Upload
dodung
View
218
Download
0
Embed Size (px)
Citation preview
Paper Number:DOE/MC/25140-97/C0711
Title:Power Systems Development Facility: Design, Construction, and CommissioningStatus
Authors:C.A. PowllP. VimalchandH.L. HendrixP.M. Honeycut
Contractor:Southern Company ServicesP.O. Box 2625Birmingham, AL 35202
Contract Number:DE-FC21-90MC25140
Conference:Advanced Coal-Fired Power Systems '96 Review Meeting
Conference Location:Morgantown, West Virginia
Conference Dates:July 16-18, 1996
Conference Sponsor:U.S. DOE, Morgantown Energy Technology Center
Disclaimer
This report was prepared as an account of work sponsored by anagency of the United States Government. Neither the United StatesGovernment nor any agency thereof, nor any of their employees,makes any warranty, express or implied, or assumes any legal liabilityor responsibility for the accuracy, completeness, or usefulness of anyinformation, apparatus, product, or process disclosed, or representsthat its use would not infringe privately owned rights. Referenceherein to any specific commercial product, process, or service by tradename, trademark, manufacturer, or otherwise does not necessarilyconstitute or imply its endorsement, recommendation, or favoring bythe United States Government or any agency thereof. The views andopinions of authors expressed herein do not necessarily state or reflectthose of the United States Government or any agency thereof.
1.4 Power Systems Development Facility:Design, Construction, and Commissioning Status
Charles A, powe]l (charles.a.powell(ijscsnet,com; 205-669-5869)panna]al Vimalchand (p.vimalchand(ijscsnet,com; 205-669-5852)Howard L, Hendrix ([email protected]; 205-669-5876)Peter M. Honeycutt (peter.m.honeycuttfj!scsnet.tom; 205-669-5875)
Southern Company ServicesP.O. BOX 1069
Wilsonville,AL35186
Abstract
This paper will provide an introduction to the Power Systems Development Facility, aDepartment of Energy sponsored, engineering scale demonstration of two advanced coal-firedpower technologies; and discuss current status of design, construction and commissioning of thisfacility.
The Power Systems Development Facility (PSDF) will test and demonstrate a secondgeneration combined cycle pressurized circulating fluidized bed combustion system with a syn-gas fired topping cycle (APFBC); an advanced circulating fluidized bed transport reactor actingas either a combustor or as a gasifier; (presently) three different Hot Gas Clean-Up technologies(Particulate Control Devices or PCDS); and (in later years) fuel cells and desulfurizationtechnologies.
Design and construction of the Transport Reactor and required associated equipment willbe completed in early summer 1996, Design of the APFBC is over 95% complete, andconstruction has begun. Commissioning of the Transport reactor is presently underway, with theseparate components and sub-systems being fully operational and work focused on integrationissues for the entire reactor system. Commissioning of APFBC components should begin inearly 1997. The first ceramic candle filter vessel has been loaded and is undergoing testing attemperatures over 1000”F. Initial operation of the transport reactor will be as a combustor, withplans to test operation as a gasifier scheduled for thk Fall.
Construction of the Granular Bed Filter is presently underway, with plans for sub-systemcommissioning to begin this Fall. The first ceramic candle filter system will be tested on thetransport reactor before being relocated mid-next year to the APFBC train; at which time it willbe replaced by another candle filter system on the transport reactor.
Research sponsored by the U.S. Department of Energy’s Morgantown Energy Technology Center, undercontract DE-FC21 -90MC25 140 with Southern Company Services, Inc., P,O. Box 1069, Wilsonville, AL 35186;te]efax: 205-669-5843
Construction of the APFBC system, with the installation of the combustor vessels, heatexchangers and refractory lined piping is underway. The electrical design is being completedthis summer; as is the assembly of the major components of this system: The CombustionTurbine, The Topping Combustor, and the inlet/outlet piping for both, By using commonBalance of Plant facilities, the condensate, cooling, control air, purge and auxiliary fuel systemsare installed to support operation of the transport reactor and require only minimal work tosupport the APFBC operation.
Construction of the PSDF has presented several problems different from thoseencountered in constructing a traditional pulverized coal plant: Pneumatic pressure boundaries,fuel (and sorbent) injection under pressure, gas sampling under temperature and pressure, exoticmaterial procurement and fabrication, and complex piping due to the large number of fluidizinggas connections to the pressurized reactor.
POWER SYSTEMS DEVELOPMENT FACILITY
DOE Cooperative Agreement No. DE-FC21-90MC25140
Southern Company Services, Inc.Wilsonville, Alabama
Design, Construction, and Commissioning Status
1 of 0796CPMT.PRE/96089
The Southern Company Power Systems Development Facility
PSDF Program Objective
15 of 0296RRBM/96045Rev. 7/10/96
Develop advanced coal-based power
generation technologies that can produce
electricity at competitive cost and meet all
environmental standards.
The Southern Company Power Systems Development Facility
PSDF Program Goal
4 of 0796RRWI.PRE/96118
The PSDF is a site where new process configurations and components for advanced power systems can be tested in an integrated process environment at sufficient size to provide data for scale-up toward commercialization. DOE’s intent is that:
The PSDF be recognized by equipment vendors, process developers, and generators of electric power as the best place to test new components and integrated process configurations for advanced power systems.
Data from the PSDF be recognized as a clear indicator of the usefulness of new components and integrated process configurations for advanced power systems and be sufficient to support commercial scale-up.
Public and private funding agencies recognize the PSDF as a readily accessible, politically neutral, cost effective testing location for advanced power system components and integrated process configurations.
The staff at the PSDF be recognized as experts in their respective technologies by all their customers.
The Southern Company Power Systems Development Facility
Project Overview
4 of 0796CPMT.PRE/96090
METC sponsored project to demonstrate two Advanced Coal-fired Power Generation Technologies, three Hot Gas Clean-Up Technologies, and Fuel Cells (future)
Southern Company Services is acting as Prime Contractor and is responsible for Operation of the facility as well as Design of Balance of Plant (BOP) Equipment, Design Integration, Construction and Start-Up
M.W. Kellogg (Kellogg), Foster Wheeler (FW), Westinghouse (W), Combustion Power Corp. (CPC) and Industrial Filter and Pump (IF&P) are major participants.
The Southern Company Power Systems Development Facility
Project Overview
5 of 0796CPMT.PRE/96091
Increased integration of process components
All possible components were commercially available to minimize scale up concerns and allow use of existing technologies if possible.
Kellogg is supplying a pressurized transport reactor that can be configured as either a combustor or a gasifier.
Foster Wheeler is supplying an integrated, Advanced Pressurized Fluidized Bed Combustion (APFBC) system, including a gas turbine equipped with a topping combustor supplied by Westinghouse.
The Southern Company Power Systems Development Facility
Project Overview
6 of 0796CPMT.PRE/96092
Particulate Control Devices (or PCD’s) are supplied by Westinghouse, CPC, and IF&P.
Two are using ceramic candle filters (Westinghouse and IF&P).
CPC is supplying a Granular Bed Filter.
The ceramic candles are being supplied by several vendors.
PARTICIPANT RESPONSIBILITIES
3 of 0495RRBM.PRE/95027Revised 7/10/96
SouthernResearchInstitute
U. S. Departmentof Energy
Southern Company ServicesProject ManagementEngineering Coordination
SouthernCompany
Electric Power
Research Institute
APFBC/ Gas
Turbine
ParticulateCollectionDevices
Foster WheelerWestinghouse
Allison
M. W. Kellogg SouthernCompanyServices
B.O.P. and
Construction
SouthernCompanyServices
TransportModule
(Gasif./PFBC)Operate
ParticulateSampling
Combustion PowerIF&P
Westinghouse
SITE STAFF
SCS 40APC 43SRI 6-8DOE 3EPRI 1Spectrum 1Vendors 6-10
TOTAL 100-106
PSDF SITE ORGANIZATION
TechnicalManager
Sr.
SecretarySr.
Secretary
TimPinkston O & M
Mgr.
DarrellMoore
GloriaBuie
CherryDupree
FW Train Lead
Engineer
PCDLead
Engineer
MWK Train Lead Engineer
DataAnalysis
Lead Engineer
HowardHendrix
P.Vimalchand
DougMaxwell
JohnWheeldon(EPRI)
Lab. Superv. &
Technicians(SRI)
Engineers Engineers Engineers
Frank MortonDavid RomansPete Honeycutt
MatthewDavidson
Oliver DaviesGuohai Liu
Roxann LeonardEdwin Galloway
(DOE)
Brandon DavisBruce Harrington
(DOE)
Mary JaneSherbert
Manager
Planning &
Analysis
GaryStyles
DOE
Technical
Liason
DarrenMollot
4 Shift Coordinators
Wayne BarnettRay Lee
T.O. TarpleyShift Coord. #4
APC0
20 PCO8 APCO
2 EO
Maint.
Coordinator
I & C
Engineer
Mech.
EngineerDesigner
Maint.
Supervisor
CharlesPowell
TonyHicks
RichardHornbuckle
JimmyHorton
BrettWingard
8 Mech.
1 Welder
APC0
4 E & I
APC01 CEM
Mech.
(Spectrum)
DavidMims
Training
Coordinator
S:\PAPRPRES\DUPREE.PRE
Admin.
Ass’t.
RandallRush
ProjectDirector
DOEMETC
John VeazeyRandy Johnson
David Mann
CharlesCantrell
Adm/Proj
Support
Mgr
PurchasingAgent/
Coordinator
Env./Safety
Coordinator
3 W/H
Clerks
Sr.
Secretary
CharlesHenderson
BeckyWatters
HughTurner
Admin
Clerk
MaryMurphree
Cost/
Analysts/
Schedule
DavidPhilpot
RachelWilson
Document
Control
TerrySpinks
ParticulateTesting
(SRI)
Vendor
Engineers
MWKFW(W)
IF&PCPC
OthersEngineers
JerryBandura
The Southern Company Power Systems Development Facility
Project Status
9 of 0796CPMT.PRE/96093
Design and Engineering are complete, except for electrical integration of Foster Wheeler equipment, which will be complete this fall.
Construction of Kellogg and Kellogg required BOP equipment is complete.
Start-up of BOP equipment began last September with the electrical station service.
Start-up of Kellogg’s transport reactor as a combustor is in the final stages.
Several design enhancements have been incorporated during construction to improve operability during system malfunctions.
The Southern Company Power Systems Development Facility10 of 0796CPMT.PRE/96094
Start-Up Bed Material Injection Spools
Propane Supply Option Spools
Steam Supply Piping Modifications
PCD Warm-Up Modifications
Using Primary Gas Cooler as a Condensation Heater
Using Sulfator Start-Up Heater
Using a Screw Cooler to Cool Pulverized Coal
Using Process Air to Fluidize the Combustion Heat Exchanger
Nitrogen Purge Connections
Design Enhancements
The Southern Company Power Systems Development Facility
Systems Operational
11 of 0796CPMT.PRE/96095
Electrical Station Service
Distributed Control and Data Collection
Cooling Water Systems
Instrument, Control, and Service Air
Feedstock (Coal and Sorbent) Storage, Reclaim and Preparation
Condensate and Steam Generation
Kellogg Process and Transport Air
Reactor Aeration, Instrument Purge, Spoiling and Fluidization
Dense Phase Transport of Feedstock and Ash
The Southern Company Power Systems Development Facility
Systems Operational
12 of 0796CPMT.PRE/96096
Burners on Thermal Oxidizer, Sulfator Start-up Heater and Transport Reactor Start-up Heater
Ash Cooler Heat Transfer Fluid and Screw Coolers
Recycle Gas Compressor
Westinghouse PCD Backpulse
Baghouse and Thermal Dilution Fan
Liquid Nitrogen Storage and Delivery
Propane Storage and Delivery
Backpulse Air
The Southern Company Power Systems Development Facility
Issues Encountered
13 of 0796CPMT.PRE/96098
Piping and electrical conduit density in the process structure
First of a kind specification requirements
Aggressive schedule forcing design decisions
Exotic material requirements due to temperature, pressure and chemical activity
Designs for single case, limiting range of operation
Pneumatic pressure boundaries
Gas sampling at pressure and temperature
Feedstock injection into pressurized reactor
Suitable start-up bed materials for reactors
The Southern Company Power Systems Development Facility
Design IssuesPiping Density in the Process Structure
14 of 0796CPMT.PRE/96099
Due to cost constraints, the structure was reduced in size by 20’ in both directions.
Every pressure tap must be supplied with a purge gas (Nitrogen) that must be metered and flow controlled to minimize biasing.
Fluidization requires many aeration nozzles to prevent layout of solids.
Staged combustion and controlled gasification require fine control of location and flow of combustion (oxidizing) air.
PSDF transport reactor has as many connections as a 150 MW unit would.
The Southern Company Power Systems Development Facility
Design IssuesFirst of a Kind Specification Requirements
15 of 0796CPMT.PRE/96100
Specifications for coal and limestone size require additional equipment and feedstock wastage to achieve design requirements.
Conservativism in inclusion of alkalai getters, cyclones, baghouses, and sulfator into process designs
High Nitrogen usage, especially during start-ups and shut-downs
Requirements for specialized alloys of limited availability and high price
Incomplete or untried control configuration
The Southern Company Power Systems Development Facility
Design IssuesAggressive Schedule
16 of 0796CPMT.PRE/96101
Aggressive schedule forcing design decisions
Coal (feedstock) prep building started before the pulverizers were purchased, requiring modification before installation could be completed.
Cooling water system redesign caused by increased requirements of Foster Wheeler, and other vendors’ equipment
Station service equipment being modified in response to increasing electrical loads
This aggressive schedule did force project to progress.
The Southern Company Power Systems Development Facility
Design IssuesSpecialized Material Requirements Due to
Temperature, Pressure and Chemical Activity
17 of 0796CPMT.PRE/96102
Gas Analyzers
Recycle Gas Compressor Piping
Foster Wheeler’s Carbonizer Gas Valves and Piping
Reactor Emergency Pressure Let-down Piping
Gas Cooler Bypass Orifices
The Southern Company Power Systems Development Facility
Design/Operation IssuesDesigns for Single Case, Limits Range of
Operation
18 of 0796CPMT.PRE/96103
Several instances of design short-comingsTransport reactor start-up burnerTransport reactor pressure control valveRecycle gas compressor control logicDense phase transport control logicTransport reactor process air compressor control logic
Kellogg Process Control is not yet integrated, unable to link process variables of different systems to allow smooth parametric changes
The Southern Company Power Systems Development Facility
Design/Operation IssuesPneumatic Pressure Boundaries
19 of 0796CPMT.PRE/96104
Reactors using piping lined with two layers of refractory totaling 9 inches thick
Refractory lined piping 36" in diameter weigh several hundred pounds per running foot
Due to weight and size, the piping is difficult to assemble in place, requiring each joint to be caulked and sealed with flexatalic gaskets.
Flexatalic gaskets are fragile during storage and installation and are single use only.
The Southern Company Power Systems Development Facility
Design/Operation IssuesPneumatic Pressure Boundaries
20 of 0796CPMT.PRE/96105
Refractory is hydroscopic and requires specialized curing procedures after thirty days at ambient air conditions.
Problems with long term storage of un-cured refractory required minor repairs.
Vessels and piping have rate of change restrictions on temperature and pressure to prevent cracking and failures
A pressure test is required after every inspection or maintenance.
The Southern Company Power Systems Development Facility
Design/Operation IssuesGas Sampling at Pressure and Temperature
21 of 0796CPMT.PRE/96106
First of a kind engineering to extract dust- laden samples at temperature and pressure
Several gas components have dew points over 700F, and the liquid phase is highly corrosive.
Requires exotic alloys for strength and corrosion protection
Concentrations and compounds require specialized analyzers.
The Southern Company Power Systems Development Facility
Design/Operation IssuesFeedstock Injection into Pressurized
Reactor
22 of 0796CPMT.PRE/96107
Tidd and Other PFBC Plants Use Hybrid Slurry Pumps to Inject Feedstock
Add water to processHigh maintenance items
PSDF Using Dense Phase Feed TechnologyDry conveying using Nitrogen or air as transport mediaMetering feedstock and transport mediaUsing pressures less than 20 psi higher than reactor
The Southern Company Power Systems Development Facility
Operation IssuesSuitable Start-Up Bed Materials for
Transport Reactor
23 of 0796CPMT.PRE/96108
Friable Alumina Initially Procured and usedFluidizes well, and temperature resistantTwice as dense as other feedstocks, causing problems with dense phase equipmentVery hard and abrasive, causing failure of control valve
Spherical AluminaNonabrasive, fluidizes wellHard to procure, very dense
The Southern Company Power Systems Development Facility
Operation IssuesSuitable Start-Up Bed Materials for
Reactors
24 of 0796CPMT.PRE/96109
River SandUsed at TiddHigh Silica will not withstand heat
Furnace AshDifficulty in finding adequate source
Conclusion: Use Alumina Until Enough Transport Reactor Ash is Generated.
Pre-sized, dry, inert, temperature resistant
The Southern Company Power Systems Development Facility
Progress to Report
25 of 0796CPMT.PRE/96110
Passed reactor pressure test with no welds failing and few minor flange leaks
Candled Westinghouse PCD with no candle breakage
Thermal oxidizer refractory was cured to 1600F, and thermal oxidizer was nearly 1000 hours of operation
Sulfator/PCD warm-up heater refractory cured in 4 days of operation
Successfully balanced purge flows to zero differential pressure transmitters at three reactor pressure settings
The Southern Company Power Systems Development Facility
Progress to Report
26 of 0796CPMT.PRE/96111
Successfully fired reactor start-up burner to cure reactor refractory lining to 1000F
Successfully fluidized reactor with alumina as start-up bed material; circulating bed material through the reactor, riser, and heat exchanger at circulation rates of up to 90,000 lbs/hr and velocities to 45 ft/sec
Demonstrated operation of feeders under pressure with alumina
Preparing for the Foster Wheeler combustor refractory cure
Currently firing with coal at 165 PSI
The Southern Company Power Systems Development Facility
Future Plans
29 of 0796CPMT.PRE/96114
July - Aug: Operate transport reactor as combustor for shake-down trials
Sept - Oct: Operate transport reactor as combustor for parametric testing
Oct - Nov: Operate transport reactor as gasifier for shake-down trials
Nov - Mar ’97: Operate transport reactor as gasifier for parametric testing
Apr - May ’97: Operate transport reactor as combustor for shake-down trials of Combustion Power’s granular bed filter
The Southern Company Power Systems Development Facility
Future Plans
30 of 0796CPMT.PRE/96116
Apr - May ’97: Foster Wheeler Combustion Turbine Start-Up
Sept - Oct ’97: PFBC Start-Up of Foster Wheeler
Jan - Feb ’98: APFBC Start-Up of Foster Wheeler