop-out with NEA Grid Division.

CC committee’s formed, a brief study has been done and submitted to NEA

First CC meeting held and initiated discussion

Applied to DoED with all required

document Received the recommendation from

DoED and letter to Ministry of Home. Ministry of Home written letter to

Ministry of Defense and concern Districts CDO to issue the carrier License.

Approval received for Nepali explosive only.

Appointed Nepal Environment and

Development Consultant for IEE update works

Application submitted on March 7,2019 Approval received on April 10, 2019 Consultant team visited site and

completed the data collection Public consultation and focus group

discussion completed Draft of Updated IEE is prepared and

submitted to DoED

17. LOCAL STAKEHOLDERS ENGAGAMENT

Local issues

Local Stakeholders Engagement through various discussion, addressing the project related environmental and social issues

Implementing various social and local infrastructural development works

Page 19: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 18 July 2019

3.3 Design and Physical Model Study

18. BASIC DESIGN REPORT (BDR)

EPC Contractors (CWTW)

Responsibility

CWTW has Submitted the Final Basic Design Report by Contractor CWTW after incorporation of Employers Comments

Employers Responsibility

Employers has again reviewed and provided the condition approval; Subject to required modification during construction.

19. PHYSICAL HYDRAULIC MODEL STUDY

Model of Revise Headworks

Consulting contract award to Hydrolab Provided required documents Hydrolab completed river model

validation works Similarly, completed model construction

of structures. First model run carried out and joint

observation of the performance was completed and noticed some modification was required for certain structures

The design modification was carried out The modified design’s model

construction completed Modified model validation /re-run carried

out on 22nd July,2019. Observed good performance with bed

load sluice; Final joint observation to be carried out

after completion of the model with all the headworks structures including settling basin.

Remaining change to be verified by the final Model.

Page 20: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 19 July 2019

3.4 Progress work in Detail/ Photographs

3.4.1 Access Road Headworks Area-Dharapani Road (Ramechhap) The track to headworks of Khimti-2 Hydropower project of 1.0 Km length was completed connecting from existing road in Dharapani, Ramechhap. Cross-drainage has been provided in three major parts of the road section along with masonry side drain in critical section of the road. Gabion works and Masonry breast wall are provided for slope protection in vulnerable portions of the road section.

Future Plans:

Side drain in full section of the road is required in order to protect the road from the heavy downpour.

Soling at certain portion are required in order for heavy vehicle to travel uphill slope of the road.

Slope Protection by gabion are required in certain portions damaged recently by rainfall.

Headworks-Intake Area (Dolakha) Massive rock backcutting just Infront of headworks’ bailey bridge in order to provide required turning radius for the vehicle has been completed.

Future Plans:

300m length section of road to dam site is remaining.

Locals are demanding the connection of existing road (Hawa-Phulping-Jiri Road) to bridge in headworks of Khimti-2 in dolakha side.

Dharapani Access Road

Access road to Headworks-Dolakha

Page 21: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 20 July 2019

HRT adit-Burke-Hodampa Road (Ramechhap) Track opening of 2.5 Km stretch of road from Burke through bhage to hodampa is completed. Earthen side drain and cross drainage through causeway are provided in burke to bhage road section. Gabion in critical road turnings are provided.

Future Plans:

• This road section is most affected by the monsoon rain causing landslide in multiple sections completely blocking the road hence, necessary gabion works and permanent cross drainage are required.

• Side drain and proper cross drainage is required.

HRT adit- Phulping-Gaighat Road (Dolakha) Track from gaighat is connected to Bailey Bridge II (Hodampa Bridge) in phulping linking dolakha and ramechhap district. This 2.0 Km section of roads serves as a connection to project HRT adit from major road Bhirkot-Jiri of dolakha side.

Future Plans:

• Grade of the road in certain portion of road is to be maintained. • Water from monsoon has eroded away fill side of the road section which needs to be

maintained providing gabion in critical sections.

Phulping-Gaighat Access Road

Burke Hodammpa Access road to Phulping Adit

Page 22: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 21 July 2019

• Widening of road section is required in certain places. • Cross drainage, side drain and slope protection are to be provided for the longevity of the

road.

Powerhouse- Bhimsenthan-Palate Road (Ramechhap) Out of 3.5 Km length of Bhimsenthan palate road, track opening of 3.0 Km road section was already completed by khimti-1 project. Remaining 0.5 Km of road to powerhouse site has been completed. Side drain has been provided throughout the length of the road. Hume pipe is provided for cross drainage of water. Freshly cut 0.5 Km section of road triggered a landslide which was controlled by providing gabion as retaining structure. Stone soling in all the slippery slopes of the road is provided to give traction to the vehicle.

Future Plans:

• Gabion work to protect road section at river side of freshly cut 0.5Km section is remaining.

Bhimsenthan-Palate Access Road

Page 23: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 22 July 2019

HRT outlet, surge tunnel-Hawa-Palate Road (Dolakha) 3.0 Km out of 5.5 Km section of hawa-tuspe-palate road track has been excavated, gabion in the venerable slopes has been completed for this 3.0 km stretch. Two major landslides were triggered in this road section, one of which is stabilized by nailing bamboo in the ground and addressing seepage by providing perforated hdpe pipes throughout the unstable slope. Hume pipe is placed for cross drainage in the road. Remaining 2.5 Km section of road is pending due to forest clearance issue.

Future Plans:

• Remaining 2.5 Km track is to be opened and provide necessary protection works. • Permanent side drain is required to protect the road.

Bhimsenthan-Palate Access Road

Page 24: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 23 July 2019

3.4.2 Bailey Bridge Bailey Bridge I (Dharapani Bridge) Civil work: By S. K. Construction pvt. Ltd. – Completed Span: 42.672m Maximum Load capacity: 30T Bailey Bridge erection work: Completed

Bailey Bridge II (Hodampa Bridge) Civil work: By Likhu Nirman Sewa – Completed Maximum Load Capacity: 20T Span: 33.528m Bailey Bridge erection work: Completed

Bailey Bridge I: Dharapani Bridge

Bailey Bridge II: Hodampa Bridge

Page 25: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 24 July 2019

Bailey Bridge III (Hawa-Palate Bridge) Civil work: By Him Sagarmatha – Completed Maximum Load Capacity: 30T Span: 51.816m Bailey Bridge erection work: Completed

Future Plans

Dirt wall and Approach wall for all three bridges are remaining which is planned to be completed after the monsoon season.

Bailey Bridge III: Hawa-Palate Bridge

Page 26: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 25 July 2019

3.4.3 Camp Facilities

Civil Works The Khimti-2 main camp located in Lamatar, Rasnalu Ramechhap contains 12 buildings with 7 Staff Quarters, one Kitchen, two office buildings, one Guest house and a Guard house. The camp is to facilitate during the construction phase of the project as well as during operation phase of the

Project.

Work progress on Camp buildings

The Fencing work surrounding the camp area with chain link and masonry wall along with erection of gate has been completed.

All civil works of 12 buildings including truss works and roofing has been completed. Complete finishing of 2 Staff Quarter has been completed. Internal Painting of 5 buildings is completed and external painting of 2 has been completed. False Ceiling works 11 buildings completed. Sanitary work for 5 buildings is completed and other 7 are also partially completed. Electrical works of 11 buildings completed.

Future Plans

Completing remaining works on Painting, False ceiling, sanitary, electrical works Landscaping of the camp area

Khimti-2 Project Camp

Page 27: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 26 July 2019

Water supply work Drinking water supply for the camp facility of the Khimti -2 project is tapped from the underground water near darkha about 1km away from the camp area.

Work Progress on Water supply to camp

Drinking water source identified and registration process completed. Pipe laying from intake to the camp has been completed. All the civil works and pipe fitting works in Intake area is completed. All the civil works of reservoir tank is completed. Pipe laying and fitting works inside the camp area are completed.

Future Plans

Works for supplying drinking water to some locals near the camp area in ongoing. Construction of reservoir tank, pipe laying and tap stand for drinking water facility to locals.

3.4.4 33Kv Transmission line for Construction Power About 9km sub-transmission line from bojini powerhouse, dharapani to powerhouse site of Khimti-2 hydropower project is required to supply power to different sites during the construction phase.

Work Progress on 33kv construction power

Contract awarded to New Satakri Khimti Construction. Pole erection, cable installation along with all necessary

accessories from headworks to powerhouse site in Ramechhap side completed.

Water Supply works: Intake Area Water Supply works: Reservoir tank

Page 28: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 27 July 2019

Future Plans

Connection from Hodammpa to Phulping adit is remaining. Connection from powerhouse site to surge shaft site is remaining. Installation of Transformer in different site location is remaining.

3.4.5 Design & Engineering Works

Design approval and site mobilization of contractor

Basic design report (BDR) submitted by CWTW has been given conditional approval: subjected to required modification during construction on 5th Dec, 2018.

Work Progress on Physical Hydraulic Modelling

Agreement done with Hydrolab for construction of Physical Hydraulic model

River model and headworks model construction completed

Joint observation of model run conducted

Noticed serious problems requiring major modification on the design

Thick bedload deposit in front of intake was observed blocking the intake

Outlet of the flushing tunnel was submerged during high flood operation.

First run of Physical hydraulic model of Khimti-2 Project

Page 29: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 28 July 2019

The modified design constructed and model validation re-run carried out on 22nd July,2019. In the modified design, bottom bedload sluice with radial gate flushing was added with

changes in forbay hopper. No. of intake was reduced to five from initially proposed eight.

After the re-run of model, the performance of the bed load sluice was satisfactory remaining changes are to be verified by the modification of the model.

Progress on CWTW site Mobilization

As mobilization of contractor is dependent on the advance payment, works on applying for the loan are at its final stage.

CWTW have finalized the civil sub-contractor.

Re-run of hydraulic model after major changes in structure

Page 30: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 29 July 2019

3.4.6 Administrative Works

Progress on Updated IEE Report

Nepal Environment and Development Consultant has been appointed for the preparation of the updated IEE report.

Consultant team visited to site and completed the data collection work Public consultation and Focus group discussions are completed. Draft of Updated IEE report is being prepared.

Progress on Survey License for Loop in Loop out

Discussion was done with NEA for shifting the connection agreement A study for the technical and economical assessment has been done and submitted to NEA. First CC meeting was held.

Progress on Other Administrative works

Survey License for Loop in Loop out has been initiated. Approval has been received for the Nepali Explosives. For the Forest Clearance Approval, the file has been forwarded to Ministry of Forest from

Forest Department.

Page 31: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 30 July 2019

CHAPTER – 4 RESOURCE DETAILS

4.1 Manpower Details

S/N Name Designation

Head Office:

1. Dev Bahadur Poudel Chhetri Director, Public Relations/Social Issues 2. Prof. Hari Prasad Pandit, Ph.D. Chief Technical Adviser 3. Ram Hari Sharma Project Manager 4. Kushal Sundar Shrestha Head, Procurement/Human Resources 5. Janardan Aryal General Manager 6. Bindu Shrestha Account Officer7. Anjuli Khadka Civil Engineer 8. Prachan Shrestha Civil Engineer9. Samrat Acharya Procurement/Admin Officer 10. Bikram Acharya Procurement/Logistics Officer 11. Anjali Aryal Account Assistant

Site Office:

12. Pradip Nepal Deputy Project Manager (Civil Engineer) 13. Toya Nath Ghimire Geologist14. Amul Tandukar Civil Engineer 15. Niroj Kusi Civil Engineer16. Sagar Poudel Civil Engineer 17. Sujan Kasichhwa Electrical Engineer 18. Hari Sharan Adhikari Social Mitigation Officer 19. Krishna Hari Neupane Accountant 20. Anish Bhandari Surveyor 21. Sangita Sunuwar Supervisor 22. Birendra Karki Sub-Overseer 23. Bishnu Gharti Vehicle Driver 24. Dhan Bahadur Magar Vehicle Driver25. Mohan Khatri Vehicle Driver 26. Dhurba Karki Cook27. Moti Lal Tamang JCB Operator 28. Surya Bahadur Bhujel Tractor Driver29. Hom Dhoj Karki Security Guard

4.2 Equipment Details

S/N Vehicle/Equipment Location Number Remarks

Page 32: PEOPLES ENERGY LIMITED · 2019. 7. 29. · 1. Survey License Issuance (27.2 MW) 2069 Kartik 15 Closed 2. Feasibility Study Completed (48.8 MW) 2070 Falgun Closed 3. Updated Survey

Peoples Energy Ltd. Khimti-2 Hydroelectric Project (48.8 MW)

Progress Report Page | 31 July 2019

1. JCB Backhoe Loader At Site 1 PEL Owned2. New-Holland Tractor At Site 1 PEL Owned 3. Mahindra Bolero Pick-up At Site 1 PEL Owned 4. Bolero Pick up Jeep At Site 1 PEL Owned 5. Motorcycle (Honda Shine) At Site 1 PEL Owned 6. Hire Excavators At Site 3 Hire

4.3 Difficulties & issues being faced / envisaged at site Local disturbances while erecting the Dharapani Bridge at Dam site. Local disturbances for the construction of sub transmission line for construction power Delay to open the access to surge shaft due to pending of forest land approval file at Ministry

of Forest to be approved by Cabinet through Ministry of Forest. Delay to get the Explosive license and bunker construction as well as security barrack

construction.