PAPER WORK.docx

Embed Size (px)

Citation preview

  • 7/24/2019 PAPER WORK.docx

    1/54

    COMPANY PROFILE SUB-CONTRACTOR

    RME SDN BHD is the main contractor for this project and sub-contractor for construction

    cast in situ for 600mm diameter bored piled is Samalaju Engineering SDN BHDformel!

    "no#n as Hue! $ian Engineering Sdn Bhd% Samalaju Engineering Sdn Bhd is a ground and

    foundation engineering specialist #ith o&er '0 !ears of trac" records and e(perience in

    pro&iding geotechnical and foundation "no# ho# in Mala!sia)s foundation * piling #or"s

    industr!% $he! belie&e that #ith them e(tensi&e bored pile jet grouting and diaphragm #all

    e(pertise together #ith the necessar! e+uipment manpo#er and technical capabilities and the

    impressi&e trac" records the! #ould ser&e as a beneficial ad&antage in a proposed

    collaboration #ith client)s in achie&ing commitments to current projects to meet client)s

    timeline and budget%

    ,n the anticipation of the increase &olume of ongoing and future foundation #or"s the! ha&e

    purchased addition piling tools and e+uipments from the leading European and apanese

    manufacturers in meeting different t!pe of difficult ground condition and in meeting client)s

    #or" program and re+uirements b! pro&iding the necessar! e(pertise and capabilities to

    underta"e foundation #or"s successfull!%

    $he! are confident that #ith current resources of manpo#er and e+uipments #ill pro&ide the

    necessar! e(pertise and capabilities to embar" on an! of client)s successful secured project%

    $he major foundation #or"s e(pertise are .

    / 1iling 2or"s

    /%/ Marine Bored 1ile

    /%' Bored 1ile b! Re&ersed 3irculation Method or R3D

    /%4 Bored 1ile b! Rotar! 3asing * 5ell! Drilling Method

    /% Barrette 1ile

    /%7 3aisson 1ile

    ' Retaining 2all 2or"s

    '%/ Diaphragm 2all

    '%' 3ontiguous Bored 1ile 2all

    '%4 Secant 1ile 2all

    '% et 8routing 2all

    4 Soil ,mpro&ement 2or"s

    4%/ et 8routing

    4%' 3hemical 8routing

    4%4 3ement 1ressure 8routing

    Retaining S!stems%/ 8round 9nchors

  • 7/24/2019 PAPER WORK.docx

    2/54

    %' ,nternal Steel Strut :1reload S!stem

    7 Basement 3onstruction

    7%/ Earth 2or"s

    7%' 1ilecaps 2or"

    7%4 R%3% 2or"s

    CORPORATE DETAILS

  • 7/24/2019 PAPER WORK.docx

    3/54

    Registered Business Name . H;E< $,9N EN8,NEER,N8 SDN

    BHD :29==B,=$ SDN BHD

    Registered 9ddress . Suite D'4 'nd>loor

    1la?a 1e"elilingNo% ' alan $un Ra?a"

    7000 5uala =umpur%

    Business 9ddress . No% '/-@ alan ;S A * 7

    Subang Business 3entre

    @6'0 ;E1 Subang a!a

    Selangor Darul Ehsan

    Mala!sia%

    $elephone Number . 04-C0'7 /0C6

    $elefa( Number . 04-C0'4 @A0C

    Business Registration Number . @6A06 M

    Nature of Business . 8eotechnical and >oundation

    Engineering 2or"s

    Email 9ddress . hue!tianhotmail%com

    ORGANISATION CHART

    =o# Boon 3h!e :Director2ang

  • 7/24/2019 PAPER WORK.docx

    4/54

  • 7/24/2019 PAPER WORK.docx

    5/54

    DRAWING AND LAYOUT PLAN

  • 7/24/2019 PAPER WORK.docx

    6/54

    GENERAL SPECIFICATION

  • 7/24/2019 PAPER WORK.docx

    7/54

    PILING WORKS

    DES3R,1$,FN

    $his #or" shall consist of the suppl! installation and testing of piles in accordance #ith this

    Specification and the lines le&els grades and cross-section sho#n on the Dra#ings and as

    directed b! the S%F%

    8ENER9= RE;,REMEN$S >FR $F=ER9N3ES

    Setting Out

  • 7/24/2019 PAPER WORK.docx

    8/54

    Setting out shall be carried out using the data and references points as sho#n on the

    Dra#ings% ,mmediatel! before installation of the pile the pile position shall be mar"ed #ith

    suitable identifiable pins pegs or mar"ers%

    Position

    >or a pile cut off at or abo&e ground le&el the ma(imum permitted de&iation of the pile centre

    from the centre points sho#n on the Dra#ings shall not e(ceed @7 mm in an! direction% >or a

    pile cut off belo# ground le&el an increase in this tolerance is permitted in accordance #ith

    &erticall! and ra"e here in belo#%

    e!ti"#$$%

    $he ma(imum permitted de&iation of the finished pile from the &ertical is / in @7

    R#&e

    $he piling rig shall be set and maintained to attain the re+uired ra"e% $he ma(imum permitted

    de&iation of the finished pile from the specified ra"e or the ra"e sho#n on the Dra#ings is /

    in '7%

    Fo!"i'$e Co!!e"tions

    >orcible 3orrections to concrete piles shall not be permitted% >orcible corrections ma! be

    permitted to other t!pes of piles if appro&ed b! the S%F% Ho#e&er no forcible corrections

    shall be made to piles #hich ha&e de&iated be!ond the permissible limits specified in

    1osition Gerticall! and Ra"e abo&e%

    Pi$es Out o( A$ign)ent o! Position

    $he 3ontractor shall if ordered b! the S%F% e(tract and reinstall an! pile #hich has de&iated

    out of position or alignment b! more than the specified limits or alternati&el! the

    substructure shall be modified to the appro&al of the S%F% $he cost of such e(traction and

    reinstallation or an! e(tra cost in the design and construction of a modified foundation shall

    be borne b! the 3ontractor if in the opinion of the S%F% such e(tra #or"s ha&e been made

    necessar! due to the error and*or negligence of the 3ontractor%

    Re"o!*s

    $he 3ontractor shall "eep records of the installation of each pile as re+uired b! the S%F% and

    shall submit t#o signed copies of these records to the S%F% not later than at noon of the ne(t

    #or"ing da! after the pile has been installed% $he signed records shall from part of the

    records for the 2or"s%

    9n! une(pected dri&ing or boring conditions shall be noted in the records%

  • 7/24/2019 PAPER WORK.docx

    9/54

  • 7/24/2019 PAPER WORK.docx

    10/54

    BORED CAST +IN-PLACE PILES

    Des"!i,tion

    $his #or" shall comprise the boring or grabbing #ith or #ithout casing and subse+uentl!

    filling the hole #ith plain or reinforced concrete to form bored cast-in-situ piles all in

    accordance #ith this Specification and to the details sho#n in the Dra#ings%

    M#te!i#$s

    3oncrete and Reinforcement

    $he concrete and reinforcement to be used and #or"manship for bored cast-in-situ piles shall

    be as specified under Section A of this Specification% $he grade of concrete and the details of

    reinforcement to be used shall be as sho#n on the Dra#ings%

  • 7/24/2019 PAPER WORK.docx

    11/54

    1ermanent 3asings

    1ermanent casings #hich from part of the designed pile shall be as specified in the Dra#ings%

    Drilling >luid

    Drilling fluid material bentonite shall compl! #ith Specification No% D> 31 of the Fil

    3ompanies Materials 9ssociation or its e+ui&alent% 9 certificate shall be obtained b! the

    3ontractor from the manufacturer of the bentonite po#der sho#ing the properties of each

    consignment deli&ered to the site% $his certificate shall be made a&ailable to the S%F% on

    re+uest%

    Bentonite shall be mi(ed thoroughl! #ith clean fresh #ater to ma"e a suspension #hich #ill

    maintain the stabilit! of the pile e(ca&ation for the period necessar! to place concrete and

    complete construction% 1reparation of the suspension shall compl! #ith the manufacturer)s

    instructions%

    2here saline or chemicall! contaminated ground #ater occurs special precautions shall be

    ta"en to modif! the bentonite suspension or pre-h!drate the bentonite in fresh #ater to render

    it suitable in all respects for the construction of piles%

    Bo!ing O,e!#tions

    Diameter of 1iles

    $he diameter of piles shall not be less than the specified design diameter at an! le&el

    throughout its length%

    Boring

    Boring shall be carried do#n to the depth as re+uired and directed b! the S%F%

    2hen deemed necessar! b! the S%F% the 3ontractor shall ta"e undisturbed soil samples #hile

    the pile is being bored% $he samples shall be ta"en to an appro&ed =aborator! for testing%

    Sampling and all subse+uent handling and testing shall be carried out in accordance #ithB%S%7A40%

    1iles shall not be bored close to other piles #hich ha&e recentl! been cast and #hich contain

    #or"able or unset concrete such that a flo# of concrete could be induced from or damage

    caused to an! of the pile

    $emporar! 3asings

    $emporar! casings of appro&ed +ualit! or an appro&ed alternati&e method shall be used to

    maintain the stabilit! of pile e(ca&ations #hich might other#ise collapse%

  • 7/24/2019 PAPER WORK.docx

    12/54

    $emporar! casings shall be free from significant distortion% $he! shall be of uniform cross-

    section throughout each continuous length% During concreting the! shall be free from internal

    projections and encrusted concrete #hich might pre&ent the proper formation of the piles

    being cast%

    Stabilit! of 1iling E(ca&ations ;sing Drilling >luid

    2here the use of drilling fluid or column of #ater is appro&ed for maintaining the stabilit! of

    boring the le&el of fluid or column of #ater in the e(ca&ation shall be maintained such that

    the fluid pressure al#a!s e(ceeds the pressure e(erted b! the soil and e(ternal ground #ater

    and an ade+uate temporar! casing shall be used in conjunction #ith the method to ensure the

    stabilit! of the strata near ground le&el until concrete has been placed% $he fluid #ater le&el

    shall be maintained at a le&el not less than / metre abo&e the le&el of the e(ternal ground

    #ater%

    ,n the e&ent of a rapid loss of bentonite suspension or #ater from the piling e(ca&ation the

    e(ca&ation shall be bac"filled #ithout dela! and the instructions of the S%F% shall be obtained

    prior to resuming boring at the location%

    Spillage and Disposal

    9ll reasonable steps shall be ta"en to pre&ent the spillage of bentonite suspension or #ater on

    the site in areas outside the immediate &icinit! of the boring operations% Discarded bentonite

    #ater shall be remo&ed from the site #ithout dela!% $he disposal of bentonite #ater shall

    compl! #ith the regulations of the =ocal 3ontrolling 9uthorities%

    1umping of Boreholes

    1umping from the borehole shall not be permitted unless a casing has been placed in to the

    stable stratum to pre&ent the further ingress of #ater in significant +uantities from other strata

    into the boring or unless it can be sho#n that pumping #ill not ha&e a detrimental effect on

    the surrounding soil or its properties%

    3ontinuit! of 3onstruction

    9 pile constructed in stable soil #ithout the use of temporar! casings or other support shall

    be bored and concreted #ithout dela! to ensure that the soil characteristics are not

    significantl! altered%

    Enlarged 1ile Bases

    $he enlarged pile base shall not be smaller than the dimensions specified and shall be

    concentric #ith the pile shaft diameter% 9 sloping surface of the frustum forming the

    enlargement shall ma"e an angle to the hori?ontal of not less than 77o%

  • 7/24/2019 PAPER WORK.docx

    13/54

    3leanliness of 1ile Bases

    Fn completion of boring loose disturbed or remoulded soil or fragments of roc" shall be

    remo&ed from the base of the pile%

    ,nspection

    >or dr! bore holes each hole shall be inspected prior to the placing of concrete in it% $he

    inspection shall be carried out from the ground surface in the case #here the borehole

    diameter is less than @70 mm% 2here the borehole diameter e(ceeds @70 mm ade+uate

    e+uipment conforming to B%S%7A40 shall be pro&ided to enable the 3ontractor and the S%F% to

    descend into the borehole for the purpose of inspection%

    >or #et bore holes i%e% holes filled #ith drilling fluid or #ater a suitable probe shall be

    pro&ided to ascertain the e&enness and cleanliness of the pile base%

    P$#"ing o( Rein(o!"e)ent

    oints in =ongitudinal Bars

    Reinforcement shall be such that the full strength of the bar is effecti&e across the joint and

    the joint shall be made so that there is no relati&e displacement of the reinforcement during

    the construction of the pile and the spacing of the reinforcing bars shall be maintained in such

    a #a! that proper concreting shall not be impeded%

    1ositions of Reinforcement

    9de+uate spacer bloc"s guide tubes and lifting #ires shall be pro&ided so as to maintain the

    reinforcing steel in the positions as specified%

    2here temporar! casings are emplo!ed the longitudinal reinforcement shall e(tend at least

    /%0 metre belo# the bottom of the casing so that mo&ement of the reinforcement during

    e(traction of the casing is minimised%

    Con"!eting O,e!#tions

    1lacing 3oncrete

    $he method of placing and the #or"abilit! of concrete shall be such that a continuous

    monolithic concrete shaft of the full cross-section is formed%

    2or"abilit! of 3oncrete

    $he #or"abilit! of the concrete shall be determined b! the slump test as described in M%S%'6%

  • 7/24/2019 PAPER WORK.docx

    14/54

    $he suggested slump details for t!pical concreting situations shall be as specified in $able

    /0%/ belo#% $he slump shall be measured at the time%

    $9B=E /0%/ S=;M1 R9N8E >FR $

  • 7/24/2019 PAPER WORK.docx

    15/54

    $he hopper and pipe of the tremie shall be clean and #atertight throughout% $he pipe shall

    e(tend to the base of the boring and sliding plug or barrier shall be placed in the pipe to

    pre&ent direct contact bet#een the first charge of concrete in the pipe of the tremie and the

    #ater or drilling fluid% $he tremie pipe shall at all times penetrate the concrete #hich has

    pre&iousl! been placed and shall not be #ithdra#n from the concrete until the completion ofconcreting% 9t all times a sufficient +uantit! of concrete shall be maintained #ithin the

    tremie pipe to ensure that the pressure from it e(ceeds that from the #ater or drilling fluid%

    $he internal diameter of the tremie pipe shall not be less than /70 mm for concrete made #ith

    '0 mm aggregate and not less than '00 mm for concrete made #ith 0 mm aggregate% $he

    tremie pipe shall be so designed that e(ternal projections are minimised allo#ing the tremie

    pipe to pass through the reinforcing cage #ithout causing damage or uplifting% $he internal

    face of the tremie pipe shall be from projections%

    Et!#"tion o( C#sing

    2or"abilit! of 3oncrete

    $emporar! casings shall be e(tracted #hile the concrete #ithin them remains sufficientl!

    #or"able to ensure that the concrete is not lifted%

    3oncrete =e&el

    2hen the casing is being e(tracted a sufficient +uantit! of concrete shall be maintained

    #ithin it to ensure that the pressure from e(ternal #ater drilling fluid or soil is e(ceeded and

    that the pile is neither reduced in section nor contaminated%

    No concrete shall be placed in the boring once the bottom of the casings has been lifted abo&e

    the top of the concrete it shall be placed continuousl! as the casing is e(tracted until the

    desired head of concrete is obtained%

    9de+uate precautions shall be ta"en in all cases #here e(cess heads of #ater or drilling fluid

    could be caused as the casing is #ithdra#n because of the displacement of #ater or fluid b!

    the concrete as it flo#s into its final position against the #all of the pile shaft% 2here double

    casings are used in the boring the proposed method of #or"ing shall be #ith the appro&al of

    the S%F%

    Gibrating E(tractors

    $he use of &ibrating e(tractors shall be permitted subject to the condition that #or" shall be

    carried out in such a manner and at such times as to minimise nuisance and disturbance%

    Const!u"tion o( Pi$e He#*s

    2ater =e&els

    ,n the e&ent of the ground #ater le&el being higher than the re+uired pile head casting le&el

    sho#n on the Dra#ings the 3ontractor shall submit his proposals for appro&al prior to

  • 7/24/2019 PAPER WORK.docx

    16/54

    placing concrete% $he pile head shall not be left belo# theground #ater le&el unless appro&ed

    precautions are ta"en%

    3utting and 1reparation of 1ile Heads

    $he top of the pile shall be brought abo&e the cut-off le&el of the pile to permit all laitanceand #ea" concrete to be remo&ed and to ensure that if can be properl! "e!ed into the pile

    cap% 1ile heads shall be constructed to the details sho#n on the Dra#ings%

    $emporar! Bac"filling 9bo&e 1ile 3asting =e&el

    9fter each pile has been cast an! empt! bore remaining shall be protected and shall be

    carefull! bac"filled as soon as possible #ith appro&ed materials%

  • 7/24/2019 PAPER WORK.docx

    17/54

    GEOTECHNICAL WORK

    CONSTRUCTION CAST IN SITU

    FOR .//)) DIAMETER BORED PILES

    INTRODUCTION

    1iling is a t!pe of ground treatment #hich is dri&ing a pile into the ground le&el% E(cept sheet

    pile other piles li"e concrete pile timber pile steel pile bored pile are used to transfer the

    building load to the ground% ,t)s used to strengthen the soil so that the ground able to support

    the load of the building% 2hile sheet pile is usuall! used to support lateral load and act as a

    supporting #all%

  • 7/24/2019 PAPER WORK.docx

    18/54

    >actors influencing the pile selection are based on the t!pe of piles a&ailable in mar"et

    installation method contractual re+uirement site conditions I constraints t!pe and

    magnitude of loading and de&elopment program I cost%

    1ile can be done in t#o t!pe precast concrete pile or cast-in-situ concrete pile% Normall!

    precast concrete pile is used for building #or" or #e can "no#n it as spun pile or R3 s+uare

    pile : reinforcement concrete s+uare pile % 2hile cast-in-situ concrete pile is used for bridge

    #or" or #e can "no#n it as bored pile because bridge #or" has a larger load compare to

    building #or"%

    ,n this project bored piles are used as the foundation for the bridge structures% $he bored pile

    is a t!pe of foundation usuall! used in propert! construction as an alternati&e for other

    foundation methods #hen earth isn)t strong enough to support standard foundations% Ha&e a

    lot ad&antage used the bored pile as foundations%

    $herefore length can be readil! &aried to suit &ar!ing ground conditions soil remo&ed in

    boring can be inspected and if necessar! sampled or in situ tests made can be installed in

    &er! large diameters end enlargements up to t#o or three diameters are possible in cla!s

    material of pile is not dependent on handling oor dri&ing conditions can be installed in &er!

    long lengths can be installed #ithout appreciable noise or &ibration can be installed in

    conditions of &er! lo# head-room and no ris" of ground hea&e%

    1rior to the piling #or" pre-drilling of a borehole drilled at each proposed pile position #as

    re+uired to determine the founding le&el of each pile% Roc"et soc"et design factors depend on

    soc"et roughness : shearing dilation intact roc" confining stiffness : roc" mass fractures I

    pile diameter 0 and soc"et geometr! ratio%

    TYPE OF MACHINERY AND E0UIPMENT

    NO DESCRIPTIONS

    1 3ra#ler 3rane

  • 7/24/2019 PAPER WORK.docx

    19/54

    2 Boring ;nit Machine :Soil Rotar! Mechanical Rig

    3 5ell! Bar

    4 E(ca&ator

    5 Gibro Hammer

    . 9ir 3ompressor

    6 8enerator Set

    7 Read! Mi( 3oncrete

    8 Soil 9uger

    1/ 3ore Barrel

    11 Roc" 9uger

    12 3leaning Buc"et

    13 3asing

    14 $remie 1ipe

    15 9 >unnel Shaped Hopper

    / 3R92=ER 3R9NE

  • 7/24/2019 PAPER WORK.docx

    20/54

    >unction $o hoist and s#ing loads at &arious radii%

    9d&antage Eas! to mo&e around on site and perform each lift #ith

    little set-up and also capable of tra&elling #ith a load

  • 7/24/2019 PAPER WORK.docx

    21/54

    ' BFR,N8 ;N,$ M93H,NE SF,= ME3H9N,39= RF$9R< R,8

    $o hold the &ibro hammer $o raised up the buc"et #hile

    concreting%

  • 7/24/2019 PAPER WORK.docx

    22/54

    >unction $o drill holes of diameters from 600 to '700 mm9d&antage 3an drill to &arious depths up to C0 m

  • 7/24/2019 PAPER WORK.docx

    23/54

    4 5E==< B9R

    $o drill using the core barrel after

    install casing%

    Raised up the soil auger after

    drill

  • 7/24/2019 PAPER WORK.docx

    24/54

    >unction9d&antage Manufactured from high-tensile steel to ensure

    minimum #eight at ade+uate strength%

  • 7/24/2019 PAPER WORK.docx

    25/54

    EJ39G9$FR

    3onnected #ith the core barrel to drill the roc" core

  • 7/24/2019 PAPER WORK.docx

    26/54

    >unction - $o digging of trenches holes foundations

    - >or material handling

    - $o dri&ing piles in conjuction #ith a pile dri&er

    - $o drilling shafts for footings and roc" blasting

    9d&antage ,t ma"es the construction easier for the #or"ers

    since it can dig mo&etransport earth handling

    material gra&el and etc% in a shorter period of time

    #ith less energ! use%

    7 G,BRF H9MMER

    Handling the o(ieen and

    acet!lene to cut the ;p&c pipe

    for the preparation sonic

    logging test

    3lear the soil at point for sonic

    logging test

  • 7/24/2019 PAPER WORK.docx

    27/54

    >unction $o install of a large number of pile t!pes and casing

    9d&antage =o# noise emissions less energ! and time to install

    casing

    $he installation of temporar! steel casing #ith generated b! air

    compressor

  • 7/24/2019 PAPER WORK.docx

    28/54

    6 9,R 3FM1RESSFR

    >unction ;sed to po#er machiner! and e+uipment that is used to

    perform hea&! and tough #or"%

    9d&antage $he elements of safet! as there is relati&el! little to no

    electricit! in&ol&ed%

    8enerated the &ibro hammer8enerated the machine #ith the

    connecting generator set

  • 7/24/2019 PAPER WORK.docx

    29/54

    @ 8ENER9$FR SE$

    >unction $o generate electric energ! from the combination of a

    diesel engine #ith an electric generator%

    9d&antage ;sed in places #ithout connection to the po#er grid

    as emergenc! po#er-suppl!%

  • 7/24/2019 PAPER WORK.docx

    30/54

    C RE9D< M,J 3FN3RE$E3onnected #ith air$he po#er suppl! of generator set

  • 7/24/2019 PAPER WORK.docx

    31/54

    >unction $o concreting using tremie method

    9d&antage Sometimes preferred o&er on-site concrete mi(ing

    because of the precision of the mi(ture and reduced

    #or" site confusion%

    A SF,= 9;8ER

    Read! mi( concrete is transferred to the buc"et

  • 7/24/2019 PAPER WORK.docx

    32/54

    >unction $o drill the soil%

    9d&antage 9lign directl! o&er the top the proposed%

    /0 3FRE B9RRE=

    Drilling the soil using soil auger

    #ill stop after reached the roc"

    core

    Start drilling the soil that align

    directl! o&er the top the proposed

    e %

  • 7/24/2019 PAPER WORK.docx

    33/54

    >unction $o drill roc" cores #hile the! being e(tracted from the

    drill hole%

    9d&antage 3an used in large diameter

  • 7/24/2019 PAPER WORK.docx

    34/54

    // RF35 9;8ER

    $he core barrel is drill the roc"

    core b borin unit machine

    3ore barrel is lo#ered into the

    borehole

  • 7/24/2019 PAPER WORK.docx

    35/54

    >unction $o drill for boring hole precisel! under hard roc" soil

    conditions

    9d&antage $he re+uirements of cutting much harder roc"s than

    e(pected #ith the lean s"e# angle of tungsten-carbine

    teeth%

    /' 3=E9N,N8 B;35E$

    S"e# angle of

    tungsten-carbine

    Roc" auger #hich is connected

    #ith "ell! bar lo#ered into

    Roc" auger is lo#ered into

    borehole to drill the soc"et roc"

  • 7/24/2019 PAPER WORK.docx

    36/54

    >unction $o remo&e the fragmented roc" material

    9d&antage Eas! and efficientl! to remo&e the soil and roc"%

    /4 39S,N8 K 600mm

    $he fragmented roc" material is

    remo&ed b! using the cleaning

    ;nplugged the scre# from

    cleaning buc"et to remo&e the

  • 7/24/2019 PAPER WORK.docx

    37/54

    >unction $o support the #ea"er soil la!ers%

    9d&antage 9ct as guide for drilling tools to ensure &erticalit! of

    the bore%

  • 7/24/2019 PAPER WORK.docx

    38/54

    / $REM,E 1,1E

    ,nstall casing #ith &ibrohammer

    $he distance from the steelcasing #ould be measured to

    reference pins%

  • 7/24/2019 PAPER WORK.docx

    39/54

    >unction $o concrete placement #hich the concrete is placed

    belo# #ater le&el%9d&antage Eas! to concrete placement and the curing conditions

    perfect using the tremie method%

    /7 9 >;NNE= SH91ED HF11ER

    $he tremie pipe is connected #ith

    the funnel shaped hopper%

    3leaning the face from concrete

    to connect #ith funnel shaped

    ho er%

  • 7/24/2019 PAPER WORK.docx

    40/54

    >unction $o connected #ith the tremie pipe #hich transfer the

    concrete

    9d&antage >lo# #ill not ca"e or spoil and controlled segregation

    $he funnel shaped is connected

    #ith the tremie i e

    $he concrete is transfer through

    the funnel sha ed ho er%

  • 7/24/2019 PAPER WORK.docx

    41/54

    METHOD STATEMENT

    SE$$,N8 F;$ F> 1,=E

    1FS,$,FNS

  • 7/24/2019 PAPER WORK.docx

    42/54

    Setting out the controlled points of

    piles and mar"ed b! steel sta"es%

    3leaning the site location

    $he consultant together #ith the

    contractor)s sur&e!or #ill chec" the

    sta"es for correctness%

    ,NS$9==9$,FN ;S,N8

    $EM1FR9R< S$EE= 39S,N8

  • 7/24/2019 PAPER WORK.docx

    43/54

    $he drilling and remo&al of dr!

    earth b! auger to a fe# meters

    depth%

    $he drilling auger directl! house and

    align directl! o&er the top the

    proposed peg%

  • 7/24/2019 PAPER WORK.docx

    44/54

    9 steel casing #ould then be

    installed into the borehole #ith

    assistance of a standard &ibro-

    $he distance from the steel casing

    #ould be measured to reference

    pins%

    ,NS$9==9$,FN ;S,N8

    $EM1FR9R< S$EE= 39S,N8

    3ont%

  • 7/24/2019 PAPER WORK.docx

    45/54

    $he installation depth of the casing is dependent on the soil

    conditions%

    DR,==,N8

  • 7/24/2019 PAPER WORK.docx

    46/54

    Drilling the soil$he core barrel is drilling the soil

    $he cleaning buc"et is lo#ered into

    the bore hole to cleaning borehole%

    $he cleaning buc"et is raised up to

    dischar e the soil and roc"%

  • 7/24/2019 PAPER WORK.docx

    47/54

    DR,==,N8

    3ont%

    3leaning the sample of roc" $he sample roc" #as ta"en for the

    testin %

  • 7/24/2019 PAPER WORK.docx

    48/54

    ,NS$9==9$,FN F> RE,N>FR3EMEN$

    :REB9R 398E

    Gie# from bottom steel cage is

    raised up and main reinforcement

    used accordance #ith the desi n%

    Steel cage is raised up and prepared

    for installation%

    $he rebar cage is lo#ered into the

    borehole%

  • 7/24/2019 PAPER WORK.docx

    49/54

    $REM,E 3FN3RE$,N8

    Measured the high slump concrete

    b! tape%

    9 sample concrete is ta"en for slump

    test and cube test%

    Read! mi( concrete is placed in the

    buc"et

    3oncrete is controlled b! manpo#er

    #hich the hopper is connected at the

    top of the tremie pipe

  • 7/24/2019 PAPER WORK.docx

    50/54

    $REM,E 3FN3RE$,N8

    3ont%

    3ompacting concrete #hich

    generate b! generator set

    3ompacting concrete b! &ibro po"er

  • 7/24/2019 PAPER WORK.docx

    51/54

    $remie pipe that joint each other is

    loosed

    $he tremie pipe is raised up to

    loosed the section using chain

    #rench$REM,E 3FN3RE$,N8

    3ontL

    $he hopper is remo&ed to connect

    the tremie i e

    $he hopper is connected #ith tremie

    i e

  • 7/24/2019 PAPER WORK.docx

    52/54

    $he concrete is topped up in the

    casing

    $he measuring tape is lo#ered

    into the borehole

    $REM,E 3FN3RE$,N8

    3ont%

  • 7/24/2019 PAPER WORK.docx

    53/54

    $he temporar! steel casing is e(tracted

    #hen sufficient concrete is discharge%

  • 7/24/2019 PAPER WORK.docx

    54/54

    SUMMARY BORED PILE

    AND

    BORED PILE RECORD