Patuakhali 1320 (2×660) MW Coal Fired Thermal Power Plant Project
Boiler Steel Structure Erection
Boiler, Turbine, Generator area [Piling and Foundation works]
Admin, Engineering Building and Multi-Purpose House [Foundation Works]
Admin, Engineering Building and Multi-Purpose House [Foundation Works]
Workshop Building [Foundation Works]
Canteen
Local labor Sheds
Boiler welding Inspection at China factory
Paint film thickness of ESP and Water Pressure testing of rain water pump
Welding Inspection of Low-pressure cylinder of #2 Steam Turbine
Paint Inspection of stator frame of #2 generator equipment
“ ”
(-)
( ) ( )
( ) ( )
( )
Project Location