Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Environmental Assessment and Review Framework July 2012
Pakistan: Sindh Cities Improvement Investment
Program (SCIP)
Prepared by North Sindh Urban Services Corporation Limited for the Asian Development Bank.
ENVIRONMENTAL ASSESSMENT AND REVIEW
FRAMEWORK (EARF) –TRANCHE 2 PFR 2012
(NORTH SINDH URBAN SERVICES CORPORATION)
(REVISED DOCUMENT AS PER TRANCHE-2 PROJECTS REQUIREMENTS)
(JULY 2012)
[This documents is prepared/ updated to identify the environmental requirements for Tranche-2 , keeping in view the Asian Development Bank safeguards policy 2009 and ADB guidelines 2003]
Supplementary Appendix L
Page 2
LIST OF ABBREVIATIONS
ACRONYM COMPLETE FORM
ADB Asian Development Bank
AMF Asbestos Management Framework
BCOP Building Code of Pakistan
DNI Distribution Network Improvement
DOS Director Operations and Services, NSUSC
EARF Environment Assessment and Review Framework
EIA Environmental Impact Assessment
EA Executive Agency
EPA Environmental Protection Agency
EMP Environmental Management Plan
GoP Government of Pakistan
HSE Health, Safety and Environment
HFL Highest Flood Level
IA Implementation Agency
ICB International Competitive Bidding
IEE Initial Environmental Examination
LARF Land Acquisition and Resettlement Framework
LARP Land Acquisition and Resettlement Action Plan
MD Managing Director
MGD Million Gallons per Day
MFF Multi tranche Finance Facility
NOC No Objection Certificate
Supplementary Appendix L
Page 3
ACRONYM COMPLETE FORM
NGO Non Governmental Organization
NSUSC North Sinth Urban Services Corporation
NEQS National Environmental Quality Standards
N/S Not Scheduled
PSU Program Support Unit
PFR Periodic financing Request
P&DD Planning and Development Department
PC Public Consultation
RAP Resettlement Action Plan
REA Rapid Environmental Assessment
RoW Right of Way
SCIP Sindh Cities Improvement Program
SEPA Sindh Environmental Protection Agency
SWM Solid Waste Management
TOR Terms of Reference
TMDP Temporary Drainage Management Plan
TMA Taluka Municipal Administration
UNESCO United Nations Educational, Scientific, and Cultural
Organization
USC Urban Service Corporation
WB World Bank
Supplementary Appendix L
Page 4
ENVIRONMENTAL ASSESSMENT AND REVIEW FRAMEWORK
Contents
LIST OF ABBREVIATIONS ........................................................................... Error! Bookmark not defined.
A. Development Activities Requiring Environmental Assessment and Review .................................. 5
B. Environmental Criteria for Additional Subproject Selection............................................................ 11
C. Responsibilities and Authorities of Various Agencies ................................................................. 12
D. Environmental Assessment and Review Procedures of Additional Subprojects .................... 14
1. Application of Selection Criteria ..................................................................................................... 14
2. Environmental Classification .......................................................................................................... 14
3. Preparation of Detailed Design ...................................................................................................... 14
4. Preparation of Construction Contracts .......................................................................................... 15
5. Monitoring During the Construction Period .................................................................................. 15
6. Monitoring of Subproject Operations............................................................................................. 15
E. Public Disclosure .............................................................................................................................. 15
F. Institutional Arrangements .............................................................................................................. 16
G. Environmental Management and Monitoring ........................................................................... 20
Table 2: Key tasks for Environmental Monitoring Plan ................................................................... 21
Table 3: Summary of Estimated Costs for EMP Implementation as per Business/Operating
Plan ........................................................................................................................................................ 21
APPENDIX 1: Draft Terms of Reference for Environmental Safeguards Specialist/Manager .. 23
APPENDIX 2: Environmental Management Plan for Tranche-1 Subprojects .............................. 25
APPENDIX-3: Semi-annual Environmental Monitoring Report ..................................................... 56
Supplementary Appendix L
Page 5
ENVIRONMENTAL ASSESSMENT AND REVIEW FRAMEWORK
A. Development Activities Requiring Environmental Assessment and Review
1. The Government of Pakistan (GoP) has requested the Asian Development Bank (ADB) to
provide a Multitranche Financing Facility (MFF) Tranche -2 PFR 2012 to the Government of Sindh
(GoS) to facilitate investments in the proposed Sindh Cities Improvement Investment Program
(SCIP or the Investment Program). This u p d a t e d Environmental Assessment and Review
Framework (EARF) is prepared as a means to ensure that the potential environmental
impacts of the subprojects financed under the MFF Tranche 2 are appropriately assessed and
mitigated to acceptable levels.
2. The MFF funding from ADB is expected to be released in stages (tranches). The
Investment Program will provide a set of investments, institutional and policy reforms, and
capacity building measures to improve service provision and address infrastructure deficiencies
and institutional constraints to the development of secondary cities of Sindh.
3. The SCIP aims to improve the quality of urban service delivery in several of Sindh’s
secondary cities. This proposed long-term program of support will target select growth centers,
clustered together to benefit from economies of scale and their strategic location along the
National Trade Corridor. This $300 million MFF will support comprehensive urban planning,
institutional reforms, including introduction of professionally-managed urban services providers,
and complementary infrastructure investments in water supply, wastewater, and solid waste
management (SWM) beginning in 2008, with phased investment over ten years. The
Investment Program will adopt a carefully phased approach; financing priority investments
where they are more likely to succeed and support improved cost recovery, with learning and
further investment subsequently rolled-out to new town clusters when ready. This long-term
partnership with the GoS will provide an opportunity for more substantive engagement on policy,
regulatory, management and financial aspects of urban service delivery, a prerequisite for
sustainable infrastructure services.
4. Under the MFF loan procedures of ADB, implementation of safeguards is to be achieved
by environmental assessment of every subproject to be undertaken following ADB Safeguard
Policy (2009). The subprojects under the Investment Program generally concern the
development of facilities in and around the urban areas of medium-size towns and are not likely to
affect sensitive areas, forests or wetlands. The subprojects might typically be expected to be
classified as Category B & C under ADB Environmental Assessment Guidelines (2003) that will
be followed for all subprojects. One Sub Project in Tranche -2 is classified as Category A
5. The GoP regulations, the Pakistan Environmental Protection Agency Review of Initial
Environmental Examination (IEE) and Environmental Impact Assessment Regulations (2000)
categorize development projects into two schedules according to their potential environmental
Supplementary Appendix L
Page 6
impact. The proponents of projects that have reasonably foreseeable impacts are required to
submit an IEE for their respective projects (Schedule 1). Projects that can have significantly
adverse environmental impact (Schedule 2) are required to submit an environmental impact
assessment (EIA) to the respective provincial environmental protection agency. The
requirements for EIA and IEE for different projects under the Investment Program will vary
(Table 1).
6. The first batch of investments under Tranche-1 covers subprojects in water supply,
drainage, and secondary solid waste connection system Two Initial Environmental Evaluations
(IEEs) have been carried out for the Tranche-1 subprojects following ADB’s safeguard Policy
(2003 now revised as per 2009) and Environmental Assessment Guidelines (2003) and
GoP’s environmental assessment regulations and guidelines. One EIA and Three IEE for
SEPA were prepared and NOC provided for the Tranche –I Project. Two IEE of ADB covers the
scopes and magnitude of the sub projects for Tranche I &II, except the sub-projects of Ghotki and
Jacobabad.
7. The table hereunder presents all sub-projects identified for Tranche-2 with environmental
requirements as per ADB guidelines 2003, ADB safeguard policy 2009 and environmental
guidelines of Pakistan Environmental Protection Agency (Pak-EPA). The Tranche II is overall
categorized as Category B
Sector Subproject Tranche Proposed ADB Category
GoP EPA Rules
Part A: Urban Planning, Institutional Development and Program Implementation Support.
Consultancy Services for new
subproject identification, detail
engineering design and preparation of
bidding document, EIA and construction
supervision and implementation of
these projects.
2 C N/S
Consultancy Services for Technical,
Operational and Business Process &
Financial Management to NSUSC
2 C N/S
Part B: Urban Water Supply and Wastewater Management Improvement
Sukkur: Construction of an extension of
the water treatment plant at
NaimashGah (NWTP) of 12 MGD
together with force main to Adam Shah
service reservoir, including meters and
pressure measuring devices.
2 B IEE
Supplementary Appendix L
Page 7
Sector Subproject Tranche Proposed ADB Category
GoP EPA Rules
Sukkur, New Sukkur, Rohri, and
Khairpur: Replacement of old water
mains and supply and laying of all new
mains/transmission lines including
district meters as part of Master Plan,
supply and install appropriate leakage
detection and NRW Equipment to
reduce physical leakage from water
supply networks. insRefer to Grg No.
MMP-977P01-P-DR-WS-S-002, MMP-
977P01-P- DR-WS-R-001 and MMP-
977P01-P-DR-WS-K-001
2 C N/S
Sukkur: Supplying and laying of new
ring/trunk mains, including bulk meters
and refurbishment of an elevated tank
(OHR), and additional HSR. Refer to
Drg No, MMP-977P01-P-DR-WS-S-
002, MMP-977P01-P-DR-WS-R-001
and MMP-977P01-P-DR-WS-K-001
2 B IEE
Construction of water treatment plant at
Airport Road of 6 MGD together with
desilting and capacity enhancement of
storage lagoons and alternative supply
of treated water from Numaish Gah via
Adam Shah service reservoir. Refer to
Drg No MMP-977P01-P-DR-WS-S-002
& Schematic layout Drg No MMP-
977P01-P-DR-WS-S-
2 B IEE/EIA
Sukkur, Khairpur, Rohri: 9 Additional
DNI Zones – replacement of distribution
network, household connections,
installation of domestic and commercial
meters and associated investment in
transmission lines. Designed to provide
3,000 customers with 24/7 potable
1 B EIA/IEE
Supplementary Appendix L
Page 8
Sector Subproject Tranche Proposed ADB Category
GoP EPA Rules
water supply.
Rohri: Construction of rapid gravity
sand filter (6MGD) and transmission
line and laboratory at Existing water
treatment plant and distribution
networks and transmission mains
improvement. Location shown on MMP-
977P01-P-DR-WS-R-001
2 B EIA/IEE
Sukkur: Construction of new raw water
intake on the River Indus
2 A EIA
Shikarpur: Rehabilitation of drainage
system, force mains, and 3 disposal
stations, 2x 100 Kva transformers and
construction/replacement of three
existing force main and Master Planning
investment for sewerage improvement
2
B
EIA/IEE
Larkana: Rehabilitation & Improvement
of Sewerage & Drainage System (
based on Detail Design of Sewerage
Project Consultancy of Federal Govt.)
including 13 Transformers for 13
Disposal stations where new
submersible pumps has been installed
2 B EIA/IEE
Rohri: Improvement of Sewerage
system and waste Water Treatment
system at in Karo Naro and
Improvement of Umar Kash Wah and
New Yard Loco Shed (area) Sewerage
Disposal Station.
2 B EIA / IEE
Khairpur: Rehabilitation and wastewater
treatment plant at existing Stabilization
Ponds at Jamali Goth.
2 B EIA / IEE
Khairpur: Diverting wastewater of all disposal stations from Mir wah canal to
2 B EIA/ IEE
Supplementary Appendix L
Page 9
Sector Subproject Tranche Proposed ADB Category
GoP EPA Rules
safe discharge point by providing additional force-main for disposal stations
All 8 Towns: Supply of sewer/drain
cleaning Equipments, 4 Jetting
machines, 4 sucking machines, 16
small skid steer loaders-excavators.
2 C N/S
Sukkur, New Sukkur, Rohri, Khairpur,
Shikarpur, Larkana, Ghotki, Jacobabad:
Small Capital Works/Projects for
operational improvement of water
supply and sewerage system.
2 B EIA/ IEE
Sukkur, Rohri, Khairpur: Establishment
of NRW reduction and pressure
management zones Teams with
required resources.
2 C N/S
NSUSC Organization Improvements
Project Equipment required to improve
operational performance including
Central and Regional Control Centers,
establishment of stores, workshops
standalone equipment; tools, office
equipment and software
2 C N/S
Sukkur, New Sukkur, Rohri, Khairpur,
Shikarpur, Larkana, Ghotki, Jacobabad:
Energy Audit Investments and energy
conservation measures in all town water
and waste water plants.
2 C N/S
Part C: Solid Waste
Management
Sukkur, Rohri,Khairpur, Shikarpur: Solid waste management improvements sanitary landfill disposal works, landfill equipment landfill
1 B EIA
Sukkur, New Sukkur, Rohri, Khairpur,
Shikarpur, Larkana, Ghotki: Additional 2 C N/S
Supplementary Appendix L
Page 10
Sector Subproject Tranche Proposed ADB Category
GoP EPA Rules
SWM Secondary collection equipment
and SKIPS, System and replacement of
old TMA system including New SMW
Secondary Collection Equipment
including road mechanical sweepers.
Ghotki.& larkana: Solid waste
management improvements sanitary
landfill disposal works, landfill
equipment including transfer station.
3 B EIA/IEE
Part D:
Transition and
Operational
Support
Funding
Operations shortfall for NSUSC Operations
2/3 C N/S
8. This EARF has been prepared/updated for subprojects that will arise in the Tranche-2 as
required by ADB. The EARF identifies the broad scope of the MFF and outlines the policy,
procedures and institutional requirements for preparing subsequent sub-projects under the MFF
loan.
9. Planning and Development Department (P&DD) of the GoS will be the Executing
Agency (EA) with overall responsibility of the Investment Program. Sindh Cities Improvement
Investment Program (SCIP) has a Program Support Unit (PSU), established within P&DD in
2008. An Urban Policy and Strategic Planning Directorate h a s b e e n e s t a b l i s h e d within
P&DD to provide advice on urban policy and regional planning in Sindh. The PSU and the
Urban D i r e c t o r a t e will be separate, but collaborative and complimentary.
10. The Investment Program is supporting the creation of regional utilities, Urban Services
Corporations (USCs) under the Companies Ordinance, 1984, beginning initially with the North
Sindh Urban Services Corporation Limited (NSUSC) under Tranche 1 of SCIP. As provided by
the Sindh Local Government Ordinance, the NSUSC was established and subsequent
USCs, 0F
1 in other geographical areas, will be established by the participating Taluka
1 As EARF applies to the MFF as a whole, the term “NSUSC” will be used
Supplementary Appendix L
Page 11
Municipal Administrations (TMA) / Municipalities to aggregate their water, wastewater and solid
waste management operations in a single institution to leverage economies of scale, introduce
new skills and management, and increase focus on systems operations, asset maintenance,
and financial and human resources management. This EARF also covers two additional cities
i.e. Ghotki and Jacobabad in operational sense with no major investment or ADB Category B is
envisaged, which are planned to be entrusted till end of 2012. All the project identified for these
two cities are also made part of this framework. Jacobabad investment needs are catered by
USAID and NSUSC will be operating the system only.
11. The NSUSC is operating under Governance of Board of Directors, will be the
implementing agency (IA) for the water supply, wastewater and SWM subprojects. In that role,
the NSUSC is responsible for ensuring that environmental assessments are prepared and
EMPs are implemented for subprojects as outlined in this framework. These EMPs are to be
submitted to ADB for review and approval prior to finalization of contracts award or
commencement of work. The NSUSC Managing Director, through Safeguards Unit working
under D i r e c t o r Operations and Services, shall monitor the progress of the environmental
work stream to ensure that all environmental assessments and clearances are submitted to
ADB prior to the Project Financing Request (PFR) for all lending tranches.
12. Each subproject will undergo environmental assessment after categorization and focus
on the most significant issues. Where a subproject requires an IEE, at least one public
consultation will be conducted with local community and potentially affected people. IEE will
be approved before commencement of detailed design while IEE results will be communicated
to the local community before commencement of construction. Any subprojects that are
categorized "A" will require full environmental impact assessment (EIA) and will include two
rounds of public consultation. The second consultation will be conducted after the draft EIA is
prepared which include the EMP. An EIA will be made available to the general public at least 120
days before the subproject approval by ADB. Similar procedure will also apply to Category “B
Sensitive” subprojects, with an IEE (including an EMP) as required. The scope and contents of
the IEE and EIA will be in accordance with ADB’s Environmental Assessment Guidelines (2003)
and ADB safeguard policy 2009.
B. Environmental Criteria for Additional Subproject Selection
13. Potential adverse environmental impacts associated with the subprojects can be
avoided or minimized through careful location, design, and route selection. Specific
environmental criteria for subproject selection are:
(i) The subprojects shall not disturb any cultural heritage designated by the
Government or by international agencies such as United Nations Educational, Scientific,
and Cultural Organization (UNESCO), and shall avoid any monuments of cultural or
historical importance.
Supplementary Appendix L
Page 12
(ii) The subprojects shall not be located within core zone of any protected
areas such as national parks, nature reserves, or wildlife sanctuaries as designated by
Environmental Protection Agency (EPA). In unavoidable case if the subproject component
is in or near the protected area, NSUSC shall ensure mitigation measures acceptable to
the ADB, Sindh Environmental Protection Agency SEPA and concerned
agency/department
(iii) The subprojects shall have a government and ADB approved EMP prior to letting of
any construction contract associated with the project. The subproject EMP must have an
implementation and monitoring budget.
(iv) The subprojects shall not clear any existing forest resources classified by
government as forest or watershed with any kind of protected status. Where
unavoidable tree cutting outside said forest resource areas will be minimized and
compensatory planting will be conducted in a least of 4:1 ratio (four saplings planted
and tended for 5 years for every one tree cut greater than 10cm in diameter). The
budget for compensatory planting shall be included in the EMP.
(v) The subprojects shall only involve activities that follow GoP laws and regulations,
ADB’s safeguard Policy (2009) and ADB Environmental Assessment Guidelines
(2003), and this EARF.
C. Responsibilities and Authorities of Various Agencies
14. The EA will have the overall responsibility of the Investment Program. The EA will (i)
facilitate inter-departmental and inter-district coordination where the environmental aspect and
management crosses the administrative boundaries; (ii) broadly monitor and evaluate the
environmental performance of the Investment Program; (iii) provide quality assurance for social
and environmental safeguards; and (v) contract independent compliance reviews and audits
environmental compliance.
15. The IA will be solely responsible for the implementation of the entire environmental
assessment and review procedures for selecting additional subprojects. This will include, but
not be limited to, ensuring that the subproject selection criteria are strictly adhered to, that
preparation of IEEs or EIA will be carried out in a timely and adequate manner, environmental
monitoring and institutional requirements will be fully met while meaningful public consultations
will be carried out satisfactorily. IA will submit the categorization checklist, IEE and EIA, and
monitoring reports to ADB for review. The NSUSC is implementing agency (IA) for this EARF.
16. Prior to the submission of the PFR for a tranche of subprojects, the IA (NSUSC) will:
(i) Prepare an environmental screening checklist to classify the subprojects in each
tranche.
Supplementary Appendix L
Page 13
(ii) Prepare the terms of reference for environmental consultants to conduct
environmental assessments, prepare environmental assessments, IEE/EIA reports
including an EMP, and IEE/EIA for public disclosure.
(iii) Ensure that information disclosure and public consultation in accordance with
ADB’s environmental assessment requirements have been undertaken with affected
groups and local NGOs, review the environmental assessments and submit the IEE,
EIA/EIA, EMP documents to ADB.
17. Prior to the commencement of civil works for subprojects in a tranche, the IA will:
(i) Submit the IEE/EIAs for regulatory approval of the relevant provincial
environmental protection agency and obtain approval, e.g., environmental clearance,
Non-Objection Certificate (NOC), forest clearance and any environmental-related
clearances as per the regulatory requirements of the federal, provincial, or local
government.
(ii) Ensure that all regulatory clearances for the subproject that are obtained from the
relevant Government authorities are submitted promptly to ADB.
(iii) Ensure that the required mitigation measures during construction or the EMP are
included in the bidding document of the subproject and that the all bidding
contractors have access to the EIA/IEE and EMP.
18. During the implementation of civil works for subprojects in a tranche, the IA will:
(i) Ensure that an environmental management plan, including all proposed
mitigation measures and monitoring programs, are properly implemented.
(ii) Monitor the implementation of EMP and post its monitoring report on the
NSUSC website Uwww.nsusc.org.pk U .
(iii) In case unpredicted environmental impacts occur during project implementation,
inform ADB, review the EMP with the contractor, and implement alternative
environmental mitigation program.
(iv) If a subproject changes in scope, inform ADB and reconfirm the environmental
classification, determine whether a supplementary IEE or EIA study is required with
ADB, and carry out the study.
(v) Submit the requisite reports on environmental compliance and implementing the
Environmental Management Plan (EMP) as required by the Pakistan EPA and ADB.
(vi) Ensure that ADB be given access to undertake environmental due diligence for all
subprojects. However, the IA shall have the main responsibility for undertaking
environmental due diligence and monitoring of all the subprojects. The due diligence
Supplementary Appendix L
Page 14
report as well as monitoring reports on EMP implementation will be systematically
prepared and be available to the public, if requested.
19. During the MFF, ADB will:
(i) Review and comment on all subproject checklists and proposed environment
category, IEEs and EIA.
(ii) Review all environmental assessment reports as a basis for subproject and
tranche approvals.
(iii) Review regular monitoring reports, posting said reports on the internet (if not
already done so by government) and officially disclosing the summary
environmental reports for Category A and B deemed sensitive on the ADB website in a
manner compliant with ADB’s Safeguard Policy (2009).
(iv) Monitor the EMP implementation and due diligence as part of MFF reviews.
(v) Provide technical guidance to NSUSC, if required, in carrying out its
responsibilities and for building capacity for safeguard compliance.
D. Environmental Assessment and Review Procedures of Additional Subprojects
1. Application of Selection Criteria
20. Any subproject not meeting the criteria listed above will not be put forward for
consideration or inclusion under the MFF tranches. The environmental assessment of the
subprojects will be conducted by IA prior to the submission of the PFR for subsequent tranches
and in line with the requirements of the FFA. A final check on conformity with the selection
criteria will be made at the submission of detailed IEEs of additional subprojects for ADB's
clearance.
2. Environmental Classification
21. Environmental categorization using the Rapid Environmental Assessment checklist
approach in compliance with the ADB Environmental Assessment Guidelines will be applied to all
subprojects. ADB Safeguard Policy 2009 requires Category A and B sensitive environmental
assessment reports to be posted on the ADB website 120 days prior to board approval.
3. Preparation of Detailed Design
22. Detailed design work for each subproject will include and follow the recommendations of
the environmental assessments. The IA will include the requirements of the EMP and IEE/EIAs in
the bid documents and ensure the detailed designs include such requirements before
contracts are finalized. The Engineering Design and Construction Supervision Consultant will
review bid documents for compliance. Where modifications to designs are incorporated at a
later stage, the requirements of the EMP and IEE/EIAs will also be included. Certification to
Supplementary Appendix L
Page 15
ADB that the detailed designs comply with IEE/EIAs (including EMP) recommendations will be
required before contracts can be signed and made effective.
4. Preparation of Construction Contracts
23. Early in the implementation period, model construction contracts will be prepared
incorporating general environmental safeguards and practices. Specific, individual contracts will
be based on the model contracts, but will also be checked by the IA to ensure that all special or
particular safeguard requirements and mitigation measures, recommended in the IEE/EIA
(including EMP) for the particular additional subproject, are all incorporated and budgeted within the
contract.
5. Monitoring During the Construction Period
24. Monitoring during construction will be the responsibility of the IA (NSUSC Monitoring
will relate to compliance with construction contracts, the affected environmental resources,
and the effectiveness of mitigation measures).
6. Monitoring of Subproject Operations
25. It is desirable to formulate the EMP in such a way so as to minimize recurrent
responsibilities and costs. However in circumstances where staff, expertise and finances are
limited, some aspects of additional subproject design may require continuous monitoring to
guard against negative environmental impacts.
26. Monitoring of issues related to compensation of landowners for land acquisition and loss of
production, if any, is separately addressed in the Land Acquisition and Resettlement Framework
(LARF) and in Land Acquisition Resettlement Action Plan (LARP).
E. Public Disclosure
27. In disclosing the environmental document to the public, (i) IA is responsible for ensuring
that all environmental assessment documentation, including the environmental due diligence
and monitoring reports, are properly and systematically kept as part of an IA project-specific
record; (ii) all environmental documents are subject to public disclosure, and therefore will be
made available to public; (iii) for category-A and B-sensitive subprojects, the EIA/IEE will be
publicly disclosed through ADB’s websites 120 days prior to PFR submission to ADB. While the
EIA/IEE w i l l be reviewed by ADB prior to disclosure; and (iv) IA will ensure that information
disclosure and public consultations, particularly with project affected persons, are undertaken in
accordance with ADB’s environmental assessment requirements as ADB guidel ines 2003,
safeguard pol icy 2009 and Public Communications Policy (2005) during the IEE/EIA
preparation process for any future subprojects.
Supplementary Appendix L
Page 16
F. Institutional Arrangements
28 . The IA will have sole responsibility for the implementation of EARF, as noted in Para 15
above. The IA will retain an environment consultant on an intermittent basis to support
achievement of responsibilities by conducting numerous tasks, including:
(i) Comment on EARF products
(ii) Recommend to the EA when revised EARF products (including, but not
limited to IEEs/EIAs/monitoring reports) should be forwarded to ADB (e.g. for clearance
as part of PFR, as semi-annual monitoring report) and Sindh EPA (e.g., for clearance
as part of PC 1 or government approval).
29. The consultant will report to NSUSC which is responsible for day to day implementation
of the project. The NSUSC has establish a Safeguards Unit to implement key tasks of the EARF,
as noted in Para 11 above.
30. The Safeguards Unit within the NSUSC has a full-time environment specialist/
manager. The specialist/manager is responsible for implementing most aspects of subproject
EMPs; this includes supervising and coordinating with consultants for supervising environmental
monitoring, quality control, and writing and internet posting of EMP progress reports for all
phases of the project including operational phase (Appendix 1 has TOR). The position has
been filled by NSUSC. The position will report to the NSUSC Director Operations and Services
(for all phases EMP tasks).
31. Environment consultant(s) will be hired to support the Safeguards Unit by
(i) Preparing IEEs and EIAs for subprojects,
(ii) Conducting field reviews of the implementation of mitigation measures and monitoring
programs as part of the EMP,
(iii) Training of local environmental safeguard officers of NSUSC’s environmental Unit
and
(iv) Prepare environmental monitoring, compliance and due diligence reports as
per GoS, SEPA and ADB requirements, and
(iv) Other tasks as instructed by the environment specialist/manager.
32. The project costs for tranche-2 have incorporated a budget and resource needed to
(i) Implement the environmental review and screening procedure,
(ii) Undertake the IEE/EIA studies for the follow-up subprojects,
(iii) Undertake environmental mitigation measures as required and
Supplementary Appendix L
Page 17
(iv) Monitor the implementation of EMPs.
33. Public disclosure and a complaints contact person within the NSUSC will be identified for
each of the subproject locations to initially receive the concerns and grievances of the local
communities and affected parties, and to ensure that they are properly handled. This NSUSC
representative will work closely with designated TMA staff and with the Provincial Government
Program Support Unit regional office staff, the latter having the role of liaising between the TMA
and NSUSC. The Safeguards Unit of NSUSC will be responsible to disseminate information
about the expected performance of the contractor. The contact person will meet with local
communities if requested or as required, and working in coordination with PSU and PSU
regional office staff and with the TMA staff as appropriate.
Grievance Redress Mechanism
34. In order to receive and facilitate the resolution of affected peoples’ concerns, complaints, and grievances about the project’s environmental performance an Environmental Grievance Redress Mechanism (GRM) will be established for each of the projects. Whilst the GRM is intended for addressing environment related grievances, in reality there is considerable cross over between environmental and social issues in relation to construction activities. Thus, it is recommended that the GRM established for environmental issues is also used to address social issues arising during project implementation.
35. The GRM will be used for addressing any complaints that arise during the implementation of projects. In addition, the GRM will include a proactive component whereby at the commencement of construction of each subproject (prior to mobilization) the community will be formally advised of project implementation details by the IA, the design and supervision consultant (SC) and the contractor (designs, scheduled activities, access constraints etc.) so that all necessary project information is communicated effectively to the community and their immediate concerns can be addressed. This proactive approach with communities will be pursued throughout the implementation of each project.
36. The GRM will address affected people's concerns and complaints proactively and promptly, using an understandable and transparent process that is gender responsive, culturally appropriate, and readily accessible to all segments of the affected people at no costs and without retribution. The mechanism will not impede access to the project’s judicial or administrative remedies.
Grievance Redress Mechanism (GRM) Establishment and Procedure
37. The GRM will be established at each project location as described below:
38. Prior to the contractor’s mobilization to the project site the IA will assist affected communities establish a Grievance Redress Committee (GRC) and identify local representatives to act as Grievance Focal Points (GFP) for that community.
Supplementary Appendix L
Page 18
39. The Grievance Redress Committee (GRC) will comprise representatives from local authorities, affected parties, and other well-reputed persons from health or education sectors, as mutually agreed with the local authorities and affected persons. It will also comprise the Contractor’s Environmental Specialist, SC’s Environment Specialist and the Environment Specialist NSUSC (the IA). The function of the GRC is to address the project related grievances of the affected parties that are unable to be resolved satisfactorily through the initial stages of the GRM procedure.
40. The Grievance Focal Points (GFPs) are designated personnel from within the community who will be responsible for: i) acting as community representatives in formal meetings between the project team and the local community he/she represents and ii) communicating community members’ grievances and concerns to the contractor during project implementation. The number of GFPs to be identified for each project will depend on the number and distribution of affected communities.
41. A pre-mobilization public consultation meeting will be convened by NSUSC and attended by GFPs, contractor, SC, Director Environment NSUSC, and other interested parties (e.g. District level representatives, NGOs). The objectives of the meeting will be as follows:
(i) Introduction of key personnel of each stakeholder including roles and responsibilities, (ii) Presentation of project information of immediate concern to the communities by the
contractor (timing and location of specific construction activities, design issues, access constraints etc.) This will include a brief summary of the EMP - its purpose and implementation arrangements;
(iii) Establishment and clarification of the GRM to be implemented during project implementation including routine (proactive) public relations activities proposed by the project team (contractor, SC, NSUSC) to ensure communities are continually advised of project progress and associated constraints throughout project implementation;
(iv) Identification of members of the Grievance Redress Committee (GRC) (v) Elicit and address the immediate concerns of the community based on information provided
above 42. Following the pre-mobilization public consultation meeting, environmental complaints associated with the construction activity will be routinely handled through the GRM as explained below and shown schematically in Figure E.1:
(i) Individuals will lodge their environmental complaint/grievance with their respective community’s nominated GFP.
(ii) The GFP will bring the individual’s complaint to the attention of the Contractor. (iii) The Contractor will record the complaint in the onsite Environmental Complaints Register
(ECR) in the presence of the GFP. (iv) The GFP will discuss the complaint with the Contractor and have it resolved; (v) If the Contractor does not resolve the complaint within one week, then the GFP will bring
the complaint to the attention of the SC’s Environmental Specialist. The SC’s Environment Specialist will then be responsible for coordinating with the Contractor in solving the issue.
(vi) If the Complaint is not resolved within 2 weeks the GFP will present the complaint to the Grievance Redress Committee (GRC).
(vii) The GRC will have to resolve the complaint within a period of 2 weeks and the resolved complaint will have to be communicated back to the community. The Contractor will then record the complaint as resolved and closed in the Environmental Complaints Register.
Supplementary Appendix L
Page 19
(viii) Should the complaint not be resolved through the GRC, the issue will be adjudicated through local legal processes.
(ix) In parallel to the ECR placed with the Contractor, each GFP will maintain a record of the complaints received and will follow up on their rapid resolution.
Figure E.1 Grievance Redress Mechanism
Gri
evan
ce
Red
ress
ed
C
om
mit
tee
Affected Person through GFP
Contractor
Not Redressed
Resolve through Local Legal Process
Redressed
Resolve with Implementation (SC) Consultant Redressed
Not Redressed
Appeal to Grievance Redress Committee Redressed
Not Redressed
Supplementary Appendix L
Page 20
G. Environmental Management and Monitoring
43. Appendix 2 summarizes an environmental management plan in matrix form that will
apply to future subprojects to be updated following submission of IEEs. Additional requirements
may be necessary for some sub-projects. The matrix is developed on the basis of environmental
assessment for the tranche- 1 & 2 subprojects. The mitigation measures for the additional
subprojects will be developed in the spirit of the principles agreed upon in this EMP. However
the EMP for all subprojects will be a working document and any unanticipated consequence(s) of
the project will be documented in the regular semi-annual reports (Appendix-3 draft table of
contents for semiannual reports) while environmental mitigation measures will be modified to
take account of unexpected impacts as necessary, throughout the implementation period.
Appendix 2 and 3 must be used as a guide for preparing all EMPs and regular semi-annual reports
in this MFF, elements of which should be adopted as appropriate after professional review. The
subproject EMP requirement must be incorporated into contract tendering documents.
Construction bids must estimate costs of compliance with the EMP. Construction contracts
cannot be awarded until EMP is approved by both ADB and the EA.
44. Environmental monitoring will be conducted based on the provisions in the subproject
EMP. Table 2 presents the summary monitoring plan for the subproject. Table 3 presents the
indicative estimated costs for EMP implementation of tranche 2 subprojects.
45. The EMP will have both internal and external monitoring. The Environmental
Specialist/manager of NSUSC will be responsible for internal monitoring of the EMP
implementation. The Environmental Specialist / Manager with assistance of consultants will
e n s u r e preparation of s e m i - a n n u a l r e p o r t s for all subprojects that will contain
progress made in EMP implementation with particular attention to compliance with the principles
and matrix set out in the EMP. The NSUSC will submit semi-annual compliance monitoring
report for category A and B subprojects to ADB. Appendix-3 is draft table of contents for
semiannual reports. ADB will post said monitoring reports on its website, in compliance with its
Safeguard Policy. Monitoring reports would also be submitted to Sindh Environmental Protection
Agency (SEPA) on projects for which regulatory approval is required. The reporting frequency
shall be semi -annual or as required by SEPA.
Supplementary Appendix L
Page 21
Table 2: Key tasks for Environmental Monitoring Plan
Environmental Monitoring Tasks Implementation
Responsibility
Implementation Schedule
Pre-Construction Phase
Receive bidding documents to ensure IEE/EIA
and EMP is included.
Engineering Design
and Construction
Supervision Engineers
Prior to issue of bidding
documents.
Audit detailed designs of Facilities and
alignment of pipeline routes to ensure standard
environmental safeguards/mitigation measures
(as identified in EMP) have been included.
NSUSC Prior to approval of
contractor’s detailed
designs.
Construction Phase
Regular monitoring and Reporting of
contractor’s compliance with contractual
environmental mitigation measures.
NSUSC through
Construction
Supervision
Consultant/Independent
Monitoring Consultant
Continuous throughout
construction period.
Operation and Maintenance Phase
Observations during routine maintenance
inspections of facilities and pipelines and rights
of way. Inspections will include monitoring
implementation status of mitigation measures
specified in EMP.
NSUSC through staff
as in table-3
As per inspection schedules
Note: Monitoring of issues related to compensation of landowners for land acquisition and loss of production, etc. are
addressed in the Land Acquisition and Resettlement Action Plan.
Table 3: Summary of Estimated Costs for EMP Implementation as per Business/Operating Plan
Item Sub Item Total Cost (PRs)
Total Cost ($)a1F
2
Monitoring staffing
Existing NSUSC Staff with additional environmental compliance and two HSE Officers operations and
as Proposed to be budgeted in New Business Plan 2012-2015
2 1$=95PKR
Supplementary Appendix L
Page 22
Item Sub Item Total Cost (PRs)
Total Cost ($)a1F
2
services, one HSE Officer for capital works and Lab Officers
Audits & ISO 140001
Annual audits and ISO 14001 Certification and EMS for Labs at PRs500,000 per audit
1,000,000 10550
Monitoring activities
As detailed under EMP2F
3 as per Bid Price of Each contract
EMP Mitigation measures
As detailed under EMPs for operational phase
As per Operating Plan
Transport Dedicated vehicles of NSUSC for Environmental Compliance of Projects and Operations by Safeguard Unit
Contingency contingency 10% 2000
UTotal U1,000,000 Uand as
per actual/budget
U12,550
3 Includes air, noise and water monitoring cost
Supplementary Appendix L
Page 23
APPENDIX 1: Draft Terms of Reference for Environmental Safeguards Specialist/Manager
A. Qualifications
1. The Environmental Safeguards Specialist/manager shall be a post graduate in
environmental science, environmental engineering or a related discipline with 7-10 years
professional experience in environmental management and monitoring of projects, environmental
assessment and / or implementation of environmental mitigation measures on international
funded projects. It is desirable for the Environment Specialist to have relevant experience with
international donors and their safeguard policies.
B. Reporting
2. The Safeguards Unit leader will report to the NSUSC Director Operations and
Services.
C. Scope of Work
(i) Ensure of environmental assessments, their associated environmental
management plans (EMP) by consultants for all subprojects. This includes both technical (e.g.
report review and comment) and administrative (e.g. consultant TOR, recruitment, and contract
management) functions.
Consultant/ IMC Contractor
Managing Director
NSUSC Safeguards
Unit
Director
(Operation & Services)
Environmental
Safeguard
Specialist/Manager
One Environmental
/HSE Engineers for
projects and two for
operations)
Water Quality Labs
Officers and Staff
Supplementary Appendix L
Page 24
(ii) Check and verify the EMP implementation progress, as reported by consultants and
through site visits. Assess the progress in the subprojects’ EMP implementation
address the gaps to ensure compliance with ADB’s environmental assessment
requirements to warrant submission of the next PFR to ADB;
(iii) Review & Oversight of regular Water Quality Monitoring results and find gaps and ensure
compliance and corrective measures
(iv) Check and verify the progress in EMP implementation of each subproject and every six
months prepare reports for EA and ADB. The report shall include, but not be limited to:
• Major achievements since last reporting period
• monitoring results of this reporting period, comparison of results with agreed-upon
performance standards
• Summary of complaints through random checking at the field level, and actions that
were taken to address complaints
• Unexpected environmental impacts, and actions taken to address those impact, issues
to address in next reporting period
(V) Implement NSUSC Environmental Policy and HSE Policy
Supplementary Appendix L
Page 25
APPENDIX 2: Environmental Management Plan for Tranche-1&2 Subprojects
The below table must be used as a guide for preparing subproject Environmental Management Plans under this Facility, as applicable. Construction
contracts cannot be awarded until the subproject EMP is approved by both ADB and the Implementing Agency, the Urban Services Corporation
(NSUSC)...
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
Subproject
location
All sub
projects
Social and
environmental
nuisances
Careful site /
route selection to
avoid existing
settlements.
Review IEE and
EMP and confirm
findings and
recommendations
.
Site location as
proposed in RRP
and IEE with
respect to nearest
SRs.
Check with
detailed
design
engineers and
land owners –
once during
feasibility
prior to detail
design stage.
NSUSC Integral part of
subproject
detailed design
and project
preparation.
All sub
projects
Loss of productive
agriculture
Minimize need to
acquire
agricultural land.
Site selection in
urban area or on
marginal land on
urban fringe (as far
as possible not
agricultural land).
Consultation
with local
authorities
and land
owners during
feasibility
prior to detail
NSUSC Integral part of
subproject
detailed design
and project
preparation
Supplementary Appendix L
Page 26
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
design stage.
Subproject
location changes
All sub
projects
Non-compliance
with subproject
selection criteria.
Conduct Rapid
Environmental
Assessment to
determine ADB
Category.
Review IEE and
EMP and confirm
findings and
recommendations
.
Categorization and
submission of REA
to ADB.
Prior to or
latest during
detailed
design stage.
NSUSC Integral part of
subproject
detailed design
and project
preparation.
Subproject
boundaries
change.
All
subprojects
EMP insufficient
to control impacts.
Non-compliance
with statutory
requirements
Pakistan
Environmental
Protection Act
Review IEE and
EMP and confirm
findings and
recommendations
.
Disclose
feasibility designs
of subprojects to
SEPA in advance
Submit REA,
revised IEE/EIA
and EMP to ADB.
Obtain waiver for
IEE
from Pak EPA OR
“Environmental
Prior to
signing of
construction
contracts.
NSUSC Integral part of
subproject
detailed design
and project
preparation.
Supplementary Appendix L
Page 27
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
1997. to clarify IEE or
EIA.
Complete the
environmental
assessment
process in line
with SEPA and
ADB Guidelines.
Approval” from
SEPA.
Layout of
facilities.
All
subprojects
Relocation of
potential
nuisances or
exposure to noise
or safety related
risks.
Check setback
and location of
noise sources
with respect to
sensitive
receivers (SRs)
and design in
accordance with
good principles.
Buffer distance to
SRs sufficient as
recommended in
IEE with respect to
nearest SRs.
Check
setback
distances to
nearest
sensitive
receivers –
twice during
design and
when layout
plans are
finalised.
NSUSC Integral part of
feasibility survey
and detailed
design.
Avoid utilities /
interface
All Interruption of Utilities
management
Maintenance of Continuous NSUSC Throughout
design and
Supplementary Appendix L
Page 28
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
management subprojects utility service coordinating
committee
services construction
phases.
Buffer Zone
/distance
encroached
All
subprojects
Buffer distance
reduced creates
potential
nuisances for
neighbors/SRs.
Check setback of
facilities from
sensitive
receivers (SRs)
off site and re
design in
accordance with
proposed buffer
or include
mitigation.
% recommended
buffer distance
achieved. Inclusion
of additional
mitigation. Residual
impacts >
predicted in IEE.
Twice
Feasibility
design and
detailed
design.
NSUSC Integral part of
feasibility survey
and detailed
design.
Equipment
location and
design.
All
subprojects
Exposure to
noise, Nuisance to
neighboring
properties.
Design and
location of
subproject to
comply with
NEQS regulations
and World Bank
guidelines.
Check potential
performance of
proposed
vehicles/equipment
.
Check
proposed
equipment is
actually
included
through
purchase and
usage
inventory.
NSUSC Part of detailed
design,
commissioning
and operational
monitoring.
Supplementary Appendix L
Page 29
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
Involuntary
Resettlement or
land acquisition
(if unforeseen
requirement
emerges).
All facilities. Social inequities Compensation
paid for
temporary/
permanent loss of
productive land as
per land laws and
its process as
specified in RAP.
RAP
implementation
Consultation
with affected
parties – once
in a quarter.
NSUSC Prior to
construction
phase.
Interference with
drainage
patterns/Irrigatio
n channels
All facilities Flooding hazards /
loss of agricultural
production
Appropriate
location of
facilities to avoid
interference with
irrigation channels
Significant distance
to nearest flood
zone, irrigation
channel
Consultation
with local
irrigation
authorities
and design
engineers -
once
NSUSC Part of project
preparation and
site selection,
detailed
alignment
survey and
design
Release of
polluting
materials
All plant
equipment
Environmental
pollution
Plant and layout
designed and
equipment
selected to
ensure
compliance with
NEQS and
Equipment
specifications with
respect to potential
pollutants.
Tender
document to
include
detailed
specifications
- once
NSUSC Part of detailed
equipment
design selection
and design
drawings
Supplementary Appendix L
Page 30
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
prevent runoff.
All
subprojects
New sites and
facilities to
include drainage
and sewage
disposal systems
to avoid offsite
land and water
pollution.
Drainage and
sewage design.
Tender
document to
include
detailed
specifications
- once
NSUSC Part of detailed
equipment
design selection
and design
drawings
Equipment
submerged
under flood
All plant
equipment
Contamination of
land and water
SRs.
Appropriate siting
and facilities
constructed
above the highest
recorded flood
level (HFL) or
design to raise
the foundation
pad (see also
drainage).
Facility design to
account for HFL
(elevation with
respect to HFL
elevation)
Base height
as per flood
design - once
NSUSC Part of detailed
layout and
design /
drawings
Explosions/Fire All facilities Hazards to life Locate and
design facilities to
Design compliance
with fire prevention
Tender
document to
NSUSC Part of detailed
layout and
Supplementary Appendix L
Page 31
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
include fire breaks
/ walls and
modern fire
control
systems/firewalls.
and control codes
(BCOP).
specify
detailed
design
requirements
– once
design /
drawings
Facility location All
subprojects
Visual impact Facilities not to be
located near
critical or
sensitive areas or
national
monuments in
areas with
potential tourist
activities. Soft
landscaping.
Trees and soft
landscaping
included in design.
Meaningful and
appropriate to
mitigate visual
impact.
Trees and
landscaping
planted and
maintained
NSUSC Detailed designs
and
commissioning.
Tree
preservation
All
subprojects
Unnecessary loss
of trees
Tree survey
during detailed
design.
Trees identified
and marked.
Trees to be
retained and
maintained
NSUSC Detailed designs
and
commissioning.
Environmentally
responsible
All
subprojects
Operational
environmental
Choose non
polluting
Checked
equipment
specifications and
During
product
acquisition,
NSUSC Detailed designs
and
Supplementary Appendix L
Page 32
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
procurement pollution equipment performance with
company
certificates /
accreditations.
prior to
purchase.
commissioning.
Environmentally
responsible
procurement
All
subprojects
Impact at
decommissioning.
Specify
equipment not to
contain asbestos,
other hazardous
or toxic
components.
Checked
equipment
specifications and
performance with
company
certificates /
accreditations.
During
product
acquisition,
prior to
purchase.
NSUSC Detailed designs
and
commissioning.
Equipment
layout and
installation
All
subprojects
Noise and
vibration.
Construction
techniques and
machinery
selection seeking
to minimize
vibration through
ground
disturbance and
minimise duration
of works.
Construction
techniques and
machinery in line
with contractual
requirements and
contractors method
statements.
Construction
techniques
and
machinery
creating
minimal
ground
disturbance -
once at the
start of each
construction
NSUSC
(Contractor
through
contract
provisions).
Construction
period
Supplementary Appendix L
Page 33
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
phase.
Physical
construction
All
subprojects
Disturbed
commercial and
community
activities.
Construction
activities timed to
optimise minimum
disturbance and
nuisances.
Timing mitigation
with respect to
community
activities and
requests.
Complaints
Received by local
authorities.
Once every
month include
in progress
reports.
NSUSC
(Contractor
through
contract
provisions).
Construction
period
Mechanized
construction
All
subprojects
Noise, vibration
and operator
safety, efficient
operation
Construction
equipment to be
well maintained
with
noise suppression
/ acoustic
insulation. Erect
local site hoarding
as necessary.
Construction
equipment
– noise levels.
Complaints
received by
local
authorities -
once every
month
NSUSC
(Contractor
through
contract
provisions)
Construction
period
All
subprojects
Noise, vibration,
equipment wear
Turning off plant
not in use. Erect
Construction
equipment
Complaints
Received by
NSUSC
(Contractor
Construction
period
Supplementary Appendix L
Page 34
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
and tear site hoarding. – estimated noise
levels and
operating
schedules
local
authorities –
once every
month
through
contract
provisions)
Excavation by
hand tools or
other means
All
subprojects
Dust increases. Erect site
hoarding, damp
down exposed
surfaces and
stockpiles to keep
moist. Cover open
ground /
stockpiles when
construction not
active.
Hoarding
installation,
covering works and
frequent damping.
Site check
weekly /
report
monthly
NSUSC to
check weekly
and report
monthly.
(Contractor
requirement
through
contract
provisions).
Construction
period
Construction of
access roads
and hoardings
All
subprojects
Increase in
airborne dust
particles
Use existing
roads and tracks
for construction
and maintenance
access to the
sites wherever
Access roads,
routes (length and
width of new
access roads to be
constructed).
Use of roads
established in
contract as
suitable –
once every
month
NSUSC
(Contractor
through
contract
provisions)
Construction
period
Supplementary Appendix L
Page 35
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
possible.
All
subprojects
Increased land
requirement for
temporary
access/constructio
n
New access ways
should be minimal
disturbance and
restricted to a
single
carriageway width
with passing bays
and shortest
distance from
existing road to
site.
Disturbance and
access width
(meters) as
agreed with
contractor.
Complaints.
Every month
– include in
progress
report.
NSUSC
(Contractor
through
contract
provisions).
Construction
period
Preparation of
site
All
subprojects
Temporary
blockage of
drainage.
Temporary
placement of
cleared top soil:
N Uot Uplaced to
obstruct
drains/canals.
Temporary fill
placement (m3)
and location.
Check no
impact (e.g.
on sensitive
drainage
areas - every
month –
include in
progress
report.
NSUSC
(Contractor
through
contract
provisions)
Construction
period
Supplementary Appendix L
Page 36
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
Site clearance All
subprojects
Vegetation Marking of
vegetation Unot Uto
be removed prior
to clearance, and
strict control on
clearing activities
to ensure minimal
clearance.
Cleared
vegetation Unot U to
be burned.
Vegetation survey,
marking and
clearance control
(area in m2) –
monitor and
inspect.
Clearance
strictly limited
to target
route/site and
minimum
working
areas- every
month when
works are
commencing
on a
particular
route/site.
NSUSC
(Contractor
required in
contracts to
provide “site
clearance
plan” as line
item before
opening new
works) prior to
handover.
Construction
period
Trimming/cutting
of trees within
RoW/site
boundary
All
subprojects
Safety hazards
and conservation
to be balanced.
Retain trees and
maintain trees
unless unsafe to
do so. Trees
allowed to grow
unless posing a
safety hazard.
Number of trees
retained vs
numbers cut.
Retained
trees and
maintained
trees in
RoW/site vs
trees
identified at
design stage
NSUSC
(Contractor
through
contract
provisions)
Construction
period
Supplementary Appendix L
Page 37
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
Trimmings
composted Unot U
burned.
– once per
quarter
All
subprojects
Felled trees and
other cleared or
pruned vegetation
to be disposed of
as authorized by
the statutory
authority but not
burned.
Disposal of cleared
vegetation as
approved by the
statutory
authorities (area
cleared in m2)
Use or
intended use
of vegetation
as approved
by the
statutory
authorities –
once per site
NSUSC
(Contractor
through
contract
provisions)
Construction
period
Surplus
earthwork/soil.
All
subprojects
Runoff to cause
water pollution,
solid waste
disposal
Soil excavated
from sites
disposed of by
placement along
roadsides, or at
nearby house /
school / hospital
gardens if
requested by
Soil disposal
locations and
volume (m3).
Acceptable
soil disposal
sites - every
month in
progress
report
NSUSC
(Contractor
through
contract
provisions)
Construction
period
Supplementary Appendix L
Page 38
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
landowners.
Storage of
materials
All
subprojects
Contamination of
adjacent receptors
(land, water, air)
Materials securely
stored above high
flood level.
covered when not
in use, at end of
shift and at night
Location of
hazardous material
storage.
Bulk materials
stored on site
extent
covered and
retaining
boards -
every month
NSUSC
(Contractor
through
contract
provisions)
Construction
period
All
subprojects
Increased land
requirement for
temporary
access/constructio
n
New access ways
should be minimal
disturbance and
restricted to a
single
carriageway width
with passing bays
and shortest
distance from
existing road to
site.
Disturbance and
access width
(meters) as
agreed with
contractor.
Complaints.
Every month
– include in
progress
report.
NSUSC
(Contractor
through
contract
provisions).
Construction
period
Storage of All Accidental spillage Fuel and other
hazardous
Record usage. Spill
records (type of
Fuel and
chemical
Storage of All subprojects
Supplementary Appendix L
Page 39
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
chemicals subprojects of chemicals materials securely
stored and above
high flood level.
material spilled,
amount (kg or m3)
and action taken to
control and clean
up
spill)
storage in
appropriate
containers in
appropriate
locations
preferably
bunded or
enclosed –
every month
chemicals
Construction
scheduling
(considerate of
local
circumstances).
All
subprojects
Noise nuisance to
neighbouring
properties.
Interference with
peak traffic hours
on adjacent roads.
Construction
activities only
undertaken during
the day.
If night working
discuss with local
communities to
keep informed of
the construction
schedule. Avoid
school exam
times and
religious festivals
Public consultation
and Timing of
construction (noise
emissions, [dB(a)]).
Complaints and
results feedback
Monthly audit
of day time –
nigh time
construction
scheduling
and feedback
of PC – every
month
Construction
scheduling
(considerate of
local
circumstances
).
All subprojects
Supplementary Appendix L
Page 40
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
near schools and
mosques
Provision of
basic sanitary
facilities for
construction
workers.
All
subprojects
Contamination of
neighborhood,
open defecation,
litter, waste
disposal.
Construction
workforce
facilities to
include portable
lavatories or
arrange proper
access to other
toilets with
adequate
sanitation, water
supply for
washing. Regular
litter collection
and site waste
disposal facilities.
Portable chemical
toilets acceptable.
Adequate
amenities and
cleansable facilities
to
be arranged prior
to
Commencement of
construction for
workforce. Within 5
(five) minutes walk
from all work sites
and kept clean at
all times.
Presence of
proper
sanitation,
water supply
and waste
disposal
facilities - one
for each
facility or one
for each
500m of
pipeline or
BTR
Construction.
Provision of
basic sanitary
facilities for
construction
workers.
All subprojects
Nuisance to
nearby
All
subprojects
Impacts on
property value
losses to
Contract clauses
to specify
acceptable
Monitor and
enforce
implementation of
Incorporating
good
construction
Nuisance to
nearby
All subprojects
Supplementary Appendix L
Page 41
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
properties neighboring land
uses.
construction
practices to
mitigate
nuisances, noise,
vibration and dust
impacts.
contract clauses
versus milestone
payments for
mitigation (e.g. per
m of hoarding
installed effectively.
management
practices
– once per
month for
each site/km
of line
under
construction.
properties
All
subprojects
Use existing
access effectively
as much as
possible.
Construction
operating
procedures and
monitor complaints.
Incorporating
good design
engineering
practices –
once for each
site. Check
monthly.
All subprojects
All
subprojects
Productive land
will be reinstated
following
completion of
construction
Reinstatement of
land status (area
affected, m2) if
necessary.
Consultation
with affected
parties –
twice
– immediately
Supplementary Appendix L
Page 42
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
after
completion of
construction
and after the
first harvest
All
subprojects
Social inequities Compensation
will be paid for
loss of livelihood
due to
construction
disruption in line
with ADB
guidelines.
Prompt
disbursement of
compensation for
lost income in line
with RAP
entitlement matrix.
Monitor amount
paid to whom, how
and when.
Monthly
monitoring
with updated
report – once
in a quarter.
NSUSC Prior to
commencement
of construction
in the relevant
location.
Complaints All
subprojects
Construction
activities
Set up complaints
hot line,
recording,
response and
resolution
monitoring
Response time to
rerecord, respond
and resolve
complaints.
Complaints
Received by
local
authorities –
tally once
every month
NSUSC
(Contractor
through
contract
provisions)
Supplementary Appendix L
Page 43
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
All
subprojects
Nuisances to
surrounding
neighborhood.
Set up complaints
hot line and
response
mechanism
Complaints
number, location,
validity,
fraudulence, review
of mitigation
measures to
improve
environmental
control.
Monitor total
complaints
weekly and
investigate as
soon as
possible after
complaint (call
back within 2
days, site visit
within the
week).
Document
action and
record
resolution
NSUSC
(Contractor
through
contract
provisions)
Throughout
construction and
at least first year
of operation.
Flooding
hazards due to
construction
impediments of
natural drainage
All
subprojects
Flooding and
damage to
property, blocking
of traffic through
roads. Pedestrian
access and
spread of surface
Temporary
drainage
management plan
(TMDP) to be
submitted to CRC
for acceptance by
NSUSC one
Submission of
TDMP as condition
of contract clauses.
Occurrence of
flooding and any
relevant
Check as line
item before
opening for
each
section/area
of the works.
Record
NSUSC
(Contractor
through
contract
provisions)
Construction
period
Supplementary Appendix L
Page 44
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
contamination month before
commencement
of construction in
the relevant
sector.
Avoid drainage
pattern facilities
being disturbed /
blocked / diverted
by the on- going
construction
activities.
Other drainage
mitigation
measures,
diversions,
protection of
drains.
complaints.
TMDP to cater for
worst case one in
five (5) year
flooding event.
Review mitigation
id flooding repeats.
flooding
events
monthly and
report
quarterly
TMDP to be
checked by
qualified
drainage
engineer and
accepted.
Incorporating
good
construction
management
practices
– Monthly for
each site.
All
subprojects
Productive land
will be reinstated
Reinstatement of
land status (area
Consultation
with affected
Supplementary Appendix L
Page 45
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
following
completion of
construction
affected, m2) if
necessary.
parties –
twice
– immediately
after
completion of
construction
and after the
first harvest
Health and
safety
All
subprojects
Injury and
sickness of
workers and
members of the
public
Contract
provisions
specifying
minimum
requirements for
construction
camps, if required
Contract clauses
covering (number
of incidents and
total lost- work
days caused by
injuries and
sickness)
Contract
clauses
compliance –
once every
quarter
NSUSC
(Contractor
through
contract
provisions)
Construction
period
All
subprojects
Contractor to
prepare and
implement a
health and safety
plan.
Supplementary Appendix L
Page 46
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
All
subprojects
Contractor to
arrange for health
and safety
training sessions
First aid All
subprojects
Minor injuries to
workforce go
unattended
presenting risk to
worker injured and
co-workers.
First aid posts to
be set up with
adequate
sanitation (at
least washing and
dressing facilities)
with first aid kits,
one for every site
or one for every
2km along the
routes
First aider to be
trained in every
contractor and
sub contractor
group to be
present onsite
every working
Nomination of first
aiders and setting
up facilities.
Contents of first aid
kits. Test run
response from
Mobile clinic.
Check records of
accidents.
Once per
month
NSUSC
(Contractor
through
contract
provisions)
Construction
period
Supplementary Appendix L
Page 47
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
day, or mobile
clinic to be
available onsite
every with driver/
first-aider and
trained nurse to
man the mobile
clinic.
Record cause of
accidents and
investigate if
hospitalisation
required.
Injuries to
workforce
All
subprojects
Avoid severe
head injuries and
foot injuries,
especially in areas
where overhead
construction will
take place.
Exclude public.
Hoard and net
edges of elevated
sections to retain
accidentally
dropped materials
tools.
Provide sufficient
Check hoardings
and safety nets,
Check availability
of hard hats and
hard shoes.
Monitor usage of
hard hats and
Once per
month
NSUSC
(Contractor
through
contract
provisions)
Construction
period
Supplementary Appendix L
Page 48
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
basic protective
equipment to
allow every
worker once per
year including a
hard hat and one
pair hard toe and
sole shoes.
shoes % workforce
using.
Check records of
accidents.
Health and
safety
All
subprojects
Injury and
sickness of
workers and
members of the
public
Contract
provisions
specifying
minimum
requirements for
construction
camps, if required
Contract clauses
covering (number
of incidents and
total lost- work
days caused by
injuries and
sickness)
Contract
clauses
compliance –
once every
quarter
NSUSC
(Contractor
through
contract
provisions)
Construction
period
All
subprojects
Contractor to
prepare and
implement a
health and safety
plan.
Supplementary Appendix L
Page 49
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
All
subprojects
Contractor to
arrange for health
and safety
training sessions
First aid All
subprojects
Minor injuries to
workforce go
unattended
presenting risk to
worker injured and
co-workers.
First aid posts to
be set up wit
adequate
sanitation (at
least washing and
dressing facilities)
with first aid kits,
one for every site
or one for every
2km along the
routes
First aider to be
trained in every
contractor and
sub contractor
group to be
present onsite
every working
Nomination of first
aiders and setting
up facilities.
Contents of first aid
kits. Test run
response from
mobile clinic.
Check records of
accidents.
Once per
month
NSUSC
(Contractor
through
contract
provisions)
Construction
period
Supplementary Appendix L
Page 50
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
day, or mobile
clinic to be
available onsite
every with driver/
first-aider and
trained nurse to
man the mobile
clinic.
Record cause of
accidents and
investigate if
hospitalisation
required.
Injuries to
workforce
All
subprojects
Avoid severe
head injuries and
foot injuries,
especially in areas
where overhead
construction will
take place.
Exclude public.
Hoard and net
edges of elevated
sections to retain
accidentally
dropped materials
tools.
Provide sufficient
Check hoardings
and safety nets,
Check availability
of hard hats and
hard shoes.
Monitor usage of
hard hats and
Once per
month
NSUSC
(Contractor
through
contract
provisions)
Construction
period
Supplementary Appendix L
Page 51
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
basic protective
equipment to
allow every
worker once per
year including a
hard hat and one
pair hard toe and
sole shoes.
shoes % workforce
using.
Check records of
accidents.
Inadequate
construction
stage
environmental
monitoring
All
subprojects
Lack of monitoring
may allow noise
and dust to
escalate,
uncontrolled.
Impacts may
increase.
No quantitative
Feedback
prevents
improvement of
mitigation
Training of
NSUSC
environmental
monitoring
personnel
Training schedules Number of
programs
attended by
each person –
twice per year
NSUSC Routinely
throughout
construction
period
Supplementary Appendix L
Page 52
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
measures
All
subprojects
Implementation of
effective
environmental
monitoring and
reporting system
using checklists
of all contractual
environmental
requirements and
EMP.
Respective
contract checklists
and Remedial
actions taken
thereof.
Submission of
duly
completed
checklists of
all contract
requirements
for each site –
once
All
subprojects
Appropriate
contact clauses to
ensure
satisfactory
implementation of
contractual
environmental
mitigation
measures.
Compliance report
related to
environmental
aspects for the
contract
Submission of
duly
completed
compliance
Report for
each contract
– once
Supplementary Appendix L
Page 53
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
Commissioning All
subprojects
Visual impact Facilities to have
areas with soft
landscaping.
Opportunity spaces
for trees and soft
landscaping to be
included in the
design.
Check trees
and
landscaping
are planted
and have
been installed
and
maintained.
Before last
payment of
contract.
NSUSC Commissioning.
Noise Impacts All
subprojects
Nuisance to
neighbouring
properties
Facility sited and
designed to
ensure noise will
not be a
nuisance.
Noise levels
(dB(A)) to meet
criteria agreed with
SEPA.
Noise levels
at boundary
nearest to
properties at
intervals (or
as agreed
with SEPA –
quarterly in
1st
year of
NSUSC During
commissioning
and
1st year of
operations
Supplementary Appendix L
Page 54
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
operation.
Inadequate
provision of
health and safety
training during
operations to
staff/workers
All
subprojects
Injury and
sickness of staff
/workers
Careful design
using appropriate
technologies to
minimise hazards
Usage of
appropriate
technologies (lost
work days due to
illness and injuries)
Preparedness
level for using
these
technologies
in crisis –
once each
year
NSUSC Design and
operation
All
subprojects
Provide adequate
sanitation and
water supply
facilities
Provision of
facilities
Complaints
received from
staff / workers
Operational
environmental
monitoring.
All
subprojects
Environmental
impacts and
nuisances are
uncontrolled.
Unexpected
impacts go
undetected.
NSUSC staff to
receive
awareness
training in
environmental
monitoring of
project operations
and maintenance
Training/awareness
programs and
mock drills for all
staff.
Number of
programs and
percent of
staff covered
– once each
year
NSUSC Operation
Supplementary Appendix L
Page 55
Project activity
/
stage / issue
Subproject
type of
component
Potential impact
Proposed
mitigation
measure
Parameter to be
monitored
Measuremen
t and
frequency
Institutional
responsibility
Implementation
schedule
activities.
Supplementary Appendix L
Page 56
APPENDIX-3: Semi-annual Environmental Monitoring Report
Table of Contents
Part I Introduction
I. Construction activities and Project Progress during previous 6 months
II. Changes in project organization and Environmental management team
III. Relationships with Contractors, owner, lender, etc.
Part II Environmental Monitoring
Environmental monitoring summary – summarise the previous six months monitoring data and provide explanations
of any instances where environmental standards or guidelines are exceeded. Typically this will cover:
Noise and Vibration
Water Quality
Air Quality
Flora and fauna monitoring
Recommendations are required to show how any exceedences will be prevented in the future.
Graphs can be used in this section to show trends, however large tables of data or multiple graphs should be
attached as an appendix.
Part III Environmental Management
EMS, SSEMP and work plans. Report on delivery of documents, required amendments etc.
Site Inspections and audits – summarise the number and type of site visits
Non-compliance notices – summarise the details on the number of notices given out and the issues covered.
Summarise the ranking of issues.
Corrective action plans - report on timeliness of preparation and completion
Consultation and complaints – report on any consultation undertaken and list any complaints received.
Annexes: i) Monitoring data, ii) Photographs, iii) Implementation report on EIA/IEE mitigation requirements
Reference Requirement Action to date Action required/comment