Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Technical Memorandum
TM-UCB-PRC-2001-1
Pay Factors for Asphalt-Concrete Construction:
Effect of Construction Quality on Agency Costs
Prepared for
California Department of Transportation
by
John A. Deacon, Carl L. Monismith, John T. Harvey, and Lorina Popescu
February 2001
Pavement Research CenterInstitute of Transportation StudiesUniversity of California, Berkeley
iii
TABLE OF CONTENTS
Table of Contents ...........................................................................................................................iii
List of Tables................................................................................................................................... v
List of Figures ................................................................................................................................xi
1.0 Introduction ............................................................................................................................. 1
2.0 Concept.................................................................................................................................... 2
3.0 Models..................................................................................................................................... 3
3.1 Performance Models ........................................................................................................... 4
3.1.1 Variability Considerations........................................................................................... 4
3.1.2 Fatigue Cracking ......................................................................................................... 5
3.1.3 Permanent Deformation ............................................................................................ 17
3.2 Cost Model ........................................................................................................................ 28
4.0 Pay Factors ............................................................................................................................ 31
4.1 Pay Factors—Twenty-Year Expected Pavement Life ...................................................... 33
4.2 Pay Factors—Influence of Expected Pavement Life and Cost Parameters ...................... 48
4.3 Comparison of Current Caltrans Pay Factors with Those Obtained from Performance
Models Presented Herein .......................................................................................................... 49
4.4 Combined Pay Factors ...................................................................................................... 62
5.0 Discussion ............................................................................................................................. 65
6.0 References ............................................................................................................................. 67
Appendix A: RELIABILITY AND VARIABILITY CONSIDERATIONS ................................ 69
Reliability.................................................................................................................................. 69
Variability.................................................................................................................................. 70
Appendix B ................................................................................................................................... 78
iv
Appendix C: Analytically-Based Approach to Rutting Prediction ............................................... 79
Mechanistic-Empirical Approach ............................................................................................. 79
v
LIST OF TABLES
Table 3.1 Construction Variation of Mix and Structural Characteristics 7
Table 3.2 Materials/Construction Component of Total Construction Variance...............................7
Table 3.3 Variation of Mix and Structural Characteristics for Monte Carlo Simulations 7
Table 3.4 Construction Targets 10
Table 3.5 Levels and Ranges for Variable Evaluated 10
Table 3.6 Summary of Parameters in Example 14
Table 3.7 Regression Coefficients Relating ln(ESALs) to Mix Variables for Specific
Levels of Rutting 17
Table 4.1 Effect of off-target asphalt content on future agency resurfacing cost based on
rutting in WesTrack pavements (change expressed as a percent of new pavement
construction cost). 34
Table 4.2 Effect of off-target air-void content on future agency resurfacing cost based on
rutting in WesTrack pavement (change expressed as a percent of new pavement
construction cost). 35
Table 4.3 Effect of off-target mineral filler on future agency resurfacing cost based on
rutting in WesTrack pavement (change expressed as a percent of new pavement
construction cost). 36
Table 4.4 Effect of off-target fine aggregate on future agency resurfacing cost based on
rutting in WesTrack pavement (change expressed as a percent of new pavement
construction cost). 37
Table 4.5 Effect of off-target asphalt content on future agency rehabilitation cost based
on Caltrans fatigue model (change expressed as a percent of new pavement
construction cost). 38
vi
Table 4.6 Effect of off-target air-void content on future agency rehabilitation cost based
on Caltrans fatigue model (change expressed as a percent of new pavement
construction cost). ................................................................................................................. 39
Table 4.7 Effect of off-target asphalt-concrete thickness on future agency rehabilitation
cost based on Caltrans fatigue model (change expressed as a percent of new
pavement construction cost).................................................................................................. 40
Table 4.8 Effect of off-target asphalt content on future agency resurfacing/rehabilitation
costs (change expressed as a percent of new pavement construction cost). ......................... 41
Table 4.9 Effect of off-target air-void content on future agency resurfacing/rehabilitation
costs (change expressed as a percent of new pavement construction cost). ......................... 42
Table 4.10 Effect of off-target mineral filler on future agency resurfacing/rehabilitation
costs (change expressed as a percent of new pavement construction cost). ......................... 43
Table 4.11 Effect of off-target fine aggregate on future agency resurfacing/rehabilitation
costs (change expressed as a percent of new pavement construction cost). ......................... 44
Table 4.12 Effect of off-target asphalt concrete thickness on future agency
resurfacing/rehabilitation costs (change expressed as a percent of new pavement
construction cost). ................................................................................................................. 45
Table 4.13 Contractor pay factors for asphalt content (percentage of future
resurfacing/rehabilitation cost in current-year dollars). ........................................................ 46
Table 4.14 Contractor pay factors for air-void content (percentage of future
resurfacing/rehabilitation cost in current-year dollars). ........................................................ 46
Table 4.15 Contractor pay factors for asphalt-concrete thickness (percentage of future
resurfacing/rehabilitation cost in current-year dollars). ........................................................ 47
vii
Table 4.16 Contractor pay factors for mineral filler (percentage of future
resurfacing/rehabilitation cost in current-year dollars). ........................................................ 47
Table 4.17 Contractor pay factors for fine aggregate (percentage of future
resurfacing/rehabilitation cost in current-year dollars). ........................................................ 48
Table 4.18 Effect of off-target asphalt content on future agency resurfacing cost based
on rutting in WesTrack pavements (change expressed as a percent of new pavement
construction cost); target life = 10 years, r = 3.5 percent...................................................... 50
Table 4.19 Effect of off-target asphalt content on future agency rehabilitation cost based
on Caltrans fatigue model (change expressed as a percent of new pavement
construction cost); target life = 10 years, r = 3.5 percent...................................................... 51
Table 4.20 Effect of off-target asphalt content on future agency
resurfacing/rehabilitation costs (change expressed as a percent of new pavement
construction cost); target life = 10 years, r = 3.5 percent...................................................... 52
Table 4.21 Contractor pay factors for asphalt content (percentage of future
resurfacing/rehabilitation cost in current-year dollars); target life = 10 years, r = 3.5
percent. .................................................................................................................................. 53
Table 4.22 Contractor pay factors for air-void content (percentage of future
resurfacing/rehabilitation cost in current-year dollars); target life = 10 years, r = 3.5
percent. .................................................................................................................................. 53
Table 4.23 Contractor pay factors for asphalt-concrete thickness (percentage of future
resurfacing/rehabilitation cost in current-year dollars); target life = 10 years, r = 3.5
percent. .................................................................................................................................. 54
viii
Table 4.24 Contractor pay factors for mineral filler (percentage of future
resurfacing/rehabilitation cost in current-year dollars); target life = 10 years, r = 3.5
percent. .................................................................................................................................. 54
Table 4.25 Contractor pay factors for fine aggregate (percentage of future
resurfacing/rehabilitation cost in current-year dollars); target life = 10 years, r = 3.5
percent. .................................................................................................................................. 55
Table 4.26 Contractor pay factors for asphalt content (percentage of future
resurfacing/rehabilitation cost in current-year dollars); target life = 30 years, r = 3.5
percent. .................................................................................................................................. 55
Table 4.27 Contractor pay factors for air-void content (percentage of future
resurfacing/rehabilitation cost in current-year dollars); target life = 30 years, r = 3.5
percent. .................................................................................................................................. 56
Table 4.28 Contractor pay factors for asphalt-concrete thickness (percentage of future
resurfacing/rehabilitation cost in current-year dollars); target life = 30 years, r = 3.5
percent. .................................................................................................................................. 56
Table 4.29 Contractor pay factors for mineral filler (percentage of future
resurfacing/rehabilitation cost in current-year dollars); target life = 30 years, r = 3.5
percent. .................................................................................................................................. 57
Table 4.30 Contractor pay factors for fine aggregate (percentage of future
resurfacing/rehabilitation cost in current-year dollars); target life = 30 years, r = 3.5
percent. .................................................................................................................................. 57
ix
Table 4.31 Contractor pay factors for asphalt content (percentage of future
resurfacing/rehabilitation cost in current-year dollars); target life = 20 years, r = 3.5
percent. .................................................................................................................................. 58
Table 4.32 Contractor pay factors for air-void content (percentage of future
resurfacing/rehabilitation cost in current-year dollars); target life = 20 years, r = 3.5
percent. .................................................................................................................................. 58
Table 4.33 Contractor pay factors for asphalt-concrete thickness (percentage of future
resurfacing/rehabilitation cost in current-year dollars); target life = 20 years, r = 3.5
percent. .................................................................................................................................. 59
Table 4.34 Contractor pay factors for mineral filler (percentage of future
resurfacing/rehabilitation cost in current-year dollars) ; target life = 20 years, r = 3.5
percent. .................................................................................................................................. 59
Table 4.35 Contractor pay factors for fine aggregate (percentage of future
resurfacing/rehabilitation cost in current-year dollars); target life = 20 years, r = 3.5
percent. .................................................................................................................................. 60
Table 4.36 Pay Factor Summary—Overlay Project, SR 299, Trinity County, July 1999 .......... 60
Table 4.37 Pay Factors for Combination Conditions (from Simulations) (Conditions Set
to Yield Individual Pay Factors of About –20 Percent) ........................................................ 64
Table 4.38 Pay Factors for Combination Conditions (from Simulations) (Conditions Set
to Yield Varying Individual Pay Factors) ............................................................................. 64
Table 4.39 Pay Factors for Combination Conditions (from Calculations) (Conditions Set
to Yield Varying Individual Pay Factors) ............................................................................. 64
Table B-1 Pavement Structures.................................................................................................. 78
x
Table C-1 Calculated ESALs to a range in rut depths for a constant loading of 60
trucks/hour, WesTrack environment. .................................................................................... 86
Table C-2 Calibration of equations for simulating ln(field a) based on mix and RSST
variables. ............................................................................................................................... 91
Table C-3 Calibration of equations for simulating field c based on mix and RSST
variables. ............................................................................................................................... 93
xi
LIST OF FIGURES
Figure 3.1 Outlines of performance model simulations for fatigue cracking and rutting. 6
Figure 3.2. Effects of as-constructed air-void content on pavement fatigue performance. 12
Figure 3.3. Effects if as-constructed asphalt content on pavement fatigue performance. 12
Figure 3.4. Effects of as-constructed surface thickness on pavement fatigue performance. 13
Figure 3.5. Effect of specification failure level on acceptability of mix compaction. 13
Figure 3.6. Influence of air-void content on pavement performance. 14
Figure 3.7. Expected pavement performance. 15
Figure 3.8. Influence of air-void content on contractor pay adjustment. 16
Figure 3.9. Influence of pavement performance on pay factors. 16
Figure 3.10. WesTrack gradings. 19
Figure 3.11. Effect of mix variables on simulated ESALs to 15 mm (0.6 in.) rut depth for
a range in fine aggregate contents; Vair = 6.5%, P200 = 6.0%. 20
Figure 3.12 Effect of mix variables on simulated ESALs to 15 mm (0.6 in.) rut depth for
a range in P200; Vair = 6.5%, fine aggregate = 28%. 21
Figure 3.13. Effect of mix variables on simulated ESALs to 15 mm (0.6 in.) rut depth for
a range in air-void contents; P200 = 6.0%, fine aggregate = 28%. 22
Figure 3.14. Effect of mix variables on simulated ESALs to 15 mm (0.6 in.) rut depth for
a range in asphalt contents; P200 = 6.0%, fine aggregate = 28%. 23
Figure 3.15. Influence of as-constructed asphalt contetn on rutting performance. 24
Figure 3.16. Influence of as-constructed air-void content on rutting performance. 25
Figure 3.17. Influence of as-constructed asphalt content on pavement rutting performance. 26
Figure 3.18. Influence of as-constructed asphalt content on pavement rutting
performance. 27
xii
Figure 3.19. Schematic illustration of annual costs of on-target and off-target
construction. 30
Figure A-1. Major components of testing and construction variance. 77
Figure C-1. WesTrack pavement respresentation for mechanistic-empirical modeling for
rutting. 81
Figure C-2. Time-hardening provedure for plastic strain accumulation under stress
repetitions of different magnitudes in compound loading. 83
Figure C-3. Framework for rut depth estimates. 85
Figure C-4. Comparison between computed and measured rut depth versus time;
Section 4. 87
Figure C-5. Comparison between computed and measured rut depth versus time;
Section 7. 88
Figure C-6. Comparison between computed and measured rut depth versus time;
Section 19. 89
Figure C-7. Comparison between computed and measured rut depth versus time;
Section 38. 90
Figure C-8. Permanent shear strain, iγ , versus load repetitions, n; rsst = 3778. 92
1
1.0 INTRODUCTION
The quality of the construction process is a major factor in determining how well a
pavement will perform under traffic loading and when subjected to environmental influences.
To improve the construction process, quality control/quality assurance (QC/QA) procedures and
pay incentives have been instituted in recent years. It is the objective of this report to
demonstrate a rational and feasible method for quantitatively establishing penalties/bonuses for
asphalt concrete construction with the initial emphasis placed on new asphalt concrete pavement
construction.
The approach makes use of performance models for asphalt concrete used to interpret the
results of the CAL/APT program (1) and WesTrack (2). The performance model for fatigue
resulted from the CAL/APT program while the one for rutting came from the WesTrack
accelerated pavement test program. For both modes of distress the system considers the means
and variances of asphalt content, air-void content, asphalt-concrete thickness, and aggregate
gradation. In estimating damage under traffic loading, the pavement is treated as a multilayer,
elastic system. The performance models compute the distribution of pavement life, expressed as
ESALs, using Monte Carlo simulation techniques.
Costs are established using a cost model which considers only the time to the next
rehabilitation activity. It understates agency costs by ignoring possible effects of construction
quality on future rehabilitation costs: it ignores future rehabilitation activity beyond the first
cycle. It requires an exogenous estimate of future rehabilitation costs, traffic growth, expected
years of new-pavement life, and a discount rate representing the time value of money.
The development of single sets of pay factors including both fatigue and rutting reflects
the following. The recommended bonus for superior work is the smaller of that for either fatigue
or rutting. For asphalt content, there are no bonuses for “dry” mixes. While such mixes may be
2
rut resistant, they may lead to early fatigue distress. The penalty for larger-than-target asphalt
content is determined by reduction in rutting resistance caused by surplus asphalt. For asphalt-
concrete thickness, the recommended pay factors are based only on fatigue performance while
for aggregate gradation, the recommended pay factors are based primarily on rutting. For air-
void content, the recommended pay factors reflect both fatigue and rutting considerations.
2.0 CONCEPT
Contractor pay incentives serve at least two objectives: (1) they encourage the contractor
to construct pavements with significantly improved performance in comparison to those meeting
minimum specification requirements, while at the same time, maintaining costs at reasonable
levels; and (2) they provide a rational alternative for dealing with marginally
inadequate/adequate construction. Many factors must be considered in the establishment of pay
schedules that not only realize these objectives but are mutually agreeable to the highway agency
and the contractor.
The approach taken herein for the development of pay factors focuses primarily on the
economic impacts to the highway agency. In this approach, the assumption is that an appropriate
penalty for inferior construction should be the added cost to the agency and that the bonus for
superior construction should be no greater than the added savings to the agency.
For new construction, for example, these agency costs/savings are associated primarily
with subsequent pavement rehabilitation. Inferior construction hastens the need for future
rehabilitation and may increase the cost of rehabilitation as well. As a result, inferior
construction increases the present worth of future rehabilitation costs. Superior construction, on
the other hand, reduces the present worth of these costs, largely by deferring the future
rehabilitation. The difference in present worths of rehabilitation costs, as constructed versus as
3
specified and as expected, provides a rational basis for setting the level of penalty/bonus for
inferior/superior construction quality.
3.0 MODELS
To compute the differential present worth of future rehabilitation requires two different
types of models: (1) a performance model or models for determining the effect of construction
quality on expected pavement performance; and (2) a cost model for translating these effects into
rehabilitation dollars.
Two performance models are described herein: one for fatigue cracking and the other for
rutting. For most construction situations, both performance models must be utilized to develop
appropriate pay factors. For this situation, the pay factors resulting from the use of the
performance models are based on the distress mode yielding the most beneficial consequence to
the agency; namely, smaller bonus and larger penalty. There may be circumstances in which
either of the two distress modes will be applicable. These situations will not be discussed herein
although the necessary information to do so is included.
The performance model used for fatigue is based on the mix analysis and design system
originally developed as a part of SHRP (3), extended to efficiently treat in-situ temperatures (4),
calibrated to the current Caltrans flexible pavement design system (5), extended to incorporate
construction variability (6), and used in interpreting the results of HVS tests on flexible
pavements, both new and overlaid, constructed at the Richmond Field Station according to
Caltrans Standards (1). The model used for rutting is based on mix performance data developed
at WesTrack (2).
In estimating damaging strains under traffic for fatigue cracking, the pavement is treated
as a multilayer elastic system. For rutting, the performance model is based on regression
4
analysis although multilayer elastic analysis was used in its development as well. In both
models, Monte Carlo simulations are used to obtain distributions of pavement lives.
The cost model considers only the time to the next rehabilitation activity; i.e., it ignores
future rehabilitation measures beyond the first cycle. It requires an estimate of future
rehabilitation cost; it considers annual inflation of rehabilitation costs, traffic growth, expected
years of the constructed life of the asphalt concrete, and a discount rate representing the time
value of money.
3.1 Performance Models
The processes embedded within the performance models are illustrated schematically in
Figure 3.1. Figure 3.1a shows the process for fatigue cracking and Figure 3.1b is that for rutting.
Central to these processes is the random selection of construction variable including air-void
content, asphalt content, aggregate gradation, and asphalt concrete thickness.1 For rutting, the
variables considered are air-void content, Vair, asphalt content, PWasp, and aggregate gradation
expressed in terms of the percent passing the No. 200 (0.075 mm) sieve, P200, and the fraction
passing the No. 8 (2.38 mm) sieve and retained on the No. 200 (0.075 mm) sieve, fa. For
fatigue, the variables include air-void content, asphalt content, and asphalt concrete thickness, t.
3.1.1 Variability Considerations
To consider the variability referred to in Figures 3.1a and 3.1b, the random selection of
the variables assumes normally distributed random variables with known or assumed means and
1 While not shown in Figure 3.1a (fatigue cracking) because it is only incidental to the computations, a randomselection was also made of the foundation modulus, a modulus representing the composite effects of base, subbase,and subgrade layers in an “equivalent” two-layer system.
5
variances. Of particular significance are the variances that might be expected under normal
construction operations. Estimates of these variances were obtained from a combination of
literature evaluation, back calculation of moduli from Falling Weight Deflectometer (FWD)
measurements, and data collected as a part of the WesTrack project (7). A summary of these
results are presented in Table 3.1.
The totals in Table 3.1 include not only materials and construction components, but also
components resulting from testing and sampling. To consider only materials and construction
effects, the testing and sampling components were removed from the variance estimates using
information contained in Table 3.2. Table 3.3 summarizes the results of this analysis, which is
briefly described in Appendix A (6). The equations for estimating the standard deviation of
asphalt-concrete thickness were developed as an approximate way to handle multilift
construction. Among the assumptions made in their development was that the coefficient of
variation of thickness in single-lift construction is about 14 percent.
3.1.2 Fatigue Cracking
The performance model used for fatigue follows the procedure illustrated schematically
in Figure 3.1a. It is based on the procedure described in Reference (5) utilizing fatigue test data
representative of mixes containing dense-graded aggregates meeting State of California
specifications.2
2 These gradings generally lie closer to the 0.45 curve than either the fine or coarse gradings used at WesTrack;however, the fatigue response of these mixes is likely similar to that of the mixes with the fine grading used atWesTrack.
6
Begin
Random selection of air-void content
Random selection of asphalt content
Random selection of asphalt-concrete thickness
Calculation of asphalt-concrete stiffness
Calculation of flexural strain in asphalt concrete
Calculation of "laboratory"fatigue life
Application of shift factor andtemperature conversion factor
Update of frequency distributionof "in-situ" fatigue life
More iterations?
End
No
Yes
3.1a
Begin
Determination of ESALs15*
Regression of ESALs15 withasphalt content, air-void content,
and gradation
Random selection of air-voidcontent
Random selection of asphaltcontent
Random selection of gradation(P200, fa)
Update of frequency distributionof "in-situ" rutting life
More iterations?
End
No
Yes
3.1b
Figure 3.1 Outlines of performance model simulations for fatigue cracking and rutting.
7
Table 3.1 Construction Variation of Mix and Structural Characteristics
Property Measure of Variation Value orRange Source
AsphaltContent
Standard DeviationStandard DeviationStandard DeviationStandard Deviation
0.15–0.44%0.1–0.4%
0.31%0.3%
Table 12.46 (7)Individual WesTrack sections (7)
WesTrack composite (7)Table 3 (8)
Air-voidContent
Standard DeviationStandard DeviationStandard DeviationStandard Deviation
0.9–1.9%0.4–1.5%
1.5%1.94%
Table 12.55 (7)Individual WesTrack sections (7)
WesTrack composite (7)Table 3 (8)
Thickness
Coefficient of VariationStandard DeviationStandard DeviationStandard Deviation
12.5–15%0–0.5 cm0.58 cm0.99 cm
Table 12.58 (7)Individual WesTrack sections (7)
WesTrack composite (7)Table 3 (8)
FoundationModulus
Coefficient of VariationCoefficient of VariationCoefficient of VariationCoefficient of Variation
11.3–14.7%17.3–44.7%3.6–17.7%14.2–28.5%
HVS test sections at UCB (1)Segment of highway in KY*
Individual WesTrack sections (7)WesTrack composite (7)
* Unpublished data, Kentucky DOT
Table 3.2 Materials/Construction Component of Total Construction Variance
Property Materials/ConstructionComponent (%) Source
Asphalt Content 4061
Figure 7 (9)Table 3 (8)
Air-Void Content 6090
Table 8 (inferred) (9)Table 3 (8)
Thickness 95 Table 3 (8)Foundation Modulus 70 Assumed
Table 3.3 Variation of Mix and Structural Characteristics for Monte CarloSimulations
Property Total StandardDeviation
Percentage of VarianceDue to
Materials/Construction
Materials/ConstructionComponent of Standard
DeviationAsphalt Content 0.30% 40 0.19%
Air-Void Content 1.6% 60 1.2%Asphalt Concrete
Thickness, t ( )cmt 69.0200.0 ⋅ 80 ( )cmt 69.0173.0 ⋅
FoundationModulus
30% (coefficientof variation) 70 25%
8
Multilayer elastic analysis with ELSYM5 was used to simulate the stress and strain states
with structures designed according to the State of California procedures. Table B-1 in Appendix
B provides a summary of the pavement structures analyzed. Loading consisted of a dual-tire
assembly of 9000 lbs. (40 kN) with a center-to-center spacing of 12 in. (300 mm) and a tire
contact pressure of 100 psi (690 kPa). The critically stressed location for fatigue was assumed to
be at the bottom boundary of the asphalt concrete layer.
As noted above, mix properties for use in the analysis were obtained by testing a
representative mix, the constituents for which included an AR-4000 asphalt cement from a
source in the Central Valley and a granite from the Logan quarry in Watsonville. The aggregate
gradation passed between the middle limits of the Caltrans 3/4 in. medium and coarse gradations.
Stiffness, Smix, and fatigue life, Nf, calibrations for this mix at 20°C (68°F) are as follows
(5):
( )Waspairmix PVS 17233.07577.0259.15exp −−= (3.1)
( )tWaspairf PVN εln71763.3575199.0164566.00012.22exp −+−−= (3.2)
Each of the Monte Carlo simulations produced an independent estimate of the laboratory
fatigue life, Nf . The corresponding simulated in-situ life, ESALs, was computed by applying a
shift factor, SF, and a temperature conversion factor, TCF, as follows:
TCFSFN
ESALs f ⋅= (3.3)
The shift factor is an empirically derived factor that accounts for differences between the
laboratory and the in-situ pavement in the rate at which fatigue damage accumulates with each
load application. For computations reported herein, the shift factor was calibrated to the Caltrans
design model following procedures described in Reference (5). Thickness replaced strain as the
9
independent variable, however, and engineering judgement was used to develop reasonable
estimates for the thickest and thinnest pavement sections. The shift factor was computed as
follows:
( ) 12t fortSF >−+= 1244.648.30 (3.4)
12t for3.6ttSF ≤≤+−= 5121.76109.23771.0 2 (3.5)
and
6.33 <= t forSF (3.6)
in which t is the asphalt-concrete thickness in inches. The temperature conversion factor, TCF,
is given by:
256.1ln754.1 −= tTCF (3.7)
4175.1 <= t forTCF (3.8)
For the analyses reported herein, the 10th percentile fatigue life was used as the basic
performance estimate. This life corresponds to about 10 percent fatigue cracking in the wheel
paths. As verified by sensitivity analysis, incremental agency costs due to off-target construction
(of either inferior or superior quality) are not significantly affected by the chosen performance
percentile (at least within a reasonable range of the 1st to the 20th percentile) (10).
Target values and standard deviations for asphalt content and air-void content are shown
in Table 3.4. This Table also contains an expression for the standard deviation of thickness (10)
used to develop this parameter for the sections analyzed. Table B-1 (Appendix B) contains a
summary of the four pavement sections used in the analyses. These are typical of California
construction for the range in traffic as defined by the Traffic Index (range 7–13).3 Table B-1 also
3 The Traffic Index provides a measure of the applied traffic expressed as ESALs according to the followingrelation: ESALs = 1.2895 × 102(TI)8.2919
10
contains the target standard deviations for thickness for the four sections, computed according to
the equation in Table 3.4.
Table 3.4 Construction Targets
Variable Mean
Total StandardDeviation (IncludingSampling andTesting)
Percent of VarianceAttributed to Materialsand Construction
Asphalt Content (%) 5.0 0.3 40Air-Void Content (%) 7.0 1.5 60Mineral Filler (%) 5.5 0.9 75Fine Aggregate (%) 30.0 3.0 85Asphalt-ConcreteThickness (in.)
4 pavementstructures
0.15 × AC thickness0.69 75
With these targets, Monte Carlo simulations were performed to quantify the effects of
construction quality on simulated in-situ fatigue performance.4 Each investigation employed
either 100,000 simulations (air-void content/relative compaction and asphalt-concrete thickness)
or 200,000 simulations (asphalt content). The levels and ranges used for these simulations are
shown in Table 3.5.
Table 3.5 Levels and Ranges for Variable EvaluatedMean As-Constructed Standard
DeviationVariableLevels Range Levels Range
Asphalt Content 21 4.0 to 6.0 9 0.114 to 0.266Air-Void Content 21 5.00 to 9.75 9 0.648 to 1.596Mineral Filler 21 3.0 to 8.0 9 0.4674 to 1.0906Fine Aggregate 21 24.0 to 36.0 9 1.6596 to 3.8724
Thickness 21 for each of 4pavement sections -1.0 to 1.0 9 4.8% to 11.2%
4 For fatigue, the effects of P200 were not included. Reference (2) describes the basis for the decision.
11
Results, for a structure identified as 11AB20 (Table B-1) are shown in Figures 3.2
through 3.4 illustrating the effects of air-void content, asphalt content, and asphalt concrete
thickness, respectively.
To illustrate the effects of air-void content (as a measure of mix compaction) on agency
costs, the information presented in Figure 3.2 will be utilized. For this example, a maximum
acceptable air-void content has been set at 9.75 percent. Because the air-void content is
considered to be a random variable, some violation of this maximum level during construction is
expected. Figure 3.5 illustrates how the tolerable level of non-compliance affects the
acceptability of various combinations of the average and the standard deviation of air-void
content. As the tolerable level of non-compliance increases, larger and more variable air-void
contents are judged to be acceptable. For the example shown herein, as well as for subsequent
calculations, the tolerable level of non-compliance has been set at 1 percent. This relatively
small (1 percent) failure percentage provides a reasonable probabilistic interpretation to what has
been viewed as a largely deterministic specification.
The influence of as-constructed air-void content on pavement performance is shown in
Figure 3.6. The best performance is associated with small averages and small standard
deviations of air-void content; that is, a consistently well-compacted asphalt concrete layer.
Details of the performance model used to produce Figure 3.6 are summarized in Table 3.6.
The highway agency can reasonably expect typical construction variability (a standard
deviation of air-void content of about 1.2 percent). It can also reasonably expect construction
operations to be in compliance with the specifications, in this case, a 1-percent failure tolerance
of the 9.75 percent air-void requirement. The expected pavement performance in this case,
corresponding to the target air-void content of 7 percent, is about 16,500,000 ESALs (Figure
12
3.7). This is a reasonable target against which to measure both inferior (less than 16,500,00
ESALs) and superior (more than 16,500,000 ESALs) construction.
0.0
0.5
1.0
1.5
2.0
2.5
3.0
5.0 5.5 6.0 6.5 7.0 7.5 8.0 8.5 9.0
As-constructed average air-void content (%)
Estim
ated
fatig
ue li
fe (m
ultip
le o
f tar
get
ESA
Ls a
t 90%
relia
bilit
y)
0.60%1.20%1.80%
As-constructedstandard
deviation ofair-void
content (%)
Figure 3.2. Effects of as-constructed air-void content on pavement fatigue performance.
0.0
0.5
1.0
1.5
2.0
2.5
3.0
4.0 4.5 5.0 5.5 6.0
As-constructed average asphalt content (%)
Estim
ated
fatig
ue li
fe (m
ultip
le o
f tar
get
ESA
Ls a
t 90%
relia
bilit
y)
0.095%0.190%0.285%
As-constructedstandard
deviation ofasphalt
content (%)
Figure 3.3. Effects of as-constructed asphalt content on pavement fatigue performance.
13
0.0
0.5
1.0
1.5
2.0
2.5
3.0
8.5 9.0 9.5 10.0 10.5
As-constructed average surface thickness (in)
Estim
ated
fatig
ue li
fe (m
ultip
le o
f tar
get
ESA
Ls a
t 90%
relia
bilit
y)
0.31 in0.62 in0.93 in
As-constructedstandard
deviation ofsurface
thickness (in)
Figure 3.4. Effects of as-constructed surface thickness on pavement fatigue performance.
Figure 3.5. Effect of specification failure level on acceptability of mix compaction.
14
Table 3.6 Summary of Parameters in ExampleContext New Pavement Construction
Performance Model
90-percent reliabilityCalifornia coastal temperaturesAverage asphalt content, 5%Standard deviation of asphalt content, 0.19%Standard deviation of thickness, 0.6 in.Coefficient of variation of foundation modulus, 25%
Construction Specification7.0% target air-void content9.75% maximum air-void content1% tolerable failure
Performance Expectation 16,500,000 ESALs
Pavement Structure
9.6-in. asphalt concrete (E = varies, v = 0.40)6-in. aggregate base (E = 25,000 psi, v = 0.45)8.4-in. aggregate subbase (E = 20,000 psi, v = 0.45)Subgrade (E = 12,200 psi, v = 0.50)
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
6.0 6.5 7.0 7.5 8.0 8.5 9.0 9.5As-constructed average air-void
10
12
14
16
18
20
Million ESALs90%
As-
cons
truc
ted
stan
dard
dev
iatio
n of
air-
void
con
tent
(%)
Figure 3.6. Influence of air-void content on pavement performance.
15
0.00
0.50
1.00
1.50
2.00
2.50
6.0 6.5 7.0 7.5 8.0 8.5 9.0 9.5
As-constructed average air-void content (%)
Expected performance(16.5 million ESALs)
Relative compaction(1% failure at 95% relative compaction)
As-
com
pact
ed s
tand
ard
devi
atio
n of
air-
void
con
tent
(%)
Figure 3.7. Expected pavement performance.
Contractor penalties can reasonably be extracted when the relative compaction
specification is not met and when performance is inferior. This penalty zone is highlighted in
the upper right of Figure 3.8. Contractor bonuses can reasonably be awarded when the relative-
density specification is met and when performance is superior. This bonus zone is highlighted in
the lower left of Figure 3.8. For other cases, no pay adjustment seems to be appropriate.
Although the left, wedge-shaped zone of Figure 3.8 represents conditions having better-than-
expected performance, a bonus should not be awarded because construction fails to meet
specification requirements. The right, wedge-shaped zone of Figure 3.8 represents complying
conditions, but performance fails to meet expectations and, hence, construction does not justify a
contractor bonus. The presence of these two wedge-shaped zones, due in part to the probabilistic
nature of both specification compliance and pavement performance, may explain traditional
problems in trying to link relative-compaction specifications with performance.
16
0.00
0.50
1.00
1.50
2.00
2.50
6.0 6.5 7.0 7.5 8.0 8.5 9.0 9.5As-constructed average air-void content (%)
Penalty (fails specificationwith inferior performance)
Bonus (meets specificationwith superior performance)
No pay adjustment(inferior performance)
No pay adjustment(fails specification)
As-
com
pact
ed s
tand
ard
devi
atio
n of
air-
void
con
tent
(%)
Figure 3.8. Influence of air-void content on contractor pay adjustment.
-30
-20
-10
0
10
20
30
50 75 100 125 150As-constructed ESALs (percent of expected ESALs)
Inferiorconstruction
Superiorconstruction
Pres
ent w
orth
of c
hang
e in
reha
bilit
atio
nco
st re
sulti
ng fr
om o
ff-ta
rget
con
stru
ctio
n(p
erce
nt o
f exp
ecte
d co
st)
Figure 3.9. Influence of pavement performance on pay factors.
17
The cost model to be discussed subsequently is based on a comparison between the as-
constructed pavement performance and the expected performance (16.5 × 106 ESALs). A
qualitative indication of the results of the use of the cost model is shown in Figure 3.9.
3.1.3 Permanent Deformation
The performance model used for permanent deformation is a regression equation based
on performance data obtained from the WesTrack experiment (2). This model includes the
effects of air-void content, asphalt content, and aggregate gradation. The resulting equation has
the following form:
( )faPafaVaVPafaa
VaPafaaVaPaaESALs
airairWasp
airWaspairWasprd
⋅⋅+⋅⋅+⋅⋅+⋅+
⋅+⋅+⋅+⋅+⋅+=
2009872
6
25
243210ln
(3.9)
where:
( )ESALsln = natural logarithm of ESALs to specific rut depth (mm),
e.g., rd = 15 mm (0.6 in.)
0a ……. 9a = regression coefficients, Table 3.7
Table 3.7 Regression Coefficients Relating ln(ESALs) to Mix Variables for SpecificLevels of Rutting
Downward Rut Depth (mm)3 6 9 12 15 18
Constant 4.15659 32.1396 35.6119 26.5116 19.6304 15.5941PWasp 4.80344 -4.13639 -4.9073 -1.07049 1.67468 3.32617Vair -0.271222 -0.9128258 -0.695417 -0.655977 -0.608102 -0.57752fa -0.0513972 -0.0561651 -0.060186 -0.066391 -0.0625076 -0.0665384
PWasp2 -0.637872 0.113609 0.174723 -0.18449 -0.430036 -0.574549
Vair2 0.162333 0.0152498 0.0176358 0.0161092 0.0204602 0.0197888
fa2 0.00134321 0.00146158 0.00160422 0.00165989 0.00170736 0.00171777PWasp·Vair 0.0275229 0.143108 0.103099 0.0964891 0.0809674 0.0765997Vair·fa -0.00849295 -0.00903533 -0.010073 -0.00935616 -0.01012 -0.00986111P200·fa 0.00863251 0.00886307 0.00964144 0.00927116 0.00949051 0.00962141R2 0.993 0.991 0.992 0.991 0.996 0.997
18
This equation is based on analysis of both the field performance of 23 test sections which
exhibited rutting (but no fatigue cracking) and the results of simple shear tests on laboratory-
prepared mixes containing gradings representative of the coarse and fine gradings at WesTrack.
Three gradings were used for each of the mixes; the target values and two variations of these
gradings. The ranges for each of the gradings are shown in Figure 3.10. Also shown in this
figure are representative gradings for the Caltrans 19.5-mm (3/4-in.) maximum coarse and
medium gradings. It will be noted that the range of gradings encompasses those likely to be used
for asphalt concrete in California. Reference (2) describes the procedure used to combine the
field and laboratory measured performance data.
Figures 3.11, 3.12, 3.13, and 3.14 illustrate the effects of specific mix parameters for
ESALs to a rut depth of 15 mm (0.6 in.). While other rut depths could be used for these
computations, the 15-mm rut depth was considered reasonable since it is in the range where
remedial action is required.
Using Equation 3.9 and the procedure shown in Figure 3.1b, a series of Monte Carlo
simulations were performed to define relationships between ESALs to 10-percent rutting [15 mm
(0.6 in.) or more] and the various mix parameters shown in Table 3.5. Figures 3.15 and 3.16
illustrate the effects of as-constructed asphalt content and air-void content on the ESALs to 10-
percent rutting (15 mm or more) for a range in standard deviations for each of the parameters.
Figure 3.17 and 3.18, respectively, illustrated the same information but plotted in the form of
asphalt content and air-void content versus as-constructed standard deviation of the associated
parameter. Isolines of ESALs to 10 percent rutting (15 mm or more) are shown in each of the
figures. Also shown are the construction targets.
0
10
20
30
40
50
60
70
80
90
100
2 1/213/41/23/848163050100
Sieve Size
Tota
l Per
cent
Pas
sing
Limits, WesTrack Coarse Low
Coarse High
Limits, WesTrack Fine High
Fine Low
3/4" Medium (middle of limits)
3/4" Coarse (middle of limits)
Figure 3.10. Range of aggregate gradings for WesTrack mixes compared with representative Caltrans gradings.
19
Figure 3.11. Effect of mix variables on simulated ESALs to 15 mm (0.6 in.) rut depth for a range in fine aggregate contents;Vair = 6.5%, P200 = 6.0%.
20
Figure 3.12 Effect of mix variables on simulated ESALs to 15 mm (0.6 in.) rut depth for a range in P200; Vair = 6.5%, fineaggregate = 28%.
21
Figure 3.13. Effect of mix variables on simulated ESALs to 15 mm (0.6 in.) rut depth for a range in air-void contents; P200 =6.0%, fine aggregate = 28%.
22
Figure 3.14. Effect of mix variables on simulated ESALs to 15 mm (0.6 in.) rut depth for a range in asphalt contents; P200 =6.0%, fine aggregate = 28%.
23
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.4 4.5 4.6 4.7 4.8 4.9 5 5.1 5.2 5.3 5.4
As-constructed average aspahlt content (%)
Sim
ulat
ed E
SAL'
s to
10%
rutti
ng (1
5mm
or m
ore
rut d
epth
) exp
rese
d as
fr
actio
n of
targ
et E
SALs
0.1140.190.266
Figure 3.15. Influence of as-constructed asphalt contetn on rutting performance.
24
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
5.5 5.6 5.7 5.8 5.9 6 6.1 6.2 6.3 6.4 6.5 6.6 6.7 6.8 6.9 7 7.1 7.2 7.3 7.4 7.5
As-constructed average air void content (%)
Sim
ulat
ed E
SALs
to 1
0% ru
tting
(15
mm
or m
ore
rut d
epth
) exp
ress
ed a
s m
ultip
le o
f tar
get E
SALs
0.61.21.8
Figure 3.16. Influence of as-constructed air-void content on rutting performance.
25
0.12
0.14
0.16
0.18
0.2
0.22
0.24
0.26
4.4 4.5 4.6 4.7 4.8 4.9 5 5.1 5.2 5.3 5.4As-constructed average asphalt content (%)
As-
cons
truc
ted
stan
dard
dev
iatio
n of
asp
halt
cont
ent
30
25
20
15
10
7
Numbers are million ESALs to 10% rutting (15mm or more)
Constructiontarget
18
Figure 3.17. Influence of as-constructed asphalt content on pavement rutting performance.
26
0.6
0.8
1
1.2
1.4
1.6
1.8
2
5.5 6 6.5 7 7.5 8 8.5
As-constructed average air-void content (%)
As-
cons
truc
ted
stan
dard
dev
iatio
n of
air-
void
con
tent
13
12 109
811
Numbers are million ESALs to 10% rutting (15 mm or more)
Construction target
Figure 3.18. Influence of as-constructed asphalt content on pavement rutting performance.
27
28
3.2 Cost Model
The performance models yield the 10th percentile in-situ lives for ruts (15 mm depth) and
fatigue cracking (10 percent in wheel paths) for both expected or on-target construction quality
as well as off-target construction quality. The relative performance, RP, the performance input
to the cost model, is computed as follows:
ESALs target-onESALs target-offRP = (3.10)
The first step in the cost model is to determine the off-target pavement life in years, OTY,
that results from the simulated performance differential. Assuming that traffic grows
geometrically, the off-target pavement life is computed as follows:
( )[ ]( )( )g
gRPOTYTY
+−++=
1ln111ln (3.11)
in which g is the annual rate of traffic growth expressed as a decimal and TY is the number of
years of pavement life resulting from on-target construction activity.
The cost model assesses the present worth of moving the first rehabilitation cycle from its
on-target position, TY, to its off-target position, OTY. The net present worth, expressed as a
percentage of the rehabilitation costs (in current-year dollars) is described in the following
paragraphs.
Assume that:
1. C is the resurfacing /rehabilitation cost in current-year dollars;
2. The pavement life, TY, is assumed to be 20 years;
3. r is the annual rate of growth in resurfacing/rehabilitation cost, that is, the
construction cost index;
4. d is the annual discount rate; and
29
5. OTY is the pavement life due to off-target construction.
Then on-target construction will result in:
1. a future cost of C(F/P, r%,20) at the end of the 20-year target period; or
2. an annual equivalent of C(F/P, r%,20)(A/F,d%,20) for 20 years.
where:
F = future worth
P = present worth
A = annuity amount
Off-target construction will result in:
1. a future cost of C(F/P, r%,20) at the end of the off-target period; or
2. an annual equivalent of C(F/P, r%,OTY)(A/F,d%,OTY) for OTY years.
In the event that the OTY is less than the target period, the off-target construction
increases the agency costs over the expected life of 20 years by the present worth of the
difference between these annual cost streams over the OTY period. These costs are illustrated
schematically in Figure 3.19. Their present worth is:
( )( ) ( )( )[ ]( )OTYdAPdFArPFCOTYdFAOTYrPFC %,,20%,,20%,,%,,%,, −
The equation for this expression is:
( )( )
( )( )
( )( )
����
�
+−+
���
���
�
−++−
−++=∆ OTY
OTY
OTY
OTY
dd
dr
drCPW
111
111
111
20
20
(3.12)
When OTY exceeds the target life, the service life for comparison purposes may be set at
either the target life, in this example, 20 years, or the longer OTY. It should be noted that if the
longer period is chosen, it is beneficial to the contractor’s interests.
0
2
4
6
8
10
12
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Year
Ann
ual c
ost
Annual cost of on-target construction = C (F/P,r%,20) (A/F,d%,20)
Annual cost of off-target construction = C (F/P,r%,OTY) (A/F,d%,OTY)
Annual difference = C (F/P,r%,OTY) (A/F,d%,OTY) -
C (F/P,r%,20) (A/F,d%,20)
Figure 3.19. Schematic illustration of annual costs of on-target and off-target construction.
30
31
While the majority of the pay factor computations to be presented subsequently are based
on the assumption of a target pavement life of 20 years (time to first rehabilitation), some
computations will be presented for other target values (TY) ranging from 10 to 30 years.
4.0 PAY FACTORS
With the information presented in Section 3, it is then possible to determine the
construction pay factors. The following considerations are reflected in the recommended pay
factor schedules included herein:
1. One pay-factor should apply to all new construction; that is, job-specific pay factors
are undesirable
2. The contractor should generally be charged a penalty for inferior construction which
is out of specification, the magnitude of which should equal the full added cost to the
agency for failure to meet the construction target;
3. The contractor should generally be rewarded for superior construction which is within
specification, the magnitude of which should be some fraction of the full added
benefit to the agency resulting from improved pavement performance;
4. Pay factor schedules should incorporate average and standard-deviation categories
consistent with the accuracy within which estimates are determined from field
measurements; and
5. The standard deviation of pay-factor schedules must reflect expected testing and
sampling errors as well as materials/construction variables.
For the actual pay factors developed in this section, bonuses for superior construction and
penalties for inferior construction reflect full agency cost increments. Eventually it will be
32
necessary to make a decision for the fraction of the bonus to be paid for superior construction as
noted in item (3) above. In addition, the examples reflect the following:
1. The sole construction quality effect is the date of first resurfacing/rehabilitation.
2. Both fatigue and rutting distress are reflected in the pay factor schedule. Each entry
in the pay factor schedule is based on the distress mode yielding most beneficial
consequence to the agency, namely, smaller bonus or larger penalty.
3. Pay factors are determined independently for each pay quantity. The combined pay
factor is computed by the following equation:
( )( )( )( )( ) 111111 −+++++= tfamfavac pfpfpfpfpffactorpayCombined (4.1)
in which all pay factors are expressed as decimals. Section 4.4 describes the basis for
this simplified expression for combining pay factors. For convenience, the
definitions which are utilized are summarized as follows:
a) Asphalt content (ac): Percentage of asphalt by weight of total mixture
b) Air-void content (av): Percentage of air voids by volume of total mixture
c) Mineral filler (mf): Aggregate passing 0.074 mm (No. 200) sieve expressed as a
percentage by weight of aggregate
d) Fine aggregate (fa): Aggregate passing 2.36 mm (No. 8) sieve and retained on
0.074 mm (No. 200) sieve expressed as a percentage by weight of aggregate
e) Rutting life: ESALs to 10-percent of rutting with downward depths of 15 mm or
more based on WesTrack performance
f) Fatigue life: ESALs to 10-percent cracking based on Caltrans experience as
summarized by the Caltrans analysis and design model.
33
4.1 Pay Factors—Twenty-Year Expected Pavement Life
The computations in this section, in addition to the assumption of a 20-year expected
pavement life (TY in Equation 3.4) are based on the following cost parameters:
1. 2% annual rate of inflation in resurfacing/rehabilitation cost (r)
2. 2.5% annual rate of traffic growth (g)
3. 5% discount rate (d)
4. Rutting failure results in resurfacing which costs 20% of the cost of new pavement
construction in current-year dollars
5. Fatigue failure results in rehabilitation which costs 50% of the cost of new pavement
construction in current-year dollars.
The cost implications of off-target construction have been determined according to the
procedure described in Section 3.3. Tables 4.1 through 4.4 present the results of the rutting
analysis based on the WesTrack model for rutting. Tables 4.5 through 4.7 present the results of
the fatigue analysis using the California model. Tables 4.5 through 4.7 present the results of the
fatigue analysis using the California model. Tables 4.8 through 4.12 present the results of the
combined analysis showing results most favorable to the agency.
With this information, it is then possible to establish pay-factor tables. These are shown
in Tables 4.13 through 4.17 for each of the five factors considered. The pay factors for air-void
content do not include the effects of either, a) the area where the specification is met but the
performance is inferior to that of the target, or b) the area where the specification is not met but
the performance is superior to that of the target (Figure 3.8).
34
Table 4.1 Effect of off-target asphalt content on future agency resurfacing cost basedon rutting in WesTrack pavements (change expressed as a percent of newpavement construction cost).
As-constructed standard deviation of asphalt content (multiple of 0.19%)As-constructedaverage asphalt
content (%) 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.44.0 -13.9 -13.9 -13.8 -13.8 -13.7 -13.6 -13.5 -13.4 -13.34.1 -13.4 -13.4 -13.3 -13.2 -13.1 -13.0 -12.9 -12.8 -12.64.2 -12.8 -12.7 -12.6 -12.5 -12.4 -12.2 -12.1 -11.9 -11.74.3 -12.0 -11.9 -11.8 -11.6 -11.5 -11.3 -11.2 -10.9 -10.84.4 -11.1 -11.0 -10.8 -10.7 -10.5 -10.3 -10.0 -9.8 -9.54.5 -10.0 -9.9 -9.6 -9.5 -9.2 -9.0 -8.7 -8.5 -8.14.6 -8.7 -8.5 -8.3 -8.1 -7.8 -7.5 -7.2 -6.9 -6.54.7 -7.2 -7.0 -6.7 -6.5 -6.2 -5.8 -5.5 -5.0 -4.74.8 -5.5 -5.3 -4.9 -4.7 -4.3 -3.9 -3.5 -3.1 -2.64.9 -3.7 -3.3 -3.0 -2.6 -2.2 -1.8 -1.3 -0.9 -0.45.0 -1.6 -1.2 -0.9 -0.4 0.0 0.5 0.9 1.5 2.05.1 0.7 1.0 1.5 1.9 2.3 2.8 3.4 3.9 4.45.2 3.0 3.3 3.8 4.2 4.8 5.2 5.8 6.2 6.85.3 5.3 5.7 6.1 6.6 7.1 7.6 8.1 8.5 9.05.4 7.6 8.0 8.5 8.9 9.3 9.8 10.2 10.7 11.15.5 9.8 10.2 10.6 10.9 11.4 11.8 12.2 12.6 13.15.6 11.8 12.1 12.5 12.9 13.2 13.6 14.0 14.3 14.75.7 13.5 13.9 14.2 14.5 14.8 15.2 15.4 15.8 16.05.8 15.1 15.3 15.7 15.9 16.2 16.4 16.7 16.9 17.25.9 16.4 16.6 16.8 17.1 17.3 17.5 17.7 17.9 18.16.0 17.4 17.6 17.8 18.0 18.2 18.3 18.5 18.6 18.7
35
Table 4.2 Effect of off-target air-void content on future agency resurfacing cost basedon rutting in WesTrack pavement (change expressed as a percent of newpavement construction cost).
As-constructed standard deviation of relativecompaction (multiple of 1.2%)As-constructed air-
void content (%)0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4
5.00 -5.1 -5.0 -4.9 -4.8 -4.6 -4.3 -4.3 -4.0 -3.85.25 -4.5 -4.4 -4.2 -4.2 -3.9 -3.9 -3.6 -3.5 -3.25.50 -3.9 -3.8 -3.7 -3.5 -3.4 -3.2 -3.1 -3.0 -2.75.7 -3.4 -3.2 -3.1 -2.9 -2.8 -2.6 -2.6 -2.4 -2.16.00 -2.7 -2.7 -2.5 -2.4 -2.2 -2.2 -2.0 -1.9 -1.76.25 -2.2 -2.1 -2.0 -1.9 -1.7 -1.6 -1.4 -1.4 -1.26.4 -1.6 -1.5 -1.5 -1.3 -1.3 -1.1 -1.0 -0.9 -0.76.7 -1.1 -1.0 -0.9 -0.9 -0.8 -0.6 -0.6 -0.5 -0.36.9 -0.6 -0.5 -0.4 -0.4 -0.3 -0.3 0.0 0.0 0.17.1 -0.1 0.0 0.0 0.1 0.2 0.3 0.3 0.4 0.57.4 0.3 0.4 0.5 0.6 0.6 0.7 0.7 0.8 0.97.6 0.8 0.8 0.9 0.9 1.0 1.0 1.1 1.2 1.27.85 1.2 1.2 1.3 1.3 1.4 1.4 1.5 1.6 1.58.1 1.6 1.6 1.6 1.7 1.7 1.8 1.8 1.9 1.98.3 2.0 2.0 2.0 2.0 2.1 2.1 2.1 2.2 2.18.6 2.3 2.3 2.4 2.4 2.4 2.4 2.5 2.5 2.48.8 2.6 2.7 2.6 2.7 2.7 2.7 2.7 2.7 2.79.0 2.9 2.9 2.9 2.9 2.9 3.0 2.9 3.0 2.99.3 3.2 3.1 3.2 3.1 3.2 3.1 3.2 3.1 3.19.5 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.39.75 3.6 3.6 3.6 3.7 3.5 3.6 3.5 3.6 3.5
36
Table 4.3 Effect of off-target mineral filler on future agency resurfacing cost based onrutting in WesTrack pavement (change expressed as a percent of newpavement construction cost).
As-constructed standard deviation of mineral filler (multiple of 0.7794%)As-constructedaverage mineral
filler (%) 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.43.00 6.9 7.0 7.0 7.2 7.3 7.4 7.5 7.7 7.83.25 6.2 6.3 6.4 6.5 6.6 6.7 6.9 7.0 7.13.50 5.5 5.5 5.7 5.8 6.0 6.0 6.2 6.3 6.53.75 4.7 4.9 5.0 5.1 5.2 5.4 5.5 5.7 5.84.00 4.1 4.1 4.2 4.4 4.4 4.6 4.8 5.0 5.04.25 3.4 3.4 3.6 3.6 3.8 3.9 4.0 4.2 4.44.50 2.6 2.7 2.8 2.9 3.0 3.1 3.3 3.4 3.64.75 1.9 2.0 2.0 2.2 2.3 2.5 2.5 2.8 2.85.00 1.1 1.2 1.3 1.4 1.6 1.7 1.8 1.9 2.15.25 0.4 0.4 0.6 0.7 0.8 0.9 1.1 1.2 1.45.50 -0.5 -0.3 -0.3 -0.1 0.0 0.2 0.3 0.5 0.65.75 -1.2 -1.1 -1.0 -0.8 -0.7 -0.6 -0.4 -0.2 -0.16.00 -1.9 -1.8 -1.7 -1.7 -1.4 -1.4 -1.2 -1.1 -0.86.25 -2.7 -2.5 -2.4 -2.3 -2.3 -2.1 -1.9 -1.8 -1.66.50 -3.4 -3.3 -3.2 -3.0 -3.0 -2.8 -2.7 -2.4 -2.46.75 -4.1 -4.0 -3.8 -3.8 -3.7 -3.5 -3.4 -3.3 -3.17.00 -4.8 -4.7 -4.6 -4.5 -4.4 -4.3 -4.1 -4.0 -3.87.25 -5.5 -5.3 -5.4 -5.2 -5.1 -4.9 -4.8 -4.7 -4.57.50 -6.1 -6.1 -6.0 -5.9 -5.8 -5.6 -5.5 -5.3 -5.27.75 -6.8 -6.7 -6.6 -6.6 -6.4 -6.3 -6.1 -6.1 -5.88.00 -7.4 -7.3 -7.3 -7.2 -7.1 -7.0 -6.8 -6.7 -6.6
37
Table 4.4 Effect of off-target fine aggregate on future agency resurfacing cost based onrutting in WesTrack pavement (change expressed as a percent of newpavement construction cost).
As-constructed standard deviation of fineaggregate (multiple of 2.7659%)
As-constructedaverage fine
aggregate (%) 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.424.0 0.1 0.1 0.1 0.1 0.0 0.0 0.0 0.0 0.024.6 0.2 0.1 0.2 0.1 0.1 0.0 0.1 0.0 0.125.2 0.2 0.2 0.2 0.2 0.1 0.1 0.1 0.0 0.025.8 0.3 0.2 0.2 0.2 0.1 0.1 0.1 0.1 0.026.4 0.3 0.2 0.3 0.2 0.2 0.1 0.1 0.1 0.127.0 0.2 0.2 0.2 0.2 0.2 0.2 0.1 0.1 0.127.6 0.2 0.2 0.1 0.2 0.1 0.2 0.1 0.1 0.028.2 0.2 0.2 0.2 0.2 0.1 0.1 0.1 0.1 0.028.8 0.2 0.1 0.1 0.1 0.1 0.0 0.1 0.0 0.129.4 0.1 0.2 0.1 0.1 0.0 0.0 0.0 0.0 -0.130.0 0.1 0.0 0.1 0.0 0.0 0.0 -0.1 -0.1 -0.130.6 0.0 0.0 0.0 -0.1 0.0 -0.1 -0.1 -0.2 -0.131.2 -0.1 -0.1 -0.2 -0.1 -0.2 -0.1 -0.2 -0.2 -0.231.8 -0.2 -0.2 -0.2 -0.2 -0.2 -0.2 -0.3 -0.2 -0.432.4 -0.3 -0.4 -0.3 -0.4 -0.3 -0.4 -0.3 -0.4 -0.433.0 -0.4 -0.4 -0.4 -0.5 -0.4 -0.5 -0.5 -0.5 -0.433.6 -0.6 -0.5 -0.6 -0.6 -0.6 -0.5 -0.7 -0.6 -0.734.2 -0.6 -0.7 -0.7 -0.7 -0.7 -0.7 -0.8 -0.7 -0.834.8 -0.8 -0.8 -0.8 -0.9 -0.8 -0.9 -0.8 -1.0 -0.835.4 -1.1 -1.0 -1.0 -1.0 -1.0 -1.0 -1.0 -1.1 -1.136.0 -1.2 -1.2 -1.2 -1.2 -1.2 -1.1 -1.2 -1.1 -1.3
38
Table 4.5 Effect of off-target asphalt content on future agency rehabilitation cost basedon Caltrans fatigue model (change expressed as a percent of new pavementconstruction cost).
As-constructed standard deviation of asphalt content (multiple of 0.19%)As-constructedaverage asphalt
content (%) 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.44.0 3.2 3.2 3.2 3.2 3.3 3.3 3.3 3.3 3.34.1 2.8 2.9 2.9 2.9 2.9 2.9 2.9 2.9 2.94.2 2.6 2.6 2.6 2.6 2.6 2.6 2.6 2.6 2.64.3 2.2 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.34.4 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 2.04.5 1.6 1.6 1.6 1.6 1.6 1.6 1.6 1.6 1.64.6 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.34.7 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.04.8 0.6 0.6 0.6 0.6 0.6 0.7 0.7 0.7 0.74.9 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.35.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.05.1 -0.3 -0.3 -0.3 -0.3 -0.3 -0.3 -0.3 -0.3 -0.35.2 -0.7 -0.7 -0.7 -0.7 -0.7 -0.7 -0.7 -0.7 -0.75.3 -1.0 -1.0 -1.0 -1.0 -1.0 -1.0 -1.0 -1.0 -1.05.4 -1.4 -1.4 -1.4 -1.4 -1.4 -1.4 -1.4 -1.4 -1.45.5 -1.7 -1.7 -1.7 -1.7 -1.7 -1.7 -1.7 -1.7 -1.75.6 -2.1 -2.1 -2.1 -2.1 -2.1 -2.1 -2.1 -2.0 -2.05.7 -2.5 -2.4 -2.4 -2.4 -2.4 -2.4 -2.4 -2.4 -2.45.8 -2.8 -2.8 -2.8 -2.8 -2.8 -2.7 -2.7 -2.7 -2.75.9 -3.1 -3.1 -3.1 -3.1 -3.1 -3.1 -3.1 -3.1 -3.16.0 -3.5 -3.5 -3.5 -3.5 -3.5 -3.5 -3.5 -3.5 -3.5
39
Table 4.6 Effect of off-target air-void content on future agency rehabilitation costbased on Caltrans fatigue model (change expressed as a percent of newpavement construction cost).
As-constructed standard deviation of relativecompaction (multiple of 1.2%)As-constructed air-
void content (%) 0.6 0.7 0.8 0.9 1.0 1.2 1.3 1.4 1.65.00 -20.4 -19.9 -19.3 -18.7 -18.1 -17.4 -16.7 -15.9 -15.15.25 -18.7 -18.1 -17.5 -16.9 -16.2 -15.4 -14.7 -13.9 -13.05.50 -16.8 -16.2 -15.6 -14.9 -14.2 -13.4 -12.6 -11.8 -10.95.7 -14.9 -14.3 -13.6 -12.9 -12.1 -11.3 -10.5 -9.7 -8.86.00 -12.9 -12.2 -11.5 -10.8 -10.0 -9.2 -8.4 -7.5 -6.66.25 -10.8 -10.1 -9.4 -8.6 -7.9 -7.0 -6.2 -5.3 -4.36.4 -8.7 -8.0 -7.3 -6.5 -5.7 -4.8 -3.9 -3.0 -2.16.7 -6.6 -5.8 -5.1 -4.3 -3.4 -2.6 -1.7 -0.8 0.26.9 -4.4 -3.6 -2.8 -2.0 -1.2 -0.3 0.5 1.5 2.47.1 -2.2 -1.4 -0.6 0.2 1.0 1.9 2.8 3.7 4.67.4 0.1 0.8 1.6 2.4 3.2 4.1 5.0 5.9 6.87.6 2.3 3.0 3.8 4.6 5.4 6.3 7.2 8.0 9.07.85 4.5 5.3 6.0 6.8 7.6 8.4 9.3 10.2 11.18.1 6.7 7.4 8.2 8.9 9.7 10.5 11.4 12.2 13.18.3 8.8 9.6 10.3 11.0 11.8 12.6 13.4 14.2 15.18.6 10.9 11.6 12.4 13.1 13.8 14.6 15.3 16.1 16.98.8 13.0 13.7 14.3 15.0 15.7 16.5 17.2 17.9 18.79.0 15.0 15.6 16.3 16.9 17.6 18.3 19.0 19.7 20.49.3 16.9 17.5 18.1 18.7 19.3 20.0 20.6 21.3 21.99.5 18.7 19.2 19.8 20.4 21.0 21.5 22.1 22.7 23.39.75 20.4 20.9 21.4 21.9 22.5 23.0 23.5 24.1 24.6
40
Table 4.7 Effect of off-target asphalt-concrete thickness on future agency rehabilitationcost based on Caltrans fatigue model (change expressed as a percent of newpavement construction cost).
As-constructed standard deviation of asphalt-concrete thickness (multiple of 8%)
Difference betweenas-measured average
asphalt-concretethickness and design
thickness (in.) 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4-1.0 17.7 18.5 19.2 19.9 20.7 21.4 22.3 23.0 23.8-0.9 15.9 16.7 17.4 18.2 19.0 19.8 20.6 21.4 22.3-0.8 14.0 14.8 15.6 16.4 17.2 18.1 18.9 19.8 20.7-0.7 12.0 12.8 13.6 14.5 15.3 16.2 17.1 18.0 18.9-0.6 9.9 10.8 11.6 12.5 13.3 14.2 15.1 16.1 17.1-0.5 7.8 8.6 9.5 10.4 11.3 12.2 13.1 14.1 15.1-0.4 5.6 6.4 7.3 8.2 9.1 10.1 11.0 12.0 13.1-0.3 3.3 4.2 5.0 5.9 6.9 7.9 8.9 9.9 11.0-0.2 1.0 1.9 2.7 3.7 4.6 5.6 6.6 7.6 8.8-0.1 -1.3 -0.5 0.5 1.4 2.3 3.3 4.3 5.3 6.40.0 -3.5 -2.7 -1.9 -1.0 0.0 1.0 2.0 3.0 4.10.1 -5.8 -5.0 -4.1 -3.2 -2.3 -1.4 -0.3 0.7 1.80.2 -7.9 -7.1 -6.3 -5.5 -4.6 -3.6 -2.7 -1.6 -0.60.3 -10.1 -9.3 -8.5 -7.7 -6.8 -5.9 -5.0 -4.0 -2.90.4 -12.1 -11.3 -10.6 -9.8 -8.9 -8.1 -7.1 -6.2 -5.20.5 -14.1 -13.3 -12.6 -11.8 -11.0 -10.2 -9.3 -8.4 -7.40.6 -16.0 -15.3 -14.6 -13.8 -13.0 -12.2 -11.4 -10.5 -9.50.7 -17.9 -17.2 -16.5 -15.8 -15.0 -14.2 -13.4 -12.5 -11.60.8 -20.0 -19.3 -18.5 -17.7 -17.0 -16.2 -15.4 -14.5 -13.70.9 -22.3 -21.4 -20.6 -19.8 -19.0 -18.2 -17.3 -16.5 -15.61.0 -24.8 -23.9 -22.9 -22.0 -21.2 -20.3 -19.4 -18.6 -17.7
41
Table 4.8 Effect of off-target asphalt content on future agencyresurfacing/rehabilitation costs (change expressed as a percent of newpavement construction cost).
As-constructed standard deviation of asphalt content (multiple of 0.19%)As-constructedaverage asphalt
content (%) 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.44.0 3.2 3.2 3.2 3.2 3.3 3.3 3.3 3.3 3.34.1 2.8 2.9 2.9 2.9 2.9 2.9 2.9 2.9 2.94.2 2.6 2.6 2.6 2.6 2.6 2.6 2.6 2.6 2.64.3 2.2 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.34.4 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 2.04.5 1.6 1.6 1.6 1.6 1.6 1.6 1.6 1.6 1.64.6 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.34.7 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.04.8 0.6 0.6 0.6 0.6 0.6 0.7 0.7 0.7 0.74.9 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.35.0 0.0 0.0 0.0 0.0 0.0 0.5 0.9 1.5 2.05.1 0.7 1.0 1.5 1.9 2.3 2.8 3.4 3.9 4.45.2 3.0 3.3 3.8 4.2 4.8 5.2 5.8 6.2 6.85.3 5.3 5.7 6.1 6.6 7.1 7.6 8.1 8.5 9.05.4 7.6 8.0 8.5 8.9 9.3 9.8 10.2 10.7 11.15.5 9.8 10.2 10.6 10.9 11.4 11.8 12.2 12.6 13.15.6 11.8 12.1 12.5 12.9 13.2 13.6 14.0 14.3 14.75.7 13.5 13.9 14.2 14.5 14.8 15.2 15.4 15.8 16.05.8 15.1 15.3 15.7 15.9 16.2 16.4 16.7 16.9 17.25.9 16.4 16.6 16.8 17.1 17.3 17.5 17.7 17.9 18.16.0 17.4 17.6 17.8 18.0 18.2 18.3 18.5 18.6 18.7
42
Table 4.9 Effect of off-target air-void content on future agencyresurfacing/rehabilitation costs (change expressed as a percent of newpavement construction cost).
As-constructed standard deviation of relativecompaction (multiple of 1.2%)As-constructed air-
void content (%) 0.6 0.7 0.8 0.9 1.0 1.2 1.3 1.4 1.6100.00 -5.1 -5.0 -4.9 -4.8 -4.6 -4.3 -4.3 -4.0 -3.899.75 -4.5 -4.4 -4.2 -4.2 -3.9 -3.9 -3.6 -3.5 -3.299.50 -3.9 -3.8 -3.7 -3.5 -3.4 -3.2 -3.1 -3.0 -2.799.25 -3.4 -3.2 -3.1 -2.9 -2.8 -2.6 -2.6 -2.4 -2.199.00 -2.7 -2.7 -2.5 -2.4 -2.2 -2.2 -2.0 -1.9 -1.798.75 -2.2 -2.1 -2.0 -1.9 -1.7 -1.6 -1.4 -1.4 -1.298.50 -1.6 -1.5 -1.5 -1.3 -1.3 -1.1 -1.0 -0.9 -0.798.25 -1.1 -1.0 -0.9 -0.9 -0.8 -0.6 -0.6 -0.5 0.298.00 -0.6 -0.5 -0.4 -0.4 -0.3 -0.3 0.5 1.5 2.497.75 -0.1 0.0 0.0 0.2 1.0 1.9 2.8 3.7 4.697.50 0.3 0.8 1.6 2.4 3.2 4.1 5.0 5.9 6.897.25 2.3 3.0 3.8 4.6 5.4 6.3 7.2 8.0 9.097.00 4.5 5.3 6.0 6.8 7.6 8.4 9.3 10.2 11.196.75 6.7 7.4 8.2 8.9 9.7 10.5 11.4 12.2 13.196.50 8.8 9.6 10.3 11.0 11.8 12.6 13.4 14.2 15.196.25 10.9 11.6 12.4 13.1 13.8 14.6 15.3 16.1 16.996.00 13.0 13.7 14.3 15.0 15.7 16.5 17.2 17.9 18.795.75 15.0 15.6 16.3 16.9 17.6 18.3 19.0 19.7 20.495.50 16.9 17.5 18.1 18.7 19.3 20.0 20.6 21.3 21.995.25 18.7 19.2 19.8 20.4 21.0 21.5 22.1 22.7 23.395.00 20.4 20.9 21.4 21.9 22.5 23.0 23.5 24.1 24.6
43
Table 4.10 Effect of off-target mineral filler on future agency resurfacing/rehabilitationcosts (change expressed as a percent of new pavement construction cost).
As-constructed standard deviation of mineral filler (multiple of 0.7794%)As-constructedaverage mineral
filler (%) 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.43.00 6.9 7.0 7.0 7.2 7.3 7.4 7.5 7.7 7.83.25 6.2 6.3 6.4 6.5 6.6 6.7 6.9 7.0 7.13.50 5.5 5.5 5.7 5.8 6.0 6.0 6.2 6.3 6.53.75 4.7 4.9 5.0 5.1 5.2 5.4 5.5 5.7 5.84.00 4.1 4.1 4.2 4.4 4.4 4.6 4.8 5.0 5.04.25 3.4 3.4 3.6 3.6 3.8 3.9 4.0 4.2 4.44.50 2.6 2.7 2.8 2.9 3.0 3.1 3.3 3.4 3.64.75 1.9 2.0 2.0 2.2 2.3 2.5 2.5 2.8 2.85.00 1.1 1.2 1.3 1.4 1.6 1.7 1.8 1.9 2.15.25 0.4 0.4 0.6 0.7 0.8 0.9 1.1 1.2 1.45.50 -0.5 -0.3 -0.3 -0.1 0.0 0.2 0.3 0.5 0.65.75 -1.2 -1.1 -1.0 -0.8 -0.7 -0.6 -0.4 -0.2 -0.16.00 -1.9 -1.8 -1.7 -1.7 -1.4 -1.4 -1.2 -1.1 -0.86.25 -2.7 -2.5 -2.4 -2.3 -2.3 -2.1 -1.9 -1.8 -1.66.50 -3.4 -3.3 -3.2 -3.0 -3.0 -2.8 -2.7 -2.4 -2.46.75 -4.1 -4.0 -3.8 -3.8 -3.7 -3.5 -3.4 -3.3 -3.17.00 -4.8 -4.7 -4.6 -4.5 -4.4 -4.3 -4.1 -4.0 -3.87.25 -5.5 -5.3 -5.4 -5.2 -5.1 -4.9 -4.8 -4.7 -4.57.50 -6.1 -6.1 -6.0 -5.9 -5.8 -5.6 -5.5 -5.3 -5.27.75 -6.8 -6.7 -6.6 -6.6 -6.4 -6.3 -6.1 -6.1 -5.88.00 -7.4 -7.3 -7.3 -7.2 -7.1 -7.0 -6.8 -6.7 -6.6
44
Table 4.11 Effect of off-target fine aggregate on future agency resurfacing/rehabilitationcosts (change expressed as a percent of new pavement construction cost).
As-constructed standard deviation of fine aggregate(multiple of 2.7659%)
As-constructedaverage fine
aggregate (%) 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.424.0 0.1 0.1 0.1 0.1 0.0 0.0 0.0 0.0 0.024.6 0.2 0.1 0.2 0.1 0.1 0.0 0.1 0.0 0.125.2 0.2 0.2 0.2 0.2 0.1 0.1 0.1 0.0 0.025.8 0.3 0.2 0.2 0.2 0.1 0.1 0.1 0.1 0.026.4 0.3 0.2 0.3 0.2 0.2 0.1 0.1 0.1 0.127.0 0.2 0.2 0.2 0.2 0.2 0.2 0.1 0.1 0.127.6 0.2 0.2 0.1 0.2 0.1 0.2 0.1 0.1 0.028.2 0.2 0.2 0.2 0.2 0.1 0.1 0.1 0.1 0.028.8 0.2 0.1 0.1 0.1 0.1 0.0 0.1 0.0 0.129.4 0.1 0.2 0.1 0.1 0.0 0.0 0.0 0.0 -0.130.0 0.1 0.0 0.1 0.0 0.0 0.0 -0.1 -0.1 -0.130.6 0.0 0.0 0.0 -0.1 0.0 -0.1 -0.1 -0.2 -0.131.2 -0.1 -0.1 -0.2 -0.1 -0.2 -0.1 -0.2 -0.2 -0.231.8 -0.2 -0.2 -0.2 -0.2 -0.2 -0.2 -0.3 -0.2 -0.432.4 -0.3 -0.4 -0.3 -0.4 -0.3 -0.4 -0.3 -0.4 -0.433.0 -0.4 -0.4 -0.4 -0.5 -0.4 -0.5 -0.5 -0.5 -0.433.6 -0.6 -0.5 -0.6 -0.6 -0.6 -0.5 -0.7 -0.6 -0.734.2 -0.6 -0.7 -0.7 -0.7 -0.7 -0.7 -0.8 -0.7 -0.834.8 -0.8 -0.8 -0.8 -0.9 -0.8 -0.9 -0.8 -1.0 -0.835.4 -1.1 -1.0 -1.0 -1.0 -1.0 -1.0 -1.0 -1.1 -1.136.0 -1.2 -1.2 -1.2 -1.2 -1.2 -1.1 -1.2 -1.1 -1.3
45
Table 4.12 Effect of off-target asphalt concrete thickness on future agencyresurfacing/rehabilitation costs (change expressed as a percent of newpavement construction cost).
As-constructed standard deviation ofasphalt-concrete thickness (multiple of 8%)
Difference between as-measured averageasphalt-concrete
thickness and designthickness (in) 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4
-1.0 17.7 18.5 19.2 19.9 20.7 21.4 22.3 23.0 23.8-0.9 15.9 16.7 17.4 18.2 19.0 19.8 20.6 21.4 22.3-0.8 14.0 14.8 15.6 16.4 17.2 18.1 18.9 19.8 20.7-0.7 12.0 12.8 13.6 14.5 15.3 16.2 17.1 18.0 18.9-0.6 9.9 10.8 11.6 12.5 13.3 14.2 15.1 16.1 17.1-0.5 7.8 8.6 9.5 10.4 11.3 12.2 13.1 14.1 15.1-0.4 5.6 6.4 7.3 8.2 9.1 10.1 11.0 12.0 13.1-0.3 3.3 4.2 5.0 5.9 6.9 7.9 8.9 9.9 11.0-0.2 1.0 1.9 2.7 3.7 4.6 5.6 6.6 7.6 8.8-0.1 -1.3 -0.5 0.5 1.4 2.3 3.3 4.3 5.3 6.40.0 -3.5 -2.7 -1.9 -1.0 0.0 1.0 2.0 3.0 4.10.1 -5.8 -5.0 -4.1 -3.2 -2.3 -1.4 -0.3 0.7 1.80.2 -7.9 -7.1 -6.3 -5.5 -4.6 -3.6 -2.7 -1.6 -0.60.3 -10.1 -9.3 -8.5 -7.7 -6.8 -5.9 -5.0 -4.0 -2.90.4 -12.1 -11.3 -10.6 -9.8 -8.9 -8.1 -7.1 -6.2 -5.20.5 -14.1 -13.3 -12.6 -11.8 -11.0 -10.2 -9.3 -8.4 -7.40.6 -16.0 -15.3 -14.6 -13.8 -13.0 -12.2 -11.4 -10.5 -9.50.7 -17.9 -17.2 -16.5 -15.8 -15.0 -14.2 -13.4 -12.5 -11.60.8 -20.0 -19.3 -18.5 -17.7 -17.0 -16.2 -15.4 -14.5 -13.70.9 -22.3 -21.4 -20.6 -19.8 -19.0 -18.2 -17.3 -16.5 -15.61.0 -24.8 -23.9 -22.9 -22.0 -21.2 -20.3 -19.4 -18.6 -17.7
46
Table 4.13 Contractor pay factors for asphalt content (percentage of futureresurfacing/rehabilitation cost in current-year dollars).
As-measured standard deviation of asphalt content (%)Difference between as-
measured average asphaltcontent and design asphalt
content (%) Below 0.255 0.255 to 0.345 Above 0.345-1.10 to -0.91 -3 -3 -3-0.90 to 0.71 -3 -3 -3-0.70 to -0.51 -2 -2 -2-0.50 to -0.31 -1 -1 -1-0.30 to -0.11 -1 -1 -1-0.10 to 0.09 0 0 -10.10 to 0.29 -3 -5 -60.30 to 0.49 -8 -9 -110.50 to 0.69 -12 -13 -140.70 to 0.89 -15 -16 -170.90 to 1.09 -18 -18 -19
Table 4.14 Contractor pay factors for air-void content (percentage of futureresurfacing/rehabilitation cost in current-year dollars).
As-measured standard deviation of relative compaction (%)As-measured averagerelative compaction (%) Below 1.32 1.32 to 1.78 Above 1.78
100.25 to 99.76 5 5 499.75 to 99.26 4 3 399.25 to 98.76 3 2 298.75 to 98.26 2 1 198.25 to 97.76 1 0 -197.75 to 97.26 -1 -3 -697.25 to 96.76 -5 -8 -1096.75 to 96.26 -10 -12 -1496.25 to 95.76 -14 -16 -1895.75 to 95.26 -17 -19 -2195.25 to 94.76 -21 -22 -24
47
Table 4.15 Contractor pay factors for asphalt-concrete thickness (percentage of futureresurfacing/rehabilitation cost in current-year dollars).
As-measured standard deviation ofasphalt-concrete thickness (%)
Difference between as-measured average asphalt-
concrete thickness anddesign thickness (in) Below 7.85 7.85 to 10.62 Above 10.62
-1.10 to -0.89 -18 -21 -23-0.90 to -0.69 -15 -17 -20-0.70 to -0.49 -11 -13 -16-0.50 to -0.29 -6 -9 -12-0.30 to -0.09 -2 -5 -8-0.10 to 0.09 3 0 -30.10 to 0.29 7 5 20.30 to 0.49 11 9 60.50 to 0.69 15 13 100.70 to 0.89 19 17 150.90 to 1.09 24 21 19
Table 4.16 Contractor pay factors for mineral filler (percentage of futureresurfacing/rehabilitation cost in current-year dollars).
As-measured standard deviation of mineral filler (%)Difference between as-measuredaverage mineral filler and design
mineral filler (%) Below 0.765 0.765 to 1.035 Above 1.035-2.75 to -2.26 -7 -7 -8-2.25 to -1.76 -6 -6 -6-1.75 to - 1.26 -4 -4 -5-1.25 to -0.76 -3 -3 -3-0.75 to -0.26 -1 -2 -2-0.25 to 0.24 0 0 00.25 to 0.74 2 1 10.75 to 1.24 3 3 31.25 to 1.74 5 4 41.75 to 2.24 6 6 52.25 to 2.74 7 7 7
48
Table 4.17 Contractor pay factors for fine aggregate (percentage of futureresurfacing/rehabilitation cost in current-year dollars).
As-measured standard deviation of fine aggregate (%)Difference between as-measured average fine
aggregate and design fineaggregate (%) Below 2.55 2.55 to 3.45 Above 3.45
-6.6 to - 5.5 0 0 0-5.4 to -4.3 0 0 0-4.2 to -3.1 0 0 0-3.0 to -1.9 0 0 0-1.8 to -0.7 0 0 0-0.6 to 0.5 0 0 00.6 to 1.7 0 0 01.8 to 2.9 0 0 03.0 to 4.1 1 1 14.2 to 5.3 1 1 15.4 to 6.5 1 1 1
4.2 Pay Factors—Influence of Expected Pavement Life and Cost Parameters
The pay factors computed in the previous section are based on what are considered
“reasonable” cost parameters and a target design life of 20 years.
In discussions with Caltrans staff, some different parameters have been suggested. For
example, Caltrans currently uses an annual rate of inflation for pavement costs of 3.5 percent. In
addition, a variety of design periods are used:
Category Design PeriodNew pavement 40Rehabilitated pavement (urban) 30-35Rehabilitated pavement (rural) 10-20CapM5 5
The influence of some of these parameters on pay factors is analyzed in this section.
The first study involved changing the target pavement life to 10 years and increasing the
annual inflation rate to 3.5 percent. The other factors were the same as used in Section 4.1., i.e.,
5 CapM refers to Capital Preventative Maintenance projects
49
g = 2.5 percent, d = 5 percent, and the cost of rehabilitation for rutting and fatigue were 20 and
50 percent of new pavement construction, respectively.
Tables 4.18 through 4.20 show the cost implications of off-target construction for both
rutting and fatigue and their combined values. Table 4.21 summarizes the pay factors for asphalt
content. It will be noted that the negative pay factors for low asphalt content are larger than
those for the 20-year target pavement life (Table 4.13) whereas the negative factors for high
asphalt content are similar to those in the table.
Tables 4.22 through 4.25 show the contractor pay factors for air-void content, AC
thickness, mineral filler, and fine aggregate. Of particular significance are the more severe pay
factors associated with pavement thickness variations for the 10-year target life as compared to
the 20-year life. The effects of aggregate grading on pay factors is relatively little influenced by
pavement life, i.e., 10 years versus 20 years.
Tables 4.26 through 4.35 illustrate the same pay factor determination for 30 and 20 year
target lives using an annual inflation rate of 3.5 percent. It will be noted that the inflation rate
has the most significant impact on pay factors for AC thickness (Table 4.23 versus Table 4.28
versus Table 4.33).
4.3 Comparison of Current Caltrans Pay Factors with Those Obtained fromPerformance Models Presented Herein
Caltrans personnel supplied information for an overlay project on SR-299 in Trinity
County between Salyer and Del Loma.(11) Construction started in June 1999 and was
completed in March 2000. In July 1999 bleeding was observed in the eastbound lane. During
the period July 7 to July 23, 1999 the contractor placed an average of 2300 tonnes per day.
Table 4.36 lists the pay factors and daily AC tonnage for this period. It will be noted that the
50
Table 4.18 Effect of off-target asphalt content on future agency resurfacing cost basedon rutting in WesTrack pavements (change expressed as a percent of newpavement construction cost); target life = 10 years, r = 3.5 percent
As-constructed standard deviation of asphalt content (multiple of 0.19%)As-constructedaverage asphalt
content (%) 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.44.0 -27.0 -26.9 -26.7 -26.5 -26.3 -26.0 -25.8 -25.4 -25.34.1 -25.5 -25.4 -25.1 -24.9 -24.6 -24.4 -24.0 -23.7 -23.34.2 -23.8 -23.6 -23.3 -23.0 -22.7 -22.4 -22.0 -21.7 -21.24.3 -21.8 -21.5 -21.3 -20.9 -20.6 -20.1 -19.8 -19.3 -18.94.4 -19.6 -19.3 -18.9 -18.6 -18.2 -17.7 -17.2 -16.7 -16.14.5 -17.1 -16.8 -16.4 -16.0 -15.4 -15.1 -14.4 -14.0 -13.24.6 -14.5 -14.0 -13.7 -13.2 -12.7 -12.1 -11.5 -10.9 -10.34.7 -11.5 -11.2 -10.6 -10.1 -9.6 -9.0 -8.4 -7.6 -7.14.8 -8.5 -8.1 -7.5 -7.0 -6.4 -5.8 -5.1 -4.5 -3.74.9 -5.4 -4.9 -4.4 -3.7 -3.2 -2.5 -1.8 -1.2 -0.55.0 -2.2 -1.7 -1.2 -0.6 0.0 0.7 1.2 2.0 2.65.1 0.9 1.3 1.9 2.5 3.0 3.6 4.3 4.9 5.65.2 3.8 4.3 4.8 5.3 6.0 6.4 7.1 7.6 8.35.3 6.6 7.1 7.5 8.0 8.5 9.0 9.6 10.0 10.55.4 9.1 9.5 10.0 10.4 10.8 11.3 11.7 12.2 12.65.5 11.3 11.7 12.1 12.4 12.9 13.2 13.6 13.9 14.35.6 13.2 13.5 13.8 14.2 14.5 14.8 15.1 15.5 15.75.7 14.8 15.1 15.3 15.6 15.9 16.2 16.4 16.7 16.95.8 16.1 16.3 16.6 16.8 17.0 17.2 17.4 17.6 17.85.9 17.2 17.4 17.5 17.7 17.9 18.1 18.2 18.4 18.56.0 18.0 18.2 18.3 18.5 18.6 18.7 18.8 18.9 19.0
51
Table 4.19 Effect of off-target asphalt content on future agency rehabilitation cost basedon Caltrans fatigue model (change expressed as a percent of new pavementconstruction cost); target life = 10 years, r = 3.5 percent.
As-constructed standard deviation of asphalt content (multiple of 0.19%)As-constructedaverage asphalt
content (%) 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.44.0 16.4 16.4 16.4 16.4 16.7 16.7 16.7 16.7 16.74.1 14.6 14.9 14.9 14.9 14.9 14.9 14.9 14.9 14.94.2 13.0 13.0 13.0 13.0 13.0 13.3 13.3 13.3 13.34.3 11.2 11.5 11.5 11.5 11.5 11.5 11.5 11.5 11.54.4 9.7 9.7 9.7 9.7 9.7 9.7 9.7 9.7 10.04.5 8.0 8.0 8.0 8.3 8.3 8.3 8.3 8.3 8.34.6 6.5 6.5 6.5 6.5 6.5 6.5 6.5 6.5 6.54.7 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 5.14.8 3.1 3.1 3.1 3.1 3.1 3.4 3.4 3.4 3.44.9 1.4 1.4 1.7 1.7 1.7 1.7 1.7 1.7 1.75.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.05.1 -1.7 -1.7 -1.7 -1.7 -1.7 -1.7 -1.7 -1.7 -1.75.2 -3.3 -3.3 -3.3 -3.3 -3.3 -3.3 -3.3 -3.3 -3.35.3 -4.9 -4.9 -4.9 -4.9 -4.9 -4.9 -4.9 -4.9 -4.95.4 -6.7 -6.7 -6.5 -6.5 -6.5 -6.5 -6.5 -6.5 -6.55.5 -8.3 -8.3 -8.3 -8.3 -8.1 -8.1 -8.1 -8.1 -8.15.6 -9.9 -9.9 -9.9 -9.9 -9.9 -9.9 -9.9 -9.6 -9.65.7 -11.6 -11.4 -11.4 -11.4 -11.4 -11.4 -11.4 -11.4 -11.45.8 -13.2 -13.2 -13.2 -13.2 -13.2 -12.9 -12.9 -12.9 -12.95.9 -14.6 -14.6 -14.6 -14.6 -14.6 -14.6 -14.6 -14.6 -14.66.0 -16.4 -16.4 -16.4 -16.4 -16.4 -16.4 -16.1 -16.1 -16.1
52
Table 4.20 Effect of off-target asphalt content on future agencyresurfacing/rehabilitation costs (change expressed as a percent of newpavement construction cost); target life = 10 years, r = 3.5 percent.
As-constructed standard deviation of asphalt content (multiple of 0.19%)As-constructedaverage asphalt
content (%) 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.44.0 16.4 16.4 16.4 16.4 16.7 16.7 16.7 16.7 16.74.1 14.6 14.9 14.9 14.9 14.9 14.9 14.9 14.9 14.94.2 13.0 13.0 13.0 13.0 13.0 13.3 13.3 13.3 13.34.3 11.2 11.5 11.5 11.5 11.5 11.5 11.5 11.5 11.54.4 9.7 9.7 9.7 9.7 9.7 9.7 9.7 9.7 10.04.5 8.0 8.0 8.0 8.3 8.3 8.3 8.3 8.3 8.34.6 6.5 6.5 6.5 6.5 6.5 6.5 6.5 6.5 6.54.7 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 5.14.8 3.1 3.1 3.1 3.1 3.1 3.4 3.4 3.4 3.44.9 1.4 1.4 1.7 1.7 1.7 1.7 1.7 1.7 1.75.0 0.0 0.0 0.0 0.0 0.0 0.7 1.2 2.0 2.65.1 0.9 1.3 1.9 2.5 3.0 3.6 4.3 4.9 5.65.2 3.8 4.3 4.8 5.3 6.0 6.4 7.1 7.6 8.35.3 6.6 7.1 7.5 8.0 8.5 9.0 9.6 10.0 10.55.4 9.1 9.5 10.0 10.4 10.8 11.3 11.7 12.2 12.65.5 11.3 11.7 12.1 12.4 12.9 13.2 13.6 13.9 14.35.6 13.2 13.5 13.8 14.2 14.5 14.8 15.1 15.5 15.75.7 14.8 15.1 15.3 15.6 15.9 16.2 16.4 16.7 16.95.8 16.1 16.3 16.6 16.8 17.0 17.2 17.4 17.6 17.85.9 17.2 17.4 17.5 17.7 17.9 18.1 18.2 18.4 18.56.0 18.0 18.2 18.3 18.5 18.6 18.7 18.8 18.9 19.0
53
Table 4.21 Contractor pay factors for asphalt content (percentage of futureresurfacing/rehabilitation cost in current-year dollars); target life = 10 years,r = 3.5 percent.
As-measured standard deviation of asphalt content (%)Difference between as-
measured average asphaltcontent and design asphalt
content (%) Below 0.255 0.255 to 0.345 Above 0.345-1.10 to -0.91 -16 -17 -17-0.90 to 0.71 -13 -13 -13-0.70 to -0.51 -10 -10 -10-0.50 to -0.31 -7 -7 -7-0.30 to -0.11 -3 -3 -3-0.10 to 0.09 0 0 -20.10 to 0.29 -4 -6 -80.30 to 0.49 -10 -11 -120.50 to 0.69 -13 -15 -150.70 to 0.89 -16 -17 -180.90 to 1.09 -18 -19 -19
Table 4.22 Contractor pay factors for air-void content (percentage of futureresurfacing/rehabilitation cost in current-year dollars); target life = 10 years,r = 3.5 percent.
As-measured standard deviation of relative compaction (%)As-measured average air-void content (%) Below 1.32 1.32 to 1.78 Above 1.78
4.8 to 5.10 8 7 65.15 to 5.7 6 5 45.75 to 6.20 4 3 36.25 to 6.65 2 2 16.7 to 7.05 1 0 -17.1 to 7.55 -1 -3 -67.6 to 8.05 -5 -8 -108.1 to 8.55 -10 -12 -148.6 to 8.95 -14 -16 -189.0 to 9.45 -17 -19 -219.5 to 10.0 -21 -22 -24
54
Table 4.23 Contractor pay factors for asphalt-concrete thickness (percentage of futureresurfacing/rehabilitation cost in current-year dollars); target life = 10 years,r = 3.5 percent.
As-measured standard deviation ofasphalt-concrete thickness (%)
Difference between as-measured average asphalt-
concrete thickness anddesign thickness (in) Below 7.85 7.85 to 10.62 Above 10.62
-1.10 to -0.89 -117 -135 -155-0.90 to -0.69 -89 -107 -128-0.70 to -0.49 -62 -79 -99-0.50 to -0.29 -34 -51 -70-0.30 to -0.09 -9 -24 -42-0.10 to 0.09 13 0 -160.10 to 0.29 31 21 80.30 to 0.49 47 38 270.50 to 0.69 59 52 440.70 to 0.89 70 64 570.90 to 1.09 80 74 68
Table 4.24 Contractor pay factors for mineral filler (percentage of futureresurfacing/rehabilitation cost in current-year dollars); target life = 10 years,r = 3.5 percent.
As-measured standard deviation of mineral filler (%)Difference between as-measuredaverage mineral filler and design
mineral filler (%) Below 0.765 0.765 to 1.035 Above 1.035-2.75 to -2.26 -8 -9 -9-2.25 to -1.76 -7 -7 -8-1.75 to - 1.26 -5 -6 -6-1.25 to -0.76 -4 -4 -4-0.75 to -0.26 -2 -2 -3-0.25 to 0.24 0 0 -10.25 to 0.74 3 2 10.75 to 1.24 5 4 41.25 to 1.74 7 7 61.75 to 2.24 9 9 82.25 to 2.74 12 11 11
55
Table 4.25 Contractor pay factors for fine aggregate (percentage of futureresurfacing/rehabilitation cost in current-year dollars); target life = 10 years,r = 3.5 percent.
As-measured standard deviation of fine aggregate (%)Difference between as-measured average fine
aggregate and design fineaggregate (%) Below 2.55 2.55 to 3.45 Above 3.45
-6.6 to -5.5 0 0 0-5.4 to -4.3 0 0 0-4.2 to -3.1 0 0 0-3.0 to -1.9 0 0 0-1.8 to -0.7 0 0 0-0.6 to 0.5 0 0 00.6 to 1.7 0 0 01.8 to 2.9 0 0 13.0 to 4.1 1 1 14.2 to 5.3 1 1 15.4 to 6.5 2 2 2
Table 4.26 Contractor pay factors for asphalt content (percentage of futureresurfacing/rehabilitation cost in current-year dollars); target life = 30 years,r = 3.5 percent.
As-measured standard deviation of asphalt content (%)Difference between as-
measured average asphaltcontent and design asphalt
content (%) Below 0.255 0.255 to 0.345 Above 0.345-1.10 to -0.91 -4 -4 -4-0.90 to 0.71 -3 -3 -3-0.70 to -0.51 -2 -2 -2-0.50 to -0.31 -2 -2 -2-0.30 to -0.11 -1 -1 -1-0.10 to 0.09 0 0 -10.10 to 0.29 -3 -4 -50.30 to 0.49 -7 -8 -90.50 to 0.69 -11 -12 -130.70 to 0.89 -14 -15 -160.90 to 1.09 -17 -18 -18
56
Table 4.27 Contractor pay factors for air-void content (percentage of futureresurfacing/rehabilitation cost in current-year dollars); target life = 30 years,r = 3.5 percent.
As-measured standard deviation of relative compaction (%)As-measured averagerelative compaction (%) Below 1.32 1.32 to 1.78 Above 1.78
100.25 to 99.76 4 3 399.75 to 99.26 3 3 299.25 to 98.76 2 2 198.75 to 98.26 1 1 198.25 to 97.76 0 0 -197.75 to 97.26 -1 -3 -697.25 to 96.76 -5 -8 -1096.75 to 96.26 -10 -12 -1496.25 to 95.76 -14 -16 -1895.75 to 95.26 -17 -19 -2195.25 to 94.76 -21 -22 -24
Table 4.28 Contractor pay factors for asphalt-concrete thickness (percentage of futureresurfacing/rehabilitation cost in current-year dollars); target life = 30 years,r = 3.5 percent.
As-measured standard deviation ofasphalt-concrete thickness (%)
Difference between as-measured average asphalt-
concrete thickness anddesign thickness (in) Below 7.85 7.85 to 10.62 Above 10.62
-1.10 to -0.89 -25 -28 -32-0.90 to -0.69 -19 -23 -27-0.70 to -0.49 -14 -17 -21-0.50 to -0.29 -8 -11 -15-0.30 to -0.09 -2 -6 -9-0.10 to 0.09 3 0 -40.10 to 0.29 8 5 20.30 to 0.49 12 10 70.50 to 0.69 16 14 110.70 to 0.89 20 17 150.90 to 1.09 24 21 19
57
Table 4.29 Contractor pay factors for mineral filler (percentage of futureresurfacing/rehabilitation cost in current-year dollars); target life = 30 years,r = 3.5 percent.
As-measured standard deviation of mineral filler (%)Difference between as-measuredaverage mineral filler and design
mineral filler (%) Below 0.765 0.765 to 1.035 Above 1.035-2.75 to -2.26 -6 -6 -6-2.25 to -1.76 -5 -5 -5-1.75 to - 1.26 -3 -4 -4-1.25 to -0.76 -2 -2 -3-0.75 to -0.26 -1 -1 -2-0.25 to 0.24 0 0 00.25 to 0.74 1 1 10.75 to 1.24 2 2 21.25 to 1.74 4 3 31.75 to 2.24 4 4 42.25 to 2.74 5 5 5
Table 4.30 Contractor pay factors for fine aggregate (percentage of futureresurfacing/rehabilitation cost in current-year dollars); target life = 30 years,r = 3.5 percent.
As-measured standard deviation of fine aggregate (%)Difference between as-measured average fine
aggregate and design fineaggregate (%) Below 2.55 2.55 to 3.45 Above 3.45
-6.6 to - 5.5 0 0 0-5.4 to -4.3 0 0 0-4.2 to -3.1 0 0 0-3.0 to -1.9 0 0 0-1.8 to -0.7 0 0 0-0.6 to 0.5 0 0 00.6 to 1.7 0 0 01.8 to 2.9 0 0 03.0 to 4.1 0 0 04.2 to 5.3 1 1 15.4 to 6.5 1 1 1
58
Table 4.31 Contractor pay factors for asphalt content (percentage of futureresurfacing/rehabilitation cost in current-year dollars); target life = 20 years,r = 3.5 percent.
As-measured standard deviation of asphalt content (%)Difference between as-
measured average asphaltcontent and design asphalt
content (%) Below 0.255 0.255 to 0.345 Above 0.345-1.10 to -0.91 -7 -7 -7-0.90 to 0.71 -5 -5 -5-0.70 to -0.51 -4 -4 -4-0.50 to -0.31 -3 -3 -3-0.30 to -0.11 -1 -1 -1-0.10 to 0.09 0 0 -10.10 to 0.29 -3 -5 -60.30 to 0.49 -8 -9 -110.50 to 0.69 -12 -13 -140.70 to 0.89 -15 -16 -170.90 to 1.09 -18 -18 -19
Table 4.32 Contractor pay factors for air-void content (percentage of futureresurfacing/rehabilitation cost in current-year dollars); target life = 20 years,r = 3.5 percent.
As-measured standard deviation of relative compaction (%)As-measured averagerelative compaction (%) Below 1.32 1.32 to 1.78 Above 1.78
100.25 to 99.76 4 3 399.75 to 99.26 3 3 299.25 to 98.76 2 2 198.75 to 98.26 1 1 198.25 to 97.76 0 0 -197.75 to 97.26 -1 -3 -697.25 to 96.76 -5 -8 -1096.75 to 96.26 -10 -12 -1496.25 to 95.76 -14 -16 -1895.75 to 95.26 -17 -19 -2195.25 to 94.76 -21 -22 -24
59
Table 4.33 Contractor pay factors for asphalt-concrete thickness (percentage of futureresurfacing/rehabilitation cost in current-year dollars); target life = 20 years,r = 3.5 percent.
As-measured standard deviation ofasphalt-concrete thickness (%)
Difference between as-measured average asphalt-
concrete thickness anddesign thickness (in) Below 7.85 7.85 to 10.62 Above 10.62
-1.10 to -0.89 -46 -52 -60-0.90 to -0.69 -35 -42 -50-0.70 to -0.49 -25 -31 -39-0.50 to -0.29 -17 -20 -28-0.30 to -0.09 -4 -10 -17-0.10 to 0.09 5 0 -60.10 to 0.29 13 9 30.30 to 0.49 20 16 120.50 to 0.69 26 23 190.70 to 0.89 31 28 250.90 to 1.09 37 34 31
Table 4.34 Contractor pay factors for mineral filler (percentage of futureresurfacing/rehabilitation cost in current-year dollars) ; target life = 20years, r = 3.5 percent.
As-measured standard deviation of mineral filler (%)Difference between as-measuredaverage mineral filler and design
mineral filler (%) Below 0.765 0.765 to 1.035 Above 1.035-2.75 to -2.26 -7 -7 -8-2.25 to -1.76 -6 -6 -6-1.75 to - 1.26 -4 -4 -5-1.25 to -0.76 -3 -3 -3-0.75 to -0.26 -1 -2 -2-0.25 to 0.24 0 0 00.25 to 0.74 2 1 10.75 to 1.24 3 3 31.25 to 1.74 5 4 41.75 to 2.24 6 6 52.25 to 2.74 7 7 7
60
Table 4.35 Contractor pay factors for fine aggregate (percentage of futureresurfacing/rehabilitation cost in current-year dollars); target life = 20 years,r = 3.5 percent.
As-measured standard deviation of fine aggregate (%)Difference between as-measured average fine
aggregate and design fineaggregate (%) Below 2.55 2.55 to 3.45 Above 3.45
-6.6 to - 5.5 0 0 0-5.4 to -4.3 0 0 0-4.2 to -3.1 0 0 0-3.0 to -1.9 0 0 0-1.8 to -0.7 0 0 0-0.6 to 0.5 0 0 00.6 to 1.7 0 0 01.8 to 2.9 0 0 03.0 to 4.1 0 0 04.2 to 5.3 1 1 15.4 to 6.5 1 1 1
Table 4.36 Pay Factor Summary—Overlay Project, SR 299, Trinity County, July 1999AC Pay Factor and Tonnes Summary
Date Day Sample Pay Factor Daily Tonnes Total Tonnes07/06/99 Tue 1-5 1.0087 2,093 2,09307/07/99 Wed 6-13 1.0447 3,569 5,66207/08/99 Thu 14-20 1.0407 3,186 8,84907/09/99 Fri 21-28 1.0367 3,547 12,39507/12/99 Mon 29-36 1.0311 3,482 15,87707/13/99 Tue 37-40 1.0341 1,838 17,71507/14/99 Wed 41-47 1.0291 3,347 21,06207/16/99 Fri 48-53 1.0281 2,866 23,92807/19/99 Mon 54-61 1.0311 3,507 27,43507/20/99 Tue 62-68 1.0291 2,930 30,36407/21/99 Wed 69-76 1.0341 3,590 33,95407/22/99 Thu 77-79 1.0371 1,635 35,59007/23/99 Fri 80-83 1.0371 1,606 37,195
61
contractor received a bonus for the project even though a segment of the resurfacing exhibited
bleeding. The project thus provided an opportunity to compare pay factors developed in Section
4.2 with those currently used in the Caltrans Specifications Quality Control/Quality Assurance
for Asphalt Concrete.
From an analysis of the mix data for the project which had been supplied by Caltrans, the
mix tends to be a “critical” mix; that is, small increases in asphalt content lead to significant
decreases in mix stability as measured by the stabilometer. It was also noted that the contractor
appeared to operate on the high side of the binder content range.
Using data prepared by one of the contractor’s testing laboratories (June 8, 1999), a
significant reduction in stability occurs in the range 5.0 to 5.5 percent binder content, a reduction
from 46 to 23, with a corresponding reduction in air-void content from 2.6 to 1.5 percent. These
air-void content determinations are based on the computation procedure described in CA Test
Method 367 using aggregate specific gravities determined in accordance with CA Test Methods
206 and 207.
With a critical mix, if the original Hveem procedure were followed, one would back off
0.5 percent from the binder content corresponding (in this case) to S=37. This would suggest a
binder content of 4.7 percent as the target value. Secondly, a stricter control in binder content
would be placed, that is ±0.3 percent.
Data from tests on field cores indicate binder contents, reported in the District 3 Materials
Lab memo data August 1999, to be on the high side resulting in low stabilometer values
associated with low air-void contents.
Using pay factors reported in Section 4.2 and considering only binder content, a pay
factor of about 0.9 would be obtained. This is based on an actual value 0.4 percent above the
62
actual target value of 4.8 percent and a standard deviation of 0.3 percent resulting in an off-target
life of about 4 years. If the standard deviation in binder content were larger or the actual value
larger than that stated, the pay factor would be further reduced. The effects of the improved
relative compaction would tend to increase the factor slightly; however, this would not overcome
the potential for bleeding such as was observed on some of the sections.
It must be emphasized that the pay factor determinations (Section .42) are based on a 10-
year life for a mix constructed at the target value for binder content and the rutting performance
model developed from the WesTrack data.
If the same target life was used, i.e., 10 years and the off-target life was assumed to be 1
year, then the pay factor used would be substantially less than the value of 0.9 noted above.
4.4 Combined Pay Factors
Combined pay factors can be determined from the information presented in, for example,
Tables 4.13 through 4.17 using Equation 4.1. This equation results from a series of simulations
reported in Reference (10), as discussed below.
Considering only fatigue performance, 10 conditions (five for air-void content and five
for thickness), which individually resulted in a “constant” pay factor of about –20 percent, were
selected. The combination effects from the simulations are shown in Table 4.37. Interestingly,
the combination pay factor is about –36 percent, when both air-void content and thickness are
off-target with individual pay factors of –20 percent each. This suggests the possibility that the
combination pay factor as a decimal fraction, cpf, might be expressed as follows:
( )( ) 111 −++= tav pfpfcpf (4.2)
in which the individual pay factors are expressed as decimal fractions instead of percents.
63
To further investigate this possibility, the simulations of Table 4.38 were performed.
Again, the focus was on air-void content/relative compaction and thickness because these are the
dominant parameters of interest. This time, however, the as-constructed conditions were
selected to yield large ranges in individual pay factors including bonuses (instead of –20
percent). Next, calculations for comparable conditions using the above equation yielded results
summarized in Table 4.39. Although there is one notable difference at one extreme (96.1 percent
versus 69.1 percent), results of the combined simulations (Table 4.38) and the computations
(Table 4.39) are in remarkable agreement. As a result, Equation 4.2 seems suitable for
determining pay factors for combined conditions. An extension to include asphalt content yields
the following recommendation for computing combined contractor pay factors:
( )( )( ) 1111 −+++= tacav pfpfpfcpf (4.3)
Equation 4.3, following completion of the WesTrack analyses, was extended to include
the effects of aggregate gradation as follows:
( )( )( )( )( ) 111111)( −+++++= tfamfavac pfpfpfpfpfCPFFactorPayCombined (4.4)
Consider the following using Tables 4.13 through 4.17. A contractor has compacted a
mix to an air-void content of 5.0 percent (target value = 7 percent) with standard deviation of 1.6
percent; the asphalt content was 0.5 percent above target with a standard deviation of 0.4
percent; the mineral filler was 0.5 percent above target with a standard deviation of 1.2 percent;
the fine aggregate was on target with a standard deviation of 3 percent; and the thickness was 0.3
in. below target with a standard deviation of 8.5 percent.
For these conditions, the combined pay factor is:
( )( )( )( )( ) %8383.008.010101.0104.0114.01 orCPF =−−−−−=
64
Table 4.37 Pay Factors for Combination Conditions (from Simulations) (Conditions Setto Yield Individual Pay Factors of About –20 Percent)
Average Air-Void Content (%)Surface Thickness (in.) 7.000 7.755 8.040 8.325 8.610Standard Deviation of Air-Void Content (%)Average Standard
Deviation 1.200 1.686 1.378 1.028 0.6379.6 0.620 0.0 -20.3 -19.6 -19.7 -20.38.8 0.353 -21.0 -37.8 -37.2 -36.5 -36.09.0 0.587 -20.7 -36.9 -36.5 -36.6 -36.89.2 0.791 -20.7 -36.2 -36.3 -36.7 -37.49.4 0.975 -20.6 -35.2 -36.2 -36.9 -38.2
Table 4.38 Pay Factors for Combination Conditions (from Simulations) (Conditions Setto Yield Varying Individual Pay Factors)
Average Air-Void Content (%)Surface Thickness (in.) 5.95 7.09 7.00 7.09 8.80Standard Deviation of Air-Void Content (%)
.0570 .0570 1.200 1.710 1.520Individual Pay Factor
Average StandardDeviation
IndividualPay Factor
0.262 0.060 0.000 -0.097 -0.32010.5 0.60 0.340 96.1 41.6 33.9 23.5 -2.89.9 0.60 0.123 39.3 18.2 12.2 2.5 -22.89.6 0.62 0.000 23.2 6.3 0.0 -9.5 -32.09.3 0.70 -0.134 11.3 -8.6 -13.7 -22.5 -41.18.5 0.80 -0.408 -24.0 -38.5 -41.0 -45.3 -56.5
Table 4.39 Pay Factors for Combination Conditions (from Calculations) (Conditions Setto Yield Varying Individual Pay Factors)
Average Air-Void Content (%)Surface Thickness (in.) 5.95 7.09 7.00 7.09 8.80Standard Deviation of Air-Void Content (%)
.0570 .0570 1.200 1.710 1.520Individual Pay Factor
Average StandardDeviation
IndividualPay Factor
0.262 0.060 0.000 -0.097 -0.32010.5 0.60 0.340 69.1 42.0 34.0 21.0 -8.99.9 0.60 0.123 41.7 19.0 12.3 1.4 -23.69.6 0.62 0.000 26.2 6.0 0.0 -9.7 -32.09.3 0.70 -0.134 9.3 -8.2 -13.4 -21.8 -41.18.5 0.80 -0.408 -25.3 -37.2 -40.8 -46.5 -59.7
65
It is possible to prepare a combined pay factor table like that shown in Reference (10).
However, with the five variables of Equation (4.4), it is recommended that Equation (4.4) be
used to calculate the combined pay factor, particularly if pay factors are computed based on the
results of one-day or shorter operations, even though the paving project may have a duration of
many days.
5.0 DISCUSSION
The approach presented herein should be applicable to virtually any type of hot mix,
although as a check, additional laboratory testing would be required. It is likely that both
bonuses and penalties may be understated because only the first rehabilitation cycle is
considered. Nevertheless, understated penalties/bonuses are likely to be more appropriate than
overstated ones for pilot or demonstration use at this time.
The pay factor tables contained herein reflect a full bonus for superior construction and a
full penalty for inferior construction. Based on current practice, the bonus to be awarded should
not exceed some prescribed level somewhat less than the maximum values shown herein.
Currently, the upper limit for Caltrans is a bonus of 5 percent. Also, as noted in Section 4.1, the
pay factors for air-void content do not include the effects of either area, Figure 3.8, where the
specification is met but the performance is inferior to that of the target or the area where the
specification is not met but the performance is superior to that of the target.
Recognizing some of the limitation noted herein, the pay factors provide a reasonable
starting point for hot mix asphalt concrete construction considering the combined effects of
rutting and fatigue cracking or only one of the distress modes if that is considered to be suitable.
For example, if only rutting is to be considered, for a target life of 20 years, the pay
factors should include those for asphalt content, air-void content, and aggregate gradation shown
66
in Tables 4.13, 4.14, 4.16, and 4.17. For fatigue for the 20-year target, the pay factors for asphalt
content, air-void content, and thickness shown in Tables 4.13 through 4.15 should be included.
(N.B. These tables are based on an inflation rate of 2.5 percent and rehabilitation costs which are
0.2 times the initial construction cost for rutting and 0.5 time the cost for fatigue.)
For an inflation rate of 3.5 percent, Tables 4.21 through 4.25 contain combined pay
factors for a 10-year target life while Tables 4.26 through 4.30 and 4.31 through 4.35 contain the
same information for target lives of 30 and 20 years, respectively. It will be noted that the pay
factors for the target life of 30 years are equal or less than those for 20 and 10 year periods.
It must be emphasized that the development of appropriate pay-factor schedules must be
viewed as an incremental process evolving over some time frame. Among future refinements
that can be considered are the following:
1. Incorporation of ride quality as a product of the construction process;
2. Inclusion, if desired, of maintenance and user costs;
3. Extension to include rehabilitation activities; and
4. Extension to include cement concrete pavements.
Moving from concept to practice is possible at this time. However, a number of
questions must be answered by Caltrans: Does interest focus on new pavements and/or overlays
and can initial consideration be limited to asphalt concrete applications as described herein?
Help is needed from Caltrans staff to validate the variances that have been utilized herein to
insure that they are representative of current construction practice. In addition to the example
presented in Section 4.3, a number of past construction projects should be reviewed to evaluate
their distribution relative to any pay-factor schedule that is ultimately proposed.
Other questions include:
67
1. Are the parameters used herein those most suitable for Caltrans usage?
2. Is the recommended procedure for displaying individual pay factors and the
procedure used to develop combined pay factors suitable?
3. How does this approach for pay factor determination relate to the QC/QA program
envisioned by Caltrans, including other construction-quality considerations?
4. How best can the CAL/APT program support the Caltrans initiative for demonstrating
a new or modified approach for pay factors for asphalt concrete construction and
what is the timeline for such a program?
6.0 REFERENCES
1. Harvey, J. T., J. Roesler, N. F. Coetzee, and C. L. Monismith. Caltrans AcceleratedPavement Test Program, Summary Report Six Year Period: 1994–2000. Prepared for theCalifornia Department of Transportation, Pavement Research Center, University ofCalifornia, Berkeley, June 2000, 112 pp.
2. Monismith, C. L., J. A. Deacon, and J. T. Harvey. WesTrack: Performance Models forPermanent Deformation and Fatigue. Pavement Research Center, University of California,Berkeley, June 2000, 373 pp.
3. Deacon, J. A., A. A. Tayebali, J. S. Coplantz, F. N. Finn, and C. L. Monsmith. FatigueResponse of Asphalt-Aggregate Mixtures: Part III, Mix Design and Analysis. Report SHRPA-404, Strategic Highway Research Program, National Research Council, Washington, D.C., 1994, 309 pp.
4. Deacon, J. A., J. S. Coplantz, A. A. Tayebali, and C. L. Monismith. “TemperatureConsiderations in Asphalt-Aggregate Mixture Analysis and Design.” Research Record 1454.Transportation Research Board, Washington, D. C., pp. 97-112.
5. Harvey, J. T., J. A. Deacon, B. W. Tsai, and C. L. Monismith. Fatigue Performance ofAsphalt Concrete Mixes and Its Relationship to Asphalt Concrete Pavement Performance inCalifornia. University of California, Berkeley, Institute of Transportation Studies, AsphaltResearch Program, CAL/APT Program, 1995, 188 pp.
6. Harvey, J. T., J. A. Deacon, A. A. Tayebali, R. B. Leahy, and C. L. Monismith. “AReliability-Based Mix Design and Analysis System for Mitigating Fatigue Distress.”Proceedings. 8th International Conference on Asphalt Pavements. University ofWashington, Seattle, August 1997, I:301-323.
68
7. Epps, J. Accelerated Field Test of Performance-Related Specifications for Hot-Mix AsphaltConstruction—Task G, Interim Report. Submitted to the Federal Highway Administration.Nevada Automotive Test Center. Chapter 12. 1996.
8. Benson, P. Comparison of End-Result and Method Specifications for Managing Quality.Paper presented at the 74th Transportation Research Board Annual Meeting, Washington, D.C.
9. Granley, E. “Part 4—Variations of Bituminous Construction.” Public Roads. Vol. 35, No. 9.1969.
10. Deacon, J. A., C. L. Monismith, and J. T. Harvey. Pay Factors for Asphalt-ConcreteConstruction: Effect of Construction Quality on Agency Costs. TM-UCB-CAL/APT-97-1.Pavement Research Center, Institute of Transportation Studies, University of California,Berkeley, 47 pp., April 1997.
11. Dietz, J. Various correspondence, September–November 2000 regarding asphalt concreteoverlay, SR-299, Trinity County, California.
12. Federal Highway Administration (FHWA). LTPP Analysis: Putting the Data to Work.FHWA-RD-99-169, USDOT, FHWA, Washington, D. C., 1999, 21 pp.
13. American Association of State Highway and Transportation Officials (AASHTO). Guide forDesign of Pavement Structures. Washington, D. C., 1993.
14. Tayebali, A. A., J. A. Deacon, J. S. Coplantz, J. T. Harvey, and C. L. Monismith. FatigueResponse of Asphalt-Aggregate Mixes. Report SHRP-A-404. Strategic Highway ResearchProgram, National Research Council, Washington, D. C., 1994, 309 pp.
15. Puangchit, P., R. G. Hicks, J. E. Wilson, and C. A. Bell. Impact of Variation in MaterialProperties on Asphalt Pavement. Oregon Department of Transportation, May 1982, 152 pp.
16. Larson, G. and B. Dempsey. ICM Software. Enhanced Integrated Climatic Model Version2.0 (ICM). University of Illinois, Urbana, Illinois, 1997.
17. Sousa, J. B., J. A. Deacon, S. Weissman, J. T. Harvey, C. L. Monismith. FatiguePerformance of Asphalt Concrete Mixes and Its Relationship to Asphalt Concrete PavementPerformance in California. Asphalt Research Program, CAL/APT Program, Institute ofTransportation Studies, University of California, Berkeley, 1996.
18. Shook, J. F., F. N. Finn, M. W. Wticzak, and C. L. Monismith. “Thickness and Design ofAsphalt Pavements The Asphalt Institute Method.” Proceedings. Fifth InternationalConference on the Structural Design of Asphalt Pavement, University of Michigan and DelftUniversity of Technology, August 1982, Vol. 2, pp. 17-44.
69
APPENDIX A: RELIABILITY AND VARIABILITY CONSIDERATIONS
To provide an acceptable level of risk in asphalt mix design and pavement performance
without excessive cost, reliability analysis can be used. Reliability, as considered in this report,
is the probability that a mix and/or a pavement structure will provide satisfactory performance
for a specific design period. To achieve a given level of reliability requires estimates of the
variance in: 1) traffic estimates; 2) variability as a function of asphalt content, degree of
compaction (as measured by air-void content), and aggregate gradation; and 3) pavement
structure variables including asphalt concrete thickness and stiffnesses and thicknesses of the
supporting layers.
This appendix contains a brief summary of both reliability and variability considerations
used to estimate the pay factors presented in this report.
Reliability
As stated above, reliability, as considered herein, is the probability that an asphalt mix or
pavement structure will provide satisfactory performance throughout the selected design period.
The reliability level for each specific situation is set by the designer. Larger levels of reliability
reduce the chances of accepting deficient mixes; however, the tradeoff is the potentially larger
cost associated with reducing the number of acceptable materials or mixes or increasing the
thickness of the asphalt concrete.
Reliability is introduced in the mix design and analysis system by a reliability multiplier,
M, which is calculated as follows:
( ) ( )ESALsNZeM lnvarlnvar += (A-1)
70
in which e = the base of natural or Naperian logarithms, Z = a factor depending solely on the
design reliability, var(ln N) = the variance of the logarithm of the laboratory fatigue or rutting
life under the standard 40-kN (9,000-lb.) wheel load, and var(ln ESALs) = the variance of the
estimate of the logarithm of the deign ESALs. Z is related to design reliability as follows:
Design reliability (percent) Z9590806050
1.641.280.840.2530.000
To estimate the var(ln N) and var(ln ESALs) requires estimates of the variabilities in the
parameters which are used to determine the two variances. These variances are discussed in the
next section.
Variability
Variability associated with forecasts of design ESALs is not well defined at this time.6 In
the absence of better information, var (ln ESALs) has been assumed to 0.300. This estimate is
based primarily on judgement of the authors of this report. As a point of reference, the 1993
AASHTO Design Guide (13) suggests that actual traffic may be 1.6 times that predicted at one-
standard-deviation level. For an assumed log normal distribution, this produces a var(ln ESALs)
of about 0.22. Thus the value selected would appear to be “reasonably” conservative.
The var(ln N), as developed in this analysis, is a function of both testing and construction
variabilities. Two components of construction variability have been considered: those affecting
mix behavior and those affecting permanent structure behavior.
6 Results of the Long Term Pavement Performance (LTPP) Program (12) should eventually provide a better definedestimate of traffic variability.
71
As currently developed, var(ln N) is thus the sum of three components as follows:
( ) 222lnvar smt sssN ++= (A-2)
in which 2ts = the testing variance, 2
ms = the mix variance, and 2ss = the structure variance.
Consider first the testing variance, 2ts , for fatigue. Testing variability reflects a
combination of factors including: 1) the inherent variability in fatigue measurements (associated
both with specimen preparation as well as testing equipment and procedures; 2) the nature of the
laboratory testing program; and 3) the extent of extrapolation necessary for estimating fatigue
life (using a least-squares, best-fit line) at the design strain level. The var(ln N) is calculated as
follows:
( ) ( )( )
�
���
�
�
� −
−++= 2
22 11lnvar
xxq
xXn
sNp
(A-3)
in which s2 = the variance in logarithm of fatigue life measurements, n = the number of test
specimens, X = ln(in-situ strain) at which ln(N) must be predicted, x = average ln(test strain), q
= number of replicate specimens at each test strain level, and xp = ln(strain) at the pth test strain
level.
The mix fatigue study conducted as an initial art of the CAL/APT Program (5) was used
to determine the testing variance. Replication which was built into the experiment design
permitted computation of the inherent variance (s2) in the logarithm of fatigue life measurements.
The experiment design involved 15 different mixes (five asphalt contents and three air-void
contents) tested at each of two strain levels with nominally three replicates at each of the 30
combinations (a few small-strain tests had four replicates). A total of 96 observations were
included in calculating the sample variance using the following relationships:
72
dn
WSSs
d
kk
−= =12 (A-4)
and
( )−==
kn
ikik NNWSS
1
2lnln (A-5)
in which WSSk = within sum of squares for factor level combination k (air-void content, asphalt
content, and strain level), n = number of observations (96), d = number of factor level
combinations (30), lnNi = logarithm of measured fatigue life for specimen i, lnNk = average
logarithm of measured fatigue lives of specimens for factor level k, and nk = number of replicates
at factor level k.
The best estimate of the overall sample variance of the natural logarithm of the fatigue
life was calculated using the aforedescribed procedure to be 0.220. The sample variance
obtained in the SHRP A-003A expanded test program, using the same testing equipment and
procedures, was 0.152. Because of greater replication in the current study [three versus two in
Reference (14)] and smaller strain levels [150 and 300 microstrain versus 400 and 700
microstrain in Reference (14)], 0.220 seems to be the best possible estimate of s2 at the current
time. It was used in developing the shift factors in the mix design and analysis model and is
recommended for use for mix design purposes.
For fatigue, the materials and construction components of variability were determined in
the following manner.
Potentially important mix variables include asphalt content and air-void content.
Fortunately, the necessary data for quantitative evaluation of these variables is available, namely,
construction variances and, for a typical mix, relationships with mix stiffness and fatigue life (5).
Other potentially important mix variables, such as aggregate gradation, were excluded from
73
consideration. This decision was supported by laboratory test data repeated by other
investigators, [e.g., Hicks et al. (15)] and by analyses of the fatigue performance, both in the
laboratory and the field, of the mixes used at WesTrack (2).
Structural variables include thickness of the asphalt concrete layer and stiffnesses and
thicknesses of other supporting layers. Asphalt concrete thickness was a critical factor to be
considered, and construction variance data was available. The supporting layers are more
problematic because knowledge of the variabilities of foundation layer thicknesses and moduli
appears to be limited, and complexity of the necessary analysis increases with increases in the
number of layers. As a result, it was decided to simplify the process by identifying an equivalent
single layer for which effects were similar to the multilayer supporting layers. The equivalent
single layer has been characterized by its modulus, and the variance of this equivalent modulus
was evaluated from post-construction falling weight deflectometer (FWD) measurements.(7)7
Estimates of the variances of asphalt content, air-void content, and asphalt-concrete
thickness were obtained from a combination of literature review and WesTrack test data.
Summary results are presented in Section 3. These totals include not only materials and
construction components but also components resulting from testing and sampling. The latter
components must be removed from the variance estimates in order to isolate materials and
construction effects: Table 3.2, Section 3, summarizes the necessary data.
Table 3.3, Section 3, provides a summary of the quantities used to represent reasonable
estimates of materials/construction variability associated with conventional construction practice.
The equations for estimating the standard deviation of asphalt-concrete thickness were developed
as an approximate way to handle multilift construction. Among the assumptions made in their
7 Table 3.1 in Section 3 contains a listing of the sources of FWD measurements used.
74
development was that the coefficient of variation of thickness in single-lift construction is about
14 percent, as stated in Section 3.
While the testing variance, 2ts can be obtained from direct computations, using Equation
4.3, computing the mix variance, 2ms , and the structure variance, 2
ss , is more complex.
Fortunately, Monte Carlo simulation is a convenient and relatively quick way to obtain the
necessary estimates. For the design pavement structure and test temperature, each simulation
proceeds as follows. A random selection is made of asphalt content and air-void content. The
mix stiffness is determined from these random selections, and a “mean” pavement strain is
calculated (ELSYM5). A randomly selected adjustment is made to this strain level to account
for random variations in surface thickness and support modulus. The fatigue life is then
computed from the random selections of tensile strain and the asphalt and air-void contents. The
process is repeated until the desired degree of convergence has been reached. In work to date,
distributions of all of the four construction variables have been assumed to be normal. The
Monte Carlo simulations include both testing variability and construction variability.
With the variance estimates, Monte Carlo simulation was used to produce estimates of
var(ln N) for the 18 hypothetical pavements summarized in Table B-1 to illustrate the process.
Stiffness and fatigue relationships contained in Section 3 (Equations 3.1 and 3.2) together with
target asphalt and air-void contents of 5 and 8 percent respectively, were utilized.
Figure A-1 illustrates the level and components of var(lnN) for each of the 18 structures.
The testing portion of the total variance increases significantly with the increases in pavement
thickness associated with larger traffic indices principally because of the increased level of
extrapolation to the smaller strain levels. Construction variability is important for all of the
pavements but is a much greater portion of the total variability for the less substantial pavements
75
which accompany smaller traffic indices. The structures component of construction variability is
slightly greater for thinner than for thicker pavements while a reverse trend is observed for the
mix component.
0
0.5
1
1.5
2
2.5
7CTB
5
7CTB
20
7CTB
40
7AB5
7AB2
0
7AB4
0
11C
TB5
11C
TB20
11C
TB40
11AB
5
11AB
20
11AB
40
15C
TB5
15C
TB20
15C
TB40
15AB
5
15AB
20
15AB
40
Pavement Section
Varia
nce
of L
n(N
)
Structure
Mix
Test
Figure A-1. Major components of testing and construction variance.
77
78
APPENDIX B
Table B-1 Pavement Structures
Designation Layer TargetThickness (in.)
Modulus(psi)
Poisson’sRatio
Target StandardDeviation
7AB20
SurfaceBaseSubbaseSubgrade
3.67.26.0-
Variable30,00020,00012,200
0.400.450.450.50
0.314
9AB20
SurfaceBaseSubbaseSubgrade
6.66.67.8-
Variable30,00020,00012,200
0.400.450.450.50
0.476
11AB20
SurfaceBaseSubbaseSubgrade
9.66.08.4-
Variable25,00020,00012,200
0.400.450.450.50
0.620
13AB20
SurfaceBaseSubbaseSubgrade
10.27.812.6-
Variable25,00020,00012,200
0.400.450.450.50
.0640
79
APPENDIX C: ANALYTICALLY-BASED APPROACH TO RUTTING PREDICTION
As a part of the WesTrack Project to develop a performance related specification (PRS)
for asphalt concrete (AC) construction, two approaches to develop performance models for
rutting were developed.(2) One, based on regression of both field and laboratory test data, has
been described in Section 3 herein and used to develop pay factors for rutting included in Section
4. The other, though not used, is briefly described in this Appendix so that it might serve to
provide a more general approach to pay factor determination if so desired. It is referred to as a
mechanistic-empirical performance model.
Mechanistic-Empirical Approach
In this approach, the pavement is assumed to behave as a multi-layered elastic system.
An idealization of a specific asphalt pavement is show in Figure C-1 together with key
parameters used to estimate rut depth development with traffic, i.e., τ, γe, and εv.*
The three parameters can be determined on an hour-by-hour basis and a program like the
Integrated Climate Model (ICM) (16) can be used to define temperature distributions both with
time and depth in the AC to permit estimates of mix stiffnesses. For convenience, if a program
like ELSYM5 is used, it is recommended that the AC layer be subdivided into three layers with
thicknesses from top to bottom of 25 mm (1 in.), 50 mm (2 in.), and the remaining AC thickness
as the third layer to simulate the effects of temperature gradients on mix stiffness. In the
computations a constant Poisson’s ratio of 0.35 is suggested. If programs are available with
capability of treating more than 5 layers, the third layer can be further subdivided to produce a
*τ, γe = elastic shear stress and strain at a depth of 50 mm (2 in.) below outside edge of tire εv = elastic vertical compressive strain at the subgrade surface
80
more representative stiffness distribution in the AC layer.
Moduli of the underlying layers can also be varied to reflect seasonal influences on the
stiffness moduli of those layers. Poisson’s ratio in the range 0.35 to 0.4 are recommended for
untreated granular layers and 0.4 to 0.45 for untreated fine-grained (subgrade) soils.
In this approach, rutting in the asphalt concrete was assumed to be controlled by shear
deformations. Accordingly, the computed values for τ and γe at a depth of 50 mm (2 in.) beneath
the edge of the tire are used for the rutting estimates, as shown in Figure C-1. Densification of
the asphalt concrete is excluded in these estimates since it has a comparatively small influence
on surface rutting.
In simple loading, permanent shear strain in the AC is assumed to accumulate according
to the following expression:
( ) cei nba γτγ exp⋅= (C-1)
where
iγ = permanent (inelastic) shear strain at 50 mm (2 in.) depth
τ = shear stress determined at this depth using elastic analysis
eγ = corresponding elastic shear strain
n = number of axle load repetitions
a, b, c = regression coefficients
81
50 mm (2 in.)
τ, γe
Asphalt ConcreteEAC, νAC
BaseEbase, νbase
∞
SubgradeEsub, νsub
εv
300 mm (12 in.)
150 mm (6 in.)
Figure C-1. WesTrack pavement respresentation for mechanistic-empirical modeling forrutting.
The time-hardening principle is used to estimate the accumulation of inelastic strains in
the asphalt concrete under in-situ conditions. The resulting equations are as follows:
( ) ejj baa γτexp⋅= (C-2)
[ ]ci na 111 ∆=γ (C-3)
( )( ) ccj
ij
ij naa �
��� ∆+= − 1
11γγ (C-4)
where:
j = jth hour of trafficking
γ = elastic shear strain at the jth hour
82
∆n = number of axle load repetitions applied during the jth hour
The concept is illustrated schematically in Figure C-2.
Rutting in the AC layer due to the shear deformation is determined from the following:
ijAC Krd γ= (C-5)
K ranges from about 5.5 for a 150-mm (6-in.) layer to 10 for a 12-in. thick AC layer when the rut
depth, rdAC, is expressed in inches.(17)
To estimate the contribution to rutting from base and subgrade deformations, a
modification to the Asphalt Institute subgrade strain criteria (18) is utilized. The equation
expressing the criterion for 12.5 mm (0.5 in.) of surface rutting is:
484.491005.1 −−×= vN ε (C-6)
where:
N = the allowable number of repetitions
εv = the compressive strain at the top of the subgrade
Since these criteria do not address rutting accumulation in the pavement structure, rut
depth (rd) contributed by the unbound layers was assumed to accumulate as follows:
ednrd = (C-7)
where
d, e = experimentally determined coefficients
ln number of load applications
ln in
elas
tic s
trai
n
1st load block
2nd load block
3rd load block
4th load block5th load block
6th load block
7th load block
8th load block
9th loadblock
10th load block
Inelastic strain-nrelationship for
smaller load
Inelastic strain-nrelationship for
larger load
Figure C-2. Time-hardening provedure for plastic strain accumulation under stress repetitions of different magnitudes incompound loading.
83
84
Least squares analyses for the WesTrack data suggest that the value for d in Equation C-7
using the Asphalt Institute criteria is:
[ ]evfd 484/491005.1 −−×= ε (C-8)
where:
f = 3.548
e = 0.372
Using the time-hardening principle, as was used for the asphalt concrete, rut depth
accumulation can be expressed in a form similar to Equation (C-4), i.e.:
( )[ ] 372.0372.011 jjjjj ndrddrd ∆+= − (C-9)
The framework for rut-depth estimation, using Equations C-1, C-4, and C-9 is illustrated
in Figure C-3. This approach has a distinct advantage over the direct regression approach in that
it permits prediction of rut depth as a function of traffic and environment as well as a function of
mix parameters.
For WesTrack, 13 sections were used to calibrate the coefficients of Equations C-1 and
C-7. Initially, a value for b = 0.0487 in Equation C-1 was used based on the results of RSST-CH
tests. Subsequently, a value of b = 0.071 (10.28 in metric units) was determined to provide
better correspondence between measured and computed rut depths.
Using the procedure illustrated in Figure C-3, least squares regression provided values of
a and c for each of the 23 WesTrack sections where rutting without observed fatigue cracking
was obtained. These are summarized in Table C-1. It will be noted that the average root mean
square error (RMSE) for rut depth for the 24 sections is 0.051 in. Figures C-4, C-5, C-6, and C-7
illustrate comparisons between computed and measured rut depths for Section 4 (fine), Section
19 (fine-plus), Section 7 (coarse), and Section 38 (replacement, coarse).
85
Begin
Select day and hour
Determine pavementtemperature distribution
Determine moduli ofelasticity
Compute stresses andstrains at key locations
Accumulate inelasticstrains in asphalt concrete
Estimate rut depth in alllayers
End
More iterations?
Figure C-3. Framework for rut depth estimates.
Table C-1 Calculated ESALs to a range in rut depths for a constant loading of 60 trucks/hour, WesTrack environment.ESALs to rut depth, in.
Section 2.5 mm 5.1 mm 7.6 mm 10.2 mm 12.7 mm 15.2 mm 17.8 mm Vair PWasp P200
1 28,039 252,287 820,069 3,591,871 9,204,604 18,398,845 8.6 5.69 5.14 236,708 611,416 1,359,344 2,773,927 3,863,423 5,878,847 7,019,202 6.9 5.24 4.47 63,999 153,055 227,630 316,256 408,645 513,061 624,134 7.6 6.28 6.49 110,563 234,749 352,391 497,064 651,076 854,130 1,082,798 3.2 6.07 5.211 117,174 482,548 2,448,516 6,534,875 12,923,017 8 5.5 5.512 116,657 435,335 1,585,887 5,124,824 9,010,004 15,295,397 3.8 5.35 613 95,473 225,983 355,542 517,591 707,157 945,578 1,273,364 6 6.01 5.714 10,769 161,277 329,455 962,944 3,077,647 6,489,484 11,865,398 7.7 6.22 4.915 29,167 287,582 1,834,871 6,728,613 16,439,353 8.8 5.55 5.218 189,538 666,122 2,747,063 6,158,581 9,973,563 15,910,029 4.6 6.22 5.119 18,607 180,272 368,802 1,021,007 2,988,579 5,954,150 9,437,925 6 5.41 5.820 8,338 92,423 234,398 499,951 1,380,435 3,205,796 6,357,843 10.4 5.4 5.221 76,781 176,680 255,239 346,170 455,231 556,356 688,619 3.6 6.25 5.422 7,119 177,636 916,839 8,948,966 6.9 4.76 5.323 69,331 224,904 446,813 905,331 2,231,318 3,215,667 5,376,272 5.8 5.78 724 26,867 105,733 202,299 308,313 447,466 632,476 929,569 7.5 5.9 6.625 58,393 153,644 234,776 335,143 459,322 584,865 766,798 3.1 6.33 6.735 929 3,339 53,879 375,289 2,160,805 3,499,640 8.75 6.12 5.637 2,971 23,206 85,712 217,934 461,473 1,216,154 9.55 6.14 5.738 819 31,835 489,242 3,054,882 7,271,094 16,890,972 7.7 5.55 6.239 1,530 47,133 489,200 2,725,955 5,423,810 10,857,714 5.5 5.94 5.754 902 2,835 44,886 276,540 1,991,198 3,010,916 7.3 6.11 5.855 2,282 29,129 89,868 231,453 454,256 883,673 1,985,619 4.3 6.04 6
(1 in. = 25.4 mm)
86
0
2
4
6
8
10
12
14
16
18
10/28/1995 2/5/1996 5/15/1996 8/23/1996 12/1/1996 3/11/1997 6/19/1997 9/27/1997 1/5/1998 4/15/1998 7/24/1998 11/1/1998
Year
Max
imum
rut d
epth
, mm
Total rut - baseTotal predicted rutTotal measured rut
Figure C-4. Comparison between computed and measured rut depth versus time; Section 4.
87
0
3
6
9
12
15
18
21
24
27
30
2/5/1996 3/26/1996 5/15/1996 7/4/1996 8/23/1996 10/12/1996 12/1/1996
Year
Max
imum
rut d
epth
, mm
Total rut - baseTotal predicted rutTotal measured rut
(1 in. = 25.4 mm)Figure C-5. Comparison between computed and measured rut depth versus time; Section 7.
88
0
3
6
9
12
15
18
10/28/1995 2/5/1996 5/15/1996 8/23/1996 12/1/1996 3/11/1997 6/19/1997 9/27/1997 1/5/1998 4/15/1998 7/24/1998 11/1/1998
Year
Max
imum
rut d
epth
, mm
Total rut - baseTotal predicted rutTotal measured rut
(1 in. = 25.4 mm)Figure C-6. Comparison between computed and measured rut depth versus time; Section 19.
89
0
3
6
9
12
15
18
6/19/1997 9/27/1997 1/5/1998 4/15/1998 7/24/1998 11/1/1998 2/9/1999 5/20/1999
Year
Max
imum
rut d
epth
, mm
Total rut - baseTotal predicted rutTotal measured rut
(1 in. = 25.4 mm)Figure C-7. Comparison between computed and measured rut depth versus time; Section 38.
90
91
Expressions reported in Reference (2) for defining field a and c could be used if mixes
similar to those used at WesTrack are being evaluated. For wider applications, however, it is
desirable to have relationships not limited to these types of mixes.
An approach recommended at this time makes use of the results of the laboratory RSST-
CH test and the mix variables-asphalt content and air-void content-to determine field a and c
values. A series of regressions were performed for the 23 WesTrack sections shown in Table C-
1 considering these variables. Results of the calibrations are shown in Table C-2 for ln(field a)
and Table C-3 for field c. In these tables, lab a is from the expression:
bi an=γ (C-10)
obtained from analysis of the RSST-CH results as shown in Figure C-8. The term rsst 5
corresponds to the repetitions corresponding to a value of γi = 5 percent, also illustrated in Figure
C-8.
From the analyses, Regression 6 in both Tables C-2 and C-3 is recommended for use to
define a and c for use in the ME procedure briefly summarized herein.
Table C-2 Calibration of equations for simulating ln(field a) based on mix and RSSTvariables.
Regr. 1 Regr. 2 Regr. 3 Regr. 4 Regr. 5 Regr. 6Constant 14.9116 24.7107 24.3317 24.9718 25.3649 20.4844PWasp -3.67001 -5.02990 -5.04342 -5.23716 -5.71438 -5.12624Vair 0.313875PWasp·Vair 0.0823738rsst5 6.219E-05 9.699E-05laba 1301.81 1622.41 1745.07 1858.91 2472.96 2264.05R2 0.611 0.629 0.684 0.752 0.888 0.951SectionsOmitted None 14 14, 15 1, 14, 15 1, 14, 15,
191, 4, 14, 15,
19
92
0.0001
0.001
0.01
0.1
1 10 100 1000 10000 100000RSST Repetitions
Perm
anen
t She
ar S
train
3778
5 %
Figure C-8. Permanent shear strain, iγ , versus load repetitions, n; rsst = 3778.
92
93
Table C-3 Calibration of equations for simulating field c based on mix and RSSTvariables.
Regr. 1 Regr. 2 Regr. 3 Regr. 4 Regr. 5 Regr. 6Constant -0.944102 -1.75309 -1.72144 -1.77798 -1.83917 -1.49931PWasp 0.312598 0.426673 0.427803 0.444915 0.493348 0.452398Vair -0.0217923PWasp·Vair -0.0064968rsst5 -6.216E-06 -8.575E-06lab a -87.5258 -113.452 -123.693 -133.748 -190.11 -175.759R2 0.556 0.591 0.648 0.728 0.890 0.936SectionsOmitted None 14 14, 15 1, 14, 15 1, 14, 15,
191, 4, 14, 15,
19