15
paul drumm; 1 st December 2004; PM&TB Report Project Management & Technical Board Reports

Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

  • View
    216

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

paul drumm; 1st December 2004; PM&TB Report

1

Project Management&

Technical Board

Reports

Page 2: Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

paul drumm; 1st December 2004; PM&TB Report

2

PM & Technical Board Report

• Monthly update on Issues - Brief– Technical Board &Technical Issues from

executive board– Management Issues…

• Safety Review (proposal)• Cost & Schedule Review (outcome…)• Gateway

Page 3: Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

paul drumm; 1st December 2004; PM&TB Report

3

Technical Board

– Technical board meets every second week by phone for ~1hr:

• Alain Blondel, Alan Bross, Paul Drumm, Yury Ivanyushenkov, Wing Lau, Vittorio Palladino, Yagmur Torun, Mike Zisman,

– Minutes & other information on the web: http://www.isis.rl.ac.uk/accelerator/MICE/TechBoard/Index.html

• MICE Technical Team Technical Board

Page 4: Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

paul drumm; 1st December 2004; PM&TB Report

4

Technical Board Report

Actions + Change Notes:Proposed design; Estimated cost; Responsibility for implementation; Impact (forces, operation, performance, schedule etc).

e.g.Radiation shielding between the tracker and the absorberMagnetic shielding between the solenoid & up/down stream detectorsConnections between the modulesInterlock for RFCryocoolers & HeliumPosition of diffuserChanges to sizes of PID detectorsGap at stage II & fixing to floor.

Page 5: Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

paul drumm; 1st December 2004; PM&TB Report

5

In progress…

Outline designs

Preliminary Assessments

Proposal for final choice

Detailed design

Manufacture and installation

Permission to operate

RAL Defined Review

Failure ModesStress CalculationsInterlocks &Operational ProceduresContingency PlansPressure Vessel &ATEX regulations….

Hazard and Operability Assessment

Working Group

SequenceDocuments Required

MICE Hydrogen Safety Review Procedure

OK for detailed design

OK to Manufacture

Preliminary Hazard and Operability Assessments

ISIS Safety Officer

Reviews

Panel Review

+

+

Page 6: Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

paul drumm; 1st December 2004; PM&TB Report

6

Proposal for a Design & Safety Review

• The AFCSWG proved to be a successful model - important safety features and risks could be critically examined.

• This experience has been beneficial to MICE– motivation and focus– confidence within the collaboration – Confidence at RAL

• Sufficient progress has been made to move to the next stage –– MICE will expand the scope of the task to include

• engineering designs and • safety aspects • of all the components of MICE: detectors and cooling channel.

• Safety Group core:– Engineering:

• Wing Lau Convenor• Steve Virostek

– Cooling Channel:• Mike Zisman

– Magnets & Absorber:• Elwyn Baynham• Mike Green

– Integration:• Yury Ivanyushenkov

– Detectors & Electronics:• Alan Bross

– Interlocks:• “Tom Bradshaw”

Group’s task is to solicit additional information

(papers, reports, presentations).to meet as part of the existing AFC

series of meetings to avoid meeting escalation. It is up to the Convenor to initiate

meetings of one or other of the groups.

The group should consider the design of MICE, including the beam line & target, and all infrastructures (shielding, RF power, electrical power systems, controls etc).

Page 7: Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

paul drumm; 1st December 2004; PM&TB Report

7

Charge to the Group

The remit of the group is to:

• Document sufficient design detail and analysis that an assessment of the design of components against appropriate engineering design rules can be made.

• Similarly for components in the integrated environment of MICE - this might examine interconnections, holding of forces, integrated vacuum systems etc.

• Provide a safety & hazard assessment of the components in the operational phase; identify procedures, risks, consequences, identification of fault conditions etc.

• The completed information will be presented to the MICE Executive Board to gain agreement and will then be subject to an external and independent review which will inform the Executive Board. The Executive Board will then take action on the report of the review.

Page 8: Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

paul drumm; 1st December 2004; PM&TB Report

8

Cost & Schedule Review

• Two weeks ago Friday 12th November– All the material supplied is available at:

http://www.isis.rl.ac.uk/accelerator/mice/cost_schedule/Document_List.html

• Review report & Response is also available– http://www.isis.rl.ac.uk/accelerator/MICE/cost_sc

hedule/Actions%20and%20Response.pdf

• Important input to the Gateway review in two weeks time!

Page 9: Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

paul drumm; 1st December 2004; PM&TB Report

9

Cost & Schedule Review II

• Overall response is positive– The cost for the muon beam looks reasonable…

…overall the panel believes the team can build the beamline within the cost envelope proposed.

– Overall the timescale for the beam-line seems to be achievable if money is available soon.

Page 10: Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

paul drumm; 1st December 2004; PM&TB Report

10

Cost & Schedule Review II

– The project does seem to be in very good shape, and the details of the organization are impressive. The team have a good control of their costs, and know where they are.

– However, the 3% inflation on technical equipment is likely to prove optimistic, and may result in an overall underestimate of late spend.

Page 11: Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

paul drumm; 1st December 2004; PM&TB Report

11

Cost & Schedule Review II

– Risks• Shutdown & Commissioning of beam line• Target Design• RF equipment

– Actions on MICE-UK team:• Reconsider inflation• Reconsider commissioning• Consider outsourcing

– Need for design reviews• Because we didn’t talk about them,• But we had been thinking about them…

Page 12: Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

paul drumm; 1st December 2004; PM&TB Report

12

Gateway Review

• Gateway Review– 20th & 21st December– One day of presentation + next day for

report/questions (TBC)

• Culham, OST, B’ham (JD), RAL (JG)

• KJP, KL, PD + AB, MZ

Page 13: Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

paul drumm; 1st December 2004; PM&TB Report

13

What we want…

• Muon Beam On ISIS• Design Work

– to provide infrastructure• Put as much in place as possible…

– Safeguard MICE-UK deliverables (Coils)

• R&D– Hydrogen system– RF power system

• Tracker for MICE Stage II• Remind them of

– Focus Coils, RF, Remaining infrastructure etc

Page 14: Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

paul drumm; 1st December 2004; PM&TB Report

14

GW Review

• Examines:– Robust Business Case– Procurement strategy is robust and appropriate.– Management & Controls in place

• Monitoring & Performance measures in place• Risk assessment & management

– Development and delivery plans and– Funding availability for the whole project.

Page 15: Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports

paul drumm; 1st December 2004; PM&TB Report

15

Input…

• Building up the document list…– Gateway 1 Report and the response to recommendations: G1-1(RTR)-R0.4 – Paper submitted to Science Committee. (Note this was in confidence).– Documents submitted to the MICE Cost & Schedule Review including the

combined Review report and the response from the MICE-UK team.– Business Case revision X and version submitted to the Gateway 1 review– MICE Project Specification and detailed MICE-UK Project Specification– Stakeholder Plan– Project Management Plan– Risk Analysis– MoU Structure– Spend & Resource Profiles– MICE WBS Cost spreadsheet– MICE UK Cost Summary– Spend to date against Plan + Various Reports…